BIOKOS - Project KA408 Karelia ENPI CBC Program 18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä Bioforum 18th of June

Upload: shona-lawson

Post on 18-Dec-2015

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BIOKOS - Project KA408 Karelia ENPI CBC Program 18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä Bioforum 18th of June

BIOKOS - Project KA408 Karelia ENPI CBC Program

18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä

Bioforum 18th of June

Page 2: BIOKOS - Project KA408 Karelia ENPI CBC Program 18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä Bioforum 18th of June

Content

• Project• Partners• Project Steps• Specific in BIOKOS• Benefits of the BIOKOS

18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä

Page 3: BIOKOS - Project KA408 Karelia ENPI CBC Program 18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä Bioforum 18th of June

Project

18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä

• BIOKOS: bioenergy plant to Kostomuksha

• Years 2013-2014• Budget 1 099 960 EUR• Investment project, target to

build 1 MW CHP plant• Technology is based on

gasification, raw materials are sludge and wood chips

• Plant will be built in connection to water treatment plant

Page 4: BIOKOS - Project KA408 Karelia ENPI CBC Program 18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä Bioforum 18th of June

Partners

• Regional Council of Kainuu, Lead Partner

• Kostomuksha Urban District, will own the plant and biggest own-funding

• PlaNoma Tmi, head planning of the plant

• RecyclingEnergy Int.Corp., technology of the gasification

• MUP Teploseti, design and construction of infrastructure

• OOO AplSov, supply of wood chips and transportation

18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä

Page 5: BIOKOS - Project KA408 Karelia ENPI CBC Program 18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä Bioforum 18th of June

Project Steps

18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä

ACTION PLAN 2013 2014Jan Feb March April May Jun Jul Aug Sep Oct Nov Dec Jan Feb March April May Jun Jul Aug Sep Oct Nov Dec

PLANT                                                

Tendering and purchasing contracts                                                

Manufacturing of components and SCM                                                

Installation and testing in Kajaani                                                

Infra building in Kostomuksha                                                

Export to Russia                                                

Installation and start-up in Kostomuksha                                                

CHP production                                               31th

OTHERS                                                

Bioforum, Kajaani           18th                                    

Bioforum, Kostomuksha                                   ?     ?     ?

Reporting                                                

Page 6: BIOKOS - Project KA408 Karelia ENPI CBC Program 18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä Bioforum 18th of June

Specific in BIOKOS• Plant delivery and investment project

– Supply Chain Management• Equipment/manufacturing, automation, technology all together

– Technical Requirements from Russian / The Custom Union’s legislation • New requirements or coming new requirements notice EU regulation like ATEX 94/9/EY,

Machinery Directive 2006/42/EY etc.– Quality Control of Manufacturing – Certification by third party (accredit by Russians requirements)– Export/Import to Russia– The first plant using both technologies together, dryer and gasification – Schedule and budget is limited

• Manufacturing, testing, transportation and customs, installation and start-up must do during project schedule and under the budget

• Project ends 31th of December 2014, no costs to project after that• Planning, Dimensioning, Risk management, Supply Chain Management, Quality Control of

Manufacturing, Co-operation with Supplies and Partners!

=> Only way is to do right things on right time and succeed

18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä

Page 7: BIOKOS - Project KA408 Karelia ENPI CBC Program 18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä Bioforum 18th of June

Benefits of the BIOKOS

• Concrete project which increases using of bioenergy in Karelia• Finnish innovations

– Thermal Dryer– Gasification

• Raw materials are sludge and wood chips– Remaining ash is a form of granular– Possibilities to develop new ash solutions for different applications: it

depends on physical, chemical and mineralogy properties of ash• In business, it creates policies and management model for any further

supply of the future

18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä

Page 8: BIOKOS - Project KA408 Karelia ENPI CBC Program 18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä Bioforum 18th of June

More information

• Project Manager Sanna Nikola-Määttä tel. +358 44 410 0745 or [email protected]

• www.biokospower.com

18/06/2013 Regional Council of Kainuu / Sanna Nikola-Määttä