Birr Public Realm 2009-2013Work achieved to date

February 2013

2

In partnership with…

We wish to thank the following groups for their support and assistance in the physical

development and enhancement of this beautiful town:• Birr Chamber of Commerce• Birr Tidy Town Association• Birr Lions Club• Birr Castle and Demesne• Birr Historical Society• Irish Georgian Society• Heritage Council• Offaly Local Development Company• Shannon Development• Department of Environment, Community & Local Government• Department of Transport, Tourism and Sport• Offaly County Council

February 2013

3

1. Castle Street - Before

February 2013

4

1. Castle Street - After

February 2013

Key Points• Vegetation reduced

improving views of Castle walls

• Unnecessary signage removed

• Damaged railings stored• High limestone kerb

provided to enhance bend and increase safety

• Corner pavement widened• Road marking to be

provided

5

2. Column Restoration

February 2013

Key Points• Civic Structures Grant €34,000• Stone conservation works

6

3. Old Church and Graveyards

February 2013

Key Points• Looking at mechanism for

controlled access after conservation of the tower

• Part of general graveyard works• Continued management scheme

7

4. Camcor River Park

February 2013

Key Points• LAMA award 2012• New pathways and footbridge

provided• Additional future proposals• Enhancing setting (Roscrea

approach)• Improved signage

8

5. Gateways – Landscaping Before

February 2013

9

5. Gateways – Landscaping After

February 2013

Key Points• Signage removed• Roadway reordered• Walkways provided with raised

tree lined bank• Cycle ways positioned between

raised banked, box hedge belt

10

6. Gateways - Sculpture

February 2013

Consultation took place, Steel elements underway, Plan to install in May 2013

11

7. Gateways – Advertising Signage

February 2013

12

8. Frontage Improvements - Before

February 2013

13

8. Frontage Improvements - After

February 2013

14

9. Shopfront Enhancement Scheme

February 2013

15

10. Street Signage

February 2013

Ongoing

16

13. Neighbourhood Spaces

February 2013

17

14. Birr Town Trail - Updated

January 2013

18

15. Cycle Network

January 2013

16. Derelict Sites

February 2013 19

• 16 Derelict Site Notices sent out last year

• Approximately 9 have since carried out improvement works

• Follow up letters, meetings and discussions with Tidy Towns

20

18. Sports and LeisureSkateboard park committee

February 2013

Active age park

21

Birr Public Realm 2013 Proposals

February 2013

RMcK

22

A. Roofscape Improvements• Proposals by BTC to provide

roofscape improvements in the form of gutter cleaning along Main Street and adjoining areas.

February 2013

23

B. Cornmarket Sq – Church St – Main St

January 2013

In Progress

24

Cornmarket Square - Sketch Proposals

February 2013

25

C. Emmet Square

February 2013

26

Proposed Traffic and Pedestrian Movement

February 2013

Two way traffic

One way traffic -Connaught Street

One way traffic – The Green, Main Street

Controlled vehicular access

Pedestrian route – Castle, Church Street to Main Street

Public Car Park

PP

PP

27

A Square for People

February 2013

28

Emmet Square – Sketch Proposals

February 2013

RMcK

Tullamore

Roscrea

Banagher

Bus

Bus

Main Street

29

D. Main Street

February 2013

30

Emmet Square / Main Street – Sketch Proposals

January 2013

RMcK

31

Sculptural Spheres

February 2013

32

E. The Green

February 2013

Public Realm Plan

33

The Green - Tree Planting

February 2013

34February 2013

The Green – Sketch Proposals

RMcK

35

The Green - Sketch Proposals

February 2013

RMcK