Page 1: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

Black Falls Off-Grid Sanitation Construction

Black Falls Water ProjectJune-Aug, 2010

Rita Sebastian, Development Planner [email protected] Tohannie, Project Director

Page 2: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

The Off-Grid Sanitation Construction was the continuation of the earlier Phase One project thatwas completed under an Environmental Justicegrant from the US EPA. Phase One providedsafe drinking water for families who were obtaining their drinking water from unsafe local water sources. The project installed temporary water storage systems in 10 homes in Black Falls and launched a community water hauling coop \to deliver water from a new pipeline access point constructed by the US Indian Health Service.

Page 3: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

The Phase Two project was a collaboration between US Indian Health Service and the Black Falls Water Project, a coop of families in the Black Falls area of the Navajo Nation.

Page 4: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

The IHS installed solar-powered underground cisterns, septic systems, and provided the plumbing for the bathrooms. The families were responsible for the bathroom construction and were assisted by the coop.

Page 5: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

The project continued the Grassroots Driven Development approach where the local community manages the planning and

implementation of development projects.

Page 6: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

Work on the project was a joint effort between the community coop and the families. Here, John Knight breaks ground for his foundation.

Page 7: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,
Page 8: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

The coop construction crew consisted of community members, young and old, men and women

Page 9: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

The homeowners participated at every step

Page 10: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

The families provided food for the workers

Page 11: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,
Page 12: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,
Page 13: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

Some of the families during construction of their bathrooms

Page 14: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

Volunteers from Home Depot assisted the community

Page 15: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

Home Depot received an award from Navajo Nation EPA for their work in phase one of the Black Falls project. The partnership continued in phase two.

Page 16: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

The extended families contributed expertise and assistance in all phases of construction - not just to the home of their immediate relations, but also to others in the community.

Page 17: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

Construction was done to the highest commerical standards: full R16 insulation; electric work conforming to building codes; highest quality materials and workmanship at every step

Page 18: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

The commitment to perfection continued to the finishing touches.

Page 19: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

Finished bathrooms included bathtup, toilet, sink, hot water, handicap accessibility, flooring, insulation, and electrical

Page 20: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,
Page 21: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

Bathroom construction was finished under budget and ahead of schedule, so some additional work was done: a porch at Katherine Peshlakai's

Page 22: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

and a new kitchen at Florabelle Paddock's

Page 23: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,

The next phase of the project is replication, so that other communities can also have access to safe drinking water and sanitation.

Page 24: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,
Page 25: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,
Page 26: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,
Page 27: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,
Page 28: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,
Page 29: Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Plannerrita@brandeis.edu Ronald Tohannie,