bill of stone work

9
Bill of Stone work in Flooring, Staircase and Kitchen for different st BETWA No of towers = 3 Stone work measurement for Staircases Note: Two staircases were present in a tower covering the 12 floors Staircase 1 area 1 from ground floor(floor) to half landing area 2 from next half of landing to floor total area of staircase connecting each floor area of stone work for stair case for building or 15 floors area of stone work for stacking stair case for building or 15 floors total stone work(including stacking) For the whole project site (including stacking) cost @ Rs. 650/ sq.m (including stacking) total stone work (excluding stacking) for project site cost @ Rs. 650/ sq.m (including stacking) Staircase 2 area 1 from ground floor(floor) to half landing area 2 from next half of landing to floor total area of staircase connecting each floor area of stone work for stair case for building or 12 floors total stone work For the whole project site cost @ Rs. 650/ sq.m total stone work (excluding stacking) for project site cost @ Rs. 650/ sq.m (including stacking) Flooring of Stone work in corridors rea of corridor+ area under flooring Stacking area of corridor 76 sq. m 10.277232 rea under staircas 11.285 sq. m 1.3716 area in free spac 6.216 sq. m 2.6838 total area 93.501 sq. m 14.332632 79475.85 rupees 12182.7372 for one building 953710.2 rupees 146192.8464 for project site 2861130.6 rupees 438578.5392 total cost 3299709.1392 rupees floors area of stone work Corridors Cost @ Rs 850/sq. m for on floor

Upload: shumank-srivastava

Post on 21-Jan-2016

5 views

Category:

Documents


0 download

DESCRIPTION

billing

TRANSCRIPT

Page 1: Bill of Stone Work

Bill of Stone work in Flooring, Staircase and Kitchen for different structures at L&T site

BETWA

No of towers = 3

Stone work measurement for Staircases Note: Two staircases were present in a tower covering the 12 floors of also basement is provided in each building and second staircase also covers the basement

Staircase 1area 1 from ground floor(floor) to half landing 7.75 sq.marea 2 from next half of landing to floor 8.375 sq.mtotal area of staircase connecting each floor 16.125 sq.marea of stone work for stair case for building or 15 floors 241.9 sq.m

area of stone work for stacking stair case for building or 15 floors39 sq.m

total stone work(including stacking) 281 sq.mFor the whole project site (including stacking) 841.7538 sq.mcost @ Rs. 650/ sq.m (including stacking) 547139.97total stone work (excluding stacking) for project site 725.625 sq. mcost @ Rs. 650/ sq.m (including stacking) 471656.25

Staircase 2area 1 from ground floor(floor) to half landing 8.25 sq.marea 2 from next half of landing to floor 7.65 sq.mtotal area of staircase connecting each floor 15.9 sq.marea of stone work for stair case for building or 12 floors 190.80 sq.marea of stone work for stacking of stair case for building or 15 floors 33.162 sq.mtotal stone work 224 sq.mFor the whole project site 671.88672 sq.mcost @ Rs. 650/ sq.m 436726.37total stone work (excluding stacking) for project site 572.4 sq. mcost @ Rs. 650/ sq.m (including stacking) 372060

Flooring of Stone work in corridors

area of corridor+ area under staircase+ three corners behind liftflooring Stacking

area of corridor 76 sq. m 10.277232 sq. marea under staircase 11.285 sq. m 1.3716 sq. marea in free spaces 6.216 sq. m 2.6838 sq. mtotal area 93.501 sq. m 14.332632 sq. m

79475.85 rupees 12182.7372 rupees

for one building 953710.2 rupees 146192.8464 rupeesfor project site 2861130.6 rupees 438578.5392 rupeestotal cost 3299709.1392 rupees

area of stone work Corridors

Cost @ Rs 850/sq. mfor on floor

Page 2: Bill of Stone Work

ROHINI

two G+12 and one G+8 building

Stone work measurement for Staircases Note: Two staircases were present in a tower covering the 12 floors of also basement is provided in each building and second staircase also covers the basement

Staircase 1area 1 from ground floor(floor) to half landing 7.75 sq.marea 2 from next half of landing to floor 8.375 sq.mtotal area of staircase connecting each floor 16.125 sq.marea of stone work for stair case for building or 15 floors 241.9 sq.marea of stone work for stacking stair case for building or 15 floors 39 sq.mtotal stone work(including stacking) 281 sq.mFor the whole project site (including stacking) 841.7538 sq.mcost @ Rs. 650/ sq.m (including stacking) 547139.97total stone work (excluding stacking) for project site 725.625 sq. mcost @ Rs. 650/ sq.m (excluding stacking) 471656.25

Staircase 2area 1 from ground floor(floor) to half landing 8.25 sq.marea 2 from next half of landing to floor 7.65 sq.mtotal area of staircase connecting each floor 15.9 sq.marea of stone work for stair case for building or 12 floors 190.80 sq.marea of stone work for stacking of stair case for building or 15 floors 33.162 sq.mtotal stone work 224 sq.mFor the whole project site 671.88672 sq.mcost @ Rs. 650/ sq.m 436726.37total stone work (excluding stacking) for project site 572.4 sq. mcost @ Rs. 650/ sq.m (including stacking) 372060

Flooring of Stone work in corridors

area of corridor+ area under staircase+ three corners behind liftflooring Stacking

area of corridor 58 sq. m 11.681344 sq. marea under staircase 11.285 sq. m 1.3716 sq. marea in free spaces 13.1096 sq. m 3.083064 sq. mtotal area 82.3946 sq. m 16.136008 sq. m

70035.41 rupees 13715.6068 rupees

for one building 840424.92 rupees 164587.2816 rupeesfor project site 2241133.12 rupees 438899.4176 rupeestotal cost 2680033 rupeesNote: one building of G+8 is present

area of stone work Corridors

Cost @ Rs 850/sq. mfor one floor

Page 3: Bill of Stone Work

Rapti

Stone work measurement for Staircases Note: Two staircases were present in a tower covering the 12 floors of also basement is provided in each building and second staircase also covers the basement

Staircase 1area 1 from ground floor(floor) to half landing 7.75 sq.marea 2 from next half of landing to floor 8.375 sq.mtotal area of staircase connecting each floor 16.125 sq.marea of stone work for stair case for building or 15 floors 241.9 sq.marea of stone work for stacking stair case for building or 15 floors 39 sq.mtotal stone work(including stacking) 281 sq.mFor the whole project site (including stacking) 841.7538 sq.mcost @ Rs. 650/ sq.m (including stacking) 547139.97total stone work (excluding stacking) for project site 725.625 sq. mcost @ Rs. 650/ sq.m (excluding stacking) 471656.25

Staircase 2area 1 from ground floor(floor) to half landing 8.25 sq.marea 2 from next half of landing to floor 7.65 sq.mtotal area of staircase connecting each floor 15.9 sq.marea of stone work for stair case for building or 12 floors 190.80 sq.marea of stone work for stacking of stair case for building or 15 floors 33.162 sq.mtotal stone work 224 sq.mFor the whole project site 671.88672 sq.mcost @ Rs. 650/ sq.m 436726.37total stone work (excluding stacking) for project site 572.4 sq. mcost @ Rs. 650/ sq.m (including stacking) 372060

Page 4: Bill of Stone Work

Bill of Stone work in Flooring, Staircase and Kitchen for different structures at L&T site

Two staircases were present in a tower covering the 12 floors of also basement is provided in each building and second staircase also covers the basement

area of corridor+ area under staircase+ three corners behind lift

Page 5: Bill of Stone Work

Two staircases were present in a tower covering the 12 floors of also basement is provided in each building and second staircase also covers the basement

area of corridor+ area under staircase+ three corners behind lift

Page 6: Bill of Stone Work

Two staircases were present in a tower covering the 12 floors of also basement is provided in each building and second staircase also covers the basement