bio-energy 7th shrestha 1st revised

Upload: soaringcrane

Post on 10-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    1/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    1

    e-learn

    ing

    co

    urs

    e

    e-learning course onBio-energy for achieving MDGs

    Prof. Ram M. ShresthaSchool of Environment, Resources and Development

    Asian Institute of TechnologyThailand

    E-mail: [email protected]

    21 June 2007

    Lecture 7:Financial Analysis of Renewable Energy Projects

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    2/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    2

    e-learn

    ing

    co

    urs

    e

    Contents Characteristics of RE Projects

    Financial analysis vs. Economic Analysis

    Components of project costs and benefits

    Time Value of Money

    Criteria for Financial Viability of Project

    Financial Analysis under Uncertainty

    - Sensitivity Analysis

    - Break-even analysis

    - Scenario Analysis

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    3/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    3

    e-learn

    ing

    co

    urs

    e

    Characteristics of RE Projects

    Most RE projects normally involve:

    - High initial costs (capital intensive)- Low operating cost

    - Environmental/climate benefits, cleaner than fossil

    fuel technologies, e.g. biomass energy- Local level employment generation (especially, from biomass

    projects)

    - Resource availability site specific and subject to fluctuations(especially in the case of solar, wind and hydro)

    - Sustainable resource use

    RE projects also help to reduce national energy import dependency.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    4/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    4

    e-learn

    ing

    co

    urs

    e

    Current Status of Renewable EnergyTechnologiesTechnology Capacity factor (%) Turnkey investment

    costs (U.S.$/Kw)Current energy costof new systems

    Potential futureenergy cost

    Biomass Energy

    Electricity

    Heat

    Ethanol

    25 - 80

    25 - 80

    900 - 3,000

    250 - 750

    5 15 /kWh

    1 5 /kWh

    8 25 $/GJ

    4 10 /kWh

    1 5 /kWh

    6 10 $/GJ

    Wind Electricity 20 - 30 1,100 1,700 5 13 /kWh 3 10 /kWh

    Solar PhotovoltaicElectricity

    8 - 20 5,000 10,000 25 125 /kWh 5 or 6 25 /kWh

    Solar ThermalElectricity

    20 - 35 3,000 4,000 12 18 /kWh 4 10 /kWh

    Low-temperature

    Solar Heat

    8 - 20 500 1,700 3 20 /kWh 2 or 3 10 /kWh

    Hydroelectricity

    Large

    Small

    35 - 60

    20 - 70

    1,000 3,500

    1,200 3,000

    2 8 /kWh

    4 10 /kWh

    2 8 /kWh

    3 10 /kWh

    Geothermal Energy

    Electricity

    Heat

    45 - 90

    20 - 70

    800 3,000

    200 2,000

    2 10 /kWh

    0.5 5 /kWh

    1 or 2 8 /kWh

    0.5 5 /kWh

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    5/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    5

    e-learn

    ing

    co

    urs

    e

    What is Financial Analysis?

    Financial evaluation mainly focuses into

    - Money aspects of the project, and

    - Rewards and financial profitability to the investors.

    The main objective of the financial analysis is to look intothe financial benefits, costs and profitability of the projectfrom the investors perspective.

    Financial analysis (FA) includes direct transfer paymentssuch as taxes, duties, subsidies in the evaluation.

    FA does not account for the externalities such asenvironmental impacts and their costs.

    FA normally uses market prices of inputs and outputs

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    6/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    6

    e-learn

    ing

    co

    urs

    e

    Financial Vs. Economical AnalysisOn the other hand, economic evaluation

    - estimates project benefits and returns from theperspective of national economy and assesses theeffects that the project will have on the overall

    economy of the country.

    - takes into account the social and environmental

    costs and benefits of the project.- excludes transfer payments and

    - uses border prices for traded goodsand shadow

    prices for non-traded goods and services.

    As the main focus of our discussion is on financial analysis, we willtry to put more concentration in this area rather than the economicalanalysis in the later part of our presentation.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    7/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    7

    e-learn

    ing

    co

    urs

    e

    Financial Analysis in the Project Cycle

    The Project Cycle is the framework to design, prepare,

    implement and supervise projects. The project cycle includes six stages such as,

    Identification

    Preparation

    AppraisalNegotiation/Approval

    Implementation, and

    Evaluation.

    The Appraisal phase includes evaluation of financial,economic, technical, institutional, environmental andsocial aspects of the project.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    8/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    8

    e-learn

    ing

    co

    urs

    e

    Components of Project Costs Project Costs:

    Investment costs Operating costs

    Investment Costs: Include initial costs and replacement costs

    Initial Costs, referred to as the first cost, which is usually made up of anumber of cost elements that do not recur after an activity is initiated. For

    example, construction and commissioning, including land, civil works,transportation, equipment & installations and other related initial expenditures

    Initial cost is the major component of an RE project. Such cost is normallyhigher in RE projects than in non-RE projects. As such, high initial cost

    presents the major barrier to the adoption of RETs.

    Replacement Costs, refers to the cost of equipment and installationsprocured during the operating phase of the project, to maintain its originalproductive capacity.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    9/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    9

    e-learn

    ing

    co

    urs

    e

    Project Costs (Contd.)

    Operating Costs: Costs experienced continually over theuseful life of the project activity. They are of two broadcategories:

    - Fixed Costs (FC)- variable costs (VC)

    Fixed Cost (FC): Group of costs whose value will remain relatively

    constant throughout the range of operational activity or output levelof the project. FC includes the following cost items:

    - maintenance- insurance- lease rentals

    - interest payment on invested capital- certain administrative expense, and- research.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    10/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    10

    e-learn

    ing

    co

    urs

    e

    Project costs (contd.)

    Variable Costs (VC): Group of costs that vary withthe level of operational activity or output. In general,VC includes costs of:

    - labor,

    - materials,- fuel cost*

    - tax

    *Biomass cost in the case of biomass energy

    projects; none in solar, wind and hydro.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    11/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    11

    e-learn

    ing

    co

    urs

    e

    Project Benefits

    RE Project Financial Benefits include:

    - Revenue earned from the output of the project

    - Tax credits (if applicable)

    - Subsidy (if applicable)

    - Carbon credits

    (if the project is eligible for such benefits, e.g., under the cleandevelopment mechanism (CDM); in the case of a biomass project, suchcredits can be available only if biomass is produced on a sustainable basis)

    A RE investment tax credit is an immediate reduction in income tax equalto a percentage of the installed cost of a new RE investment. Tax creditsfor renewable energy technologies (RETs) can enhance after-tax cash flowand promote RE investment.

    Often, governments may also provide subsidy on the cost of RETsequipments to promote RE.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    12/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    12

    e-learn

    ing

    co

    urs

    e

    Flow Chart of Financial Analysis Under CertaintyDefine the parameters of the project

    e.g. Service life, Discount Rate, Size of the Project,

    Dem and, etc.

    For a given size of the RE project,

    determine the cash inflows and cashoutflows for each Year

    Calculate the total NPW oralternative financial indicator of

    the project

    Use of decision rule forproject investment

    Investment

    Decision

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    13/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    13

    e-learn

    ing

    co

    urs

    e

    Time Value of Money

    Interest rate, or the rate of capital growth, is the rate of gain

    received from an investment. For example, a 11% interestrate indicates that for every dollar of money used, anadditional $0.11 must be returned as payment for the use ofthat money.

    The relationship between interest and time leads to theconcept of the time value of money.

    Money has an earning power. A dollar in hand now is worthmore than a dollar received n years from now. This isbecause having the dollar now provides the opportunity forinvesting that dollar for n years more than the dollar to bereceived n years hence, i.e. this investment will earn a return.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    14/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    14

    e-learn

    ing

    co

    urs

    e

    Time Value of Money (Contd.)

    This can be illustrated as:

    The purchasing power of a dollar changes through time. This is because

    the future values are eroded by inflation.

    An entrepreneur expects to gain a premium on his investment, to allow forthe following three factors: inflation, risk taking and the expectation of a realreturn.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    15/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    15

    e-learn

    ing

    co

    urs

    e

    Present Worth Calculation Present valuing (discounting) is central to the financial and

    economical evaluation process. Since most of the project costs, aswell as benefits, occur in the future, it is essential that these shouldbe discounted to their present value (worth) to enable properevaluation.

    Hence, the present worth (P) of a future amount (say, Fn) in year n

    will be calculated as:

    P = Fnx [1/(1+i)n]

    That is,

    Present Value (P) = Fnx Discount Factor

    where, discount factor = 1/(1+i)n

    For example, if Fn= $1,000, i = 12% per year and n = 5 Years, then,

    P = $1,000 x [1/(1 + 0.12)5] = $567.40

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    16/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    16

    e-learn

    ing

    co

    urs

    e

    Future Worth Calculation

    Future worth analysis calculates the future worth of an

    investment undertaken. Future value is simply the sumto which a dollar amount invested today will grow givensome appreciation rate.

    The future amount (Fn) in year n of a present principalamount, P, is given by:

    Fn= P(1 + i)n ..(1)

    For example, if P= $567.40, i = 12% per year and n = 5 Years,

    then, Fn= $567.40 x (1 + 0.12)5= $1,000

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    17/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    17

    e-learn

    ing

    co

    urs

    e

    Equivalence relationship between F and P

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    18/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    18

    e-learn

    ing

    co

    urs

    e

    Capital Recovery Factor (CRF)

    A Capital Recovery Factor (CRF) converts a present

    value into a stream of equal annual payments over aspecified time, at a specified discount rate (interest).

    The value of an equal payment (A) to be made in each ofn periods here is given by:

    A = P [i(1+i)n

    ]/[(1+i)n-1

    ]That is, A = P x CRF

    Where, CRF= capital recovery factor = [i(1+i)n]/[(1+i)n-1]

    The capital recovery factor can be interpreted as theamount of equal (or uniform) payments to be received forn years such that the total present value of all theseequal payments is equivalent to a payment of one dollarat present, if interest rate is i.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    19/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    19

    e-le

    arn

    ing

    co

    urs

    e

    Annuity factor

    Given uniform cash flow series (A), Find P.

    Present value of the series in this case is givenby:

    P = A x Annuity factor

    where, Annuity factor = 1/CRF

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    20/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    20

    e-le

    arn

    ing

    co

    urs

    e

    Example

    Given, P = $250,000, i = 8% per year, N = 6 years, find A.

    $ 250,000

    0

    1 2 3 4 5 6

    A A A A A A

    Years

    Figure: A loan cash flow diagram

    Here, CRF = 0.2163

    A = $250,000x CRF = $54,075

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    21/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    21

    e-le

    arn

    ing

    co

    urs

    e

    Criteria for Financial Viability of a Project

    There are several alternative criteria for financialevaluation. They are:

    Net Present Worth (NPW) (or Net Presentvalue)

    Annual Equivalent Worth (AE) Financial Internal Rate of Return (FIRR)

    Benefit-Cost Ratio (B/C ratio) Payback Period (a simple but not sound

    basis)

    Net Present Worth (NPW): It is the difference

    between the present value of cash inflows (revenues) andthe present value of cash outflows (costs) at the minimumattractive rate of return of the project owner.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    22/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    22

    e-le

    arn

    ing

    co

    urs

    e

    Basic procedure for net present worth calculation

    1. Determine the interest rate that the firm wishes to earn on its

    investments. This interest rate is often referred to as either arequired rate of return or a minimum attractive rate of return(MARR).

    2. Estimate the service life of the project.3. Estimate the cash inflow for each period over the projects

    service life.4. Estimate the cash outflow over each service period.5. Determine the net cash flows:

    net cash flow = cash inflow cash outflow

    6. Find the present worth of each years net cash flow at theMARR.

    7. Add up all the present worth figures during the service life of theproject. The sum so obtained is the projects NPW.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    23/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    23

    e-le

    arn

    ing

    co

    urs

    e

    Net Present Worth Criterion (Contd.)

    A positive NPW means that the equivalent worth of the inflows isgreater than the equivalent worth of outflows, so the project makes aprofit.

    Therefore, the decision rule will be as follows:

    If NPW(i) > 0, accept the project for investment.

    If NPW(i) = 0, remain indifferent.

    If NPW(i) < 0, reject the investment.

    where, i = MARR.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    24/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    24

    e-le

    arn

    ing

    co

    urs

    e

    Annual Equivalent Worth

    The annual equivalent worth (AE) criterion provides an alternative

    basis for measuring the worth of an investment by determining equalpayments on an annual basis.

    To compute AE, first of all we have to find the net present worth(NPW) of the original series and then multiply this amount by the

    capital recovery factor. The decision rule is as follows:

    If AE(i) > 0, accept the project for investment.

    If AE(i) = 0, remain indifferent to the investment.

    If AE(i) < 0, reject the project for investment. Note that, accepting a project that has a positive AE(i) is equivalent to

    accepting a project that has a positive PW(i).

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    25/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    25

    e-le

    arn

    ing

    co

    urs

    e

    Financial Internal Rate of Return (FIRR) The FIRR is an indicator to measure the financial return on

    investment of an income generation project and is used to make theinvestment decision.

    The FIRR is obtained by equating the present value of investmentcosts (as cash out-flows) and the present value of net incomes (ascash in-flows) and thus finds out the break-even interest rate, i*.

    In general, the decision rule is as follows: If FIRR > MARR, then, accept the project. If FIRR = MARR, then, remain indifferent. If FIRR < MARR, then, reject the project.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    26/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    26

    e-le

    arn

    ing

    co

    urs

    e

    Benefit-Cost Ratio (B/C ratio)

    B/C ratio is the ratio of the total present value ofbenefits during the service life of the project to thetotal present value of the costs at the MARR.

    A project is accepted for investment if B/C ratio isgreater than or equal to unity and rejected otherwise.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    27/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    27

    e-le

    arn

    ing

    co

    urs

    e

    B/C Ratio (Contd.)

    A

    Initial cost $ 2Annual benefit and

    costs:$ 1Power Sales

    -

    Let us consider an example of a hydropowerproject as follows:

    Interest rate=12%, Life=50 yearsAnnual Benefit = 1000000 + 250000

    + 350000 + 100000

    = $ 1700000

    Present value of benefit

    = 1700000 *(annuity factor)

    = 1700000*18.2559

    = $ 31035030Then,Present value of operating and maintenance cost = 200000 * 18.2559

    = $ 3651180Total cost (C) = 25000000+ 3651180B/C ratio = 31035030 / (3651180 + 25000000) = 1.08Since the B/C ratio is greater then unity, the project is accepted!

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    28/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    28

    e-le

    arn

    ing

    co

    urs

    e

    Payback Period The payback period is the time that a project is expected to take in

    order to earn net revenue equal to the capital cost of the project.

    It is utilized for small investments, like improvements and energyefficiency measures, since it is easy to understand by business

    managers.

    Drawbacks

    - It tells the analyst nothing about the project earning rate after thepayback period and does not consider the total profitability or size ofthe project.

    - If a company makes investment decisions solely on the basis of thepayback period, it considers only those projects with a paybackperiod shorter than the maximum acceptable payback period.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    29/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    29

    e-le

    arn

    ing

    co

    urs

    e

    Payback Period (Contd.)

    The payback period method ignores inflation and discriminatesagainst large capital-intensive infrastructure projects with longgestation times. Therefore, it is a poor criterion in itself and it mustbe used in conjunction with other criteria.

    The Pay- Back Period can be calculated as

    Pay-back period = Total Investment Cost Subsidy amountAnnual Revenue Annual Expenditure

    If the subsidy amount is not given then we can exclude the subsidy

    amount in the above example.

    Fl Ch f Fi i l A l i d U i

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    30/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    30

    e-le

    arn

    ing

    co

    urs

    e

    Flow Chart of Financial Analysis under UncertaintyDefine the parameters of the project

    e.g. Service life , Discount Rate , Size ofthe Project , Demand , etc .

    For a given size of the RE project ,

    determine the cash inflows and cash

    outflows for each Year

    Calculate the total NPW or

    alternative financialindicator of the project

    Use of decision rule

    for project investment

    Investment

    Decision

    Sensitivity Analysis

    Break -even Analysis

    Scenario Analysis

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    31/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    31

    e-le

    arn

    ing

    co

    urs

    e

    Financial Analysis under Uncertainty In the foregoing discussion, we assumed that all the parameters of the

    project for financial evaluation are known for certainty. However, this isnot usually the case. From a practical point of view the project

    parameters may face uncertainty and the actual value could vary.

    Projects that involve new technologies (renewable and clean-coaltechnologies), or projects with lengthy lead times (nuclear and hydro-power) involve a lot of investment and have more than the average levelof risk.

    For example, the demand may not turn out to be as estimated, the tariffis lower than expected, project execution may take more time andinvolve more cost than planned.

    In RE projects, RE resource availability itself is subject to some

    uncertainty and hence the uncertainty in RE output.

    Cost overruns, which are caused by project delays, or inaccuracies inestimation do not only significantly change project costs but alsosubstantially reduce net benefits.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    32/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    32

    e-le

    arn

    ing

    co

    urs

    e

    Financial Analysis under Uncertainty(contd.)

    Generally, there are several procedures toanalyze the project under uncertainty,such as:

    Sensitivity Analysis

    Break-Even Analysis

    Scenario Analysis

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    33/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    33

    e-le

    arn

    ing

    co

    urs

    e

    Sensitivity Analysis A sensitivity analysis reveals how much the NPW will

    change in response to a given change in an input variable.

    This kind of analysis determines the effect on the NPWwith variations in the input variables such as revenues,operating cost, and salvage value etc.

    Sensitivity analysis sometimes also called as what-ifanalysis.

    Sensitivity analysis begins with a base case situation,which is developed by using the most likely values foreach input. Then the value of the specific variable ofinterest is changed above or below its most likely value,while holding all other variables constant.

    S (C )

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    34/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    34

    e-le

    arn

    ing

    co

    urs

    e

    Sensitivity Analysis (Contd.)Next, a new NPW for each of the values are obtained.

    A convenient and useful way to present the results of asensitivity analysis is to plot sensitivity graphs.

    The slopes of the lines show how sensitive the NPW is to

    changes in each of the inputs.

    The steeper the slope, the more sensitive the NPW is toa change in a particular variable. Sensitivity graphsidentify the crucial variables that affect the final outcomemost.

    Let us construct a sensitivity graph for five of the transmissionprojects key input variables such as unit price, product demand,variable cost, fixed cost and salvage value.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    35/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    35

    e-le

    arn

    ing

    co

    urse

    Sensitivity Analysis (Contd.)

    The base case NPW is $40,169. We plot the base case NPW on the

    ordinate of the graph with 0% deviation and then reduce the value ofthe input variables by 5% of its base case value and recompute theNPW with all other variables held at their base case value. Werepeat the process by either decreasing or increasing therelative deviation from the base case.

    FromFigure 1, we can see that the projects NPW is

    - Very sensitive to the changes in product demand and

    unit price,

    - Fairly sensitive to changes in variable costs, and

    - Relatively insensitive to changes in the fixed cost and the salvage

    value.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    36/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    36

    e-le

    arn

    ing

    co

    urse

    Sensitivity Analysis (Contd.)

    Sensitivity Analysi

    0

    10000

    20000

    30000

    4000050000

    60000

    70000

    80000

    90000

    -20% -15% -10% -5% 0% 5% 10% 15% 20%

    Deviation

    NPW(1

    5%) Unit Price

    Demand

    Variable Cost

    Fixed Cost

    Salvage Value

    Figure 1: Sensitivity Graph

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    37/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    37

    e-le

    arn

    ing

    co

    urse

    Break-Even Analysis

    When we perform a sensitivity analysis of a project, we are asking

    how serious the effect of lower revenues or higher costs will be onthe projects profitability. Sometimes the question may be insteadhow much sales or revenue can decrease below forecasts beforethe project begins to lose money. This type of analysis is known asbreak-even analysis.

    Break-even analysis is a technique for studying the effect ofvariations in output on a firms NPW.

    Figure 2 shows the plot of the PWs of cash inflows and outflowsunder various assumptions about annual sales. The two lines

    crosses when sales are X1 units, the point at which the project hasa zero NPW. It is seen that as long as the sales are greater orequal to X1 units the project has a positive NPW.

    Break even Analysis

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    38/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    38

    e-le

    arn

    ing

    co

    urse

    Break-even Analysis

    0

    0

    Y1

    Y2

    Y

    NPW(MARR %)

    Annual Sales Units (X)

    X1 units

    Loss

    ProfitBreak - even point

    Outflow

    Inflow

    Break Even Analysis basedon net cash flow

    Figure 2:

    X1

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    39/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    39

    e-le

    arn

    ing

    co

    urse

    Scenario Analysis

    A more comprehensive approach to deal with uncertainty than

    sensitivity and break-even analysis is Scenario Analysis. Both Sensitivity and Break-even analysis are useful but they have

    certain limitations. Often it is quite difficult to specify precisely therelationship between a particular variable and the NPW. Therelationship is further complicated by interdependencies among the

    variables. It may also complicate the analysis too much to permitmovement in more than one variable at a time.

    Scenario Analysis is a technique that considers the sensitivity ofNPW both to changes in key variables and to the range of likely

    values of those variables. For example, in its simplest form it involves selecting scenarios such

    as, a best-case scenario, a worst-case scenario and the most-likely-case scenario.

    S (C )

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    40/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    40

    e-le

    arn

    ing

    co

    urse

    Scenario Analysis (Contd.)

    The best-case scenario will incorporate future parameters that are morefavorable to the project success than they appear at the time of evaluation.

    The worst-case scenario is the analysis with less favorable values such aslow unit sales, low unit price, high variable cost per unit, high fixed cost etc.

    The most-likely-case scenario (base case) is the analysis with the mostlikely inputs and outputs from the point of view of the project evaluator.

    The NPW under the worst and the best conditions are then calculated andcompared with the expected, or the base case, NPW.

    Generally, we find that the worst case produces a negative NPW, the bestcase produces a large positive NPW and the most likely case produces apositive NPW.

    But still by only observing all these results, it is not possible and easy tointerpret the scenario analysis or make a decision based on it.

    Clearly, we need estimates of the probabilities of occurrence of the worstcase, the best case and the most likely or base case and all the otherpossibilities.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    41/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    41

    e-le

    arn

    ing

    co

    urse

    Concept of MARR

    The minimum attractive rate of return (MARR) is the

    interest rate at which a firm can always earn orborrow money under a normal operatingenvironment. It is generally dictated by managementand is the rate at which NPW analysis should be

    conducted.

    Usually the selection of the MARR is a policydecision made by top management and it is possible

    for the MARR to change over the life of the project.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    42/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    42

    e-le

    arn

    ing

    co

    urse

    Basis for Selecting the MARR:

    The Cost of Capital of a firm is the required rate of

    return that makes an investment project worthwhile.

    The cost of capital of a firm investing in the projectcan be expressed as the weighted average cost of

    capital if the firm mobilizes its fund through differentsources of financing, e.g., debt and equity.

    The cost of capitalis normally considered as the rate

    of return that a firm would receive if it invested itsmoney somewhere else with a similar risk.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    43/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    43

    e-le

    arn

    ing

    co

    urse

    Basis for Selecting the MARR (contd.)

    Any additional risk associated with the project also has tobe considered.

    If the project belongs to the normal risk category, thecost of capital may already reflect the risk premium.

    However, if we are dealing with a project with higher risk,the additional risk premium may be added onto the costof capital.

    In total, the discount rate (or, MARR) to use for financialevaluation would be equivalent to the firms cost ofcapital for a project of normal risk, but could be muchhigher if we are dealing with a risky project.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    44/45

    JFITASIAN INSTITUTE OF TECHNOLOGY

    44

    e-le

    arn

    ing

    co

    urse

    References

    Park, Chan S., Contemporary Engineering Economics, 4th edition,

    Prentice-Hall, N.J., 2007.

    Hisham Khatib, Economic Evaluation of Projects in the ElectricitySupply Industry, IEE Power and Energy Series 44, London.

    United Nations Development Programme, United NationsDepartment of Economic and Social Affairs, World Energy Council,2000, World Energy Assessment, Energy and the Challenge ofSustainability.

    Intermediate Technology Development Group, 1997, FinancialGuidelines for Micro Hydro Projects, Nepal.

  • 8/8/2019 Bio-Energy 7th Shrestha 1st Revised

    45/45

    45

    e-le

    arn

    ing

    co

    urse

    Thank you!