bill of quantities block 7b, no 7, san Ġwann t'għuxa, bormla · pdf file ·...

17
BOQ - RGP 18/2012 Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T BILL No. 1 DEMOLITION & REMOVAL WORKS Preambles A Rates are to include all ancillary costs for the successful execution of the items of work such as scaffolding, cranage/high up or other hauling equipment and Local Council and Warden fees as may be necessary. Claims for reimbursement of expenses in addition to the items of work listed hereunder shall be rejected. B Contractor to take all necessary precautions to prevent damage to existing structure and finishes. Contractor will repair at his own expense any damage caused, such as breakage of any 'xorok', during the execution of the works. Contractor shall also abide by all regulations and legislation regarding Health and Safety measures to be adopted for the safeguard of public and employees. The cost for such measures shall be deemed as included within the rates hereunder. C Before commencement of any works done on site, contractor is to provide the employer with detailed condition reports, including photographs of properties adjoining the site and which may be affected in any way by the works. The cost of these reports is deemed to be included in the items of work and no claims for additional payment shall be accepted. The contractor shall repair at his own expense any damage carried within site or to adjoining third party properties as a direct result of the execution of the works. D Contractor is to provide water and electricity supply required for the execution of the works. The cost for this shall be deemed as included in the rates for execution of the works and requests for additional payment shall be rejected. 1.01 Remove, load and cart away all movable or loose contents at roof level and dispose in an authorised site. 1.00 l.s. 1.02 Demolish and cart away existing roof structure over sitting room and main bedroom, remove surplus material and dispose material to an approved site. Rate is to include for propping of falsework and formwork. Refer to drawing RGP 04/2013 (01). 38.00 m² 1.03 Break up, load and cart away existing kontrabejt over entire roof structure. Care is to be taken not to damage underlying roof structure. Rate also includes the disposal of all resultant material in an authorised dumping site. Refer to drawing RGP 04/2013 (04). 90.00 m² 1.04 Demolish, load and cart away existing bathroom, including floor and wall tiles, sanitary ware, accessories and fixtures, and dispose of any resultant material in an authorised dumping site. Refer to drawing RGP 04/2013 (04). 1.00 l.s. Carried forward 1

Upload: buidung

Post on 24-Mar-2018

221 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Bill of Quantities

Block 7B, No 7, San Ġwann t'Għuxa, Bormla

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

BILL No. 1 DEMOLITION & REMOVAL WORKS

Preambles

A

Rates are to include all ancillary costs for the successful execution of

the items of work such as scaffolding, cranage/high up or other

hauling equipment and Local Council and Warden fees as may be

necessary. Claims for reimbursement of expenses in addition to the

items of work listed hereunder shall be rejected.

B

Contractor to take all necessary precautions to prevent damage to

existing structure and finishes. Contractor will repair at his own

expense any damage caused, such as breakage of any 'xorok', during

the execution of the works. Contractor shall also abide by all

regulations and legislation regarding Health and Safety measures to

be adopted for the safeguard of public and employees. The cost for

such measures shall be deemed as included within the rates

hereunder.

C

Before commencement of any works done on site, contractor is to

provide the employer with detailed condition reports, including

photographs of properties adjoining the site and which may be

affected in any way by the works. The cost of these reports is deemed

to be included in the items of work and no claims for additional

payment shall be accepted. The contractor shall repair at his own

expense any damage carried within site or to adjoining third party

properties as a direct result of the execution of the works.

D

Contractor is to provide water and electricity supply required for

the execution of the works. The cost for this shall be deemed as

included in the rates for execution of the works and requests for

additional payment shall be rejected.

1.01Remove, load and cart away all movable or loose contents at roof

level and dispose in an authorised site.1.00 l.s.

1.02

Demolish and cart away existing roof structure over sitting room and

main bedroom, remove surplus material and dispose material to an

approved site. Rate is to include for propping of falsework and

formwork. Refer to drawing RGP 04/2013 (01).

38.00 m²

1.03

Break up, load and cart away existing kontrabejt over entire roof

structure. Care is to be taken not to damage underlying roof structure.

Rate also includes the disposal of all resultant material in an

authorised dumping site. Refer to drawing RGP 04/2013 (04).

90.00 m²

1.04

Demolish, load and cart away existing bathroom, including floor and

wall tiles, sanitary ware, accessories and fixtures, and dispose of any

resultant material in an authorised dumping site. Refer to drawing

RGP 04/2013 (04).

1.00 l.s.

Carried forward

1

Page 2: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

Brought forward

1.05

Remove, load and cart away all existing internal and external

plumbing runs and electricity conduits and any rain water / foul water

drain pipes that will not be used (as instructed by the Architect in

Charge or his representative). Remove, load and cart away asbestos

water tank at roof level. Rate also includes the disposal of all resultant

material in an authorised dumping site and safety measures required,

expecially with respect to handling of asbestos.

1.00 l.s.

1.06

Relocate existing water tank at roof level to another location (as

instructed by the Architect in Charge or his representative). Rate shall

include for any works required to move the water tank. Rate also

includes any works necessary to temporarily restore the functionality

of the water tank.

1.00 l.s.

1.07

Demolish, load and cart away existing shed structure at roof level.

Rate also includes the disposal of all resultant material in an

authorised dumping site. (provisional)

1.00 l.s.

1.08

Remove, load and cart away existing kitchen wall tiles. Rate also

includes the disposal of all resultant material in an authorised

dumping site. (provisional)

17.00 sq.m.

Total Bill No. 1 carried to Summary

2

Page 3: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

BILL No. 2 CONSTRUCTION WORKS

Preambles

A

Rates are to include all ancillary costs for the successful execution of

the items of work such as scaffolding, cranage/high up or other

hauling equipment and Local Council and Warden fees as may be

necessary. Claims for reimbursement of expenses in addition to the

items of work listed hereunder shall be rejected.

B

Contractor shall take all necessary precautions to prevent damage to

existing structure and finishes. Contractor shall repair at his own

expense any damages caused, such as breakage of any 'xorok', during

the execution of the works. Contractor shall also abide by all

regulations and legislation regarding Health and Safety measures to

be adopted for the safeguard of the public, HA representatives and its

own employees. The cost for such measures shall be deemed as

included within the rates hereunder.

CAll soft stone is to be of first quality franka stone and is to be bedded

and jointed in gauged mortar.

D

In all items of work involving widening of existing, or creation of

new apertures, quoted prices are to include cost of reformation of neat

jambs and, where applicable, removal of masonry to 50 mm below

proposed finished floor level.

E

Before commencement of any works done on site, contractor is to

provide the Housing Authority with detailed condition reports by his

own architect, including photographs of properties adjoining the site

and which may be affected in any way by the works. The cost of these

reports is considered to be included in the items of work and no

claims for additional payment shall be accepted. The contractor shall

repair at his own expense any damage carried within site or to

adjoining third party properties as a direct result of the execution of

the works.

FRates are to include for the loading and carting away of resultant

material to an authorised dumping site.

GThe Contractor SHALL NOT carry out any works on the façade

before obtaining clearance in writing from the HA architect.

Carried forward

3

Page 4: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

Brought forward

2.01

Supply, transport, lay and compact concrete grade C25 to form

150mm thick reinforced concrete suspended slab over sitting room

and main bedroom. Rate is to include for all the necessary formwork,

falsework, vibration, smooth finish, and adequate curing.

Reinforcement measured seperately. Refer to drawing RGP 04/2013

(02).

38.00 m²

2.02

Supply, transport, hoist, lay (horizontal or vertical) and fix in position

C305 meshes in location specified in Item 2.01. Rate shall include for

all cutting and bending, as necessary and/or as indicated by the

architect in charge. Measurement will be taken net of overlaps.

38.00 m²

2.03

Formation of triangular cement/sand (mix 1:3) fillet, min. Dimensions

75mm x 75mm, at junction between the horizontal flat roof and wall. 55.00 m

2.04

Supply, transport, hoist and lay 100mm (average) thick bed of torba

laid to the required falls on a horizontal flat surface, tamped down,

wetted and consolidated as instructed by the architect in charge. Rate

is to include for all levelling and setting out required to achieve the

requested falls as per specifications and as instructed by the architect

in charge. No additional payment will be done for extra thickness

over and above the mentioned benchmark in layer of ''torba'', unless

otherwise requested by the architect in charge. Refer to drawing RGP

04/2013 (04).

90.00 m²

2.05

Supply, transport, hoist and lay concrete Grade C25 on torba of Item

2.05, 100mm thick laid to the required falls (in one or more

directions) as instructed by the architect in charge. Rate is to include

for all levelling and setting out required to achieve the requested falls

and for formation of bays not greater than 3.5 m x 3.5m, also

allowing for 12mm wide expansion joints between bays, as per

specifications and as instructed by the architect in charge. No extra

payment will be approved as regards to extra laid concrete thickness.

Rate shall also include for adequate curing of the concrete as

indicated and requested by the architect in charge. Refer to drawing

RGP 04/2013 (04).

90.00 m²

2.06

Break up and remove all spalling concrete up to a depth of 50mm

from suspended slab exposing all corroded rebar. Clean up surface

rust and blisters from rebar, apply an approved propriety cement

based primer. Dampen concrete surface and apply an approved

propriety concrete repair mortar, smoothly finished. Allow for

necessary shuttering. (Provisional) Refer to drawing RGP 04/2013

(01).

a. Main bedroom 3.50 m²

b. Spare bedroom 3.50 m²

2.07

Rake out joints of external masonry surfaces (roof parapet wall), clean

open joints from dust and loose materials, wet stone and surrounding

area adequately using clean water and point with a mason trowel in

layers not exceeding 10mm thickness using the following mortar mix:

1 part hydraulic lime and 3 parts sand with stone dust as colour

additive. Any sound pointing will be retained. The use of a

mechanical disk or any other method that might cause damage to the

stone, or which might increase the width of the joints, is prohibited.

Care is to be taken in the removal of any hard pointing which might

cause damage to the stone. The use of Portland cement mixes is not

allowed. Rate to include for working in confined spaces and working

around fixed objects. Care should be taken not to damage the existing

wall-mounted objects. (provisional)

50.00 sq.m.

Total Bill No. 2 carried to Summary

4

Page 5: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

BILL No. 3 ELECTRICAL & ELV SYSTEMS

Preambles

A

Rates to include for all chasing and making good, PVC conduit,

wiring and fitting. Contractor is to include in his rates for works

which vary ground to first floor level. Refer to drawing RGP 04/2013

(05) for electrical lighting layout.

B

The stripping and carting away of existing installation has been

included in Item 1.05. No claims for additional payment in this

respect shall be entertained.

C

Contractor is to test the existing electrical plant as to ensure and

verify that the existing electrical material, if this is to be retained, is

satisfactory.

D

Installation to be strictly in accordance with IEE regulations and

contractor shall be bound to provide the employer with an

electrician's certificate to this effect before payment is issued.

Electrician is to submit

EHorizontal runs shall be over the floor slab, covered and well

protected with a sand/cement mix (1:3).

LIGHTING INSTALLATION

3.01Supply and install one light point, controlled by one way switch,

including wiring accessories.8 No.

3.02Supply and install the following power points including wiring

accessories.

a. Double socket outlets. 10 No.

b. Switched fuse connection units (Water heater). 1 No.

3.03Bell system complete with switch transformer push installed near

outside door.1 No.

CONSUMER UNIT

3.04Supply, install and connect Consumer Unit complete with protective

devices and circuits as per schedule.1 No.

Total Bill No. 3 carried to Summary

5

Page 6: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

BILL No. 4 PLUMBING & DRAINAGE WORKS

Preambles

A All items to include supply and on-site installation.

B

Rates are considered to be inclusive of stripping and carting away of

existing installation and no claims for additional payment in this

respect shall be entertained.

CAll plumbing to be in proprietary PVC push fit system and all drains

in heavy duty PVC pipework.

D

All bathroom appliances and fittings to be suitable for use by

wheelchair bound users. Appliances which are found to be non-

compatible with this requirement shall have to be replaced at the

contractor's expense.

EPipes shall run within the screed and covered using sand cement

haunching. Cost to include closing off wall plates with plugs.

4.01

Supply, deliver to site, install, connect, test and commission the

complete plumbing system. Refer to drawing RGP 04/2013 (06) for

plumbing layout.

A Lump sum price is to be quoted and is to include the following:

a.

The provision of a direct water supply to the kitchen, including

supply to kitchen sink, the necessary sleeves as protection to

underground pipe work where necessary and in particular in

preparation for supply to meter, all fittings support brackets, chasing

in walls, making good and plugging.

b.The rising main to the water tank inclusive of fittings, support

brackets and chasing in walls and making good where necessary.

c.

The supply and fixing of a fiber glass 500 litre capacity water tank

including ball valve, stopcock, supports, overflow pipe, securable lid,

water inlet and outer connection parts as specified. Rate to include

placing of water tank raised to a minimum height of 2 meters on

appropriate hollow channels.

d.

Supply pipe including gate valves, taking into account the variation

in height. This is to be inclusive of all fittings, support brackets, gate

valves, chasing in walls, making good and plugging as necessary.

One outlet is to be fitted with brass tap for testing of the installation.

e.

The supply and installation of two (kitchen for washing machine and

bath room) chrome bib taps, diameter 1/2", complete with wall

covering back plate.

f.

Supply and fix drain waste PB pipes to sanitary fittings, washing

machine and kitchen to nearest stack. Cost to include for sand

cement haunching.

Carried forward

6

Page 7: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

Brought forward

g.

Supply and install plumbing and drainage for flow and attached

flushing cisterns, including the replacement of part of the soil water

drainage system connecting to the third party drainage system at

ground floor level.

h.Supply and install plumbing and drainage for flow for each wash

hand basin in bath room.

i.Supply and install plumbing and drainage for flow for bath and floor

drain in bath room.

j) Supply and install plumbing and drainage for flow for washing

machine.

A Lump sum price is to be quoted for the above nine items 4.01

(a)-(i)1.00 l.s.

4.02

Supply and install sanitary ware and accessories complete with traps,

angle valves, flexible hoses, fittings and fixing material. Refer to

drawing RGP 04/2013 (07) for bathroom layout.

a.

White vitreous china wash hand basin in bath room, having overall

dimensions of approximately 600mm wide x 450mm, wall-hung (no

pedestal), including all support brackets and other accessories.

1 No.

b.

White vitreous china back to wall type water closet and flushing with

cistern located above the closet and attached directly to the wall,

white in colour. Approximate water closet dimensions 360mm wide

by 600mm. Including dual flush system, matching heavy duty plastic

toilet seat and cover with rubber inserts and all support brackets and

accessories.

1 No.

c.

1/2" wash hand basin mixer with lever operated tap (no less than

75mm long) with pop-up waste mechanism operated from the mixer

tap.

1 No.

d.

Thermostatic controlled detachable bath set consisting of an anti-

vandal bath head and holder, a flexible hose, a shut off thermostatic

mixer valve, in white/chrome finish. Thermostatic mixer shall be

lever operated and have a calibrated dial. Including separate control

for controlling the flow of the water. The overall assemblage shall

limit the water flow rate to a maximum of 9 litres/min when operated

at 3 bar pressure. Including shrouded supply pipe, 2m long.

1 No.

e.Acrylic bath including mixer with wall tap and hand held shower with

wall bracket connection to plumbing service and waste.1 No.

4.03Supply and install accessory set in matching white vitreous china,

including all fixing accessories and screws.

a. Soap holder with overall dimensions of 150mm x 90mm x 10mm. 3 No.

b. Towel ring holder, wall mounted. 2 No.

c.

Toilet roll holder, wall mounted with overall dimensions of 90mm x

90mm. Holder shall be installed 300mm in front of the edge of the

toilet bowl at a height of 660mm from finished floor level.

2 No.

dToothbrush holder, wall mounted, with overall dimensions of

100mm x 90mm x 50mm.1 No.

4.04

Supply and install plate glass, wall-hung mirror having overall

approximate dimensions of 500mm x 700mm, complete with light

fitting. To include fixing, screws and chrome plated screw head

covers.

1.00 No.

4.05

Pressure testing of all pipework distribution including installation

inside wet areas as specified. Commissioning including including

standard pressure test.

1.00 l.s.

Carried forward

7

Page 8: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

Brought forward

4.06

Permanently restore functionality of water tank in item 1.06. Rate to

include any works necessary to permanently restore the functionality

of the water tank including all required plumbing works and fittings;

and any necessary steel beams to support the water tank. (provisional)

1.00 l.s.

4.07

Relocate water tank in item 1.06 in a location as instructed by the

Architect in charge or his representative. Rate shall include for any

works required to move the water tank; any works necessary to

permanently restore the functionality of the water tank including all

required plumbing works and fittings; and any necessary steel beams

to support the water tank. (provisional)

1.00 l.s.

Total Bill No. 4 carried to Summary

8

Page 9: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

BILL No. 5 FLOOR & WALL TILING WORKS

Preambles

AAll work shall be measured net as laid. Rates are to include for all

waste and straight or raked cutting.

B

Contractor shall make available to HA three different coloured

samples of each item of floor/wall tiles, of the same quality but with a

different colour for approval by the Architect in charge or his

representative. Rates shall be inclusive of these samples.

C

Rates for wall and floor tiles shall include for the necessary amount of

samples required for testing by an independent laboratory to ascertain

the quality of the tiles submitted for approval.

DRates for floor tiles shall include the necessary hole preparation for

the floor bolts of each internal or external door.

BATHROOM

Waterproofing membrane

5.01

Thoroughly clean surface of floor of bathroom and apply

waterproofing membrane. Waterproofing membrane shall be heat-

applied and shall consist of 4mm thick polyester reinforced flexible

membrane, raised a minimum of 230mm from the horizontal. Top

surface of membrane shall be sealed with proprietary adhesive, or

equivalent, prior to covering with tiles. As per specifications. The

Contractor is to inform the HA representative two days in advance in

order to inspect membrane before any further works are carried out.

Refer to drawing RGP 04/2013 (04).

7.00 sq.m.

Preparation of walls to receive tiles

5.02

Hack walls to achieve a good key, clean down and scrape where

required to prepare them to receive wall tiles. Refer to drawing RGP

04/2013 (04).

25.00 sq.m.

Floor Tiles

5.03

Supply and lay best quality straight edged non-slip matt internal

ceramic floor tiles (as per specs) specific for bathrooms, dimensions

not less than 300mm x 300mm and minimum thickness approx. 9mm

thick (or any other size approved by the Architect in Charge or his

representative) including laying with 4mm spacers in joints and

grouting with flexible grout compound. Tile colour to be in a

medium to dark brown/beige colour. Tiles shall be specifically

indicated by the supplier for use in bathrooms and an official

certificate/specifications obtained from the supplier is to be submitted

to the HA for approval prior to installation. Refer to drawing RGP

04/2013 (04).

7.00 sq.m.

Carried forward

9

Page 10: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

Brought forward

Wall Tiles

5.04

Supply and lay best quality straight edged glazed ceramic wall tiles

(as per specs) specific for bathrooms, forming part of the same set

(and supplier) of tiles in Item 5.03 with dimensions to be compatible

with tiles chosen for the floor including laying with 3mm spacers in

joints and grouting with flexible grout compound, matching in colour.

Wall tiles to be installed up to a height of 2metres from finished floor

level. Tile colour to be in a lighter shade of Item 5.03. Tile shall be

specifically indicated by the supplier for use in bathrooms and an

official certificate/specifications obtained from the supplier is to be

submitted to the HA for approval prior to installation. Refer to

drawing RGP 04/2013 (04).

25.00 sq.m.

SITTING ROOM, KITCHEN/DINING, BEDROOMS

5.05

Polishing of tiles and grouting of joints of existing floor tiles in sitting

room, kitchen / dining, main bedroom, spare bedroom and boxroom.

Refer to drawing RGP 04/2013 (04).

85.00 sq.m.

KITCHEN

5.06

Supply and lay best quality straight edged glazed ceramic wall tiles,

with dimensions to be compatible with tiles chosen for the floor

including laying with 3mm spacers in joints and grouting with

flexible grout compound, matching in colour. Wall tiles to be

installed up to a height of 2metres from finished floor level. Tile

colour shall be specified by HA. Tile shall be specifically indicated

by the supplier for use in kitchens and an official

certificate/specifications obtained from the supplier is to be submitted

to the HA for approval prior to installation. Refer to drawing RGP

04/2013 (04). (provisional)

17.00 sq.m.

Total Bill No. 5 carried to Summary

10

Page 11: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

BILL No. 6 JOINERY WORKS

Preambles

A

In the case of apertures with existing fixtures to be replaced, quoted

prices for manufacture and installation of new fixtures must be

inclusive of loading, carting away of existing fixtures and disposing

in an authorised dumping site.

B

All external timber fixtures to be in red deal and treated with

comprehensive paint system to include preserver solution, primer, two

coats of undercoat and two coats of brush applied finish paint in a

colour similar to other apertures, or as directed by the Architect in

Charge or his representative.

C Warped or split timber element shall not be accepted.

D

Rates for internal joinery are to include for the manufacture and

fixing in white deal of doors and fittings inclusive of all necessary

frames/linings, architraves, ironmongery, painting one coat primer

and glazing where necessary.

E

Rates for external joinery are to include for the manufacture and

fixing in Red Deal wood or as specified in the respective item,

inclusive of all frames, weather bars ("parakwa"), ironmongery and

finish as specified in the item, to render the fixtures completely

weathertight.

F

Fibreboard will not be considered as acceptable and any fibreboard

items manufactured and/or fixed will have to be replaced by the

proper joinery as specified and at contractor's expense.

GAll hardware shall be in satin finish stainless steel. Chrome hardware

shall be rejected.

H

Where indicated, all external timber windows to have outward

opening external louvred shutters ('persjani') finished as described in

B above.

J All external doors and windows to be weather proof and secure.

Carried forward

11

Page 12: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

Brought forward

6.01

Repair/restore existing timber apertures including timber frame and

architrave, specified below, including scraping off of all paint (or

rubbing down where necessary), the replacement of corroded

hardware and rails, replacement of damaged/deteriorated timber parts

and broken or missing glazing, stocking of cracks in timber,

replacement of cracked glazing putty, sanding and repainting using

brush application (apply one coat wood preserver, one undercoat and

two finish coats of different colours with finish paint in a colour

similar to existing apertures) and removal of insect screens, making

good around timber apertures frame, where necessary and disposal of

resulting material in an authorised dumping site. Rates are to be

deemed inclusive of supply, installation and dismantling of

scaffolding where necessary, or cherry picker or high-up, as

necessary. Claims for additional payments for supply of scaffolding

shall not be considered. Refer to drawing RGP 04/2013 (08) and RGP

04/2013 (09).

a. Glazed timber window with closed panel shutters. ('W01') 2 No.

b. Glazed timber door with closed panel shutters. ('D02') 2 No.

c. Glazed timber window. ('W02') 2 No.

6.02

Repair/restore existing internal single leaf door, including timber

frame and architrave, including scraping off of all paint (or rubbing

down where necessary), sanding and repainting using brush

application (apply one coat wood preserver, one undercoat and two

finish coats of different colours with finish paint in a colour similar to

existing apertures), making good around timber apertures frame,

where necessary and disposal of resulting material in an authorised

dumping site, setting of doors, especially those which require

adjustment. Particular attention shall be given to those doors which

have decorative mouldings. Doors are to be stored in a safe place

whilst other works are being carried out to ensure that they are not

damaged whilst other trades are being completed. Rate to include for

the removal, storage and re-installation of the doors after all other

works are completed. Refer to drawing RGP 04/2013 (08) and RGP

04/2013 (09). ('D03')

5 No.

6.03Supply and install door knobs on internal doors. Refer to drawing

RGP 04/2013 (08) and RGP 04/2013 (09). ('D03')5 No.

6.04

Repair/restore existing timber main door including timber frame and

architrave, specified below, including scraping off of all paint (or

rubbing down where necessary), the replacement of corroded

hardware and rails, replacement of damaged/deteriorated timber parts,

stocking of cracks in timber, sanding and repainting using brush

application (apply one coat wood preserver, one undercoat and two

finish coats of different colours with finish paint in a colour similar to

existing apertures), making good around timber apertures frame,

where necessary and disposal of resulting material in an authorised

dumping site. Refer to drawing RGP 04/2013 (08) and RGP 04/2013

(09). ('D01')

1 No.

Total Bill No. 6 carried to Summary

12

Page 13: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

BILL No. 7 WATERPROOFING WORKS

Preambles

A

Polyester reinforced waterproofing membrane laid that shall remain

exposed is to incorporate a mineral chippings surface of approved

colour and quality.

B

The membrane shall be laid and installed strictly as per

manufacturer’s instructions. The Contractor shall submit a copy (in

English) of the installation methodology before the start of the Works.

C

The surface to receive the membrane should be dry, free from

standing water, sharp protrusions and hollows. The surface shall be

primed with 2 coats of bituminous primer (min. 55% penetration

grade bitumen residue) before applying the membrane.

D

The membrane shall extend over any cement/sand fillets and up all

upstands and sides of parapet walls to a height of not less than 230

mm above finished roof level. The membrane shall be lapped and heat

welded at all joints so as to give a continuously unbroken,

impermeable surface.

E

Vertical surfaces shall be smooth, regular, dry and free from nails and

primed with a bituminous primer (min. 55% penetration grade

bitumen residue) at the rate depending on the porosity of the surface

and allowed to dry completely before the application of the

membrane. Masonry work and brickwork shall be flush pointed and

rendered respectively to provide a smooth surface before priming.

Any adhering paintwork shall be removed.

G The membrane shall be installed in such a manner that:

a. would allow for differential thermal and structural movement

between the membrane and the roof.

b. would include all necessary accessories such as edge flashings,

funnel inserts for down pipes, and air-vents.

F

All cracks, expansion and construction joints and blisters shall be

raked out, thoroughly swept, washed, cleaned and made good with an

approved joint sealer before the application of the waterproofing

treatment by the Contractor.

7.01

Remove existing waterproofing membrane from roof level of

apartment and load, cart away and dump in an authorised dumping

site. Refer to drawing RGP 04/2013 (04).

1.00 l.s.

7.02Chase groove 25mm x 25mm in parapet wall/stairwell wall to end

torch welded membrane - and pointing of same.55.00 m

7.03

Clean thoroughly surfaces to receive membrane and ensure that

surfaces are dry, free from standing water and any sharp protrusions

or hollows. Apply two coats of bituminous primer (min. 55%

penetration grade bitumen residue). Rate to include for any

rectification to surface to ensure proper adhesion, including flush

pointing of any masonry and the removal of any adhering paintwork

to provide a smooth surface before priming. Refer to drawing RGP

04/2013 (04).

90.00 m²

Carried forward

13

Page 14: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

Brought forward

7.04

Supply and install flexible reinforced polyester torch welded

waterproofing membrane over entire roof surface over the apartment.

The membrane shall be brought down and overlapped adequately

where changes in level occur. The membrane will be raised and

inserted into chased groove. To include 10 year guarantee for

material and workmanship. Refer to drawing RGP 04/2013 (04).

90.00 m²

Total Bill No. 7 carried to Summary

14

Page 15: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

BILL No. 8 FINISHES TO WALLS & CEILINGS

Preambles

A

Rates are to include for removal and replacement of drain and rain

water pipes fixed to walls in external areas, terraces and balconies for

pointing, where applicable.

B

Existing surfaces to be painted shall be sound, free from loose areas

and significant cracks of gaps, free from deteriorating, damp or

unsuitable material, cleaned of loose mortar, fins, grease, dirt,

efflorescence, mould or dust.

C

All cutting, chasing, making good, fixing of conduits and surface

outlets shall be completed before painting. Surface flatness/regularity

shall be within the specified tolerance limits.

8.01

Render surfaces of concrete surfaces internally of sitting room and

main bedroom in two coats which shall consist of a 6mm base coat in

cement and sand (1:3) and 3mm setting coat in cement:lime:sand

(1:1:6). Sufficient time shall be allowed between successive coats.

Followed by one coat of sealer and two coats of acrylic internal paint.

Paint is to be white in colour, or as directed by the Architect in

Charge. Refer to drawing RGP 04/2013 (04).

38.00 sq.m.

8.02

Sand down and apply three coats of external good quality breathable

paint to balcony parapet wall to ensure total coverage. Paint is to be

white in colour, or as directed by the Architect in Charge. The

necessary time between each layer is to be allowed.

1.00 l.s.

8.03

Sand down, treat with Galvacoat and repaint in two coats, railing of

external balcony. Care should be taken not to damage galvanised

metal. Refer to drawing RGP 04/2013 (04).

7.20 m

8.04

Make good and apply three coats of internal good quality breathable

paint to all internal walls to ensure total coverage. Paint is to be white

in colour, or as directed by the Architect in Charge. The necessary

time between each layer is to be allowed.

##### sq.m.

8.05

Sand down and apply three coats of internal good quality breathable

paint to all ceilings to ensure total coverage. Paint is to be white in

colour, or as directed by the Architect in Charge. The necessary time

between each layer is to be allowed.

90.00 sq.m.

Total Bill No. 8 carried to Summary

15

Page 16: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

Item Description Qty Unit Rate (€) Amount (€)

incl. V.A.T incl. V.A.T

BILL No. 9 HEALTH AND SAFETY PROCEDURES

Preambles

AAll other requirements not specifically mentioned in this bill of

quantities but referred to in any of the contract documents.

B

The unit rates used by the tenderer are deemed to include all and any

incidental and/or supplemental and/or complementary items, work

etc. required to complete the project to the required standard and

specifications. No requests for variations on these items will be

entertained.

C

All items must be executed without fail, otherwise the OHSA and

MEPA will be notified to take action against the defaulting

contractor. If in default, the contractor will be fully liable for any

penalties imposed by the OHSA/MEPA.

9.01

Provide personal protective equipment (PPE) to all workmen on site.

Particular attention is to be given to the provision of safety harnesses

to workers working at heights.

1.00 l.s.

9.02

Keep the site clear and free from accumulated debris and waste at all

times. This is particularly important in staircases and landings. A

programme of how such cleaning is to be carried out on a regular

basis is to be provided to the Perit in charge prior to the start of

works.

1.00 l.s.

9.03Provision of first aid kits and availability of at least one contractor's

representative who is well versed in first aid.1.00 l.s.

9.04

Provide fencing to all edges, such as the staircase in the yard and low

walls to protect against accidental falls from heights. Such fencing is

to be maintained at all times.

1.00 l.s.

Total Bill No. 9 carried to Summary

16

Page 17: Bill of Quantities Block 7B, No 7, San Ġwann t'Għuxa, Bormla · PDF file · 2014-10-28BOQ - RGP 18/2012 Item Description Qty Unit Rate (€) Amount (€) incl. V.A.T incl. V.A.T

BOQ - RGP 18/2012

BILL No. 1 DEMOLITION & REMOVAL WORKS

BILL No. 2 CONSTRUCTION WORKS

BILL No. 3 ELECTRICAL & ELV SYSTEMS

BILL No. 4 PLUMBING & DRAINAGE WORKS

BILL No. 5 FLOOR & WALL TILING WORKS

BILL No. 7 WATERPROOFING WORKS

BILL No. 8 FINISHES TO WALLS & CEILINGS

BILL No. 9 HEALTH AND SAFETY PROCEDURES

Grand Total including VAT

Signature of Contractor Date

Name of Tenderer

Address

I.D. No

Tel. No

Fax No

Mobile Phone

VAT Registration No

BILL No. 6 JOINERY WORKS

SUMMARY

Block 7B, No 7, San Ġwann t'Għuxa, Bormla

AMOUNT including VAT

17