bill of materials
DESCRIPTION
pdf fileTRANSCRIPT
1/5Project Title: Proposed Two-Storey Residence
Location: Poblacion Ilaya Panay, CapizOwner: Mrs. Tara Ann Alayon Caragayan
S.No. Description Quantity Price/Unit Total Sub Total
1) Earthworks
1 Soil-Ground Fill 5 truck load 2200 11000 11000
2) CONCRETE WORKS
A) Footings
1 Portland Cement 60 bags 240 14400
2 Washed Sand 4 cu. Mts. 500 2000
3 Washed Gravel 8 cu. Mts. 900 7200
4 16mm Dia. @ 6.0 mts. RSB 50 bars 320 16000
5 No. 16 G.I Tie Wire 30 kg. 55 1650 41250
B) Footing Tie Beam
1 Portland Cement 30 bags 240 7200
2 Washed Sand 2 cu. Mts. 500 1000
3 Washed Gravel 4 cu. Mts. 900 3600
4 16mm Dia. @ 6.0 mts. RSB 44 bars 320 14080
5 10mm Dia. @ 6.0 mts. RSB 46 bars 130 5980
6 No. 16 G.I Tie Wire 20 kg. 55 1100 32960
C) Columns
1 Portland Cement 80 bags 240 19200
2 Washed Sand 4 cu. Mts. 500 2000
3 Washed Gravel 8 cu. Mts. 900 7200
4 16mm Dia. @ 9.0 mts. RSB 144 bars 530 76320
5 10mm Dia. @ 6.0 mts. RSB 220 bars 130 28600
6 No. 16 G.I Tie Wire 35 kg. 55 1925 135245
D) Wall Footing
1 Portland Cement 38 bags 240 9120
2 Washed Sand 2 cu. Mts. 500 1000
2/5Project Title: Proposed Two-Storey Residence
Location: Poblacion Ilaya Panay, CapizOwner: Mrs. Tara Ann Alayon Caragayan
S.No. Description Quantity Price/Unit Total Sub Total
3 Washed Gravel 4 cu. Mts. 900 3600
4 12mm Dia. @ 6.0 mts. RSB 26 bars 180 4680
5 10mm Dia. @ 6.0 mts. RSB 18 bars 130 2340
6 No. 16 G.I Tie Wire 25 kg. 55 1375 22115
E) Ground Floor Slab
1 Portland Cement 75 bags 240 18000
2 Washed Sand 4 cu. Mts. 500 2000
3 Washed Gravel 8 cu. Mts. 900 7200
4 10mm Dia. @ 6.0 mts. RSB 50 bars 130 6500
5 No. 16 G.I Tie Wire 15 kg. 55 825 34525
F) Second Floor Slab
1 Portland Cement 77 bags 240 18480
2 Washed Sand 4 cu. Mts. 500 2000
3 Washed Gravel 8 cu. Mts. 900 7200
4 10mm Dia. @ 6.0 mts. RSB 180 bars 130 23400
5 No. 16 G.I Tie Wire 30 kg. 55 1650 52730
G) Second Floor Beam
1 Portland Cement 35 bags 240 8400
2 Washed Sand 3 cu. Mts. 500 1500
3 Washed Gravel 6 cu. Mts. 900 5400
4 16mm Dia. @ 6.0 mts. RSB 80 bars 320 25600
5 10mm Dia. @ 6.0 mts. RSB 73 bars 130 9490
6 No. 16 G.I Tie Wire 30 kg. 55 1650 52040
H) Roof Beam & Lintel Beam
1 Portland Cement 35 bags 240 8400
2 Washed Sand 2 cu. Mts. 500 1000
3/5Project Title: Proposed Two-Storey Residence
Location: Poblacion Ilaya Panay, CapizOwner: Mrs. Tara Ann Alayon Caragayan
S.No. Description Quantity Price/Unit Total Sub Total
3 Washed Gravel 4 cu. Mts. 900 3600
4 16mm Dia. @ 6.0 mts. RSB 30 bars 320 9600
5 12mm Dia. @ 6.0 mts. RSB 22 bars 180 3960
6 10mm Dia. @ 6.0 mts. RSB 53 bars 130 6890
7 No. 16 G.I Tie Wire 35 kg. 55 1925 35375
I) Concrete Stair & Landing
1 Portland Cement 20 bags 240 4800
2 Washed Sand 2 cu. Mts. 500 1000
3 Washed Gravel 4 cu. Mts. 900 3600
4 16mm Dia. @ 6.0 mts. RSB 6 bars 320 1920
5 12mm Dia. @ 6.0 mts. RSB 15 bars 180 2700
6 10mm Dia. @ 6.0 mts. RSB 20 bars 130 2600
7 No. 16 G.I Tie Wire 15 kg. 55 825 17445
3) MASONRY WORKS
A) Concrete Hollow Block Wall
1 Portland Cement 70 bags 240 16800
2 Washed Sand 6 cu. Mts. 500 3000
3 Washed Gravel 12 cu. Mts. 900 10800
4 8mm Dia. @ 6.0 mts. RSB 115 bars 80 9200
5 4" CHB 4000 pcs. 12 48000
6 6" CHB 1700 pcs. 15 25500
7 No. 16 G.I Tie Wire 35 kg. 55 1925 115225
B) Plastering & Finishing
1 Portland Cement 150 bags 240 36000
2 Washed Sand 20 cu. Mts. 500 10000 46000
C) Septic Vault
4/5Project Title: Proposed Two-Storey Residence
Location: Poblacion Ilaya Panay, CapizOwner: Mrs. Tara Ann Alayon Caragayan
S.No. Description Quantity Price/Unit Total Sub Total
1 Portland Cement 20 bags 240 4800
2 Washed Sand 3 cu. Mts. 500 1500
3 Washed Gravel 6 cu. Mts. 900 5400
4 10mm Dia. @ 6.0 mts. RSB 30 bars 130 3900
5 No. 16 G.I Tie Wire 10 kg. 56 560
6 4" CHB 400 pcs. 12 4800 20960
4) Forms & Scaffoldings & Hardwares
1 300-2x2x12' Coco Lumber 1200 Bd. Ft. 18 21600
2 200-2x3x12' Coco Lumber 1200 Bd. Ft. 18 21600
3 Bamboo Pole (Medium size) 60 pcs. 100 6000
4 1/4x4'x8' Ord. Plywood 30 Shts. 400 12000
5 Hacksaw Blade 20 pcs. 65 1300
6 Allow. For assorted nails 15000 77500
5) Roof Framing (Truss-Rafter, Purlins, Facia Frames)
1 1/4"x2"x2"x20' Angle Bars 25 bars 900 22500
2 1/4"x1 1/2"x1 1/2"x20' Angle Bars 20 bars 800 16000
3 1/4"x1"x1"x20' Angle Bars 20 bars 350 7000
4 10mm Dia. @ 6.0 mts. RSB 8 bars 130 1040
5 1.2mm THK. x2"x3"x20' C-Purlins 33 bars 520 17160
6 Welding Rod (Wipeweld) 30 kilo 100 3000
7 Sphero Pre-pacoat 6 gallon 600 3600
8 Paint Thinner 3 gallon 200 600 70900
6) Roofing
1 .5mm THK. GI. Prepainted Longspan 100 lm 500 50000
2 .5mm THK. GI. Ridge Roll 27 lm 450 12150
3 .5mm THK. GI. Valley Gutter 6 lm 450 2700
5/5Project Title: Proposed Two-Storey Residence
Location: Poblacion Ilaya Panay, CapizOwner: Mrs. Tara Ann Alayon Caragayan
S.No. Description Quantity Price/Unit Total Sub Total
4 .5mm THK. GI. Wall Flashing 27 lm 450 12150
5 .5mm THK. GI. Gutter 40 lm 450 18000
6 .5mm THK. GI. Facia 40 lm 350 14000
7 Allow. For Rivets, Teks screw & Sealant 10000 119000
7) Doors & Windows
1 Panel Doors (1.00mx2.10m) 1 sets 4000 4000
2 Panel Doors (0.80mx2.10m) 7 sets 3500 24500
3 UPVC Doors (0.70mx2.10m) 3 sets 2000 6000
4 Sliding Window Glass W/ Alum. Frame 192 sq. ft. 250 48000
5 Fixed on Alum. Frame 163 sq. ft. 250 40750
6 Allow. For Hinges, Door Knobs, Teks screw & Sealant 15000 138250
8) Plumbing Works (Including fixtures, Fittings & Catch Basin etc.)
1 Water Closets Sets & Accessories 3 sets 3500 10500
2 Shower Sets & Accessories 2 sets 2000 4000
3 Kitchen Sink Stainless & Accessories 1 sets 3000 3000
4 20000 37500
9) Electrical Works
1 Allow. For Main Switch Panel 10000
2 Allow. For PVC conduits 5000
3 Allow. For electrical fitting, utility box, junction box & etc. 8000
4 Allow. For Lighting fixtures 15000
5 Allow. For Switches, convenience outlets, etc. 5000
6 Allow. For lines & other electrical materials 5000 48000
Total Material Cost 1108020
Allow. For Catch Basin, Fittings & other Plumbing materials