bitumen water proofing
TRANSCRIPT
-
7/29/2019 Bitumen Water Proofing
1/23
Water ProofingWater Proofing
Flat RoofsFlat Roofs
byby
Modified BituminModified Bitumin
MembraneMembrane
ByP.J.Sharma,DEN/GHY & K.K.Goswami,DyC
-
7/29/2019 Bitumen Water Proofing
2/23
NecessityNecessity
Conventional methodsConventional methodsWhy this method?Why this method?
What is Modified BituminoWhat is Modified Bitumino
waterproofing membranewaterproofing membrane
EconomicsEconomics
Structural propertiesStructural properties
Sequence of operationSequence of operation
PrecautionsPrecautions
ConclusionConclusion
-
7/29/2019 Bitumen Water Proofing
3/23
NECESSITYNECESSITY
-
7/29/2019 Bitumen Water Proofing
4/23
Conventional methoConventional metho
##
%%
&&
''
((
$*$*
++
-
7/29/2019 Bitumen Water Proofing
5/23
Why Modified Bituminous Watehy Modified Bituminous Wate
Membrane?Membrane?
Proved efficacy of water proofingProved efficacy of water proofing
Aesthetic advantageAesthetic advantage
Easy applicabilityEasy applicability
Excellent structural property,rot prooExcellent structural property,rot proo
Cheap in long term economicsCheap in long term economics
Best suited to high rainfall regions liBest suited to high rainfall regions li
ER & westernER & western ghatghat. In. In LumdingLumding div.div.seasons passed without problem afseasons passed without problem af
this method.this method.
-
7/29/2019 Bitumen Water Proofing
6/23
What is Modified BitumWhat is Modified Bitum
waterproofing membrwaterproofing membr
Manufactured from rich bitumen &Manufactured from rich bitumen &polymer blended together to obtapolymer blended together to obtaexcellent heat resistance & coldexcellent heat resistance & cold
temperature flexibility.temperature flexibility.Polymer modified bitumen is thenPolymer modified bitumen is thenon to a dimensionally stable nonon to a dimensionally stable non--wwpolyester/polyester/fibrefibre glass to obtain higglass to obtain hig
strength, tear & puncture resistanstrength, tear & puncture resistanhighly resistant to substrate movehighly resistant to substrate move
-
7/29/2019 Bitumen Water Proofing
7/23
Modified Bitumen waterproofing Modified Bitumen waterproofing
rollsrolls
-
7/29/2019 Bitumen Water Proofing
8/23
EconomicsEconomics
Long term good performance.Long term good performance.( 10 years manufacturers guaran( 10 years manufacturers guaran
Cost nominal if aesthetic, usabilitCost nominal if aesthetic, usabilit( Terrace remains accessible) co( Terrace remains accessible) co
Easy availability in markets.Easy availability in markets.
-
7/29/2019 Bitumen Water Proofing
9/23
Structural propertieStructural propertie
No floNo floHeat resistanceHeat resistance
Less Less Water absorption (%)Water absorption (%)
No leNo leResistance to water pressureResistance to water pressure
150/1150/1Tear resistance (L/T)NTear resistance (L/T)N
MoreMoreLap joint strength(L/T)N/5cmLap joint strength(L/T)N/5cm
150150Softening point, deg CSoftening point, deg C
10x110x1Roll size, MRoll size, M
44Thickness of Membrane, mmThickness of Membrane, mm
5050Roll weight, KGRoll weight, KG
160g/160g/Carrier weight,Carrier weight,
1515--2525Penetration at 25 deg CPenetration at 25 deg C dmmdmm
700/5700/5Tensile strength (L/T) N/5cmTensile strength (L/T) N/5cm
4040--5050Elongation at Break (L/T)%Elongation at Break (L/T)%
-
7/29/2019 Bitumen Water Proofing
10/23
Sequence of operaSequence of operat
The concrete surface shall be cleaneThe concrete surface shall be cleanethoroughly of all laitance, loose particthoroughly of all laitance, loose particetcetc
Existing substrate treated with any oExisting substrate treated with any o
waterproofing method like limewaterproofing method like lime surkhsurkhbe dismantled & surface to be modifiebe dismantled & surface to be modifiepolymer modified mortar as per manupolymer modified mortar as per manuspecifications.specifications.
Apply primer coat with solvent basedApply primer coat with solvent based primer as specified by the manufactuprimer as specified by the manufactucleaned &cleaned & levelledlevelled surface.surface.
-
7/29/2019 Bitumen Water Proofing
11/23
Prepared substrate
-
7/29/2019 Bitumen Water Proofing
12/23
Application of primer
-
7/29/2019 Bitumen Water Proofing
13/23
Sequence of operaSequence of operaUnroll the modified bitumen waterprooUnroll the modified bitumen waterproo
membrane rolls. Align the rolls correcmembrane rolls. Align the rolls correcit in alignment before torching.it in alignment before torching.
Use gas burner to heat substrate & unUse gas burner to heat substrate & un
softening points. When the embossingsoftening points. When the embossing
disappears, roll forward & press firmlydisappears, roll forward & press firmlysubstrate to bond from the lower end substrate to bond from the lower end
higher end.higher end.
Keep overlap margin for minimum 80Keep overlap margin for minimum 80
longitudinal & 150 mm in transverse dlongitudinal & 150 mm in transverse d
The treatment of the horizontal surfacThe treatment of the horizontal surfac
continued to the vertical side wall.continued to the vertical side wall.
-
7/29/2019 Bitumen Water Proofing
14/23
Aligning the rolls
-
7/29/2019 Bitumen Water Proofing
15/23
Heating the substrate & underside of roll to s
-
7/29/2019 Bitumen Water Proofing
16/23
Heating the substrate & underside of roll to s
-
7/29/2019 Bitumen Water Proofing
17/23
Sequence of operSequence of opera
Heat both the overlaps & use rouHeat both the overlaps & use rou
trowel to seal overlap. Excess cotrowel to seal overlap. Excess co
should be smoothened & presseshould be smoothened & presse
seam using hot trowel.seam using hot trowel.All angles &All angles & upstandsupstands should be should be
with extra care to ensure the perwith extra care to ensure the per
bondage. Seal the edges well intbondage. Seal the edges well int
& protect with a& protect with a PolysulphidePolysulphide seasea
-
7/29/2019 Bitumen Water Proofing
18/23
Sealing theoverlaps
-
7/29/2019 Bitumen Water Proofing
19/23
Treated surface
-
7/29/2019 Bitumen Water Proofing
20/23
Sequence of operaSequence of operatFor nonFor non--foot traffic area, applyfoot traffic area, apply alal
paint over the treated surface.paint over the treated surface.
For foot traffic area, overlay with For foot traffic area, overlay with
thick concrete screed of 1:2:4 (Bythick concrete screed of 1:2:4 (By
with 10mm & down well gradedwith 10mm & down well gradedaggregates & concrete should beaggregates & concrete should be
with a normal admixture as per thwith a normal admixture as per th
direction of manufacturer.direction of manufacturer.
The concrete shall be cured with The concrete shall be cured with atleastatleast 7 days.7 days.
-
7/29/2019 Bitumen Water Proofing
21/23
PrecautionsPrecautionsSurface preparation is extremely imSurface preparation is extremely im
Slope of substrate has to be correcSlope of substrate has to be correc
minutest detail, standing water is hminutest detail, standing water is h
WorkmanshipWorkmanship.over burning,unde.over burning,unde
to be avoided.to be avoided.
No wetness during fixing.No wetness during fixing.
-
7/29/2019 Bitumen Water Proofing
22/23
ConclusionConclusion
This method takes advantage of tThis method takes advantage of trevolution of polymer science to prevolution of polymer science to p
high strength , non degradable,high strength , non degradable,
impermeable character to traditioimpermeable character to tradition
bituminous overlaybituminous overlayNo glue fixing, but torch burning gNo glue fixing, but torch burning g
permanent bond with substrate.permanent bond with substrate.
Hence this method can be effectivHence this method can be effectiv
adopted in all areas for waterprooadopted in all areas for waterproo
-