BLINDING CONCRETE
Objective
To define the Standard Procedure and arrangements for Lean
Concrete (1200 psi)
Scope
This work procedure covers the Lean Concrete activity to be placed on
a flat excavated surface (76.2mm to 152.4 mm thick) under floor slabs
and foundations of structures.
Procedure
Prior to the start of activity, design mix, material samples will be
submitted to Engineer for approval.
Ground surface is trimmed to level
Surface is compacted to required level using roller/plate compactors
& compaction requirements as specified in specs will be ensured
prior to Lean concreting
PCC will be laid on compacted surface, special care will be given to
maintain thickness, and surface of concrete will be leveled using
floats.
Blinding concrete will be allowed to set for 24 hours prior to
placement of fresh concrete.
Lean surface will be kept clean & free of loose material before
laying Reinforcing steel.