BIWEEKLY SUMMARY REPORT June 26, 2020 – July 9, 2020 Construction Management of the Jordan School Expansion Project (JSEP) and the Schools for a Knowledge Economy Project (SKEP) Submission Date: July 12, 2020 IDIQ Contract Number: AID-OAA-I-15-00053 Task Order Number: 72027818F00005 Activity Start Date and End Date: Sept. 16, 2018 to Sept. 15, 2021 COR Name: Dr. Issam Omar Submitted by: Michael McGovern, Chief of Party Trigon Associates, LLC Um Uthaina, Saad B. A. Waqqas St. Tel: +962-6-77-047-4411 Email: [email protected] This document was produced for review by the United States Agency for International Development Jordan Mission (USAID/JORDAN). TABLE OF CONTENTS 1.0 CURRENT JSEP AND SKEP CM TASK ORDER ACTIVITIES REPORT ....................................................................................................................................... 1 2.0 JSEP SUMMARY .............................................................................................................................................................................................................................. 5 3.0 SKEP SUMMARY............................................................................................................................................................................................................................. 7 4.0 JSEP & SKEP DETAILED PROGRESS REPORT .............................................................................................................................................................................. 8

Upload: others

Post on 17-Apr-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BIWEEKLY SUMMARY REPORT

BIWEEKLY SUMMARY REPORT June 26, 2020 – July 9, 2020

Construction Management of the Jordan School Expansion Project (JSEP) and the Schools for a Knowledge Economy Project (SKEP) Submission Date: July 12, 2020 IDIQ Contract Number: AID-OAA-I-15-00053 Task Order Number: 72027818F00005 Activity Start Date and End Date: Sept. 16, 2018 to Sept. 15, 2021 COR Name: Dr. Issam Omar Submitted by: Michael McGovern, Chief of Party

Trigon Associates, LLC Um Uthaina, Saad B. A. Waqqas St. Tel: +962-6-77-047-4411 Email: [email protected] This document was produced for review by the United States Agency for International Development Jordan Mission (USAID/JORDAN).

TABLE OF CONTENTS 1.0  CURRENT JSEP AND SKEP CM TASK ORDER ACTIVITIES REPORT ....................................................................................................................................... 1 

2.0  JSEP SUMMARY .............................................................................................................................................................................................................................. 5 

3.0  SKEP SUMMARY ............................................................................................................................................................................................................................. 7 

4.0  JSEP & SKEP DETAILED PROGRESS REPORT .............................................................................................................................................................................. 8 

Page 2: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            1    

1.0 CURRENT JSEP AND SKEP CM TASK ORDER ACTIVITIES REPORT

SN Activity Description Status 1 COVID-19 Emergency and JSEP

and SKEP Disruption While it is clear that the COVID-19 Emergency is not over, the GOJ has almost completely opened the economy and relaxed all restrictions. The Ministry of Public Works and Housing (MPWH) continues to increase staffing levels in their offices but it is still not operating at full strength. Construction at JSEP Phase IV and SKEP Phase II sites has practically returned to full capacity (even though they are both extremely late) In summary, activity has restarted. JSEP and SKEP Contractors unfortunately are not doing a good job complying with the Ministry of Labor (MOL) Directive #12 – Prevention of CV-19 Transmission Measures - Construction Activities.

2 JSEP Phase V Contractor Mobilization and SE Start Up

The MPWH issued the Phase V, Package 1 & 2 Commencement Letter to Bitar on May 27, 2020. JSEP Phase V: is in the Mobilization Stage. Commencement Date for Construction Work was effective on June 28, 2020.

3 Ending JSEP Phase IV ASAP Without Sacrificing Construction Quality

Medanat Bi-weekly Phase IV Progress Meetings. A good and Proposed Close Out Plan was presented by Medanat SE for the JSEP Phase IV Contract at a meeting with MPWH, USAID/JORDAN and the CMTO team. MPWH and Medanat will coordinate to complete Taking Over inspections for Substantially Completed schools and to start studying Extension of time and Variation Orders. The CMTO team will assist as appropriate. There was an informational meeting held at the CMTO office on June 23, 2020 with engineers from MPWH and Medanat in presence of a USAID/JORDAN representative to discuss the Time Extensions and Variation Orders. Medanat continues to work with the four Contractors to obtain letters from them regarding their potential Time Extensions to be discussed and submitted to MPWH for final review and approval. Three school projects went to Substantial Completion during the reporting period, 9 Projects remain to achieve Substantial Completion but all are remarkably close.

   

Page 3: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            2    

4 SKEP II, Package 2, Rawashdeh Contractor Performance Improvement Evaluation.

All three projects remain far behind schedule. CCG recommended during the reporting period to MPWH to terminate the Rawashdeh contract. MPWH intends to send Notice Letter for the Contractor regarding the delay in the project. CMTO team attended joint meeting with MPWH on July 1, 2020 at CCG offices to discuss the disputes that were submitted by the Contractor. It was agreed that CCG will ask for required supporting documents to be submitted by the Contractor in order to proceed. CMTO team attended meeting at Engicon on July 8, 2020 to discuss the septic waste holding tank at Althanieh school and site water drainage issues at Alameer Hamzeh school. CMTO team also discussed the Defects & Liability issues of SKEP Phase I and the required actions from Engicon and MPWH.

5 MPWH JSEP and SKEP Procurement Status Summary

STATUS SUMMARY: CMTO staff continues submitting the weekly JSEP and SKEP PROCUREMENT SUMMARY STATUS Report to follow up the procurement program calendar and issues with MPWH. Most of procurement activities continued. These reports are private and are close-held. JSEP Phase V Supervisory Engineer Contract Review: For Package 6, 7 & 8. The technical evaluation is under process. JSEP Phase V – Construction Contract – For Packages 6, 7 & 8. The technical evaluation is under process. JSEP Phase V Supervising Engineer Contract- For Package 3, 4 & 5. Under technical evaluation. JSEP Phase V – Construction Contract – For Package 3, 4 & 5. Under technical evaluation. SKEP Phase III – Supervisory Engineer Contract Review – Under process. SKEP Phase III – Construction Contract Agreement for Package 2 signed and it was transferred to Construction stage, for Package 1 the IFT released for retendering with new conditions.

   

Page 4: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            3    

6 SKEP Phase II – Elevators SKEP Phase I

SKEP Phase II: Elevator work: Elevators have been totally completed and initially operated by the Contractor, the only still pending items are Testing and Commissioning and the inspection by JISM; Testing and Commissioning of the Elevators are still pending in all schools due to pending electrical connections. For Package 2, MPWH issued the letter of approval of the Sub-Contract Agreement that the Contractor had already signed with the Supplier. The Contractor is still in the process of preparing and submitting the workshop drawings, the elevators are expected to be delivered within the next four (4) months. The CMTO team is trying to find commencement and projected completion dates and will report them when we will have the information. SKEP Phase I All sites were handed over to the Elevators’ Contractor and the Commencement Letter has not been issued yet. The Advance Payment letter signed by MPWH and submitted to USAID/JORDAN. The CMTO team has met the Contractor at Al Tase’a School in Aqaba for handing over on July 1, 2020, it was explained to the Contractor the working conditions during the Tawjihi Exams, and CMTO’s H&S Engineer explained the appropriate way, tools and signs of closing the Elevator rooms needs to be done so as to secure it safely against safety issues with the students and teachers.

7 JSEP IV, V and SKEP II, lll CONTRACT COMMUNICATION TRACKING LOG

CMTO team continues to track all correspondences between all stakeholders, filter them and assign the concerned personnel to do the necessary follow-up actions. During this reporting period 67 items of correspondence were recorded, two of them needed a CMTO staff personnel prompt action.

8 JSEP Phase II, III, IV/SKEP Phase ll Electrification/Wet Utilities Connection Delays

This reporting period has witnessed good progress of connecting utilities in JSEP Phase lV, eleven (11)new utilities were connected in JSEP Phase lV and one (1) new Utility in SKEP Phase ll. Most of the fees for connecting SKEP Phase ll utilities were paid by MOE and the Contractors of the Electrical and Water Companies are now in the process of getting the Utilities Connected. No new progress have been seen in JSEP Phases ll & lll, although CMTO team had pushed many Utilities to the final stages of connections and made MOE pay for many Utilities, a meeting was held with JSEP Phase ll SE on June 28, 2020 to refocus on connecting the remaining utilities in the schools of this phase. Note that this is a serious issue that could prevent some JSEP Phase IV and SKEP Phase II schools being ready for MOE operations before 1 September 2020. CMTO team continues to assist two Ministries to push the process as appropriate. It was agreed that the USAID/JORDAN COR and CMTO team will meet jointly with the new MOE SG at the end of this month to discuss and stress on the need of MOE support and action here.

Page 5: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            4    

9 Joint Weekly Coordination Meeting with MPWH, USAID/JORDAN

The weekly USAID/JORDAN – MPWH coordination meeting with the USAID/JORDAN COR and the MPWH International Programs Director hopefully continue. One meeting was held at MPWH on Thursday July 2, 2020, the main activities of JSEP and SKEP Programs were discussed, it was agreed to continue these meetings Biweekly as necessary.

10 Coordination Teleconference with USAID/JORDAN, Educational and Youth Sectors.

The Monthly Meeting was held on July 2, 2020, but COP apologies for not attending, since he had another meeting.

11 Field visit to Fatima Alzahraa school at Alaghwar, Karak Governorate

According to the USAID/JORDAN COR request, CMTO team (COP, SGL and Civil Engineer) conducted field visit to the school that was built previously through one program with USAID/JORDAN funded projects, the CMTO team made their assessment and submitted a report to the COR .

12 Mini Workshop: Writing Supervisory Engineer Proposals and Providing Oral Presentations for USAID/JORDAN Funded JSEP and SKEP School Construction Projects Workshop

(CMTO) for JSEP and SKEP team presented a two-hour Workshop at the MPWH Conference Hall that was intended to assist Jordanian architectural & engineering (A&E) firms in developing and presenting excellent and relevant SKEP and JSEP (1) written Supervisory Engineer proposals and (2) oral presentations. The Workshop was based on PowerPoint material and Presentations made by CMTO’s COP and SGL. Nine Jordanian firms sent representatives, as did USAID/JORDAN, the MPWH and the CMTO team.

Page 6: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            5    

2.0 JSEP SUMMARY

Phase Package Supervision Firm Contractor Estimated Physical

Completion (%) * Time Elapsed

(%) ** Comments

Phase I All

Packages Bitar Sadeen Contracting CC CC •This phase is under final taking over stage.

Phase II

1 Al Mostaqbal Al Joud Contracting CC CC • Closing out completed for all packages. • Utilities connections are still in progress.

2 Mohammad Tahayneh for Contracting

CC CC

3 Mohammad Eidi & Sons

CC CC

4 Babel for Contracting CC CC

Phase III 1 Al Baha Mansour Essa Elagaileh

& Partners CC CC • Closing out completed for all packages.

• Utilities connections are still in progress. 2 Chart General CC CC 3 Faz Contracting CC CC

Phase IV

1 Waheeb Medanat

Samara & Yousef Contracting SC SC

• Only 9 Schools out of 47 still Under Construction. All Schools in Package 1 and Package 4 are Substantially Completed. • Due to lack of definitive schedules; it is agreed to use the cost percent complete for controlling and monitoring the work progress.

2 Al Sha’air Contracting SC: (Maymoneh Bent Alhareth (KG), Fahmi Hashim (KG) & Qatr Al Nada (KG))

Ateka (KG) 213% Expansions 213%

Ateka (KG) 87% Expansions 90-95%

3 Taisser Abu Arja Contracting

SC (All KGs, Sport Facility and All Expansions except for Al Karamah Expansions)

Al Karamah Expansions 213%

Al Karamah Expansion 85%

4 Hussein Miqdadi & Partner SC SC

   

Page 7: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            6    

5 Samara & Yousef Contracting

SC: All KGs and Hofa Expansion

Remaining Expansions 211%

Remaining Expansions 83-90%

Phase V

1

Bitar Al Joud Contracting Still in Mobilization Stage (Commencement Date for Construction Work was effective on June 28).

KGs 5% Expansions 4%

• Commencement Date was effective on June 28, 2020. • Soil test completed for five (5) out of six (6) schools in Package 1, and for two (2) out of four (4) schools in Package 2. Test Results are not issued yet. • Demolishing works completed for one (1) out of three (3) schools in Package 1, and for two (2) out of three (3) schools in Package 2.

2

Faz Contracting Still in Mobilization Stage (Commencement Date for Construction Work was effective on June 28).

KGs 5% Expansions 4%

*Estimated Physical Completion for JSEP IV is the Cost Percent Complete due to lack of definitive schedules. **Percentage of Time Elapsed = (Actual Time Elapsed / Original Contract Duration) where Actual Time Elapsed starts from Commencement Date. Note: CC means Construction Completed; SC means Substantially Completed.

Page 8: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            7    

3.0 SKEP SUMMARY

Phase Package Supervision Firm Contractor

Estimated Physical

Completion (%)

Time Elapsed

(%) * Comments

Phase I

1 Engicon Hussein Miqdadi & Partner

CC CC • All schools are completed. • Utilities connections are completed. • Substantially payment submitted to USAID/JORDAN. • All School Sites are handed over to Elevators’ Contractor. Notice to Commence is not issued yet.

2 Al Sha’aer Contracting

CC CC • All schools are completed. • Utilities connections are completed. • All School Sites are handed over to Elevators’ Contractor. Notice to Commence is not issued yet.

Phase II

1

CCG Dijlah Contracting SC SC • All Package 1 schools are Substantially Completed excluding elevators works. The elevators have been totally completed and operated by the Contractor, the only still pending items are Testing and Commissioning and the Inspection by JISM. Testing and Commissioning of the Elevators are still pending in all schools due to pending electrical connections.

2 Mohammad Al Rawashdeh & Sons

64-69% 150% • Construction work progress is behind the schedule; Contractual Completion Date is November 24, 2019. Works were resumed partially since May 03, 2020 in Al Amal School and Al Thaniah School and May 10, 2020 for Prince Hamza School. Based on the current status of SKEP II Package 2 schools; the Completion of the school will not be before the end of the year. • Elevators: MPWH issued the letter of approval the contractor signed the agreement with the Supplier. The Contractor is still in the process of preparing and submitting the workshop drawings, the elevators are expected to be delivered within the next four (4) months.

*Percentage of Time Elapsed = (Actual Time Elapsed / Original Contract Duration) where Actual Time Elapsed starts from Commencement Date. Note: CC means Construction Completed

Page 9: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            8    

4.0 JSEP & SKEP DETAILED PROGRESS REPORT

Phase Schools Per Phase

Supervising Firm

Package No.

Schools Per

Package Contractor Activities and Status Participations and

Comments

Jordan School Expansion (JSEP) Project: Phase I: 27 Schools of JSEP which are Completed the Defects Liability Period (DLP); Phase II, III, IV and V: 138 active project sites, includes schools under construction or taking over in progress or utilities connection in progress or

in warranty period and final handing over JSEP Phase II & III in warranty period and still have not connected all schools with utilities, JSEP Phase IV under construction/taking over in process and utilities in process/ and JSEP Phase V Package1& 2 under construction.

1 27 Bitar Consultants

1 8 Sadeen Contracting

• Remaining punch list items are still pending between MPWH and Contractor.

• This phase is under final taking over stage. 2 9 Sadeen

Contracting • Remaining punch list items are still pending between MPWH and Contractor.

3 10 Sadeen Contracting

• Remaining punch list items are still pending between MPWH and Contractor.

II 36 Al Mostaqbal 1 9 Al Joud Contracting

• Utilities (Electricity) remain a major challenge; there is a minor progress, five (5) schools are completed and four (4) schools are still pending. • For more details see Attached Annex for Utilities Connection. • Package 1 Close-out is completed. • The substantial completion payment submitted to USAID/JORDAN.

2 9 Mohammad Tahayneh for Contracting

• Utilities (Electricity) in eight (8) schools are completed and one (1) school is still pending. • For more details see Attached Annex for Utilities Connection. • Package 2 Close-out is completed. • The Substantial payment submitted to USAID/JORDAN.

Page 10: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            9    

3 12 Mohammad Eidi & Sons

• Utilities (Electricity) remain a major challenge; eight (8) schools are completed and four (4) schools are still pending. MOE agreed on payment of installation the cables for the four schools, and the installation is under process. • For more details see Attached Annex for Utilities Connection. • Package 3 Close-out is completed. • The Substantial payment Submitted to USAID/JORDAN.

4 7 Babel for Contracting

• Utilities (Electricity) remain a major challenge; five (5) schools completed and two (2) schools still pending. • For more details see Attached Annex for Utilities Connection. • Package 4 Close-out is completed. • The substantial completion payment submitted to USAID/JORDAN.

III 33 Baha Consultant Engineering

1 11 Mansour Essa Elagaileh & Partners

• Utilities status: For Electricity there is one (1) school still pending. • For more details see Attached Annex for Utilities Connection. • Package 1 Close-out is completed. • The Substantial payment submitted to USAID/JORDAN.

Page 11: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            10    

2 10 Chart General

• Utilities (Electricity) are connected for all ten (10) schools. • For more details see Attached Annex for Connection. • Package 2 Close-out is completed. •The Substantial payment submitted to USAID/JORDAN.

3 12 Faz Contracting

• Utilities status for Electricity: there is progress; eight (8) schools are completed and four (4) schools still pending. • For more details see Attached Annex for Utilities Connection. • Package 3 Close-out is completed. • The substantial payment submitted to USAID/JORDAN.

IV 48 Waheeb Medanat

1 10 Samara & Yousef Contracting

• All KGs and Expansions are Substantially Completed. For more details, see attached JSEP Phase IV Taking over Table. • First Hand over Inspection for Jabal Al Akhdar School for Girls in JSEP Phase IV Package 1 is completed on July 5, 2020. • Second Hand over Inspection for Sakeb Secondary School for Boys in JSEP Phase IV Package 1 is completed on July 8, 2020. • Utilities-Electricity: six (6) schools are connected, two (2) all payments and procedures are done and waiting for final connection and two (2) is still pending MOE payment. •For more details see Attached Annex for Utilities Connection.

• Only 9 Schools out of 47 still Under Construction. All Schools in Package 1 and Package 4 are Substantially Completed.

• CMTO team attended the First Hand over Inspection for Jabal Al Akhdar School in JSEP Phase IV Package 1 on July 5, 2020. • CMTO staff attended the Second Hand over Inspection for Sakeb Secondary School for Boys in JSEP Phase IV Package 1 on July 8, 2020.

Page 12: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            11    

2 8 Al Sha’air Contracting

• Maymoneh Bent Alhareth (KG), Fahmi Hashim (KG) and Qatr Al Nada (KG) are Substantially Completed. For more details, see attached JSEP Phase IV Taking over Table. • Works are resumed since the second week of May. Percentage of Completion for Ateka (KG) is still 87%. Also, Percentage of Completion for School Expansions range between 90% and 95% (Only percentage of completion of Al Hassan Bin Al Haithem Expansion is increased from 93% to 94%). For more details, see attached JSEP IV Progress Summary Table. • Utilities: Electricity: three (3) Schools will be connected to their existing, all payments and procedures for one (1) school is done and waiting for final connection, two (2) schools have electrical company initiate the implementation and the electrical connection, and two (2) Schools are already connected. • For more details see Attached Annex for Utilities Connection.

• CMTO team (COP &SGL) conducted jointly site visit with Medanat staff on July 9, 2020 to Dahiet Al Ameer Hasan school to inspect the school and if it is ready for Substantially completed. • Utilities: CMTO team continued following up utilities. • CMTO team conducted site visit to Maymounah Bint Al Hareth Basic School( KG) in JSEP Phase IV Package 2 on July 1, 2020 to re-assess and evaluate the existing Sand Area (Play Area) jointly with Medanat and Contractor. CMTO team confirmed on the recommendations mentioned on the Field Trip report dated February 23, 2020 on the followings:

1) Remove the existing Sand Area due to Safety issue,

2) Construct new Sand Area to meet the requirements and specifications.

Page 13: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            12    

3

10

Taisser Abu Arja Contracting

• All KGs, Sport Facility and Expansions are Substantially Completed EXCEPT for Al Karamah School Expansions is still under construction. • Second Handing over is completed for Alhashmieh Boys on July 2, 2020. For more details, see attached JSEP Phase IV Taking over Table. • Works are resumed since the second week of May. Percentages of completion for Al Karameh School is 85% (increased 5%). For more details, see attached JSEP IV Progress Summary Table. • Utilities: Electricity; Six (6) schools are connected, all payments and procedures are completed for two (2) schools and now awaiting final connection, one (1) school is still pending MOE payment, and one (1) will be connected to the existing. • For more details see Attached Annex for Utilities Connection.

• CMTO team conducted site visit to Al Karameh Basic Mixed School JSEP IV Package 3 on July 6, 2020 to observe the Health & Safety and report on findings and provide recommendations.

4 9 Hussein Miqdadi & Partner

• All Schools are Substantially Completed. For more details, see attached JSEP Phase IV Taking over Table. • Utilities: Electricity; five (5) schools are connected and two (2) all payments and procedures are done and awaiting final connection and two (2) awaiting MOE payment. • For more details see Attached Annex for Utilities Connection.

Page 14: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            13    

5 10 Samara & Yousef Contracting

• All Six (6) KGs are Substantially Completed. In addition, Hofa School Expansion is Substantially Completed. For more details, see attached JSEP Phase IV Taking over Table.

• Works are resumed since the second week of May. Percentage of completion of School Expansions are ranging between 83% and 90% (increased 6% for Samma Expansion and 1% for Sammoa and Alshounel Alshamalieh Expansions). For more details, see attached JSEP IV Progress Summary Table.

• Utilities: Electricity; one (1) will be connected to the existing schools, all payments and procedures are done for five (5) Schools and now awaiting final connection, and four (4) are connected. • For more details see Attached Annex for Utilities Connection.

• CMTO team conducted site visit to North Shouneh Basic School l JSEP IV Package 5 on June 28, 2020 to observe the Corrective Actions on the Health & Safety and report on findings and provide recommendations.

V

21

Bitar Consultants

1 12 Al Joud Contracting Co.

• The sites are handed over to the Contractor and they are at Mobilization stage. Commencement Date for Construction Work was on June 28, 2020.

• Soil test was completed for five (5) out of six (6) Schools. Test results not issued yet.

• Demolishing Works were completed for one (1) out of three (3) Schools.

• Status of tress removal: The Contractor to coordinate with the Ministry of Agriculture for trees removal in construction sites.

• Furniture for Ministry of Education was removed from the Bint Adi (KG) construction

Page 15: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            14    

site. Also, the materials of the maintenance contractor were removed.

2 9* FAZ Contracting Co.

• The sites are handed over to the Contractor and they are at Mobilization stage. Commencement Date for Construction Work was on June 28. • Soil test was completed for two (2) out of four (4) Schools. Test results not issued yet. • Demolishing Works were completed for two (2) out of three (3) Schools. • Status of trees removal: The Contractor to coordinate with the Ministry of Agriculture for trees removal in construction sites. • Iskan Al Hashmyeh Basic Mixed School was changed to Omar Bin Al Khattab Primary Boys School.

Page 16: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            15    

Schools for a Knowledge Economy Project (SKEP) (12 Current Sites (i.e schools under construction or taking over in progress or utilities connection in progress))

I 6 Engicon 1 3 Hussein Miqdadi & Partner

• Utilities for all schools are completed. • Package 1 Close-out is completed; Substantial payment submitted to USAID/JORDAN. • Elevators Work:

• Elevators of SKEP Phase I: . All School Sites are handed over to Elevators’ Contractor. Notice to Commence is not issued yet.

2 3 Al Sha'aer Contracting

• Utilities for all schools are completed. • Package 2 Close-out is completed; Substantial payment submitted to USAID/JORDAN.

II 6 CCG 1 3 Dijlah Contracting • All three (3) Schools are Substantially Completed; excluding elevators works. • Second Handing-over Inspection is Completed for all School. • Electrical connections for all schools are still pending. • Water supply are still pending for all schools. • Sewer connection still pending for two (2) schools. • For more details see Attached Annex for Utilities Connection.

• All Package 1 schools are Substantially Completed excluding elevators works. Elevators have been totally completed and operated by the Contractor, the only still pending items are Testing and Commissioning and the Inspection by JISM; Testing and Commissioning of the Elevators are still pending in all schools due to pending electrical connections.

Page 17: BIWEEKLY SUMMARY REPORT

BIWEEKLY REPORT NO. 40 (26 JUN 2020 to 9 JUL 2020)                                            16    

2 3 Mohammad Al Rawashdeh & Sons

• Construction work progress is behind the schedule; Contractual Completion Date is November 24, 2019. Works are resumed partially since May 03, 2020 in Al Amal School and Al Thaniah School and May 10, 2020 for Prince Hamza School. The work percentages of completion are ranging between 64% and 69% (increased only 1%). • Based on the current status of SKEP II Package 2 schools; the Completion of the school will not be before the end of the year. For more details, see attached SKEP Phase II Progress Summary Table. • Electrical connections are still pending for two (2) schools. • Water supply is still pending for all schools. • Sewer connections are still pending for two (2) schools (Alameer Hamzeh and Alamal). • For more details see Attached Annex for Utilities Connection.

• Utilities: CMTO staff continued following up utilities For SKEP Phase ll, • CMTO team conducted site visit to Prince Hamza Secondary School SKEP Phase II Package 2 on June 30, 2020 jointly with MPWH and USAID/JORDAN to observe the Quality, Health & Safety and Work Progress and report on findings and provide recommendations. • CMTO team conducted site visit to Al Thaniah Basic School SKEP Phase II Package 2 on July 1, 2020 to observe the Quality, Health & Safety and Work Progress and report on findings and provide recommendations. • CMTO team conducted site visit to Amal School for Special Education SKEP Phase II Package 2 on July 2, 2020 to observe the Quality, Health & Safety and Work Progress and report on findings and provide recommendations.

*The number of schools includes one school (Alsukhna School) that has only renovation works. **CMTO team attended the Design Review Workshop on July 6, 2020 that managed by ESMP. The purpose of the workshop is to identify the problems on design review process and agree on recommendations for improving the process. The MPWH, MOE, JEA and CMTO members participated on the Workshop

Page 18: BIWEEKLY SUMMARY REPORT

JSEP Phase IV-Progress Update Note:

1 Due to lack of definitive schedules; percent complete (physical) is the same as the percent complete (cost)2 Projected Late = (Projected completion date (column k)-Scheduled completion date (column j))/Contract (Days) (column d)

09-Jul-20

Contract (Days)

Contract Time

Elapsed (%)

Percent Complete(Physical)

% Behind Schedule

Percent Complete

(Cost)

% Complete Cost - %

Complete Physical

Scheduled Completion

Date

Projected Completion Date by

Supervision Firm

Projected % Late

a b c d e f g h i j k lPhase IVPackage 1

Contract Signing Date 10-Dec-181 Umalquttain (KG) Almafraq 1502 Albostanieh (KG) Almafraq 1503 Aldajanieh primary mixed school (KG) Almafraq 1504 Rbaa Alsarhan (KG) Almafraq 1505 Hayyan Almoshref (KG) Almafraq 1506 Aidon Bany Hassan (KG) Almafraq 1507 Aljabal Alakhdar Almafraq 2708 Deir Allayyat (KG) - Cancelled Jerash9 Bab Amman (KG) Jerash 15010 Sakeb Jerash 27011 Bab Amman (Extension) Jerash 270

Package 2Contract Signing Date 12-Dec-18

12 Fahmy Hashem (KG) Amman 15013 Atekah Bent Abdelmottaleb (KG) Amman 270 213% 87% 126% 87% 0% 8-Sep-19 31-Jul-20 121%14 Dahiet Alameer Hassan Amman 270 213% 92% 121% 92% 0% 8-Sep-19 25-Jul-20 119%15 Alhassan Bin Alhaytham Amman 270 213% 94% 119% 94% 0% 8-Sep-19 31-Jul-20 121%16 Qatr Alnada (KG) Zarqa 27017 Jabal Alameer Hassan Zarqa 270 213% 95% 118% 95% 0% 8-Sep-19 25-Jul-20 119%18 Safieh Bin Abdelmottaleb Zarqa 270 213% 90% 123% 90% 0% 8-Sep-19 31-Jul-20 121%19 Maymoneh Bent Alhareth (KG) Balqa 150

121% 0% 120%

Substantially Completed

Update Date

SN School Location

Construction Progress

Name of the Contractor: Samara & Yousef Co.

Substantially CompletedSubstantially CompletedSubstantially CompletedSubstantially CompletedSubstantially Completed

Substantially Completed

Substantially CompletedSubstantially Completed

Package Non-weighted Average

Name of the Contractor: Al Shaer Construction Co.

Substantially Completed

Package Non-weighted Average

Substantially Completed

Substantially Completed

Substantially Completed

Page 1 of 3

Page 19: BIWEEKLY SUMMARY REPORT

Contract (Days)

Contract Time

Elapsed (%)

Percent Complete(Physical)

% Behind Schedule

Percent Complete

(Cost)

% Complete Cost - %

Complete Physical

Scheduled Completion

Date

Projected Completion Date by

Supervision Firm

Projected % Late

a b c d e f g h i j k l

SN School Location

Construction Progress

Package 3Contract Signing Date 11-Dec-18

20 Kufr Awwan(KG) Irbid 15021 Rhaba Boys Irbid 27022 Rhaba Boys -Sport facility Irbid 15023 Baleela (KG) Jerash 15024 Alhashmieh Girls (KG) Ajloon 150

25 Alzobair Ben Alawwam (KG) Ajloon 15026 Anjarah(KG) Ajloon 15027 Ebben Ebblein Ajloon 27028 Alkarameh Ajloon 270 213% 85% 128% 85% 0% 7-Sep-19 25-Jul-20 119%29 Alhashmieh Boys Ajloon 270

128% 0% 119%Package 4

Contract Signing Date 12-Dec-1830 Alramtha (KG) Irbid 15031 Alzahraa (KG) Irbid 15032 Alshajarah (KG) Irbid 15033 Moghayyar (KG) Irbid 15034 Emrawah Irbid 27035 Ibn Hazem Irbid 27036 Mohyye Aldeen Alaraby Irbid 27037 Maymoneh Bent Alhareth Irbid 27038 Haleemeh Al Saadeyah Irbid 150

Package 5Contract Signing Date 16-Dec-18

39 Tubnah (KG) Irbid 15040 Ein Jaloot (KG) Irbid 15041 Nusaibah Almazenieh (KG) Irbid 15042 Kufr Asad(KG) Irbid 15043 Jeneen Alsafa (KG) Irbid 15044 Sammoa (KG) Irbid 150

Substantially Completed

Name of the Contractor: Abu Arja Construction Contracting Est.Substantially CompletedSubstantially Completed

Substantially Completed

Substantially Completed

Substantially Completed

Substantially CompletedSubstantially CompletedSubstantially Completed

Substantially CompletedPackage Non-weighted Average

Name of the Contractor: Hussien Miqdadi Contracting Co.Substantially CompletedSubstantially Completed

Substantially Completed

Substantially CompletedSubstantially CompletedSubstantially CompletedSubstantially CompletedSubstantially CompletedSubstantially Completed

Name of the Contractor: Samara & Yousef Co.Substantially CompletedSubstantially Completed

Substantially CompletedSubstantially CompletedSubstantially Completed

Page 2 of 3

Page 20: BIWEEKLY SUMMARY REPORT

Contract (Days)

Contract Time

Elapsed (%)

Percent Complete(Physical)

% Behind Schedule

Percent Complete

(Cost)

% Complete Cost - %

Complete Physical

Scheduled Completion

Date

Projected Completion Date by

Supervision Firm

Projected % Late

a b c d e f g h i j k l

SN School Location

Construction Progress

45 Samma (Extension) Irbid 270 211% 90% 121% 90% 0% 12-Sep-19 20-Jul-20 116%

46 Hofa secondary school Irbid 27047 Sammoa (Extension) Irbid 270 211% 87% 124% 87% 0% 12-Sep-19 25-Jul-20 117%48 Alshouneh Alshamalieh Irbid 270 211% 83% 128% 83% 0% 12-Sep-19 31-Jul-20 120%

125% 0% 118%Phase IV 75% 71%

Package Non-weighted AveragePHASE Non-weighted Average

Substantially Completed

Page 3 of 3

Page 21: BIWEEKLY SUMMARY REPORT

SKEP Phase II-Progress Update Note:

1 Projected Late = (Projected completion date (column k)-Scheduled completion date (column j))/Contract (Days) (column d)

09-Jul-20

Contract (Days)

Actual Contract

Time Elapsed

(%)

Percent Complete(Physical)

% Behind Schedule

Percent Complete

(Cost)

% Complete Cost - %

Complete Physical

Scheduled Completion

Date

CMTOProjected

Completion Date

Projected% Late

a b c d e f g h i j k l

Phase IIPackage I

Contract Signing Date 1-Sep-18

1 Alsamt Irbid 450

2 Hamad Al Farhan Irbid 450

3 AlSareeh Irbid 450

Package IIContract Signing Date 1-Sep-18

1 Alameer Hamzeh Madaba 450 150% 65% 85% 63% -2% 25-Nov-19 31-Dec-20 89%

2 Alamal Aqaba 450 150% 69% 81% 63% -6% 25-Nov-19 31-Dec-20 89%

3 Althanieh Alkarak 450 150% 64% 86% 61% -3% 25-Nov-19 31-Dec-20 89%

84% -4% 89%

Update Date

SN School Location

Construction Progress

Name of the Contractor: Al Rawashdeh

Package Non-weighted Average

Name of the Contractor: Dijla

Substantially Completed EXCEPT FOR ELEVATORS

Substantially Completed EXCEPT FOR ELEVATORS

Substantially Completed EXCEPT FOR ELEVATORS

Page 1 of 1

Page 22: BIWEEKLY SUMMARY REPORT

JSEP Phase IV-Taking over Status Update Notes:

Update for this biweekly report period (June 26 to July 9)

Contractor's Letter

Engineer's Recommendation

First Inspection

Second Inspection

a b c d e f  g h i jPhase IVSummary of Phase IVNo. & % of Schools Substantially Completed

38 81%

No. & % of Schools Completed First Handing over Inspection

32 68%

No. & % of Schools Completed Second Handing over Inspection

22 47%

Package 11 Umalquttain(KG) Almafraq 11-Jun-20 25-Jun-202 Albostanieh(KG) Almafraq 08-Dec-19 22-Dec-19 22-Jan-20 09-Feb-203 Aldajanieh primary mixed school Almafraq 26-Dec-19 08-Jan-20 26-Feb-20

4 Rbaa Alsarhan(KG) Almafraq 08-Dec-19 22-Dec-19 21-Jan-20 12-Feb-20                     5 Hayyan Almoshref(KG) Almafraq 16-Oct-19 28-Oct-19 18-Dec-19 02-Feb-20

6 Aidon Bany Hassan(KG) Almafraq 13-Feb-19 27-Feb-20 01-Jul-20

7 Aljabal Alakhdar Almafraq 13-Feb-19 27-Feb-20 05-Jul-20

8 Deir Allayyat(KG) Cancelled Jerash

9 Bab Amman(KG) Jerash 16-Oct-19 28-Oct-19 27-Nov-19 11-Dec-19 20-Jan-20

10 Sakeb Jerash 23-Jan-19 8-Feb-20 11-Mar-20 8-Jul-20

11 Bab Amman(Extension) Jerash 11-Jun-20 25-Jun-20

Package 212 Fahmy Hashem(KG) Amman 20-Jun-20 22-Jun-20

13 Atekah Bent Abdelmottaleb(KG) Amman

14 Dahiet Alameer Hassan Amman

15 Alhassan Bin Alhaytham Amman

16 Qatr Alnada (KG) Zarqa 20-Jun-20 22-Jun-2017 Jabal Alameer Hassan Zarqa18 Safieh Bin Abdelmottaleb Zarqa

19 Maymoneh Bent Alhareth(KG) Balqa 22-Dec-19 7-Jan-20 23-Feb-20

SN School Location

Taking over Status

Notes Supervising Engineer

InspectionSubstantial Completion

Inspections Signed Memorandum

Taking over Certificate

Page 1 of 2

Page 23: BIWEEKLY SUMMARY REPORT

Contractor's Letter

Engineer's Recommendation

First Inspection

Second Inspection

a b c d e f  g h i j

SN School Location

Taking over Status

Notes Supervising Engineer

InspectionSubstantial Completion

Inspections Signed Memorandum

Taking over Certificate

Package 3

20 Kufr Awwan(KG) Irbid 31-Jul-19 21-Aug-19 07-Oct-19 18-Nov-19 11-Dec-19

21 Rhaba Boys Irbid 11-Mar-20 18-May-20 23-Jun-20

22 Rhaba Boys -Sport facility Irbid 24-Oct-19 29-Oct-19 26-Nov-19 17-Feb-19 23-Jun-20

23 Baleela(KG) Jerash 31-Jul-19 21-Aug-19 10-Oct-19 14-Nov-19 11-Dec-19

24 Alhashmieh Girls (KG) Ajloon 31-Jul-19 21-Aug-19 07-Oct-19 18-Nov-19 11-Dec-19

25 Alzobair Ben Alawwam(KG) Ajloon 31-Jul-19 21-Aug-19 09-Oct-19 20-Nov-19 11-Dec-1926 Anjarah(KG) Ajloon 31-Jul-19 21-Aug-19 09-Oct-19 20-Nov-19 11-Dec-1927 Ebben Ebblein Ajloon 15-Jan-20 30-Jan-20 25-Feb-20

28 Alkarameh Ajloon

29 Alhashmieh Boys Ajloon 11-Jan-20 15-Jan-20 6-Feb-20 2-Jul-20

Package 430 Alramtha Irbid 27-Nov-19 10-Dec-19 13-Jan-20 10-Mar-20

31 Alzahraa Irbid 27-Nov-19 10-Dec-19 13-Jan-20 30-Jan-20

32 Alshajarah(KG) Irbid 27-Nov-19 10-Dec-19 08-Jan-20 18-Feb-20

33 Moghayyar(KG) Irbid 24-Dec-19 11-Jan-20 12-Feb-20

34 Emrawah Irbid 24-Dec-19 11-Jan-20 11-Feb-20

35 Ibn Hazem(KG) Irbid 14-Mar-20 17-May-20 25-Jun-20

36 Mohyye Aldeen Alaraby Irbid 30-Nov-19 10-Dec-19 30-Jan-20 10-Mar-20

37 Maymoneh Bent Alhareth Irbid 24-Dec-19 11-Jan-20 22-Jan-20 12-Mar-20

38 Haleemeh Al Saadeyah Irbid 27-Nov-19 10-Dec-19 08-Jan-20 18-Feb-20

Package 539 Tubnah(KG) Irbid 08-Dec-19 22-Dec-19 20-Jan-20 10-Mar-20

40 Ein Jaloot(KG) Irbid 2-Nov-19 10-Nov-19

41 Nusaibah Almazenieh(KG) Irbid 2-Nov-19 10-Nov-19 05-Jan-20 10-Feb-20

42 Kufr Asad(KG) Irbid 08-Dec-19 22-Dec-19 27-Jan-20

43 Jeneen Alsafa(KG) Irbid 2-Nov-19 10-Nov-19 06-Jan-20 3-Feb-20

44 Sammoa(KG) Irbid 26-Dec-19 08-Jan-20 3-Feb-20 10-Mar-20

45 Samma(Extension) Irbid

46 Hofa secondary school Irbid 04-Mar-20 11-Jun-20

47 Sammoa(Extension) Irbid

48 Alshouneh Alshamalieh Irbid

Page 2 of 2

Page 24: BIWEEKLY SUMMARY REPORT

1 of 11

JSEP AND SKEP UTILITIES CONNECTION UPDATE REPORTDATE:

Conn-ected (Y/N)

NotesConn-ected (Y/N)

NotesConn-ected (Y/N)

Notes

a b c d e f g h i j

JORDAN SCHOOL EXPANSION PROGRAM (JSEP) 165 Number and % of Schools connected to Water Supply 135 82%Number and % of Schools connected to Wastewater System 134 81%Number and % of Schools connected to Electricity System 104 63%

PHASE I # of schools - 27

Number and % of Schools connected to Water Supply 27 100%Number and % of Schools connected to Wastewater System 27 100%Number and % of Schools connected to Electricity System 27 100%

PACKAGE I # of schools - 8

Number and % of Schools connected to Water Supply 8 100%Number and % of Schools connected to Wastewater System 8 100%Number and % of Schools connected to Electricity System 8 100%

1 1.1.1 Ali Bin Aby Taleb Basic Boys Irbid Y Y Y2 1.1.2 Al-Mazar Basic Boys Irbid Y Y Y3 1.1.3 Saydour Basic Mixed Irbid Y Y Y4 1.1.4 Zaynab Bint Al-Rasool Mixed Irbid Y Y Y5 1.1.5 Al-Ramtha Secondary Boys Irbid Y Y Y6 1.1.6 Zibdat Farkooh Basic Boys Irbid Y Y Y7 1.1.7 Qafqafa Secondary Girls KG Jerash Y Y Y8 1.1.8 Qafqafa Secondary Girls KG Jerash Y Y Y

PACKAGE 2 # of schools - 9

Number and % of Schools connected to Water Supply 9 100%Number and % of Schools connected to Wastewater System 9 100%Number and % of Schools connected to Electricity System 9 100%

9 1.2.1 Hayan Rwaibed Al-Sharqi Secndry Boys Mafraq Y Y Y10 1.2.2 Al-Zaa`tari Basic Boys Mafraq Y Y Y11 1.2.3 Raba'a Al Adawyah KG Al Zarqa Y Y Y12 1.2.4 Abu Al-Zighan Secondary KG Al Zarqa Y Y Y13 1.2.5 Tafeh Secondary Mixed Al Zarqa Y Y Y14 1.2.6 Iskan Al-Hashimyeh Basic Boys Al Zarqa Y Y Y15 1.2.7 Hay Al-Ameer Abdullah Basic Mixed Al Zarqa Y Y Y16 1.2.8 Balqees Secondary Mixed Al Zarqa Y Y Y17 1.2.9 Al-Doqara Secondary Boys Al Zarqa Y Y Y

PACKAGE 3 # of schools - 10

Number and % of Schools connected to Water Supply 10 100%Number and % of Schools connected to Wastewater System 10 100%Number and % of Schools connected to Electricity System 10 100%

18 1.3.1 Um Anas Basic Mixed KG Amman Y Y Y19 1.3.2 Um Anas Basic Mixed Amman Y Y Y

S. # # Phase Package, School

Electricity

Location

July 07 2020

Water Wastewater

Total # of schools -

1  of  11

Page 25: BIWEEKLY SUMMARY REPORT

2 of 11

JSEP AND SKEP UTILITIES CONNECTION UPDATE REPORTDATE:

Conn-ected (Y/N)

NotesConn-ected (Y/N)

NotesConn-ected (Y/N)

Notes

a b c d e f g h i j

S. # # Phase Package, School

Electricity

Location

July 07 2020

Water Wastewater

20 1.3.3 Jumana Bint Abi Taleb KG Al Zarqa Y Y Y21 1.3.4 A`awajan Secondary Girls Al Zarqa Y Y Y22 1.3.5 Al-Rasheed Secondary School for Boys Al Zarqa Y Y Y23 1.3.6 Tamador Bint A'mr Secondary Mixed Al Zarqa Y Y Y24 1.3.7 Maymona Bint Sa'd Basic for Girls Al Zarqa Y Y Y25 1.3.8 A`tekah Basic Mixed Al Zarqa Y Y Y26 1.3.9 Merheb Basic for Boys Al Zarqa Y Y Y27 1.3.10 Um Romanah Secondary for Boys Al Zarqa Y Y Y

PHASE II # of schools - 37

Number and % of Schools connected to Water Supply 37 100%Number and % of Schools connected to Wastewater System 37 100%Number and % of Schools connected to Electricity System 26 70%

PACKAGE 1 # of schools - 9

Number and % of Schools connected to Water Supply 9 100%Number and % of Schools connected to Wastewater System 9 100%Number and % of Schools connected to Electricity System 5 56%

28 2.1.1 Haya Bint Alhussein (KG) Amman Y Y N Not connected

fees were paid waiting the

contractor to extend the cable

29 2.1.2 Haya Bint Alhussein (Extension) Amman Y Y N Not connected

fees were paid waiting the

contractor to extend the cable

30 2.1.3 Manshiet Hesban Amman Y Y Y 31 2.1.4 Ijmayyel Amman Y Y N Conflict between MOE/JEPCO

about the transformer room

rental agreement

32 2.1.5 Umalwaleed Amman Y Y N Room has been constructed

waiting final connection33 2.1.6 Alrawda(KG) Albalqa Y Y Y34 2.1.7 Alrawda (Extension ) Albalqa Y Y Y35 2.1.8 Rayeh Bint Alhussein Madaba Y Y Y36 2.1.9 Aisha Madaba Y Y Y

PACKAGE 2 # of schools - 9

Number and % of Schools connected to Water Supply 9 100%Number and % of Schools connected to Wastewater System 9 100%Number and % of Schools connected to Electricity System 8 89%

2  of  11

Page 26: BIWEEKLY SUMMARY REPORT

3 of 11

JSEP AND SKEP UTILITIES CONNECTION UPDATE REPORTDATE:

Conn-ected (Y/N)

NotesConn-ected (Y/N)

NotesConn-ected (Y/N)

Notes

a b c d e f g h i j

S. # # Phase Package, School

Electricity

Location

July 07 2020

Water Wastewater

37 2.2.1 Sweileh (KG) Amman Y Y Y38 2.2.2 Umhabibah (KG) Amman Y Y Y39 2.2.3 Aeshah & Marjalhamam (KG) Amman Y Y Y40 2.2.4 Alzahraa (KG) Amman Y Y Y41 2.2.5 Iraq Alameer Amman Y Y N Electrical Company

Mobilization42 2.2.6 Qurtoba Amman Y Y Y43 2.2.7 Wadi Alseer Amman Y Y Y44 2.2.8 Albnayyat Amman Y Y Y45 2.2.9 Marj Alhamam Amman Y Y Y

PACKAGE 3 # of schools - 12

Number and % of Schools connected to Water Supply 12 100%Number and % of Schools connected to Wastewater System 12 100%Number and % of Schools connected to Electricity System 8 67%

46 2.3.1 Alarqam (KG) Amman Y Y Y 47 2.3.2 Hafsah Bint Amr (KG) Amman Y Y Y

48 2.3.3 Alemam Albokhary(KG ) Amman Y Y Y49 2.3.4 Almowaqqar primary (KG) Amman Y Y Y50 2.3.5 Almowaqqar secondary KG Amman Y Y Y51 2.3.6 Iskan Almalieh Amman Y Y Y52 2.3.7 Abu Alanda Amman Y Y N Cables Problem53 2.3.8 Alemam Albokhary(Extension ) Amman Y Y Y54 2.3.9 Khraibet Alsook Amman Y Y N Cables Problem55 2.3.10 Alkhashafieh Aljanoubieh Amman Y Y Y56 2.3.11 Alkhashafieh Algharbieh Amman Y Y N Cables Problem57 2.3.12 Maghayer Mhana Amman Y Y N Cables Problem

PACKAGE 4 # of schools - 7

Number and % of Schools connected to Water Supply 7 100%Number and % of Schools connected to Wastewater System 7 100%Number and % of Schools connected to Electricity System 5 71%

58 2.4.1 Roqayah Ben Alrasool (KG) Amman Y Y Y59 2.4.2 Almanarah(KG) Amman Y Y Y60 2.4.3 Um Ammar Amman Y Y Y61 2.4.4 Umaimah Amman Y Y N Paid62 2.4.5 Albaida Amman Y Y N Conflict between MOE/JEPCO

about the transformer room

rental agreement

3  of  11

Page 27: BIWEEKLY SUMMARY REPORT

4 of 11

JSEP AND SKEP UTILITIES CONNECTION UPDATE REPORTDATE:

Conn-ected (Y/N)

NotesConn-ected (Y/N)

NotesConn-ected (Y/N)

Notes

a b c d e f g h i j

S. # # Phase Package, School

Electricity

Location

July 07 2020

Water Wastewater

63 2.4.6 Almanarah(KG) Mafraq Y Y Y64 2.4.7 Almanarah(Extension) Mafraq Y Y Y

PHASE III # of schools - 33

Number and % of Schools connected to Water Supply 33 100%Number and % of Schools connected to Wastewater System 33 100%Number and % of Schools connected to Electricity System 28 85%

PACKAGE 1 # of schools - 11

Number and % of Schools connected to Water Supply 11 100%Number and % of Schools connected to Wastewater System 11 100%Number and % of Schools connected to Electricity System 10 91%

65 3.1.1 Nusaibah Almazenieh (KG) Y Y Y66 3.1.2 Amneh Bint Waheb (KG) Y Y Y67 3.1.3 Hamzeh Bent Abdelmottaleb Y Y Y68 3.1.4 Al Baqaa Y Y Y69 3.1.5 Alkarameh (KG) Y Y Y70 3.1.6 10th Area girls (KG) Y Y Y71 3.1.7 Alkarameh (Extension) Y Y Y72 3.1.8 10th Area girls (Extension) Y Y Y73 3.1.9 8th Area boys Y Y Y74 3.1.10 8th Area mixed Y Y Y75 3.1.11 Al Tweisah Y Y N Not connected. Claim was

paid, there are some regulation

problems with the municipality,

JEPCO contacted MOE

regarding this issue

PACKAGE 2 # of schools - 10

Number and % of Schools connected to Water Supply 10 100%Number and % of Schools connected to Wastewater System 10 100%Number and % of Schools connected to Electricity System 10 100%

76 3.2.1 Ierenbeh Y Y Y

77 3.2.2 Alqastal Y Y Y

78 3.2.3 Daleelah Y Y Y

79 3.2.4 Maeen Y Y Y

4  of  11

Page 28: BIWEEKLY SUMMARY REPORT

5 of 11

JSEP AND SKEP UTILITIES CONNECTION UPDATE REPORTDATE:

Conn-ected (Y/N)

NotesConn-ected (Y/N)

NotesConn-ected (Y/N)

Notes

a b c d e f g h i j

S. # # Phase Package, School

Electricity

Location

July 07 2020

Water Wastewater

80 3.2.5 Madaba mixed Y Y Y 81 3.2.6 Alyaroot Y Y Y

82 3.2.7 Zahhom Y Y Y 83 3.2.8 Alqaser Y Y Y 84 3.2.9 Altaybeh Y Y Y

85 3.2.10 Faqqoa Y Y Y

PACKAGE 3 # of schools - 12

Number and % of Schools connected to Water Supply 12 100%Number and % of Schools connected to Wastewater System 12 100%Number and % of Schools connected to Electricity System 8 67%

86 3.3.1 Um Qsair & Moqabaleen(KG) Y Y N All fees are paid, Connection is

under process87 3.3.2 Alyarmook Y Y N To check with JEPCO 3rd area

88 3.3.3 Um Qsair & Moqabaleen (Extension) Y Y Y

89 3.3.4 Alfarooq Y Y N MPWH to Invoice MOE

90 3.3.5 Bayader Wadi Alseer Y Y N MPWH to Invoice MOE

91 3.3.6 Alhasnaa Y Y Y 92 3.3.7 Muthallath Alardeh Y Y Y 93 3.3.8 Yafa Y Y Y 94 3.3.9 Albalawneh Y Y Y 95 3.3.10 Khuzma Y Y Y 96 3.3.11 Abo Obaidah Y Y Y 97 3.3.12 Alqadesieh Y Y Y

PHASE IV # of schools - 47

Number and % of Schools connected to Water Supply 38 9%Number and % of Schools connected to Wastewater System 37 8%Number and % of Schools connected to Electricity System 23 5%

PACKAGE 1 # of schools - 10

Number and % of Schools connected to Water Supply 10 100%

5  of  11

Page 29: BIWEEKLY SUMMARY REPORT

6 of 11

JSEP AND SKEP UTILITIES CONNECTION UPDATE REPORTDATE:

Conn-ected (Y/N)

NotesConn-ected (Y/N)

NotesConn-ected (Y/N)

Notes

a b c d e f g h i j

S. # # Phase Package, School

Electricity

Location

July 07 2020

Water Wastewater

Number and % of Schools connected to Wastewater System 10 100%Number and % of Schools connected to Electricity System 6 60%

98 4.1.1Umalquttain(KG) Almafraq Y Y N

Electrical Company

Mobilization99 4.1.2 Albostanieh(KG) Almafraq Y Y Y

100 4.1.3 Aldajanieh primary mixed school. Almafraq Y Y Y101 4.1.4 Rbaa Alsarhan(KG) Almafraq Y Y Y102 4.1.5 Hayyan Almoshref(KG) Almafraq Y Y Y103 4.1.6

Aidon Bany Hassan(KG) Almafraq Y Y Y

104 4.1.7Aljabal Alakhdar Almafraq Y Y N

Electrical Company

Mobilization105 4.1.8 Bab Amman(KG) Jerash Y Y Y106 4.1.9 Sakeb Jerash Y Y N Awaiting Final Connection107 4.1.10

Bab Amman(Extension) Jerash Y Y N Awaiting Final Connection

PACKAGE 2 # of schools - 8

Number and % of Schools connected to Water Supply 5 63%Number and % of Schools connected to Wastewater System 3 38%Number and % of Schools connected to Electricity System 2 25%

108 4.2.1 Fahmy Hashem(KG) Amman N Will be connected to existing

schoolN Water company invoices

MPWH

N Awaiting Final Connection

109 4.2.2 Atekah Bent Abdelmottaleb(KG) Amman N Will be connected to existing

schoolN Will be connected to existing

schoolN Will be connected to existing

school110 4.2.3 Dahiet Alameer Hassan Amman Y Y N Will be connected to existing

school111 4.2.4 Alhassan Bin Alhaytham Amman Y N MPWH Notice to Wastewater

company

N Electrical Company

Mobilization112 4.2.5 Qatr Alnada9KG) Zarqa N Will be connected to existing

schoolN MPWH Notice to Wastewater

company

N Will be connected to existing

school

113 4.2.6 Jabal Alameer Hassan Zarqa Y N Will be connected to existing

schoolN Electrical Company

Mobilization114 4.2.7 Safieh Bin Abdelmottaleb Zarqa Y Y Y115 4.2.8 Maymoneh Bent Alhareth(KG) Balqa Y Y Y

PACKAGE 3 # of schools - 10

Number and % of Schools connected to Water Supply 8 80%Number and % of Schools connected to Wastewater System 9 90%

6  of  11

Page 30: BIWEEKLY SUMMARY REPORT

7 of 11

JSEP AND SKEP UTILITIES CONNECTION UPDATE REPORTDATE:

Conn-ected (Y/N)

NotesConn-ected (Y/N)

NotesConn-ected (Y/N)

Notes

a b c d e f g h i j

S. # # Phase Package, School

Electricity

Location

July 07 2020

Water Wastewater

Number and % of Schools connected to Electricity System 6 60%116 4.3.1 Kufr Awwan(KG) Irbid Y Y Y117 4.3.2 Rhaba Boys Irbid Y Y N MOE Pays MPWH118 4.3.3 Rhaba Boys -Sport facility Irbid Y Y N Will be connected to existing

school119 4.3.4 Baleela(KG) Jerash Y Y Y120 4.3.5 Alhashmieh Girls (KG) Ajloon Y Y Y121 4.3.6 Alzobair Ben Alawwam(KG) Ajloon Y Y Y122 4.3.7 Anjarah(KG) Ajloon Y Y Y

123 4.3.8 Ebben Ebblein Ajloon Y Y Y124 4.3.9 Alkarameh Ajloon N Will be connected to existing

school

N Will be Connected to existing

school

N Electrical Company

Mobilization125 4.3.10 Alhashmieh Boys Ajloon N Will be connected to existing

school

Y N Electrical Company

MobilizationPACKAGE 4 # of schools - 9

Number and % of Schools connected to Water Supply 9 100%Number and % of Schools connected to Wastewater System 7 78%Number and % of Schools connected to Electricity System 5 56%

126 4.4.1 Alramtha Irbid Y N MOE Pays MPWH N Electrical Company

Mobilization127 4.4.2 Alzahraa Irbid Y Y Y128 4.4.3 Alshajarah(KG) Irbid Y Y Y129 4.4.4 Moghayyar(KG) Irbid Y Y Y130 4.4.5 Emrawah Irbid Y Y N Electrical Company

Mobilization131 4.4.6 Ibn Hazem(KG) Irbid Y Y N Awaiting Final Connection132 4.4.7 Mohyye Aldeen Alaraby Irbid Y N MOE Pays MPWH N Awaiting Final Connection133 4.4.8 Maymoneh Bent Alhareth Irbid Y Y Y134 4.4.9 Haleemeh Al Saadeyah Irbid Y Y Y

PACKAGE 5 # of schools - 10

Number and % of Schools connected to Water Supply 6 60%Number and % of Schools connected to Wastewater System 8 80%Number and % of Schools connected to Electricity System 4 40%

135 4.5.1 Tubnah(KG) Irbid Y Y Y136 4.5.2 Ein Jaloot(KG) Irbid Y Y N Awaiting Final Connection137 4.5.3 Nusaibah Almazenieh(KG) Irbid Y Y N Awaiting Final Connection138 4.5.4 Kufr Asad(KG) Irbid Y Y N Awaiting Final Connection139 4.5.5 Jeneen Alsafa(KG) Irbid Y Y Y

7  of  11

Page 31: BIWEEKLY SUMMARY REPORT

8 of 11

JSEP AND SKEP UTILITIES CONNECTION UPDATE REPORTDATE:

Conn-ected (Y/N)

NotesConn-ected (Y/N)

NotesConn-ected (Y/N)

Notes

a b c d e f g h i j

S. # # Phase Package, School

Electricity

Location

July 07 2020

Water Wastewater

140 4.5.6 Sammoa(KG) Irbid N Will be connected to existing

school

Y N Will be connected to existing

school141 4.5.7 Samma(Extension) Irbid N Will be connected to existing

school

N Will be connected to existing

school

Y

142 4.5.8 Hofa secondary school Irbid Y Y Y143 4.5.9 Sammoa(Extension) Irbid N Will be connected to existing

school

Y N Electrical Company

Mobilization144 4.5.10 Alshouneh Alshamalieh Irbid N Will be connected to existing

school

N Will be connected to Septic

Tank

N Awaiting Final Connection

PHASE V # of schools - 21

Number and % of Schools connected to Water Supply 0 0%Number and % of Schools connected to Wastewater System 0 0%Number and % of Schools connected to Electricity System 0 0%

PACKAGE 1 # of schools - 12

Number and % of Schools connected to Water Supply 0 0%Number and % of Schools connected to Wastewater System 0 0%Number and % of Schools connected to Electricity System 0 0%

145 5.1.1 Al Qweismeh and Abu Alanda School (KG) Amman N N N146 5.1.2 Bint Adi Secondary School (KG) Amman N N N147 5.1.3 Khawalah Bint Al Azwar Secondary School foAmman N N N148 5.1.4 Laila Al Ghafaryeh Primary School Amman N N N149 5.1.5 Jabal Amman Basic Girls School Amman N N N150 5.1.6 Al Faisalieh Secondary School for Boys Amman N N N151 5.1.7 Husban Secondary Boys School Amman N N N152 5.1.8 Southern Al-Azraq Secondary Mixed School Al Zarqa N N N153 5.1.9 Al Khatabiyeh Primary Mixed School (KG) Madaba N N N154 5.1.10 Khadija Bent Khuwayled Basic School for Gi Madaba N N N155 5.1.11 Fatimah Al-Zahraa Primary Mixed School (K Madaba N N N156 5.1.12 Al-Shayma Primary Mixed School (KG) Madaba N N N

PACKAGE 2 # of schools - 9

Number and % of Schools connected to Water Supply 0 0%Number and % of Schools connected to Wastewater System 0 0%Number and % of Schools connected to Electricity System 0 0%

157 5.2.1 Summerqand primary mixed school Al Zarqa N N N158 5.2.2 Al-Sukhneh Primary Girls School Al Zarqa N N N159 5.2.3 Hend Bent Umayah Primary Mixed School (KAl Zarqa N N N160 5.2.4 Um Salama Secondary School for Girls (KG)Al Zarqa N N N161 5.2.5 Um Kulthom Secondary School Al Zarqa N N N162 5.2.6 Iskan Al-Hashmieh Basic Mixed School Al Zarqa N N N

8  of  11

Page 32: BIWEEKLY SUMMARY REPORT

9 of 11

JSEP AND SKEP UTILITIES CONNECTION UPDATE REPORTDATE:

Conn-ected (Y/N)

NotesConn-ected (Y/N)

NotesConn-ected (Y/N)

Notes

a b c d e f g h i j

S. # # Phase Package, School

Electricity

Location

July 07 2020

Water Wastewater

163 5.2.7 Al-Hashmyeh Secondary Mixed School (KG)Al Zarqa N N N164 5.2.8 Makah Basic Mixed School (KG) Al Zarqa N N N165 5.2.9 Jabal Tareq Basic Boys School Al Zarqa N N N

SCHOOLS FOR A KNOWLEDGE ECONOMY (SKEP) 25 Number and % of Schools connected to Water Supply 6 24%Number and % of Schools connected to Wastewater System 7 28%Number and % of Schools connected to Electricity System 7 28%

PHASE I # of schools - 6

Number and % of Schools connected to Water Supply 6 100%

Number and % of Schools connected to Wastewater System 6 100%

Number and % of Schools connected to Electricity System 6 100%

PACKAGE 1 # of schools - 3

Number and % of Schools connected to Water Supply 3 100%

Number and % of Schools connected to Wastewater System 3 100%

Number and % of Schools connected to Electricity System 3 100%

1 1.1.1 Al Ashrafieh Irbid Y Y N/A (Septic Tank) Y

2 1.1.2 Al Amal Zarqa Y Y Y Connected. (to existing

transformer)3 1.1.3 Amneh Bint Waheb Rusaifah Y Y Y Connected. (to existing

transformer)PACKAGE 2 # of schools - 3

Number and % of Schools connected to Water Supply 3 100%

Number and % of Schools connected to Wastewater System 3 100%

Number and % of Schools connected to Electricity System 3 133%

4 1.2.1 Altalbieh Amman Y Y Y

5 1.2.2 Zaid Bin Harethah Albalqa Y Y Y

6 1.2.3 Al Taseah Aqaba Y Y Y

PHASE II # of schools - 6

Number and % of Schools connected to Water Supply 0 0%

Number and % of Schools connected to Wastewater System 1 17%

Number and % of Schools connected to Electricity System 1 17%

PACKAGE 1 # of schools - 3

Number and % of Schools connected to Water Supply 0 0%

Number and % of Schools connected to Wastewater System 1 33%

Number and % of Schools connected to Electricity System 0 0%

7 2.1.1 Alsamt Irbid N MOE Paid Y N Connection works started

Total # of schools -

9  of  11

Page 33: BIWEEKLY SUMMARY REPORT

10 of 11

JSEP AND SKEP UTILITIES CONNECTION UPDATE REPORTDATE:

Conn-ected (Y/N)

NotesConn-ected (Y/N)

NotesConn-ected (Y/N)

Notes

a b c d e f g h i j

S. # # Phase Package, School

Electricity

Location

July 07 2020

Water Wastewater

8 2.1.2 Hamad Al Farhan Irbid N MOE Paid N In the Connection Process N Connection works started

9 2.1.3 AlSareeh Irbid N MOE Paid N MOE Paid N Connection works started

PACKAGE 2 # of schools - 3

Number and % of Schools connected to Water Supply 0 0%

Number and % of Schools connected to Wastewater System 0 0%

Number and % of Schools connected to Electricity System 1 33%

10 2.2.1 Alameer Hamzeh Madaba N Yarmok water to invoice

MPWH

N Yarmok water to invoice

MPWH

N Electrical Company

Mobilization11 2.2.2 Alamal Aqaba N MOE Paid N MOE Paid N Electrical Company

Mobilization12 2.2.3 Althanieh Alkarak N Pending technical study N No public network Y

PHASE III # of schools - 6

Number and % of Schools connected to Water Supply 0 0%Number and % of Schools connected to Wastewater System 0 0%Number and % of Schools connected to Electricity System 0 0%

PACKAGE 1 # of schools - 3

Number and % of Schools connected to Water Supply 0 0%Number and % of Schools connected to Wastewater System 0 0%Number and % of Schools connected to Electricity System 0 0%

13 3.1.1 Um Al Dananir Basic Mixed Al Balqa N N N

14 3.1.2 Thahr Al Sarow Basic for Boys Jerash N N N

15 3.1.3 Al Khansa'a Basic Mixed Al Balqa N N N

PACKAGE 2 # of schools - 3

Number and % of Schools connected to Water Supply 0 0%Number and % of Schools connected to Wastewater System 0 0%Number and % of Schools connected to Electricity System 0 0%

16 3.2.1 Hay Al Iskan Basic Mixed Jerash N N N

17 3.2.2 Khadija Bint Khwailed Basic Mixed Al Balqa N N N

18 3.2.3 Jumana Bint Abi taleb Basic Mixed Amman N N N

PHASE IV # of schools - 7

Number and % of Schools connected to Water Supply 0 0%Number and % of Schools connected to Wastewater System - 0%Number and % of Schools connected to Electricity System - 0%

PACKAGE 1 # of schools - 3

Number and % of Schools connected to Water Supply 0 0%Number and % of Schools connected to Wastewater System 0 0%Number and % of Schools connected to Electricity System 0 0%

10  of  11

Page 34: BIWEEKLY SUMMARY REPORT

11 of 11

JSEP AND SKEP UTILITIES CONNECTION UPDATE REPORTDATE:

Conn-ected (Y/N)

NotesConn-ected (Y/N)

NotesConn-ected (Y/N)

Notes

a b c d e f g h i j

S. # # Phase Package, School

Electricity

Location

July 07 2020

Water Wastewater

19 4.1.1 Um Al Hasheem Basic Mixed Al Karak N N N

20 4.1.2 Iskan Abu Nusair Secondary Mixed Amman N N N

21 4.1.3 Al Nuwairi Secondary Mixed Tafieleh N N N

PACKAGE 2 # of schools - 4

Number and % of Schools connected to Water Supply 0 0%Number and % of Schools connected to Wastewater System 0 0%Number and % of Schools connected to Electricity System 0 0%

22 4.2.1 Southern Western Rujm Al Shami Basic Mix Amman N N N

23 4.2.2 Mu’ta Basic for Boys Al Karak N N N

24 4.2.3 Al Farouk Secondary for Girls Amman N N N

25 4.2.4 Ghour Al Haditha Secondary for Girls Al Karak N N N

11  of  11