bill no. 1 preliminaries notes: engineering works … 1.1 ombika - section 1... · internationale...
TRANSCRIPT
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/1PRELIMINARIESLOT 1.1 : OMBIKA GATE
BILL NO. 1
PRELIMINARIES
Item Quantity Rate AmountNo.
NOTES:
i) The Conditions of Contract for Construction for Building andEngineering Works Designed by the Employer as issued by theFederation internationale des Ingenieurs-Conseils (FIDIC), FirstEdition 1999, shall be the applicable contract for the execution ofthe Works.
ii) The Model Preliminaries as recommended and published by theAssociation of South African Quantity Surveyors, 1988 editionshall be deemed to be incorporated herein.All references to the "Architect" in The Model Preliminaries shallbe deemed to be the "Engineer" for the purposes of thiscontract.
In addition, the items in these Bills of Quantities are deemed tobe read and priced in conjunction with and the descriptionsregarded as amplified by the Model Preambles for Trades, asrecommended and published by the Association of SouthAfrican Quantity Surveyors (2008 Edition).
Supplementary Preambles as well as Project Specificationsattached to this Tender document, amending/supplementingstandard clauses in the Model Preambles for Trades with regardto items of a general nature and/or specific materials and/ormodes of procedure are incorporated in these Bills of Quantitiesto fulfil the requirements of these building works.
No claim arising from brevity of description of items fullydescribed in the said Model Preambles for Trades and/orSupplementary Preambles and/or Project.
iii) Tenderers are referred to the abovementioned documentsfor the full intent and meaning of each clause thereof (hereinafterreferred to by heading and clause number only) for which suchallowance must be made as may be considered necessary.
All references in the above mentioned documents and thisPreliminaries Bill to "Architect"/"Principal Agent" are deemed tobe references to "The Engineer"
iv) Where standard clauses or alternatives are not applicable tothis contract such modifications, corrections or supplementsas will apply are given under each relevant clause heading.
Carried to Collection N$
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/2PRELIMINARIESLOT 1.1 : OMBIKA GATE
v) Where N/A appears opposite any clause, such clause as detailedin the standard documents referred to is NOT APPLICABLE tothis contract.
The following documents will form the basis of the Tender andContract:-
1. The Conditions of Contract for Construction for Building and EngineeringWorks Designed by the Employer as issued by the FederationInternationale des Ingenieurs-Conseils (FIDIC), First Edition 1999,
2. Form of Tender
3. Project drawings
4. Bills of Quantities (fully priced out)
5. Model Preliminaries (1988 Edition)
6. Model Preambles for Trades (2008 Edition) with supplementaryProject Specifications (where applicable)
The Contractor is advised to examine the above documents and makehimself thoroughly acquainted with the nature and requirements of the work,as no claim for extra payment in this connection will afterwards beentertained. Should any parts of the documents or drawings not be clearlyintelligible to the Contractor, he must, before submitting his tender obtainclarification from the Engineer.
SECTION A : CONDITIONS OF CONTRACT FOR CONSTRUCTION FORBUILDING AND ENGINEERING WORKS DESIGNED BY THE EMPLOYER
A.1 - GENERAL PROVISIONS
1 Clause 1.1 : Definitions Item
2 Clause 1.2 : Interpretation Item
3 Clause 1.3 : Communications Item
4 Clause 1.4 : Law and Language Item
The language to be used in all matters pertaining to this contract shall be inEnglish. The law of the Republic of Namibia shall be applicable to thisContract.
5 Clause 1.5 : Priority of Documents Item
6 Clause 1.6 : Contract Agreement Item
7 Clause 1.7 : Assignment Item
Carried to Collection N$
8 Clause 1.8 : Care and Supply of Documents Item
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/3PRELIMINARIESLOT 1.1 : OMBIKA GATE
9 Clause 1.9 : Delayed Drawings or Instructions Item
10 Clause 1.10 : Employer’s Use of Contractor’s Documents Item
11 Clause 1.11 : Contractor’s Use of Employer’s Documents Item
12 Clause 1.12 : Confidential Details Item
13 Clause 1.13 : Compliance with Laws Item
i) Contractor to comply with the Namibia EnvironmentalManagement Act No. 7 of years 2007 as well as theEnvironmental Assessment Policy of year 1995 by implementingthe Environmental Management Plans (EMP) documentedseparately as part of this contract.
ii) Contractor to comply with the Namibia Public Health and SafetyManagement Policy under Act No. 11 of year 2007 byimplementing the Public Health and Safety Awareness Plan(PHSAP) documented separately as part of this contract.
14 Clause 1.14 : Joint and Several Liability Item
A.2 - THE EMPLOYER
15 Clause 2.1 : Right of Access to the Site Item
16 Clause 2.2 : Permits, Licences or Approvals Item
17 Clause 2.3 : Employer’s Personnel Item
18 Clause 2.4 : Employer’s Financial Arrangement Item
19 Clause 2.5 : Employer’s Claims Item
A.3 - THE ENGINEER
The Engineer shall be deemed for the purposes of this contract, to be thePrincipal Agent, Architect or any other person appointed by the Employerto fulfil such duties.
20 Clause 3.1 : Engineer’s Duties and Authority Item
21 Clause 3.2 : Delegation by the Engineer Item
22 Clause 3.3 : Instructions of the Engineer Item
23 Clause 3.4 : Replacement of the Engineer Item
24 Clause 3.5 : Determinations Item
Carried to Collection N$
A.4 - THE CONTRACTOR
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/4PRELIMINARIESLOT 1.1 : OMBIKA GATE
25 Clause 4.1 : Contractor’s General Obligations Item
26 Clause 4.2 : Performance Security Item
27 Clause 4.3 : Contractor’s Representative Item
28 Clause 4.4 : Sub-Contractors Item
29 Clause 4.5 : Assignment of Benefit of Sub-contract Item
30 Clause 4.6 : Co-operation Item
31 Clause 4.7 : Setting out Item
32 Clause 4.8 : Safety Procedures Item
33 Clause 4.9 : Quality Assurance Item
34 Clause 4.10 : Site Data Item
35 Clause 4.11 : Sufficiency of accepted Contract Amount Item
36 Clause 4.12 : Unforeseeable Physical Conditions Item
37 Clause 4.13 : Right of Way and Facilities Item
38 Clause 4.14 : Avoidance of Interference Item
39 Clause 4.15 : Access Route Item
40 Clause 4.16 : Transport of Goods Item
41 Clause 4.17 : Contractor’s Equipment Item
42 Clause 4.18 : Protection of the Environment Item
43 Clause 4.19 : Electricity, Water and Gas Item
44 Clause 4.20 : Employer’s Equipment and Free-issue Material Item
45 Clause 4.21 : Progress Reports Item
46 Clause 4.22 : Security of the Site Item
47 Clause 4.23 : Contractor’s Operations on Site Item
48 Clause 4.24 : Fossils Item
Carried to Collection N$
A.5 - NOMINATED SUB-CONTRACTORS
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/5PRELIMINARIESLOT 1.1 : OMBIKA GATE
49 Clause 5.1: Definition of “nominated Sub-Contractor” Item
50 Clause 5.2 : Objection to Nomination Item
51 Clause 5.3 : Payments to nominated Sub-Contractors Item
52 Clause 5.4 : Evidence of Payments Item
A.6 - STAFF AND LABOUR
53 Clause 6.1 : Engagement of Staff and Labour Item
54 Clause 6.2 : Rates of Wages and Conditions of Labour Item
55 Clause 6.3 : Persons in the Service of the Employer Item
56 Clause 6.4 : Labour Laws Item
57 Clause 6.5 : Working Hours Item
58 Clause 6.6 : Facilities for Staff and Labour Item
59 Clause 6.7 : Health and Safety Item
60 Clause 6.8 : Contractor’s Superintendence Item
61 Clause 6.9 : Contractor’s Personnel Item
62 Clause 6.10 : Records of Contractor’s Personnel and Equipment Item
63 Clause 6.11 : Disorderly Conduct Item
A.7 – PLANT, MATERIALS AND WORKMANSHIP
64 Clause 7.1 : Manner of Execution Item
65 Clause 7.2 : Samples Item
66 Clause 7.3 : Inspection Item
67 Clause 7.4 : Testing Item
68 Clause 7.5 : Rejection Item
69 Clause 7.6 : Remedial work Item
70 Clause 7.7 : Ownership of Plant and Materials Item
71 Clause 7.8 : Royalties Item
Carried to Collection N$
A.8 – COMMENCEMENT, DELAYS AND SUSPENSION
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/6PRELIMINARIESLOT 1.1 : OMBIKA GATE
72 Clause 8.1 : Commencement of Works Item
73 Clause 8.2 : Time for Completion Item
74 Clause 8.3 : Programme Item
75 Clause 8.4 : Extension of Time for Completion Item
76 Clause 8.5 : Delays Caused by Authorities Item
77 Clause 8.6 : Rate of Progress Item
78 Clause 8.7 : Delay Damages Item
79 Clause 8.8 : Suspension of Work Item
80 Clause 8.9 : Consequences of Suspension Item
81 Clause 8.10 : Payment for Plant and Materials in Event of Suspension Item
82 Clause 8.11 : Prolonged Suspension Item
83 Clause 8.12 : Resumption Work Item
A.9 – TESTS ON COMPLETION
84 Clause 9.1 : Contractor’s Obligation Item
85 Clause 9.2 : Delayed Tests Item
86 Clause 9.3 : Retesting Item
87 Clause 9.4 : Failure to Pass Tests on Completion Item
A.10 – EMPLOYER’S TAKING OVER
88 Clause 10.1 : Taking over of the Works and Sections Item
89 Clause 10.2 : Taking Over of Parts of the Works Item
90 Clause 10.3 : Interference with Tests on Completion Item
91 Clause 10.4 : Surfaces Requiring Reinstatement Item
Carried to Collection N$
A.11 – DEFECTS LIABILITY
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/7PRELIMINARIESLOT 1.1 : OMBIKA GATE
92 Clause 11.1 : Completion of Outstanding work and Remedying Defects Item
93 Clause 11.2 : Cost of Remedying Defects Item
94 Clause 11.3 : Extension of Defects Notification Period Item
95 Clause 11.4 : Failure to Remedy Defects Item
96 Clause 11.5 : Removal of Defective Work Item
97 Clause 11.6 : Further Tests Item
98 Clause 11.7 : Right of Access Item
99 Clause 11.8 : Contractor to Search Item
100 Clause 11.9 : Performance Certificate Item
101 Clause 11.10 : Unfulfilled Obligations Item
102 Clause 11.11 : Clearance of Site Item
A.12 – MEASUREMENT AND EVALUATION
103 Clause 12.1 : Works to be Measured Item
104 Clause 12.2 : Method of Measurement Item
105 Clause 12.3 : Evaluation Item
106 Clause 12.4 : Omissions Item
A.13– VARIATIONS AND ADJUSTMENTS
107 Clause 13.1 : Right to Vary Item
108 Clause 13.2 : Value Engineering Item
109 Clause 13.3 : Variation Procedure Item
110 Clause 13.4 : Payment in Applicable Currencies Item
111 Clause 13.5 : Provisional Sums Item
112 Clause 13.6 : Daywork Item
113 Clause 13.7 : Adjustments for Changes in Legislation Item
114 Clause 13.8 : Adjustment for Changes in Cost Item
Carried to Collection N$
A.14– CONTRACT PRICE AND PAYMENT
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/8PRELIMINARIESLOT 1.1 : OMBIKA GATE
115 Clause 14.1 : The Contract Price Item
116 Clause 14.2 : Advance Payment Item
117 Clause 14.3 : Application for interim Payment Certificates Item
118 Clause 14.4 : Schedule of Payments Item
119 Clause 14.5 : Plant and Materials intended for the Works Item
120 Clause 14.6 : Issue of interim Payment Certificates Item
121 Clause 14.7 : Payment Item
122 Clause 14.8 : Delayed Payment Item
123 Clause 14.9 : Payment of Retention Money Item
124 Clause 14.10 : Statement at Completion Item
125 Clause 14.11 : Application for Final Payment Certificate Item
126 Clause 14.12 : Discharge Item
127 Clause 14.13 : Issue of Final Payment Certificate Item
128 Clause 14.14 : Cessation of Employer’s Liability Item
129 Clause 14.15 : Currencies of Payment Item
A.15– TERMINATION BY EMPLOYER
130 Clause 15.1 : Notice to Correct Item
131 Clause 15.2 : Termination by Employer Item
132 Clause 15.3 : Valuation at Date of Termination Item
133 Clause 15.4 : Payment after Termination Item
134 Clause 15.5 : Employer’s Entitlement to Termination Item
Carried to Collection N$
A.16– SUSPENSION AND TERMINATION BY CONTRACTOR
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/9PRELIMINARIESLOT 1.1 : OMBIKA GATE
135 Clause 16.1 : Contractor’s Entitlement to Suspend Work Item
136 Clause 16.2 : Termination by Contractor Item
137 Clause 16.3 : Cessation of Work and Removal of Contractor’s Equipment Item
138 Clause 16.4 : Payment on Termination Item
A.17 – RISK AND RESPONSIBILITY
139 Clause 17.1 : Indemnities Item
140 Clause 17.2 : Contractor’s Care of the Works Item
141 Clause 17.3 : Employer’s Risks Item
142 Clause 17.4 : Consequences of Employer’s Risks Item
143 Clause 17.5 : Intellectual and Industrial Property Rights Item
144 Clause 17.6 : Limitation of Liability Item
A.18 – INSURANCE
145 Clause 18.1 : General Requirements for Insurance Item
146 Clause 18.2 : Insurance for Works and Contractor’s Equipment Item
147 Clause 18.3 : Insurance against Injury to Persons and Damage to Property Item
148 Clause 18.4 : Insurance for Contractor’s Personnel Item
A.19 – FORCE MAJEURE
149 Clause 19.1 : Definition of Force Majeure Item
150 Clause 19.2 : Notice of Force Majeure Item
151 Clause 19.3 : Duty to Minimise Delay Item
152 Clause 19.4 : Consequences of Force Majeure Item
153 Clause 19.5 : Force Majeure Affecting Subcontractor Item
154 Clause 19.6 : Optimal Termination, Payment and Release Item
155 Clause 19.7 : Release from Performance under the law Item
Carried to Collection N$
A.20– CLAIMS, DISPUTES AND ARBITRATION
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/10PRELIMINARIESLOT 1.1 : OMBIKA GATE
156 Clause 20.1 : Contract’s Claim Item
157 Clause 20.2 : Appointment of the Dispute Adjudication Board Item
158 Clause 20.3 : Failure to Agree to Dispute Adjudication Board Item
159 Clause 20.4 : Obtaining Dispute Adjudication Board’s Decision Item
160 Clause 20.5 : Amicable Settlement Item
161 Clause 20.6 : Arbitration Item
162 Clause 20.7 : Failure to Comply to Dispute Adjudication Board’s Decision Item
163 Clause 20.8 : Expiry of Dispute Adjudication Board’s Appointment Item
SECTION B : MODEL PRELIMINARIES
B.1 – SUPPLEMENTARY DOCUMENTATION
164 B1.1 : Bills of Quantities
These Bills of Quantities have been prepared in accordance with the SixthEdition (Revised) of the Standard System of Measuring Building Work1999 including all amendments and addendum thereto as issued by theAssociation of South African Quantity Surveyors.
Any remeasurement of work required during the contract will be similarlyremeasured in accordance with the above system of measurement.
In addition, the items in these Bills of Quantities are deemed to be readand priced in conjunction with and the descriptions regarded as amplifiedby the Model Preambles for Trades as recommended and published by theAssociation of South African Quantity Surveyors (2008 Edition) and noclaim arising from brevity of description of items fully described in the saidModel Preambles for Trades will be entertained. Item
165 B1.2 : Provisional bills of quantities N/A
166 B1.3 : Availability of construction documentation for contracts based on billsof quantities Item
167 B1.4 : Name of Architect, Quantity Surveyor and other Consultants:
ENGINEER
PDNA Holdings (Pty) Ltd represented by PDNA International25 Scott StreetWaverleySouth Africa2090Telephone No.: +27 11 566 8300Fax No.: +27 11 566 8600
Carried to Collection N$
ELECTRICAL AND MECHANICAL ENGINEERs
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/11PRELIMINARIESLOT 1.1 : OMBIKA GATE
PDNA Holdings (Pty) Ltd represented by PDNA International25 Scott StreetWaverleySouth Africa2090Telephone No.: +27 11 566 8300Fax No.: +27 11 566 8600
CIVIL AND STRUCTURAL ENGINEERS
PDNA Holdings (Pty) Ltd represented by PDNA International25 Scott StreetWaverleySouth Africa2090Telephone No.: +27 11 566 8300Fax No.: +27 11 566 8600
QUANTITY SURVEYORS
PDNA Holdings (Pty) Ltd represented by PDNA International25 Scott StreetWaverleySouth Africa2090Telephone No.: +27 11 566 8300Fax No.: +27 11 566 8600
ARCHITECT
Crafford & Crafford Architects Without Boundaries in association withBob Mould Architects (Windhoek)No. 7 – 1
stStreet
Menlo ParkSouth Africa0081Telephone No.: +27 12 362 3992Fax No.: +27 12 362 9025 Item
168 B1.5 : Lodging and scrutiny of priced bills of quantities Item
The attention of the Tenderer is directed to the fact that his original pricedBills of Quantities used for tendering purposes must be completed inblack ink and must be submitted together with the Form of Tender.
The use of correcting fluid and failure to initial every page may result inthe disqualification of the Tender.
Carried to Collection N$
169 B1.6: Meaning of words Item
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/12PRELIMINARIESLOT 1.1 : OMBIKA GATE
170 B1.7 : Performance guarantee by the Contractor Item
The full security for the due fulfilment of all obligations under this contractis to remain in force after the 60 (sixty) days after the issue of the PracticalCompletion certificate.
No guarantee containing any clause which allows the financial institutionproviding such guarantee to withdraw from their undertaking before 60(SIXTY) calendar days after the date of issue of the Practical CompletionCertificate by the Engineer nor any guarantee stipulating an expiry date,will be acceptable by the Employer.
Notwithstanding the above, the guarantee will only be returned to thecontractor after receipt of satisfactory proof that the contractor has metall his obligations under any and all selected and nominated sub-contractagreements applicable to this contract.
171 B1.8 : Payment guarantee by Employer N/A
172 B1.79: Waiver of contractor’s lien Item
173 B1.10: Signing powers Item
174 B1.11 : Tenders Item
Notwithstanding anything contained in this clause tenders shall be validfor a period of ninety days (90) from the closing date of tenders
The Employer reserves the right to correct any arithmetical or other errorsin the extension of the rates and totals in the tender and / or to adjust anyrates that are considered by him to be imbalanced and unacceptable. Suchadjustments will be done without affecting the Tender Sum.
Tenderers shall complete all the information requested on the Form ofTender and provide copies of all supporting documentation requested onthe Form of Tender and clause B1.5.
Tenders shall be submitted on all official forms and shall NOT be qualifiedby the Tenderer’s own conditions of tender.In the event of discrepancies in the prices quoted in the Form of Tender, inwords and those quoted in figures, the words shall control.
Tenderes are referred to the Form of Tender for the closing date of theTender.
Failure to comply with these requirements will disqualify the Tender.
Carried to Collection N$
175 B1.12 : Inspection of documents Item
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/13PRELIMINARIESLOT 1.1 : OMBIKA GATE
The first two sentences are amended to read as follows:
The project drawings illustrating the scope of the Works and any othersupplementary documentation (including The Conditions of Contract forConstruction for Building and Engineering Works Designed by theEmployer as issued by the Federation Internationale des Ingenieurs-Conseils (FIDIC), First Edition 1999, Model Preliminaries and ModelPreambles for Trades) can be inspected at the offices of the Engineerduring office hours.
Notwithstanding any information supplied on the drawings or in these Billsof Quantities, the Tenderer, as a pre-requisite of submitting a tender, isinstructed to inspect the site and to examine the drawings, contractdocuments, etc. and to make himself thoroughly acquainted with thenature and requirements of the Works / contract before the submission ofhis tender, as no claim whatsoever will be entertained through theTenderer having failed to do so.
B.2 – THE SITE
176 B2.1 : Site and site boundaries Item
The site of the Works is situated at the Ombika Gate area in the EtoshaNational Park, Namibia (see attached site plan layout).
177 B2.2 : Area of the works Item
The area of the works to be occupied by the contractor, any restriction tothe area and the limit of access or exit will be pointed out to the contractorby the engineer on handing over of the site.
Storage space for materials and site management offices shall be locatedby the Engineer.
178 B2.3 : Boundary beacons, setting out pegs and master datum Item
The Contractor shall notify the Engineer if any encroachments of adjoiningfoundations, buildings, structures, pavements, etc. exist, so that the necessaryarrangements can be made for the rectification of such encroachments.
179 B2.4 : Site soil investigation Item
A geotechnical report is available for downloading in PDF format on the“Procurements” page on the Employer’s website www.mcanamibia.organd the Tenderer is also advised, before the submission of his tender, toinspect the site to ascertain the exact nature of the ground as no extra willbe granted due to the Tenderer having failed to comply with the aboveinstruction. Item
Carried to Collection N$
180 B2.5 : Viewing of the site Item
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/14PRELIMINARIESLOT 1.1 : OMBIKA GATE
The Tenderer is strongly advised to inspect the site and make himselfthoroughly acquainted with the nature and extent of the works, the site
conditions pertaining to power and water supply, transport facilities,condition of adjacent existing buildings and also access to the site, limitationsand availability of working space, etc. before submitting his tender as noextras arising out of his failure to do so will be entertained. Item
181 B2.6: Existing premises occupied Item
182 B2.7: Dimensional accuracy of work executed under the previous contract Item
183 B2.8 : Patent defects of work executed under the previous contract Item
184 B2.9 : Existing known services Item
Existing services and points of connection are shown on the site plan or willbe pointed out on the site by the Engineer.
185 B2.10 : Unknown services Item
186 B2.11 : Protection of trees, etc.
Natural vegetation on the project site is to be preserved as far as possibleand no trees will be removed or branches cut off without prior writtenconsent of the Engineer.
All existing trees that are not to be removed must be clearly marked withhazard warning tape and adequately protected from damage. Suchprotection and tape is to remain in position until the completion of thecontract or any extension thereof. Item
187 B2.12 : Articles of value Item
188 B2.13 : Inspection of nearby properties etc. Item
B.3 – MANAGEMENT OF CONTRACT
189 B3.1 : Management of works Item
190 B3.2 : Programming of the works Item
The contract shall be programmed by the contractor in accordance withalternative A.
The programme is to be of a format to the approval of the Engineer.
Carried to Collection N$
191 B3.3 : Progress meetings
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/15PRELIMINARIESLOT 1.1 : OMBIKA GATE
Progress meetings will be held on the project site once every monthand shall be attended by the Contractor, his site representative, his selectedsub-contractors, Consultants and representatives of the User Ministry and theEmployer.
Should any of the Consultants and / or representatives of the Employer haveto make separate trips to the project site for any reason, which is in theopinion of the Engineer due to the fault of the Contractor, the cost of suchtrips will be at the Contractor’s expense. Item
192 B3.4 : Technical meetings
Technical meetings will be held on the project site once every two weeks andshall be attended by the Contractor, his site representative, his selected sub-contractors, Consultants and representatives of the User Ministry and theEmployer.
Should any of the Consultants and / or representatives of the Employer haveto make separate trips to the project site for any reason, which is in theopinion of the Engineer due to the fault of the Contactor, the cost of suchtrips will be at the Contractor’s expense. Item
B.4 – MATERIALS AND WORKMANSHIP
193 B4.1 : Samples of materials Item
194 B4.2 : Samples of workmanship and mockups Item
195 B4.3 : Ordering of materials
The Contractor will be solely responsible for any delay in the delivery ofMaterials required for the execution and completion of the Works. Item
B.5– TEMPORARY WORKS AND PLANT
196 B5.1 : Deposits and fees Item
197 B5.2 : Enclosure of works Item
198 B5.3 : Pavement crossings and parking meters Item
199 B5.4 : Advertising Item
200 B5.5 : Plant and equipment
Add the following clause:
Materials stored on site for use as formwork and shuttering will be deemedTo be plant and equipment and will not be valued in monthly progressCertificates as “unfixed materials on site” Item
Carried to Collection N$
201 B5.6 : Special scaffolding Item
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/16PRELIMINARIESLOT 1.1 : OMBIKA GATE
No special scaffolding is measured, as these Bills of Quantities are based on theStandard System for Measuring Building Work (6
thEdition). (Revised)
All scaffolding required for this contract for the use of the workmen (includingall domestic and selected sub-contractors) shall be provided by the MainContractor.
202 B5.7 : Contractor’s offices and sheds Item
Under NO circumstances may any of the buildings at any stage be used fortemporary accommodation for workers, contractor’s offices or the storageof materials.
203 B5.8 : Offices Item
204 B5.9 : Office of the clerk of works Item
205 B5.10 : Main noticeboard
One main noticeboard per project site, complying with the requirements ofThe Namibia Institute of Architects and described in English, shall be provided.
The lettering shall be to the Engineer’s approval and shall include the crests ofthe relevant professional institutes and associations. Item
206 B5.11 : Sub-contractors’ noticeboard Item
B.6– TEMPORARY SERVICES
207 B6.1 : Water Item
The contractor shall provide water for the works in accordance withalternative A.
Contractors must note that the Employer does not accept anyresponsibility for any additional cost that the Contractor may incur due tofailure or inadequacy of any supply already available on the site.
208 B6.2 : Electricity and lighting Item
The contractor shall provide electricity for the works in accordance withalternative A.
Contractors must note that the Employer does not accept anyresponsibility for any additional cost that the Contractor may incur due tofailure or inadequacy of any supply already available on the site.
Carried to Collection N$
209 B6.3 : Telephones
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/17PRELIMINARIESLOT 1.1 : OMBIKA GATE
The Contractor shall install a facsimile machine in the site office in additionto a telephone.
Should the Main Contractor be unable to procure a temporary telephone linefrom Telecom Namibia for the site office, he shall, in areas where cellulartelephone coverage exists, ensure the foreman has a cellular telephone inhis possession for use on the site. Item
210 B6.4 : Toilets Item
The contractor shall provide toilets in accordance with alternative A.
B.7– PRIME COST AND PROVISIONAL SUMS
211 B7.1 : Cash discount Item
All prime cost items and provisional sums are nett and do not include acash discount, nor will the Contractor be allowed or entitled to a cashdiscount.
An item for profit for work executed by specialist sub-contractors isincluded after each Provisional Sum for percentage mark-up pricing by theContractor (if so desired).
Any such percentage mark-up priced by the Contractor on Provisionalsums in this contract, will be used as a basis to determine the final amountfor profit to be paid to the Contractor in direct proportion to the final costof the relevant selected sub-contracts.
212 B7.2 : Taking delivery and fixing of prime cost items Item
213 B7.3 : Nominated or selected sub-contract documents
These sub-contracts shall not be nominated but Selected Sub-Contractsand shall be executed using the Fidic Sub-Contract Agreement as issuedby the Federation Internationale des Ingenieurs-Conseils (FIDIC), FirstEdition 2009
These documents shall be supplied by the Main Contractor at his own cost. Acopy of each signed selected sub-contract document shall be delivered to theEngineer. Item
214 B7.4 : Attendance on nominated or selected sub-contractors
Items for special attendance upon selected sub-contractors have beenmeasured after each Provisional Sum for pricing by the Main Contractor (ifdesired)
Amounts priced for attendance shall remain fixed unless, in the opinion ofthe Engineer, the scope of the sub-contract has been changed substantially. Item
Carried to Collection N$
215 B7.5 : Fuel, power and water for commissioning of mechanical and other
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/18PRELIMINARIESLOT 1.1 : OMBIKA GATE
specialised installations Item
B.8– FINANCIAL ASPECTS
216 B8.1 : Sales taxes Item
Delete the whole of this clause and replace with the following:
Provision is made in the separate Bid invitation for inclusion of ValueAdded Tax (VAT)
217 B8.2 : Contract Price Adjustment Provisions N/A
No adjustment in this regard will be made.
218 B8.3 : Payment of preliminaries Item
Payment of preliminaries will be calculated from the priced items withinthe preliminaries in accordance with alternative B.
219 B8.4 : Adjustment of preliminaries Item
The adjustment of preliminaries will be on the basis of fixed price, valuerelated and time related items in accordance with method 2.
The successful Tenderer, shall submit together with his priced Bills ofQuantities written confirmation of a breakdown of each item priced in thePreliminaries bill accordance to the following three categories:
a) Fixed (N$)b) Value Related (N$)c) Time Related (N$)
Failing which Method “1” shall be applicableThe final adjustment of the Preliminaries, for any reason whatsoever, shallbe done at the end of the contract period.
In addition to the exclusions mentioned in the third paragraph of thisclause, it shall be deemed that “day works” be added as a fourth exclusion.
220 B8.5 : Certificate payment projection Item
221 B8.6 : Day works Item
Payment of any work on the basis of day works will only be made,provided that written authorization is obtained from the Engineer priorcommencing with daywork.
Notwithstanding anything contained in this clause, the signature of theEngineer shall not indicate acceptance of quantum, value or method ofvaluation of the work executed thereunder. The quantum of these dayworks and the method of valuation will be decided by the Engineer.
Carried to Collection N$222 B8.7 : Information supplied by contractor
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/19PRELIMINARIESLOT 1.1 : OMBIKA GATE
Should the Main Contractor or any of his domestic or selected sub-contractors execute any of the work which, in his opinion, constitutes avariation to the contract and is not covered in the Bills of Quantities, andhence results in a loss or expense to the Contractor. The onus rests on theContractor to inform the Engineer in writing within one calendar Monthfrom the date on which the work was executed, failing which the executedwork shall be deemed to be at the Contractor’s own expense. Item
B.9– GENERAL
223 B9.1 : Protection Item
224 B9.2 : Protection of existing and / or partially occupied works Item
225 B9.3 : Safety
Delete clause and replace with the following clause:
“The Contractor shall adhere to all necessary requirements regardingMachinery and Occupational Safety, as stipulated in the Labour Act No. 6 of1992, gazetted in Government Gazette No. 1617 as at 1
stAugust 1997.” Item
226 B9.4 : Site security Item
227 B9.5 : Notice before covering work Item
228 B9.6 : Disturbance Item
229 B9.7 : Clearing and cleaning Item
230 B9.8 : Vermin Item
231 B9.9 : Overhand work Item
232 B9.10 : Jobbing Item
SECTION C : SPECIFIC PRELIMINARIES
233 Clause C1.1 : Workmens’s Compensation Insurance
The Contractor and Selected Sub-Contactors shall insure workmen interms of the Workmen’s Compensation Act of 1941 and shall depositimmediately with the Engineer written confirmation of evidence ofregistration under the Workmen’s Compensation Act when signing theContract.
Persons not falling under the above-mentioned Act must be insured underAccident Insurance to the satisfaction of the Engineer. Item
Carried to Collection N$
234 Clause C1.2 : Non cession of monies
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/20PRELIMINARIESLOT 1.1 : OMBIKA GATE
The Contractor shall not cede or assign his rights or claims to any moniesdue or to become due under this contract, as no cession or assignment willbe recognised by the Employer. Item
235 Clause C1.3 : Site Instructions
Site instructions issued by any of the Consultants on site are to berecorded in triplicate in a site instruction book which is to be maintainedon site by the Contractor.
It shall be the Main Contractor’s responsibility to ensure that any verbalInstructions given on the site are recoded in the site instruction book andSigned by the Engineer. Item
236 Clause C1.4 : Employment of Namibian People
No employee of the Contractor originating from any other country shallenter Namibian territory without a work permit and a residence permit,obtainable from the Ministry of Home Affairs.
It is an explicit condition of this Contract that no unskilled or semi-skilledlabour may be employed on the works unless he or she is a Namibiancitizen.
It is a further condition that a minimum of 30% skilled labour employed onthe works, shall be Namibian citizens.
Where a Tenderer’s labour component consists of more than 30% or up to100% Namibian citizens, the requirement stipulated below still applies.
“The Tenderer is encouraged to employ Namibian citizens for skilled andsemi-skilled artisans and employ unskilled labour from the areas ofintervention."
“All Namibian skilled artisan and unskilled employees are to beregistered in accordance with the Social Security Act of 1994 (Act No. 34of 1994) and the Tenderer must submit Certificates of good standingfrom the Social Security Commission, which are obtainable from theCommission’s offices. Item
237 Clause C1.5 : As built drawings (structural concrete)
The position of construction joints and the extent of individual concretepours are to be recorded by the Contractor on the Structural Engineer’sdrawings and are to be submitted to the Engineer and the StructuralEngineer for their records. Item
Carried to Collection N$
238 Clause C1.6 : As built drawings (plumbing and drainage)
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/21PRELIMINARIESLOT 1.1 : OMBIKA GATE
The Contractor is to allow for one set of plumbing and drainage drawings“marked up” by the sub-contractor to indicate for internal and externalinstallations as executed on the project site ,to facilitate the preparation ofthe “as built” drawings to be and submitted by the Engineer to the UserMinistry. Item
239 Clause C1.7 : Specific Products
The Contractor is advised that his rates must be based on specific productsor items as described in these Bills of Quantities. He may only deviate fromthe designated product or item to another product or item after writtenconsent has been obtained from the Engineer, and only after theContract has been awarded to the successful Tenderer.
Where applicable, the cost of such substitution with another product oritems shall be adjusted by the Engineer in the final account for this project.
The Contractor shall take delivery of, handle, store, use, apply and / or fixall proprietary branded products or items in strict accordance with themanufacturer’s instructions after consultation with the manufacturer’sauthorised representative.
Where no specific product or item is specified, but a product or item isreferred to as “approved:, the Contractor shall obtain written approvalfrom the Engineer for the product or item, he intends to use in the Works,prior to ordering such products / items or using such products / items in theWorks. Item
240 Clause C1.8 : Proprietary branded products
The Contractor shall take delivery of, handle, store, use, apply and / or fixall proprietary branded products in strict accordance with themanufacturer’s instructions after consultation with the manufacturer’sauthorised representative. Item
241 Clause C1.9 : Labour record
At the end of each week the Contractor shall provide the Engineer with awritten record, in schedule form, reflecting the number, description andcitizenship of tradesmen and labourers employed by him and all sub-contractors on the works each day. Item
242 Clause C1.10 : Plant record
At the end of each week the Contractor shall provide the Engineer with awritten record, in schedule form, reflecting the number, type and capacityof all plant, excluding hand tools, currently used on the works. Item
Carried to Collection N$
243 Clause C1.11 : Guarantee
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/22PRELIMINARIESLOT 1.1 : OMBIKA GATE
Where guarantees are called for, the Contractor shall obtain a writtenguarantee, addressed to the Employer, from the firm supplying thematerials and / or doing the work and shall deliver same to the Engineerupon the certified final completion of the contract.
The guarantee shall state that the materials, workmanship and installationare guaranteed for a specified period from the date of certified finalcompletion of the contract and that any defects that may arise during thespecified period shall be made good at the expense of the firm supplyingthe materials and doing the work, upon written notice of Engineer to do so. Item
244 Clause C1.12 : Registration of Firm as a Company and a Namibian Tax Payer
The Tenderer must provide proof that he is registered as a Namibian TaxPayer. A copy of form 6-0/0020 or an original document ofcorrespondence with the Ministry of Finance proving registration as aNamibian Tax Payer must be attached.
The Tenderer must provide a copy of the firm’s registration form, (Ministryof Trade and Industry) containing names of responsible person(s) listed atregistration. Item
245 Clause C1.13 : Open Fires
No open fires will be permitted, except in such places as are approved bythe Engineer. Any workmen lighting fires in unauthorised places are to beimmediately dismissed. Item
246 Clause C1.14 : Alternative Temporary access, etc. to site where necessary
The Contractor shall allow here for any alternative temporary access tothe site, including taking out and replacing fencing and gates, boundarywalls, etc. if necessary to facilitate access to the project site, includingobtaining the necessary permission and / or permits from the relevantauthorities or neighbours, as well as the removal of such access upon thecompletion and making good all to match existing and leaving the siteclean and in a perfect condition. Item
247 Clause C1.15 : Final Account
The Contractors attention is drawn to the fact that the various foundation,plumbing and drainage and external works items, as well as items marked“Provisional” in these Bills of Quantities are subject to variation and willbe re-measured and adjusted at the rates submitted in the tender Bills ofQuantities during the preparation of the Final Account.
Should the Contractor not endeavour to finalise the Final Account for thiscontract with the Engineer within 3 (THREE) calendar months after receiptof same, the final account sum as reflected in the Engineer’s Final Accountwill be taken to be the final cost of the project and no further negotiationswill be entertained by the Employer or the Engineer. Item
Carried to Collection N$
248 Clause C1.16 : Testing and Handing over Specialist Installations
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/23PRELIMINARIESLOT 1.1 : OMBIKA GATE
i) The Contractor shall satisfy himself that the installation is inaccordance with the specifications and any variations that havebeen issued, before requesting the Engineer to inspect the works.
ii) The Contractor shall at his own expense provide all testingequipment and materials for carrying out the tests.
iii) Prior to inspection the Contractor shall furnish the Engineer with allwiring maintenance manuals, operation methods of procedure,circuit drawings, etc.
iv) At the taking over inspection, the Contractor will be issued with acertificate stating all defects of the installation or part thereof atthat time.
v) A “Taking over Certificate” will be issued once all defects (asmentioned in (iv) above) have been rectified.
vi) Only on issue of the “Taking over Certificate” will retention bereduced, the contract surety released and the guarantee andmaintenance period will commence from that date. Item
249 Clause C1.17 : Drawings and dimensions
All drawings, wherever their origin, are to be issued to the project site, orto any other person(s) only through the office of the Engineer, bearing theEngineer’s office stamp.
The Contractor shall keep a date register of all drawings issued at theproject site at all times.
Any drawings not issued through the Engineer to the project site, will beused at the Contractor’s own risk and should any work be incorrect due tothe use of unauthorised drawings, any rectification of work done inaccordance with unauthorised drawings, shall be at the expense of theContractor.
All drawings used on site must be properly mounted on suitable sheetmaterial, or otherwise protected to the approval of the Engineer, andkept in good condition. Any drawings that become bleached orunreadable, must be returned to the Engineer for replacement. Anyrectification of work done in accordance with unreadable drawings, shallbe at the expense of the Contractor. Item
Carried to Collection N$
250 Clause C1.18 : Blasting
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/24PRELIMINARIESLOT 1.1 : OMBIKA GATE
The Contractor shall take all responsibility during blasting operations,should any be necessary, and must observe all conditions as set for and inthe Government and Local Authority Regulations. The use of explosives isleft to the discretion of the Contractor who must indemnify the Employeragainst any claims for damages to persons or property on or near theproject site, from any cause whatsoever arising out of the use ofexplosives.
The Contractor will be held responsible for and must immediately makegood, at his own expense, any damage that may occur through the use ofexplosives. Item
251 Clause C1.19 : Revenue Stamps
The Contractor must allow for any necessary revenue stamps required inconnection with The Conditions of Contract for Construction for Buildingand Engineering Works Designed by the Employer as issued by theFederation Internationale des Ingenieurs-Conseils (FIDIC), First Edition1999 and Guarantee in accordance with the Stamp Duty Act 1911 or anyamendment thereto. Item
252 Clause C1.20 : Earned Value Management
Within 28 days signing the contract, the Contractor shall submit a revisedProgram of Works to the Engineer for his acceptance.The Program of Works shall be in bar chart format and shall indicate themajor work components (including design and procurement) and the mainsub-activities. The program shall have a unit of time of one month (withpart months indicated), unless the Engineer indicates otherwise.The program (or, if necessary, a secondary program Similarly constructed)shall clearly indicate the various work teams by discipline, includingspecialist sub-contracts and suppliers, as well as the Contractor's majorplant requirements, in order to demonstrate sequencing and non-conflictof resources.The Engineer may request summary versions of the program, or additionaldetail for critical sections. The Contractor shall comply with all suchrequests.
Once a Work Program has been accepted by the Engineer it shall remainas the current version until such time as the Engineer instructs theContractor to update the program. The Contractor shall not modify hisprogram without such instruction from the Engineer. Specifically, theContractor's progress reports shall relate to the current program, and anyindicated.
Carried to Collection N$
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/25PRELIMINARIESLOT 1.1 : OMBIKA GATE
The exact format of the Work Program shall be to the approval of theEngineer, but shall comprise the minimum of a detailed, resource and costloaded schedule for the work, using Prima Vera (P6 enterprise) or a similarapproved software system. This schedule, to be finalised and agreedbetween Employer and Contractor, will be used to measure Earned Valueto enable the Contractor and Employer to monitor the progress of theproject in terms of integrated cost, schedule and technical performancemeasures. In order for Earned Value to be implemented, the Contractor willprovide a system that can accurately and demonstrably measure thefollowing three fundamental factors:
i. The PLANNED VALUE COST also known as the Budgeted Cost of WorkScheduled (BCWS). This is the amount of expenditure the Employeranticipated he would have spent at time of reporting.
ii. The ACTUAL COST of the progress made, known as the Actual Cost ofWork Performed (ACWP). This is the actual amount of expenditure theEmployer incurs at time of reporting.
iii. The EARNED VALUE, known as the Budgeted Cost of Work Performed.This is the percentage complete
Refer to attachment 1b. Item
Carried to Collection N$
MCAN/COMRFP/2A02002
TENDER DOCUMENT
Section No. 1 1/26PRELIMINARIESLOT 1.1 : OMBIKA GATE
Section No. 1
Bill No. 1
PRELIMINARIES
COLLECTION
Page No Amount
Total Brought Forward from Page No. 1/1
1/2
1/3
1/4
1/5
1/6
1/7
1/8
1/9
1/10
1/11
1/12
1/13
1/14
1/15
1/16
1/17
1/18
1/19
1/20
1/21
1/22
1/23
1/25
Carried to Final Summary N$