bim assignment using revit

2
Brenden Ritola CEE 431: BIM Assignment Winter 2013 April 14, 2013 Task 1 2c. i. Rebar length: 62’ 6 41 128 ii. Comment: 8” slab rebar iii. Spacing: (no information is given) 3c. The slab on grade and apron are shown specifically in the BIM model, under building section A-A Task 2 2a. i. Grand total of concrete needed: 232.07 CY 2b. i. Foundation Slab, 8” slab, Apparatus Room: 71.87 CY ii. Foundation Slab, 8” slab, Aprons: 5.85 + 5.95 = 11.80 CY 3b. Grand total for slab edge: 111.91 CF ≈ 4.14 CY From the BIM model it is evident that it does have its limitations to what it can actually do. With regards to the “Slab Edge” example, the first issue is the fact that since Revit does not include the thickened edges in its quantity takeoff, the grand total of required concrete is approximately 4.14 CY short of the actual required quantity. Furthermore, for some reason, all concrete quantities under “Concrete Slab and Footing” are listed in cubic yards yet under the “Slab Edge” the quantities are in cubic foot. So not only is the extra concrete not included in the takeoff but it isn’t even presented in the same units. Obviously, there are some improvements to be made

Upload: ritolab

Post on 23-Oct-2015

23 views

Category:

Documents


4 download

DESCRIPTION

BIM Assignment Revit

TRANSCRIPT

Page 1: BIM Assignment Using Revit

Brenden Ritola

CEE 431: BIM Assignment

Winter 2013

April 14, 2013

Task 1

2c. i. Rebar length: 62’ 6 41128

ii. Comment: 8” slab rebar

iii. Spacing: (no information is given)

3c. The slab on grade and apron are shown specifically in the BIM model, under building section A-A

Task 2

2a. i. Grand total of concrete needed: 232.07 CY

2b. i. Foundation Slab, 8” slab, Apparatus Room: 71.87 CY

ii. Foundation Slab, 8” slab, Aprons: 5.85 + 5.95 = 11.80 CY

3b. Grand total for slab edge: 111.91 CF ≈ 4.14 CY

From the BIM model it is evident that it does have its limitations to what it can actually do. With regards to the “Slab Edge” example, the first issue is the fact that since Revit does not include the thickened edges in its quantity takeoff, the grand total of required concrete is approximately 4.14 CY short of the actual required quantity. Furthermore, for some reason, all concrete quantities under “Concrete Slab and Footing” are listed in cubic yards yet under the “Slab Edge” the quantities are in cubic foot. So not only is the extra concrete not included in the takeoff but it isn’t even presented in the same units. Obviously, there are some improvements to be made in the software’s ability to except more variety in its inputs but also to keep consistent units in its quantities.