Page 1: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

District of Columbia Water and Sewer Authority George S. Hawkins, CEO and General Manager

August 15, 2017

Carlton M. Ray Director, DC Clean Rivers Project, DC Water

Tunnel Achievement Awards Banquet

10th Annual Breakthroughs in

Tunneling Short Course

BLUE PLAINS TUNNEL

DC CLEAN RIVERS PROJECT

Page 2: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

DC Water

DC Clean Rivers Background

Anacostia River Tunnel System

Blue Plains Tunnel

Procurement

Lessons Learned

Questions

Agenda

1

Page 3: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Who We Are

DC Water (District of Columbia Water and Sewer Authority)

Provides

Drinking water distribution for DC

Wastewater collection and treatment

Stormwater collection and conveyance

Treats wastewater for a population of 2.1 million

District of Columbia

Montgomery & Prince George’s Counties, Maryland

Fairfax & Loudoun Counties, Virginia

Operates the world’s largest Advanced Wastewater Treatment Plant

Average daily capacity, 370 mgd

Peak daily capacity, 1 billion+ gallons

Serves a regional area of approximately 725 Square Miles

Blue Plains Advanced Wastewater Treatment Plant

2

Page 4: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Dulles International

Airport

Who We Serve

Blue Plains Service Area

3

Provides

Drinking water distribution for DC

Wastewater collection and treatment

Stormwater collection and conveyance

Treats wastewater for a population of 2.1 million

District of Columbia

Montgomery & Prince George’s Counties, Maryland

Fairfax & Loudoun Counties, Virginia

Operates the world’s largest Advanced Wastewater Treatment Plant

Average daily capacity, 370 mgd

Peak daily capacity, 1 billion+ gallons

Serves a regional area of approximately 725 Square Miles

Blue Plains Advanced Wastewater Treatment Plant

Blue Plains

Advanced Wastewater

Treatment Plant

Page 5: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

DC Clean Rivers Background

Magnitude of the Challenge

Chronic Sewer Flooding

Combined Sewer Overflows

CSO Discharge to Anacostia River

Trash in Anacostia River

4 Current chance of flood occurring in any given year

Chance of flood after Northeast Boundary Tunnel

Page 6: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Clean Rivers Background

Plan

• DC Clean Rivers Project: $2.7 Billion • Nitrogen Removal: $950 Million • Total > $ 3.5 Billion • 25 yr implementation (2005 – 2030) • 96% reduction in CSOs & flood relief in Northeast

Boundary • Approx 1 million lbs/yr nitrogen reduction predicted

DC CLEAN RIVERS PROJECT AND

NITROGEN REMOVAL PROGRAMS

5

Page 7: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Clean Rivers Background

21st Century Sewer System

6

Page 8: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Clean Rivers Background

Benefits

7

CSO Reduction to Anacostia River

2,142

1,063

49

3,254

1,282

638

48

1,968

54 79 5 138

0

500

1,000

1,500

2,000

2,500

3,000

3,500

Anacostia River Potomac River Rock Creek Total System

CS

O O

verf

low

(m

g/a

vg y

ear)

1996 2016 Clean Rivers Completed

96% Reduction Overall, 98% on Anacostia River

Flood Mitigation in Northeast Boundary

14.1

8.7 6.0 6.2 7.3 6.3 5.2 5.3 5.4

6.7 5.3 4.8 3.7 3.2 3.1 3.8 2.6 2.6

Chesapeake Bay Agreement Goal

8.5 million pounds/year New NPDES Permit Limit

4.4 million pounds per year

Effluent TN Discharged in million pounds/year

Nitrogen Removal for Chesapeake Bay

1st & V St NW

Rhode Island Metro

Page 9: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

ANACOSTIA RIVER TUNNEL SYSTEM

8

Page 10: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Project Diameter Length Start Finish

Blue Plains Tunnel

($319M)

23 24,207

5/2011 8/2015

Anacostia River

Tunnel ($254M)

23 12,484 6/2013 12/2017

Northeast Boundary

Tunnel ($580M)

23 27,000 9/2017 5/2023

First Street Tunnel

($158M)

20 2,700 10/2013 10/2016

Various other contracts to connect to tunnel system

Blue

Plains

Tunnel

Poplar Point PS

Anacostia River Tun.

Main PS Diversions

Tingey St Div. Sewer

CSO 007

CSO 019

Northeast

Boundary

Tunnel

M St Div. Sewer

First St Tunnel

JBAB Diversions

J

Legend Completed

Construction

Procurement

LID at DC

Water

Facilities

A Blue Plains Tunnel

B Tingey Street Diversion Sewer

C CSO 019 Overflow and Diversion Structures

D JBAB Overflow and Potomac Outfall Sewer Diversion

E M Street Diversion Sewer (CSOs 015, 016 and 017)

G CSO 007 Diversion Structure and Diversion Sewer

H Anacostia River Tunnel

I Main Pumping Station Diversions

N LID at DC Water Facilities

P First Street Tunnel

J Northeast Boundary Tunnel

S Irving Street Green Infrastructure

Y Blue Plains Dewatering Pumping Station and ECF

Z Poplar Point Pumping Station Replacement

Anacostia River Tunnel System

Snapshot

More than $1.8 B in Contracts have been let for the Anacostia River Projects

9

Page 11: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Anacostia River Tunnel System

Tunnel Profile

Pumping station and wet weather treatment facility at Blue Plains

Minimum Grade = 0.1%

Depth determined by going under the following facilities: Bridges

Structures

Utilities

Working depth limited to 3 bars of water

10

Page 12: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

BLUE PLAINS TUNNEL

11

Page 13: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Blue Plains Tunnel

23 feet in diameter

24,207 feet long

05/2011 to 08/2015

Traylor-Skanska-JayDee 12

• Key component of Clean Rivers Project

• Key component of TN/Wet Weather Plan

• First major tunnel in program

• Significant suburban cost contribution

What is it?

• 23’ inside dia, 24,207 feet long

• 5 shafts – 50’ to 132’ Inside diameter

• 75 million gallons storage

Capacities

• Traylor-Skanska-JayDee (Designer CH2M)

• $330 million contract amount, $319 M final amount

• Award: May 2011

• Substantial completion: Dec 2015

Design-Builder

Page 14: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Blue Plains Tunnel

13

• Best day: 150 feet

• Best Week: 631 feet

• Average: 57 ft/day (excludes zero days)

• 726 calendar days

• Bolted and gasketed concrete steel fiber reinforced segments

• EPBM - Herrenknect

Tunnel Boring Machine

• Design MBE/WBE = 46%/5% (goal= 28%/4%)

• Construction MBE/WBE = 38%/3% (goal= 32%/6%)

• Total payments to MBE/WBE more than $110 M

MBE/WBE

• 591 cumulative employees on project

• 239 from DC and user jurisdictions

• 40 new hires sourced from Dept. of Employment Services (DOES)

Local Resident Hiring

Page 15: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Lady Bird Advances

14

Page 16: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

First design-build project for DC Water

100 yr design life 100 yr Green

Century bond

Proprietary collaboration procurement

process

Protected 100 year old sewers from

shaft excavation with unintrusive soil

mix columns

Slurry wall containment wall replaces

jet grouting for watertight TBM launch

Circular deaeration at intermediate

shafts eliminated separate drop shafts

and deaeration tunnels

Binocular shaft at Blue Plains

eliminated connecting tunnel between

shafts

Blue Plains Tunnel

Innovations

15

SURGE RISER (EQUAL

TO ID OF TUNNEL)

DEAERATION

CHANNEL

23-FT DIA.

TUNNEL

PLUNGE

POOL

BAFFLE

WALL

DRAIN

ORIFICE

PARTITION

WALL

DROP

PIPE 50-65-FT

SHAFT

“Binocular” Shaft

Circular Deaeration Shaft

Slurry Wall Replaces Jet Grout for TBM Launch

Slurry walls

TBM launch area

Soil Mix Columns Protect 100-yr Old Active Sewers

Soil mix columns improve ground

Shaft

100 yr old sewers (typ)

Page 17: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Completed more than 1.6 million person-hours without a lost time accident

Maintained a recordable incident rate (RIR) well below the Bureau of Labor

Statistics (BLS) national average for heavy civil construction:

TSJD: 1.82

BLS national average: 3.0

Blue Plains Tunnel

Safety

16

Page 18: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

17

Page 19: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

PROCUREMENT

18

Page 20: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Historical Delivery Methods

DC Water has typically used traditional Design-Bid-Build (DBB) delivery process

For LTCP projects, DC Water considered alternative project delivery methods, recognizing:

Tunneling projects differ from typical DC Water CIP

Early contractor involvement can reduce risks

Consent Decree schedule was a big driver

19

Page 21: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Project Delivery

Rationale for Design-Build

Benefits from early contractor involvement: Opportunity to reduce uncertainties between parties (mutual risk reduction)

Contractor design decisions

Facilitates discussing issues in a confidential setting pre-bid

Enhances alternative technical approaches

Schedule compression and flexibility

Need for price certainty

Price competition

20

Sensitive to marketplace’s concerns on risk

allocation and procurement confidentiality

Consent Decree

20

Page 22: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Design-Build Procurement Process

Industry Outreach

Generate Project Interest,

Update on Project

Progress

M/WBE Networking

RFQ Request

Qualifications Statements

Shortlist Evaluate SOQ

and Shortlist up to 4 Teams

Confidential Meetings

Teams Provide Technical

Approach to Build Project

Select Based on Best Value

Review Technical Approach

Collaboration

Technical and Cost Proposals

Evaluation Review and

Score Technical Proposals

Interviews

Conduct Interviews with

Shortlisted Teams

Selection Review Final Scoring

Open Price Proposals

Clarifications and Debrief

Contract Clarifications

Incorporate Components of

Technical Proposals

Hold Debrief Meetings with Unsuccessful

Teams

Provide Stipend to Unsuccessful

Teams

Best Value Technical Proposal Evaluation Factors (35% of score)

Project Management and Organization

Design and Construction Plan

M/WBE Business Development Plan, Local Hiring Initiative

and Subcontracting Plan

Price Proposal (65% of score)

Selection on price and technical proposal = best value

21

1 to 2 weeks

1 month

2 months

1 month before RFQ

8 to 9 months

1 month before RFP Issued

6 month process

TIMEFRAME

Page 23: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

LESSONS LEARNED

22

Page 24: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

Become owner of choice

Be fair, listen to contractors concerns, pay on time, fairly adjudicate claims

Design-builder participation during collaboration extremely valuable

Select key topics for collaboration and conduct substantive discussions on construction approaches

e.g. TBM selection, shaft construction techniques, dewatering, maintenance of traffic

Clarifications phase is valuable in reaching a final contract

Challenges bring up opportunities to make broader changes that benefit the entire program

Remain focused on your overall vision and goals – keep these in mind when approaching problems

Lessons Learned

23

Blue Plains Tunnel was an excellent project, built on time, under budget, safely and with high quality

Page 25: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

A Drop’s Life

24

Page 26: BLUE PLAINS TUNNEL DC CLEAN RIVERS PROJECT EPBM - Herrenknect Tunnel Boring Machine • Design MBE/WBE = 46%/5% (goal= 28%/4%) • Construction MBE/WBE = 38%/3% (goal= 32%/6%) •

25

Questions

Carlton M. Ray

email: [email protected]

phone: 202-787-4469