bioremediation

29
BIOREMEDIATION 1

Upload: reshma-soman

Post on 09-Jan-2017

92 views

Category:

Environment


0 download

TRANSCRIPT

Page 1: Bioremediation

1

BIOREMEDIATION

Page 2: Bioremediation

2

INTRODUCTION• Bioremediation is defined as the use

of biological treatment systems to destroy or reduce the concentration of hazardous wastes from contaminated sites.

• Economical, safety• Cost-effective, permanent solution to

clean up soils contaminated with xenobiotic compounds

• At least six times cheaper than incineration and three times cheaper than confinement

Page 3: Bioremediation

3

Introduction• New and exciting field • Performed off-site when

contamination is superficial, but it will have to be in situ when the contaminants have reached the saturated zone

• General components and characteristics

Microbial systemsType of contaminantGeological and chemical conditions

at the contaminated site

Page 4: Bioremediation

4

Page 5: Bioremediation

5

Advantages• Can be done on site• Minimum site disruption is caused• Eliminates transportation costs and

liabilities• Eliminates long-term liabilities• Uses biological system, often less

expensive• Can be coupled with other treatment

techniques

Page 6: Bioremediation

6

Disadvantages• Some chemical compounds are not

biodegradable • Extensive monitoring required• Each site has specific requirements• Potential production of toxic unknown

sub-products is possible• Strong scientific support is needed

Page 7: Bioremediation

7

BIOREMEDIATION TECHNIQUES

Page 8: Bioremediation

8

Bioremediation techniques• Divided into 3 categories :

In-situ, ex-situ and ex-situ slurry• In situ - soil and associated ground water

is treated in place without excavation• Ex situ – excavated prior to treatment• Ex situ slurry – creation and maintenance

of soil- water slurry as bioremediation medium

• Slurry can be maintained either in a bioreactor or in a pond lagoon

Page 9: Bioremediation

9

In situ remediation techniques

Page 10: Bioremediation

10

In situ remediation techniques• Bioremediation on land• Land farming• Bioventing• Biosparging• Bioaugmentation

Page 11: Bioremediation

11

Bioremediation on land• Depend on the area contaminated, the

properties of the compounds involved, the conc of contaminants, time required to complete the bioremediation

• The contamination can be treated on site or the contaminated material excavated and treated on or off site.

• If contaminant is water soluble a pump-and-treat technique used

• Introduced into contaminated areas and removed at another site to be treated on or off site

Page 12: Bioremediation

12

Land farming• The simplest of the on-site treatment• Involve mixing of the soil by

ploughing or some form of mechanical tilling

• Ploughing increases the O₂ levels in the soil and distributes contaminants more evenly, which increases the rate of degradation.

• Nutrients added to increase biodegradation

• 4-6 months required to remove contaminants such as PAHs

Page 13: Bioremediation

13

Land farming• Method is best suited for shallow

contamination of soil surface• Treatment area is lined and dammed

to retain any contaminated leachate• Rate of degradation depends on the

microbial pollution, the type and level of contamination, and the soil type

• Avg half-life for the degeneration of diesel fuel and heavy oils is in the order of 54 days with this type of system

Page 14: Bioremediation

14

Land farming

Page 15: Bioremediation

15

Bioventing • In situ process, which combines an

increased oxygen supply with vapour extraction

• A vacuum is applied at some depth in the contaminated soil

• This draws air down into the soil from holes drilled around the site and sweeps out any volatile organic compounds

• Nutrient supplementation can be provided by running nutrients into trenches dug across the site

Page 16: Bioremediation

16

Bioventing • The increased supply of air will

increase the rate of natural degradation by the aerobic micro-organisms.

• Only effective for reasonably volatile compounds, where soil is permeable

• Vapour extracted may need some form of treatment

• One biological solution is the use of biofilters

Page 17: Bioremediation

17

Page 18: Bioremediation

18

Biosparging • Process to increase the biological

activity of the soil by increasing the supply of oxygen by sparging air or oxygen into the soil

• Air injection replaced by pure oxygen – increase degradation rates

• The expense of treatment limited its application to highly contaminated sites but on-site degradation of oxygen has reduced costs

Page 19: Bioremediation

19

Biosparging • Hydrogen peroxide used on a

number of sites but it can be toxic at low concentrations to MO

• This process is similar to soil vapor extraction, which can be used for volatile contaminants

Page 20: Bioremediation

20

Bioaugmentation • The addition of nutrients injected into

contamination well below the surface can be used to stimulate the indigeneous microbial population.

• This technique can be combined with the addition of specific MO

Page 21: Bioremediation

21

Ex situ remediation techniques

Page 22: Bioremediation

22

Ex situ remediation techniques• If the contaminated material is

excavated it can be treated on or off site, which is often a more rapid method of de-contaminating the area

• The techniques include– Composting– Biopile process– Bioreactors

Page 23: Bioremediation

23

Composting • Solid-phase treatment carried out

after extraction• Composting materials such as straw,

bark and wood chips is mixed with the contaminated soil and piled into heaps

• Process work in the same way as normal system which rise the temp to 60° C and above cause microbial activity

• higher temp encourages the growth of thermophilic bacteria

• Increased costs of this type of system restrict it to highly contaminated materials

Page 24: Bioremediation

24

Composting • Organic materials added vegetables,

fruit and garden waste• Added at a conc of 33-75%• Temp above 70° C achieved after 6-

22 days of incubation, with turning every 7 days and 84-86% of the contamination was removed by day 40 compared with 35% in untreated soil.

Page 25: Bioremediation

25

Biopile process• Soil heaped into piles within a lined

area to prevent leaching• Piles covered with polythene and

liquid nutrients applied to the surface• Aeration improved by applying

suction to the base of the pile as in a composting system

• Leachate collected by pipes at the base and recycled if necessary

• Space limited

Page 26: Bioremediation

26

Biopile process

Page 27: Bioremediation

27

Bioreactors • Soil extracted from a contaminated site can be

treated as a solid waste or a liquid leachate in bioreactors of various designs.

• Control of parameters such as temp, pH, mixing and O₂ supply – improve degradation rates

• Used for Solid waste slurries can be solid-bed, fluidized bed, and stirred tank bioreactors

• When treating liquid leachates and contaminated ground water all those reactors – waste water treatment are used

Page 28: Bioremediation

28

Bioreactors

Page 29: Bioremediation

29