board of directors meeting · a recovery planning group was established in order to mitigate...
TRANSCRIPT
Integrated Performance Report Wednesday 29 February 2012 Page 1 of 35
Board of Directors Meeting
Date: Wednesday 29 February 2012
Agenda item: 8.1, Open
Title: Integrated Performance Report incorporating:
Quality / Performance / Finance and Activity / HR
Prepared by: Warwick Heale, Associate Director of Planning & Performance Ann Goodridge, Corporate Performance Manager
Presented by: Em Wilkinson-Brice, Director of Nursing & Patient Care
Action required: The Board is asked to receive the Performance Report and note the progress that has been made together with any actions that are planned.
Monitoring Information Please specify CQC standard numbers
and tick other boxes as appropriate
Care Quality Commission Standards Outcomes
Monitor Finance
Service Development Strategy Performance Management
Local Delivery Plan Business Planning
Assurance Framework Complaints
Equality, diversity, human rights implications assessed
Other (please specify)
Integrated Performance Report Wednesday 29 February 2012 Page 2 of 35
1. PURPOSE
1.1 To advise the Board of the Trust’s performance against the key performance standards and targets.
2. BACKGROUND
2.1
The Trust’s Annual Plan sets out the programme of work to be undertaken to ensure compliance with the Monitor Compliance Framework and local and national standards and targets included in PCT commissioning contracts. Detailed results of achievement as at 31 January 2012 are presented in Data Appendices - Performance (Dashboards and Data Tables).
3. KEY ISSUES
3.1 The rise in non-elective activity was sustained over the month of January particularly in the over 80 years old cohort. The impact of a 7.8% increase in general non-elective admissions over the first week in January when combined with a 31% increase in over 80 years old cohort admissions, culminated on the 6th January when the Trust took the unprecedented decision to request a divert for emergency patients. This divert remained in place for a period of 24 hours and resulted in 12 patients being diverted to other local providers; however ED remained open throughout and continued to receive self-referral. In total 55 emergency patients were admitted despite the divert arrangements. In response to Trust capacity pressures the daily Cluster Capacity Pressures Strategy Group conference calls were re-established with all health partners represented. The response of the wider health community was effective in creating the conditions from which recovery could be planned. The community response included additional resources being provided by Care Direct Plus to facilitate the discharge process. Devon Doctors extended provision of services, particularly over the weekend periods and GPs provided additional surgeries. Reablement services were bolstered in the community to support admission avoidance programmes and a community-wide communications plan was implemented. The continued capacity pressures resulted in 232 elective cancellations in the month of January with the Trust reducing elective activity to clinically urgent cases. Orthopaedics as the largest surgical specialty was most significantly impacted by this restriction as a very low proportion of its patients fall within this category. The reduction in elective activity was marginally less than had been experienced in the previous month despite greater pressure in the system. This is attributable to the planned reduction in elective activity for the month of January and the ability to plan staffing to sustain additional escalation areas. The Trust has been required to maintain 28 escalation beds over and above the planned escalation capacity of 30 beds for the majority of the reporting period. A recovery planning group was established in order to mitigate against disruption to RTT performance and the immediate action plan was agreed by the Trust Executive on the 16th January.
Integrated Performance Report Wednesday 29 February 2012 Page 3 of 35
The Trust, NHS Devon, Devon Partnership Trust and the South of England SHA have developed a joint action plan to improve Accident and Emergency whole system performance against the A&E target through a shared responsibility of demand management, capacity planning, patient flow and public communication regarding choice of healthcare provision.
3.2 Performance Targets Two of the Monitor targets assessed on a quarterly basis are currently not being met for Quarter 4. MON01 - Clostridium Difficile target. The Trust achieved the target for January with 7 cases (1 toxin positive) against a trajectory of 7 but has now exceeded the trajectory for the year with 77 cases (31 toxin positive) against a full year target of 74. Monitor’s Executive Committee met on the 13 February 2012 and decided that they would not escalate the Trust at this time but would review the situation after the end of quarter 4. The risk rating for the Trust was amended from red to amber-red accordingly. Draft guidance has been circulated by the South of England SHA that clarifies the reporting of Clostridium Difficile cases prior to implementation from 1 April 2012. Trusts will then be required to use a two test protocol consisting of a Glutamate Dehydrogenase (GDH) Enzyme Immunoassay (EIA) or Nucleic Acid Amplification Test (NAAT) followed by a sensitive toxin EIA test. Tests that are GDH EIA positive and toxin positive will be reportable. The Trust is expecting to have to change the toxin tests currently used which may have an impact on the numbers of toxin positives reported but overall the number will still be lower than those reported currently.
MON08.I - Cancer 14 Day GP Urgent target. The position for January was 92.1% against a target of 93%. The 39 of the 60 breaches related to haematuria clinic capacity issues during the month resulting from a change in booking rules. Plans have now been put in place to resolve the temporary increase in demand and to prevent a recurrence of the situation further details of which can be found in Appendix B. The Trust position is expected to return to achieving before the quarter end as the current underperformance of 0.9% equates to 7 breaches. Targets Currently being Met but at Risk for this Quarter The Referral to Treatment target for admitted pathways remains at risk for Q4. The Trust will flag to Monitor expected failure of the target in Q1 and Q2 in 2012/13 because of the impact of treating the backlog of patients whose routine elective procedures were deferred as a result of operational pressures during the winter period details of which are given in the Key issues section above MON09 – ED performance returned to above 95% during January but is sensitive to the impact of increased emergency admissions. A community wide action plan has been agreed to ensure continued compliance with this standard but there remains a risk of non compliance during the quarter.
3.3 Finance The key areas of financial performance are as follows:
At month 10 a year to date surplus of £3.5m has been generated compared to a budgeted surplus of £2.5m. A year end surplus of £2.8m is forecast compared to the budgeted £3.5m.
£15.6m CIP has been achieved for the current year and £11.1m on a recurrent basis against a requirement of £17.1m.
Integrated Performance Report Wednesday 29 February 2012 Page 4 of 35
A year to date Monitor Risk rating of 4 has been achieved but is forecast to be 3 at year end.
Clinical income is £0.1m under recovered year to date and is expected to be £0.8m adverse at year end.
Pay is under-spent by £316k year to date and is forecast to be £103k over-spent by year end. Non-pay is £884k over-spent at month 10 and forecast to be £1.1m over-spent by year end.
The Capital programme is £1.6m under-spent at month 10 and is expected to be £1.0m under-spent at year end.
3.4 Quality Key issues are:
The trustwide pressure sore assessment rate has improved in January and is above the 95% threshold.
There has been a small improvement in the compliance with initial assessment of nutritional screening (MUST). A further step increase has been observed in the early part of February following the Nutrition Matters campaign and active nurse leadership. Further improvement is necessary in the remainder of the quarter, in order to secure achievement of this CQUIN target in Q4.
Monthly spot audits of recording of VTE Risk Assessments are being undertaken to provide supplementary evidence to electronic recording of risk assessments. The Trustwide performance as measured by the electronic recording methodology was 80.12% in January, whereas the latest snapshot audit or practice demonstrates that the Trust is achieving 90.6%. Work is in progress through the VTE group, reporting to the Clinical Effectiveness Committee, to improve reporting of this target.
3.5 Human Resources Key issues are:
A reduction in the sickness absence rate. The sickness absence rate for the Trust for the twelve month period ending 31st December 2011 was 3.65%.
A decrease of 31.54 full time equivalents (FTE) in the Trust’s workforce to 4965.93 FTE; beneath the current funded establishment of 5154.65. Analysis of the volume of staff leaving the Trust indicates an elevated number of Band 5 registered nurses in December. Work is ongoing to collate the staff members’ stated reasons for leaving and their destination on leaving to enable the Trust to gauge the extent of any issues.
The rate of turnover for the twelve month period ending 30th November 2011 was 9.65%, a slight decrease on the position reported last month.
PDR compliance rates have improved, with the Trust target rate of 80% being achieved for the second consecutive month. A review of essential training compliance rates is being undertaken by Internal Audit. A position statement and Trustwide action plan will be submitted to the Governance Committee in March 2012.
4. FINANCIAL/OTHER IMPLICATIONS Achieving NHS plan targets and milestones is an important feature of the Trust’s
Integrated Performance Report Wednesday 29 February 2012 Page 5 of 35
overall performance and demonstrates our commitment to delivering good quality care to patients. Commissioners have the discretion to apply financial penalties in respect of underperformance for the following targets:
Non-achievement of the Clostridium difficile target (depending on the degree of target underperformance, between 0.1% and 2% of the total contract year revenue), the standard contract allows for penalties to be applied where the current year outturn exceeds the number of cases identified in the previous contract year, by more than 2 cases. In order that the Trust is not disadvantaged by the introduction of the new testing methodology, it has been agreed to exclude the impact of the cases identified using the new testing methodology from both last year's baseline and this year's figures, for the purposes of financial and contract penalties. Based on current performance, the risk of penalties in 2011/12 is assessed as low.
Non-achievement of the referral to treatment time standard (depending on the degree of target underperformance between 0.5% and 5% of monthly elective care revenue). The risk of penalties, based on current performance is assessed as low, but there may be risks in Q4 as a result of cancellations in Q3. Depending on the degree of underperformance against the referral to treatment waiting time standard, this could equate to a maximum penalty of c£400k per month in relation to admitted patient care, or c£130k per month in relation to non-admitted patient care, but totalling no more than c£450k per month in aggregate.
each of the following cancer waiting times standards (2% of the actual outturn value of the service line revenue)
o 14 day urgent GP referral
o 14 day symptomatic breast
o 62 days first definitive treatment for GP urgent referral, NHS Cancer Screening Services and Consultant Upgrades
o 31 day first definitive treatment
o 31 day second or subsequent treatment (surgery)
o 31 day second or subsequent treatment (drug treatments)
o 31 day second or subsequent treatment (radiotherapy)
There may be a failure in any one month due to low volumes of cases. However as the penalties are viewed as relating to full year performance, the risk of financial penalties for 2011/12 is assessed as low.
breaches of the Eliminating Mixed Sex Accommodation Plan (£250 per breach per day). There have been no clinically unjustified breaches for first ten months of the financial year. The risk of penalties for 2011/12 above a very low financial value is assessed as low.
5. RECOMMENDATIONS The Board is asked to receive the Performance Report and note the progress that has been made together with any actions that are planned.
Integrated Performance Report Wednesday 29 February 2012 Page 6 of 35
Graph YTD Indicator Current Source Report
R1 Red ↑ Accident and Emergency Maximum 4 Hour Wait Green Performance
R2 Amber → Clostridium Difficile Infections Green Performance
R3 Green → Cancer 31 Day Wait: Subsequent Treatment Green Performance
R4 Green → Cancer 62 Day Wait Green Performance
R5 Green ↓ Hand Hygiene Green Quality
R6 Amber ↓ New MRSA Isolates Red Quality
R7 Green → Referral to Treatment for Admitted Pathways Green Performance
R8 Green ↓ Referral to Treatment for Non-Admitted Pathways Green Performance
Graph YTD Indicator Current Source Report
D1 Amber ↑ Outpatient New Attendances Amber Finance
D2 Green ↑ Elective Daycase Admissions Green Finance
D3 Amber ↓ Elective Inpatient Admissions Amber Finance
D4 Green ↓ Non-Elective Inpatient Admissions Green Finance
D5 Green ↑ Pressure Sores Assessment Green Quality
D6 Amber ↓ Pressure Sores Incidence Green Quality
D7 Red ↑ MUST Scoring Red Quality
D8 Amber → Capital Expenditure Amber Finance
Graph YTD Indicator Current Source Report
E1 Amber ↓ Bank and Agency Spend All Staff Amber Human Resources
E2 Green → Cash Green Finance
E3 Green ↓ Cost Improvement Programmes Green Finance
E4 Green ↑ Income and Expenditure Green Finance
E5 Amber ↑ PDR/PDPs Completed & Essential Training Compliance Amber Human Resources
E6 Green → Risk Ratings Green Finance
E7 Green ↑ Sickness Absence Rate Green Human Resources
E8 Green ↑ Staff Employed Green Human Resources
E9 Amber → Staff Percentage Turnover Rate Amber Human Resources
E10 Amber ↓ Reason for Leaving Amber Human Resources
Red Off target or significant concerns re. achievement. Board to review exception report.
Amber Slightly off target or minor concerns re. achievement. Board to be aware, but no action required.
Green On target, no significant concerns re. achievement. No Board attention required.
→ Direction indicators point up for improvement, down for worsening and horizontal for no material change.
Deliver services in a comfortable, friendly environment in which staff can care for patients effectively.
Recognise our wider responsibility to the environment and local community by using resources wisely.
Respond
Integrated Performance Report - Summary Table
Be the provider of choice, delivering care in the most convenient and appropriate location, with no delay.
Eliminate all avoidable hospital infections.
Future and sustained success through good financial management.
Deliver
A high standard of care delivered by experts, which meets the needs and aspirations of patients, staff, carers and the
A full range of cost-effective accessible local hospital services.
A range of excellent specialist services.
Staff to have a good work/life balance, and achieve their full potential.
Staff to do their jobs to the best of their ability, by valuing them, ensuring they have the right skills and giving them the
opportunity to focus on meeting the needs of patients, so making the RD&E the employer of choice.
Enable
Additional Reported Indicators (by Exception)
Integrated Performance Report Wednesday 29 February 2012 Page 7 of 35
Be the provider of choice, delivering care in the most convenient and appropriate location, with no delay.
Eliminate all avoidable hospital infections.
Deliver services in a comfortable, friendly environment in which staff can care for patients effectively.
Recognise our wider responsibility to the environment and local community by using resources wisely.
YTD Indicator Current YTD Indicator Current
R R1 - Accident and Emergency Maximum 4 Hour Wait G A R2 - Clostridium Difficile Infections G
G R3 - Cancer 31 Day Wait: Subsequent Treatment G G R4 - Cancer 62 Day Wait G
G R5 - Hand Hygiene G A
R6 - New MRSA Isolates Identified > 72 Hours After
Admission R
Quality Quality
Respond
Performance Performance
PerformancePerformance
0
1
2
3
4
5
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
Average SPC +1sd
0
10
20
30
40
50
60
70
80
90
100
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
90%
91%
92%
93%
94%
95%
96%
97%
98%
99%
100%
Ap
r-1
0
May
-10
Jun
-10
Jul-
10
Au
g-1
0
Sep
-10
Oct
-10
No
v-1
0
Dec
-10
Jan
-11
Feb
-11
Mar
-11
Ap
r-1
1
May
-11
Jun
-11
Jul-
11
Au
g-1
1
Sep
-11
Oct
-11
No
v-1
1
Dec
-11
Jan
-12
% T
reat
ed
Wit
hin
4 H
ou
rs
Wonford WIC Attendance figures are
added to A&E position replacing
community MIU data from July 2011.
75%
80%
85%
90%
95%
100%
Ap
r-0
9
Jun
-09
Au
g-0
9
Oct
-09
Dec
-09
Feb
-10
Ap
r-1
0
Jun
-10
Au
g-1
0
Oct
-10
Dec
-10
Feb
-11
Ap
r-1
1
Jun
-11
Au
g-1
1
Oct
-11
Dec
-11
% T
reat
ed
Wit
hin
31
Day
s
Subsequent Surgery Subsequent Radiotherapy
Radiotherapy Target introduced Jan-
11
95%
96%
97%
98%
99%
100%
Ap
r-0
9
Jun
-09
Au
g-0
9
Oct
-09
Dec
-09
Feb
-10
Ap
r-1
0
Jun
-10
Au
g-1
0
Oct
-10
Dec
-10
Feb
-11
Ap
r-1
1
Jun
-11
Au
g-1
1
Oct
-11
Dec
-11
% T
reat
ed
Wit
hin
31
Day
s
0
5
10
15
20
25
Ap
r-0
9
Jun
-09
Au
g-0
9
Oct
-09
Dec
-09
Feb
-10
Ap
r-1
0
Jun
-10
Au
g-1
0
Oct
-10
Dec
-10
Feb
-11
Ap
r-1
1
Jun
-11
Au
g-1
1
Oct
-11
Dec
-11
Trust Attributed Infections Toxin Positive Tests Trajectory
New PCR Test
Introduced in
October 2010
Integrated Performance Report Wednesday 29 February 2012 Page 8 of 35
YTD Indicator Current YTD Indicator Current
G R7 - Referral to Treatment for Admitted Pathways G G R8 - Referral to Treatment for Non Admitted Pathways G
PerformancePerformance
0
5
10
15
20
25
Ap
r-1
0
May
-10
Jun
-10
Jul-
10
Au
g-1
0
Sep
-10
Oct
-10
No
v-1
0
Dec
-10
Jan
-11
Feb
-11
Mar
-11
Ap
r-1
1
May
-11
Jun
-11
Jul-
11
Au
g-1
1
Sep
-11
Oct
-11
No
v-1
1
Dec
-11
Jan
-12
95
th P
erc
en
tile
(w
ee
ks)
0
2
4
6
8
10
12
14
16
18
20
Ap
r-1
0
May
-10
Jun
-10
Jul-
10
Au
g-1
0
Sep
-10
Oct
-10
No
v-1
0
Dec
-10
Jan
-11
Feb
-11
Mar
-11
Ap
r-1
1
May
-11
Jun
-11
Jul-
11
Au
g-1
1
Sep
-11
Oct
-11
No
v-1
1
Dec
-11
Jan
-12
95
th P
erc
en
tile
(w
ee
ks)
Integrated Performance Report Wednesday 29 February 2012 Page 9 of 35
YTD Indicator Current YTD Indicator Current
A D1 - Outpatient New Attendances A G D2 - Elective Daycase Admissions G
A D3 - Elective Inpatient Admissions A G D4 - Non-Elective Inpatient Admissions G
G D5 - Pressure Sores Assessment G A D6 - Pressure Sores Incidence G
Current month vs plan: 17% below plan
17% lower than the same month last year
1% lower than the previous month
Year to date:17% lower than the same period in 2010-11
Year to date vs plan:12% below plan
Current month vs plan: 5% below plan
4% lower the same month last year
5% lower than the previous month
Year to date: 2% lower than the same period in 2010-11
Year to date vs plan: 1% below plan
Deliver
Finance Finance
FinanceFinance
A high standard of care delivered by experts, which meets the needs and aspirations of patients, staff, carers and the
public.A full range of cost-effective accessible local hospital services.
A range of excellent specialist services.
Current month vs plan: 6% below plan
4% higher than the same month last year
16% higher than the previous month
Year to date: same as the same period in 2010-11
Year to date: 9% below plan
Current month vs plan:11% higher than plan
11% higher than the same month last year
21% higher than the previous month
Year to date: 4% higher than the same period in 2010-11
Year to date vs plan: 4% above plan
Quality Quality
0
10
20
30
40
50
60
70
80
90
100
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
0%
5%
10%
15%
20%
25%
30%
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
6000
6500
7000
7500
8000
8500
9000
9500
10000
10500
11000
Jan
-09
Mar
-09
May
-09
Jul-
09
Sep
-09
No
v-0
9
Jan
-10
Mar
-10
May
-10
Jul-
10
Sep
-10
No
v-1
0
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
Plan Actual
2000
2500
3000
3500
4000
4500
5000
5500
6000
Jan
-09
Mar
-09
May
-09
Jul-
09
Sep
-09
No
v-0
9
Jan
-10
Mar
-10
May
-10
Jul-
10
Sep
-10
No
v-1
0
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
Plan Actual
500
700
900
1100
1300
1500
1700
1900
2100
Jan
-09
Mar
-09
May
-09
Jul-
09
Sep
-09
No
v-0
9
Jan
-10
Mar
-10
May
-10
Jul-
10
Sep
-10
No
v-1
0
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
Plan Actual
1500
1750
2000
2250
2500
2750
3000
3250
Jan
-09
Mar
-09
May
-09
Jul-
09
Sep
-09
No
v-0
9
Jan
-10
Mar
-10
May
-10
Jul-
10
Sep
-10
No
v-1
0
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
Plan Actual
Integrated Performance Report Wednesday 29 February 2012 Page 10 of 35
YTD Indicator Current YTD Indicator Current
R D7- MUST Scoring R A D8 - Capital Expenditure A
Spend YTD: £10.7m Planned Spend YTD: £12.3m
Forecast Y/E Spend: £15.6m Planned Y/E Spend: £16.7m
FinanceQuality
0
10
20
30
40
50
60
70
80
90
100
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
Initial compliance with MUST Screening onAdmission
General compliance with MUST Screening atWeekly Review
0
2
4
6
8
10
12
14
16
18
£M
Month
Capital Spend
Capital Plan 11/12
Actual Capital Spend
Forecast Capital Spend
Elective inpatient activity is 12% below plan, but day case activity is 11% above plan (year to date). As day cases account for the majority of elective activity, the combined position is 0.7% below plan. Day cases are a more efficient way to deliver surgery and, in most cases, attract the same tariff income as inpatients. However, the cancellations of elective cases experienced through the winter has led to pressure on the admitted waiting time targets and additional elective activity will be required in Q4 2011/12 and the first half of 2012/13 to sustainably achieve these targets in every specialty.
Integrated Performance Report Wednesday 29 February 2012 Page 11 of 35
YTD Indicator Current YTD Indicator Current
A E1 - Bank, Agency & Overtime Spend All Staff A G E2 - Cash G
G E3 - Cost Improvement Programmes G G E4 - Income and Expenditure G
A E5 - PDR/PDPs Completed & Essential Training Compliance A G E6 - Risk Ratings G
ESR is used for the purpose of recording and reporting PDR activity excluding Medical and Dental staff.
Actual Surplus YTD: £3.5m Plan Surplus YTD: £2.9m
Forecast Surplus Y/E: £2.8m Plan Surplus Y/E: £3.5m
Actual Efficiency: 0.80% Planned Efficiency: 1.03%
FinanceFinance
The above chart indicates the amount of spend relating to staff registered on the bank, staff
supplied by agencies and overtime worked by substantive staff.
Research and innovation.
FinanceHuman Resources
Enable
Human Resources Finance
Staff to do their jobs to the best of their ability, by valuing them, ensuring they have the right skills and giving them the
opportunity to focus on meeting the needs of patients, so making the RD&E the employer of choice.
Staff to have a good work/life balance, and achieve their full potential.
Future and sustained success through good financial management.
Cash in hand and at bank: £55.3m
Working Capital Facility: £0m
Cash Invested @ Month End: £43.0m
£0
£50,000
£100,000
£150,000
£200,000
£250,000
£300,000
£350,000
£400,000
Dec-1
0
Jan-1
1
Feb-1
1
Mar-
11
Apr-
11
May-1
1
Jun-1
1
Jul-11
Aug-1
1
Sep-1
1
Oct-
11
Nov-1
1
Dec-1
1
Agency Bank Overtime
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
Jan-1
1
Feb-1
1
Mar-
11
Apr-
11
May-1
1
Jun-1
1
Jul-11
Aug-1
1
Sep-1
1
Oct-
11
Nov-1
1
Dec-1
1
Jan-1
2
PDR Equality & DiversityFire Infection ControlManual Handling
-3,000
-2,000
-1,000
0
1,000
2,000
3,000
4,000
5,000
April
May
June
July
August
Septe
mber
Octo
ber
Novem
ber
Decem
ber
January
Febru
ary
Marc
h
Month
£
Actual
Plan
Risk Ratings
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
EBITDA Margin
EBITDA % Achieved
ROA
I&E Surplus Margin
Liquidity
Overall Rating
Plan YTD
Actual YTD
Plan Y/E
Forecast Y/E
Other Ratios Plan YTD Actual YTD Plan Y/E Forecast Y/E
Trade Creditor Days 6.3 8.7 6.4 6.2
NHS Trade Debtor Days 9.7 9.6 8.9 9.4
Debt to Asset Ratio 6.5% 6.6% 6.3% 6.5%
Other items £ £ £ £
Revenue available for debt service 19.8m 20.6m 23.9m 23.1mDebt 20.8m 20.8m 20.2m 20.2m
Total Assets 319.8m 318.1m 321.9m 309.3m
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
April
May
June
July
August
Septe
mber
Octo
ber
Novem
ber
Decem
ber
January
Febru
ary
Marc
h
Month
£m
CIP Plan
CIP Actual
CIP Forecast
12 Month forecast cashflow v plan
(20)
(10)
-
10
20
30
40
50
60
70
80
Ap
r-1
1
Ma
y-1
1
Ju
n-1
1
Ju
l-11
Au
g-1
1
Se
p-1
1
Oc
t-1
1
No
v-1
1
Dec
-11
Ja
n-1
2
Feb
-12
Ma
r-12
Month
£M
Plan
Actual
Forecast
Commited Facility
Integrated Performance Report Wednesday 29 February 2012 Page 12 of 35
YTD Indicator Current YTD Indicator Current
G E7 - Sickness Absence Rate G G E8 - Staff Employed G
A E9 - Staff Percentage Turnover Rate A A E10 - Reason for Leaving A
The total FTE has decreased by 31.54 to 4965.93. This is below the funded FTE establishment of
5154.65. Headcount has decreased by 32 to 5746.The cumulative rate for 12 months to 31st December 2011 is 3.65%.
Human Resources Human Resources
Human ResourcesHuman Resources
The turnover rate of 9.63% for the combined 12 month period to end of December 2011 is
higher than the 8.70% for the equivalent period last year. Based on FTE for all staff groups (excludes Bank workers)
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
Dec-1
0
Jan-1
1
Feb-1
1
Mar-
11
Apr-
11
May-1
1
Jun-1
1
Jul-11
Aug-1
1
Sep-1
1
Oct-
11
Nov-1
1
Dec-1
1
Long Term Medium Term Short Term
0%
2%
4%
6%
8%
10%
12%
Dec-1
0
Jan-1
1
Feb-1
1
Mar-
11
Apr-
11
May-1
1
Jun-1
1
Jul-11
Aug-1
1
Sep-1
1
Oct-
11
Nov-1
1
Dec-1
1
Substantive Staff
Substantive less retirements
Predicted Substantive less retirements
0
20
40
60
80
100
120
140
160
180
Dec-1
0
Jan-1
1
Feb-1
1
Mar-
11
Apr-
11
May-1
1
Jun-1
1
Jul-11
Aug-1
1
Sep-1
1
Oct-
11
Nov-1
1
Dec-1
1
Dismissal End of Fixed Term Contract
Retirement Voluntary Resignation
4,800
4,900
5,000
5,100
5,200
5,300
5,400
Dec-1
0
Jan-1
1
Feb-1
1
Mar-
11
Apr-
11
May-1
1
Jun-1
1
Jul-11
Aug-1
1
Sep-1
1
Oct-
11
Nov-1
1
Dec-1
1
Contracted FTE Funded FTE
Worked FTE
Integrated Performance Report Wednesday 29 February 2012 Page 13 of 35
Finance FINANCIAL REPORT FOR THE TRUST COVERING THE PERIOD
ENDING 31ST JANUARY 2012
Executive Summary
The Trust has generated a year to date surplus at month 10 of £3.5m compared to a budgeted surplus of £2.5m and a planned surplus of £2.9m. At year end the Trust is forecasting a surplus of £2.8m compared to the budgeted and planned surplus of £3.5m. The year to date surplus is an improvement on last month’s report by £900k, the surplus was budgeted to improve during January by £836k. Further improvement has been seen mainly due to an over recovery on income and a reduction in expected pay spend. The year end forecast has improved by £941k compared to last months report due to similar improvements seen in the year to date position. This position gives the Trust a Monitor Financial Risk Rating of 4 year to date and forecast to drop to 3 at year end in line with plan. Please note all variances given below are compared to budget.
INCOME Clinical income at month 10 is £111k under recovered which is a £356k improvement on last month’s report. The forecast is £785k adverse and is also an improvement on that reported at month by £293k. Both year to date and forecast improvements have been seen mainly within Critical Care (due to increased ICU activity) and Women & Childs’ Health (partly in Gynaecology but mainly due to an increase in non-elective events in Maternity). At month 10 (based on 9 months actual activity) the contract with NHS Devon is £1.6m over recovered. It is expected all areas of over performance will be settled by the relevant commissioner (please see Receivables section below for further details). Winter pressures and the cancellation of elective work have started to reduce along with the risk of not meeting the Refer to Treat (RTT) target for quarter 4. At present plans are being formulated in conjunction with NHS Devon on ensuring all elective patients can be treated within the RTT target by specialty. The majority of these plans are expected to start next financial year. The main Divisional over/under performances year to date (for all Commissioners) are;
Women & Childs’ Health continues to be the main area to over recover (£1.5m). Gynaecology planned activity is the main specialty to over-perform by £944k. This is
YTD Month 10 YTD Month 9 Change
£’000 £’000 £’000
I&E year to date 3,537 2,652 885
I&E Forecast 2,790 1,849 941
I&E year end forecast variance to budget/Plan
-710 -1,651 941
Total Income variance to date 413 -79 492
CIP variance to date -525 117 -642
Pay expenditure variance to date 316 -7 324
Non pay (excl. R&D) expenditure variance to date
-884 -779 -105
Cash at month end 55,256 49,228 6,028
Integrated Performance Report Wednesday 29 February 2012 Page 14 of 35
due to day-cases activity treating 29% more patients than budgeted. Midwife activity is another area to over recover £844k due to approximately 536 more non elective patients being treated than budgeted.
The Surgery Division continues to be the main area to under-perform by £1.2m. General Surgery (£664k) is one of the main areas due to elective activity being 23% down on budget. Thoracic Surgery (£523k) is the other main area to under recover also treating less elective activity than budgeted (46%).
Trauma & Orthopaedics Directorate is another area to under-perform compared to budget (£1.1m). Orthopaedic elective is 16% down compared to budget which is mainly due to cancelling work as a result of winter pressures.
EXPENDITURE At month 10 pay is £316k underspent which is an improvement by £324k on the position reported at month 9. The forecast position on pay has also improved by £102k to a forecast overspend of £103k. The deterioration between the year to date and forecast is due to additional spend forecast on nursing due to the increased emergency activity experienced during December and is forecast to continue. Admin & Clerical (A&C) staff is the main area to under-spend year to date by £804k, this is partially offset by spend on agency staff (£315k). Following the A&C review it is likely that a significant portion of underspend will transfer to CIP. Further under-spends are occurring within technical/Estates officers (£266k) and domestics (£282k) budgets. This is being offset by an over-spend on Non NHS staff (£311k, excluding A&C mentioned above), medical staffing (£260k) and nursing/bank/agency nurses (£452k). Non-pay expenditure at month 10 is over-spent by £884k year to date which is a deterioration on last month’s report by £105k. The forecast year end position on non pay is £1.1m adverse which is comparable to the month 9 report. The main areas to under/over-spend year to date are as follows:
Spend on drugs (not those rechargeable back to the Commissioners) continues to be below budgeted levels, £347k favourable. This is mainly due to blood usage across the Trust being lower than planned.
Clinical supplies is an area over-spending by £307k with activity related spend in Medicine, Radiology and Women and Childs’ Health the main reason.
Maintenance contractor costs are over-spent by £437k with spend across the Trust but mainly within the Trust’s Estates Departments (£285k RD&E Estates, £70k Community Estates which is recoverable).
Electricity expenditure at month 10 is £210k over budget, this is partially offset with underspends on gas and oil (£160k).
COST IMPROVEMENT PROGRAMME (CIP)
Current Year Savings of £15.6m have been achieved at month 10 for the year so far. £7.0m has been generated via the 10 work streams and a further £8.6m has been generated centrally. The remaining requirement of £1.6m to meet the £17.1m target is expected to be generated by year-end. Recurrently On a recurrent basis £11.1m of savings have been achieved, £8.4m via the 10 work streams and £2.7m centrally. A further £6m of savings is forecast to be achieved by year end. Of the £2.6m currently shown as unidentified in appendix 7, £1.5m is expected to be achieved by service lines, with a further £400k generated through MARS. The remaining shortfall of £700k is expected to be identified and delivered by year end. The level of unidentified
Integrated Performance Report Wednesday 29 February 2012 Page 15 of 35
schemes reflects in part a decision taken earlier this year to reduce the savings from the number of beds given the operational pressure on the hospital. In addition to the £700k shortfall there remains £250k which is categorised as high risk in relation to medical staffing. Please refer to appendix 7 for more detail on the 10 CIP work streams.
CAPITAL
Actual capital expenditure for the first ten months of the year was £10.7m in comparison to £12.3m in the plan. Capital expenditure is therefore £1.6m lower than planned, representing 13% of planned capital expenditure (excluding the University’s RILD capital additions, capital expenditure would be £2.9m lower than planned representing a 24% capital slippage). Capital expenditure for the year is now forecast to be £15.6m, which is £1m less than plan. The forecast capital additions represent a 6% capital plan reduction (excluding the University’s RILD capital additions, capital expenditure is forecast to be £2.8m lower than planned representing a 17% capital slippage). Guidance has been received from the Trust’s external auditors on the accounting treatment of the RILD building. The University’s element of the building should be classed in the Trust’s assets under construction additions until the asset is brought into use. When brought into use the University’s element will be disposed of and their contribution towards the building costs will be treated as the sale proceeds, therefore no loss on disposal is expected. Appendix 6 provides details of expenditure variances for capital schemes in excess of £1 million. There is a risk that capital expenditure could slip further as several large capital schemes are forecast to incur expenditure in March 2012. The annual plan included an estimated 5% increase in the value of land and buildings as at 31 March 2012. The District Valuer has advised that there will be a small fall in value for land and buildings. The change in value is not considered sufficiently material to require the Trust to revalue its land and buildings and the forecast position therefore no longer includes a change in valuation. The Trust’s external auditors have been advised.
RECEIVABLES
Receivables are £2.4m higher than budget and £2.0m higher than plan. Receivables include £2.4m of income due from NHS Devon relating to the variance for additional activity between periods 1 to 8, this amount is now overdue. NHS Devon have been requested to settle this debtor.
CASH
The cash balance at the end of January is £55.3m, which is very similar to the budget and plan (£55.8m).
INVESTMENTS The above cash includes £43m of investments placed with permitted financial institutions in accordance with the Treasury Management Policy approved by the Board. See below table for further details.
Integrated Performance Report Wednesday 29 February 2012 Page 16 of 35
Investor £m Interest rate Period Return date
Barclays Bank £10m 0.72% 54 days 23/3/2012 NatWest Bank £3m 1.18% 90 days 90 days notice National Loans Funds £15m 0.48% 89 days 5/3/2012 National Loans Funds £5m 0.42% 18 days 16/2/2012
Nationwide B/Soc £10m 0.57% 26 days 24/2/2012
Total £43m
As at 3 February 2012, a total of £63m of investments had been placed. An additional £13m was invested with National Loans Funds and £7m with the Nat West Bank.
The Board of Directors approved, in November 2011, permitted financial institutions that the Trust may place investments with subject to them meeting credit rating requirements. Lloyds Bank no longer complies with the agreed short and long term Standard and Poors credit rating criteria, as set by the Board of Directors, as it has been down graded to short term A-2 (minimum requirement per the Treasury policy A-1) and long term A- (minimum requirement per the Treasury policy A). This has reduced the approved investment options available to the Trust
ACTIVITY Outpatient and day-case activity for January is higher than that delivered in December (16% and 21% respectively) with elective and non-elective inpatient activity lower (1% and 5% respectively). Compared to January 2011 this January has seen a similar trend with higher activity for outpatients and day-cases (4% and 11% respectively) and lower activity for elective and non-elective inpatients (17% and 4% respectively). So far for the year compared to the first 10 months of last year outpatient activity has been virtually the same. For day-cases 4% more patients have been treated and for both elective and non-elective inpatients fewer patients have been treated (17% and 2% respectively) Compared to plan, for the year to date with the exception of day-cases (4% above plan), outpatient, elective and non elective inpatient activity are below plan (9%, 12% and 1% respectively). This trend is the same for January activity with day-cases 11% above plan, outpatients 6% below, elective inpatients 17% below and non-elective 1% below plan. Referrals for January are 4.72% (448 referrals) higher than January 2011, however referrals for the first 10 months of the year are 2.12% lower than the first 10 months of last year. This trend compares to last months report of 2.84%.
OTHER ISSUES Service Line Reporting Appendix 8 shows a surplus/deficit analysis by Directorate and is based on a Service Line Reporting perspective. It should be noted the figures relate to the Month 9 position. As the year unfolds SLR reporting reflects how profitability across Directorates shifts during the year, for example as a result of winter pressures where elective surgery is cancelled and income reduced. Of greatest interest is the deficit shown for Medicine with the Care of the Elderly Service Line being of greatest concern. The Finance department in conjunction with the Service line have undertaken rigorous investigation to refine and understand the position and some valuable lessons have been learned which will be used to improve accuracy of the SLR financial reporting in future months. However, the SLR financial reporting for Care of the Elderly will continue to show significant deficit which will now be examined further as part of
Integrated Performance Report Wednesday 29 February 2012 Page 17 of 35
Fit for the Future in 2012/13. More work is needed to understand the loss making nature of the activity and what can be done to improve the position. Other services which have reported deficit positions will also be required to achieve improvements in financial performance going forward. An action plan of work around the next phase of the SLR/SLM agenda has now been agreed by the SLM Project Board. Planned developments include extending the scope of SLR to include the Diagnostics Directorate in order to drive financial improvement in this area through a focus on demand management and financial performance. Improving performance management information and systems is a key part of the action plan and will require considerable focus and effort if the move towards SLM is to be successful. The plan sets out a timetable of work to draft an SLM Framework and task and finish groups are being established to progress this work urgently so that consultation and pilots can follow later in the year.
Month 9 Foundation Trust Consolidation Schedules (FTCS)
The Trust was required to prepare FTCS for the nine month period ending 31 December 2011. The FTCS are equivalent in content to preparing full statutory accounts and also include additional information relating to inter NHS balances and transactions and further information requested by Monitor to assist with their accounts consolidation. The FTCS were submitted to Monitor in January and February in accordance with Monitor’s timetable.
CONCLUSION
The key areas of financial performance are as follows:
At month 10 a year to date surplus of £3.5m has been generated compared to a budgeted surplus of £2.5m. A year end surplus of £2.8m is forecast compared to the budgeted £3.5m.
£15.6m CIP has been achieved for the current year and £11.1m on a recurrent basis against a requirement of £17.1m.
A year to date Monitor Risk rating of 4 has been achieved but is forecast to be 3 at year end.
Clinical income is £0.1m under recovered year to date and is expected to be £0.8m adverse at year end.
Pay is under-spent by £316k year to date and is forecast to be £103k over-spent by year end. Non-pay is £884k over-spent at month 10 and forecast to be £1.1m over-spent by year end.
The Capital programme is £1.6m under-spent at month 10 and is expected to be £1.0m under-spent at year end.
Integrated Performance Report Wednesday 29 February 2012 Page 18 of 35
Performance
BOARD EXCEPTION REPORT
CORPORATE TARGET NUMBER & DESCRIPTION:
Cancer Waiting Times
CURRENT CORPORATE RATING:
RESPONSIBLE DIRECTOR: Chief Operating Officer
Brief description of how the rating was derived – All Cancer Two week wait
Maximum two week wait from urgent GP referral for suspected cancer to first hospital assessment.
Background & Contributing factors
Prior to December 2011, haematuria referrals could either be referred under the 2WW system or as a routine new referral if the consultant and GP agreed the risk of cancer was minimal. In December 2011 the Urology team amended their booking rules to be in line with NICE guidance which advised that all patients presenting with haematuria should be referred under the 2WW rules.
The overall demand did not rise but the 2WW demand saw a sharp rise in December 2011 & January 2012. Urology have got past this one-off increase it is not anticipated that there should be any further problems meeting this demand.
Details of actions necessary to return performance back to either good or excellent
Action Dept responsible
Timescale Progress
Increased Endoscopy Capacity for Urology 1 stop haematuria clinic
Endoscopy 24/02/2012 An additional endoscopy clinic was held on the 3rd February and a further additional clinic has been arranged on the 24th February to accommodate the increased one-off demand following the reclassification of urgent patients to 2 week wait patients. The Clinical Service Manager (CSM) for Urology will monitor the demand for the haematuria clinic and in the event of any capacity issues will work with endoscopy to create an additional clinic within 1 week to accommodate the demand.
Increased ultrasound capacity for Urology1 stop haematuria clinic
Radiology 24/02/2012 Support for the additional clinics above has been arranged. The CSM for Urology will arrange for additional ultrasound support for any haematuria clinic created to accommodate increased demand.
Extra outpatient clinic and Surgery / 06/02/2012 In order to mitigate any risk
Integrated Performance Report Wednesday 29 February 2012 Page 19 of 35
corresponding ultrasound support for a 2 stop haematuria service. This is an interim measure and only necessary for a small number of patients to get past the temporary increase in 2 week wait demand.
Radiology Completed
where endoscopy capacity and ultrasound capacity cannot be implemented at the same time extra slots have created during February by implementing a 2 stop service where patient with ultrasound is seen by consultant first and then referred for cystoscopy if clinically indicated. This is not a long term solution and will only be implemented if all other actions fail.
Integrated Performance Report Wednesday 29 February 2012 Page 20 of 35
Quality MUST Scoring There has been some improvement in this measure from last month to 78% but the Trust is currently falling short of the Q4 CQUIN target in this area. The target for Q4 (90%) is significantly higher than that for Q3 (78%). There has been an increase in performance in the early part of February to 88% following the Nutrition Matters campaign and active nurse leadership. Extra support has been provided to ensure the Matron on AMU gives dedicated time to securing improvement for patients on admission to AMU. Whilst challenging, nursing staff are striving to sustainably achieve this target, accepting the clinical importance for patients of robust nutritional assessment on admission. MRSA Isolates There has been an increase in the number of MRSA isolates identified on patients who have been in hospital for more than 72 hours. These have been examined and have been cross-correlated with other ward level infection control indicators. There are no significant patient safety risks currently associated with the increase in this indicator as it does not relate to MRSA bacteraemia but any MRSA identified from a specimen greater than 72 hours after admission. This does not necessarily indicate infection or that it is hospital acquired. Electronic VTE Risk Assessment The target for this is 90% and currently the electronic reporting against this indicator is showing the Trust is achieving 80%. However, the latest snapshot audit of practice demonstrates that the Trust is achieving 90.6%. Work is in progress through the VTE group (accountable to the Clinical Effectiveness Committee) to improve electronic reporting of this target. Pressure Sores Assessment Pressure Ulcer Risk Assessment has improved in January and is back above the 95% threshold following a three month dip in performance.
Integrated Performance Report Wednesday 29 February 2012 Page 21 of 35
Human Resources
Sickness Absence It is pleasing to report the sickness absence rate has dropped to 3.65% from the 3.79% reported last month. As a result of the measures introduced to manage sickness absence this shows a significant reduction on the January 2011 rate of 4.25%. This reduction represents an estimated saving of £500,000.
Turnover The annual rate of turnover for December 2011 of 9.63% shows a small drop in the rate reported last month and continues the trend over the last six months. The rate of turnover for substantive staff leaving the organisation for reasons other than retirement is 5.26% and this compares favourably with the anticipated rate of 5%.
Staff Numbers After the increase in contracted staffing numbers reported last month the December 2011 figure has decreased by 31.54 FTE’s to 4965.93. This is still less than the funded FTE of 5154.65. Total headcount is now 5746, a decrease of 32 from last month. During the month of December 65 staff, 16 of which were Band 5 Registered Nurses, left the Trust and this contributed to the reduction in staffing numbers. Based on the six months prior to December the average number of Band 5 Registered Nurses leaving the Trust was 7 a month. Given the increase reported this month, work is ongoing to ensure data collected around reason for leaving and destination on leaving is complete and accurate to enable the Trust to gauge the extent of this problem. The number of staff employed on fixed term contracts ending in the next twelve months has continued to rise with 345 staff (284.67 FTE) recorded at the end of December 2011.
Bank, Agency & Overtime Spend The December 2011 agency spend is almost double the amount recorded last month with the Medical Directorate accounting for the majority of the increase. This is due to the staffing by substantive employees of the escalation wards set up to alleviate winter bed pressures. These staff are ‘back filled’ by agency nurses. In contrast, both bank and overtime spend show a small reduction on the last months reported amounts.
Personal Development Reviews (PDRs) and Essential Training Compliance After last month’s success in reaching the Trust PDR target rate of 80% the December 2011 rate shows a further small increase. The compliance rate for Manual Handling however has reduced, with a reported rate for December of less than 60%, subject to a data validation project to check the accuracy of this figure. This project is due to be completed by the end of March. All other Trustwide essential training rates have remained fairly static this month, although Fire and Infection Prevention and Control continue to have rates below the Trust target rate of 80%. In order to improve the Trust’s compliance rates, Internal Audit have been instructed to identify any variances between central ESR records and those held locally at directorate level. This will establish whether training has taken place but not recorded on ESR. Where there are areas of low compliance, those directorates will be asked to submit an action plan. A position statement and Trustwide action plan will be submitted to the Governance Committee in March.
Integrated Performance Report Wednesday 29 February 2012 Page 22 of 35
Data Appendices – Performance
IndicatorPosition for
QuarterTarget
Monitor
Weighting
Risk for
Period
Risk for
YearIndicator
Position for
Quarter
Target for
Period
Monitor
Weighting
Risk for
Period
Risk for
Year
Indicates that the target has been achieved for the quarter Indicates that the target has been achieved for that month but the quarter has not yet finished
Indicates that the target has not been achieved for the quarter Indicates that the target has not been achieved for that month but the quarter has not yet finished
Indicates that the target is not yet enforced
1 MON01 - Clostridium Difficile - The Department of Health are currently reviewing the impact of increased testing. This target may be subject to change.
Low Lowmin. 96%
MON11
Learning Disability
Compliance
The position for Cancer targets is subject to change when the data is uploaded to the National Cancer Waiting Times Database 6 weeks after month end.
Trend graphs run from April 2010 to current month
96.9%
(6 of 195)0.5 Compliant
Monitor Dashboard - January 2012
Trend Trend
MON01
Clostridium
Difficile1
7 (19)max. 74
annualHigh Very Low
Not Set
MON07
Cancer 31 Day
First Treatment
1.0
max. 3
annual0 (0)
MON03.I
Cancer 31 Day
Subsequent
Surgery
100.0%
(0 of 17)min. 94% Low
min. 98%
1.0
Medium
Medium
MON03.III
Cancer 31 Day
Subsequent
Radiotherapy
min. 94% Low
MON03.II
Cancer 31 Day
Subsequent Drug
100.0%
(0 of 88)
96.5%
(5 of 143)
MON02
MRSAMedium
High
MON08.I
Cancer 14 Day
GP Urgent
92.1%
(60 of 763)
Medium
Medium
MON08.II
Cancer 14 Day
Symptomatic Breast
96.1%
(2 of 51)Very Low
0.5
min. 93%
Not Set
Not Set Not Set
min. 93% Low
Very Low
95th Percentile
max.
4 hours
Not Set4.0MON09.I
A&E - Total Time2
MON05
RTT Admitted
95th Percentile
Medium
High 1.7%1.0
MON09.IV
A&E - Unplanned
Reattendance Rate2
MON09.III
A&E - Time to
Treatment Decision2
18.9
min. 85%
MON09.II
A&E - Time to Initial
Assessment2
Medium
1.0 Low
MON06
RTT Non-Admitted
95th Percentile
MON04.II
Cancer 62 Day
Screening
94.4%
(1 of 18)
Medium
1.0
min. 90% Medium
MON04.I
Cancer 62 Day
GP Urgent
85.0%
(15.5 of
103.5)
95th Percentile
max.
23 weeksmax. 5%
37.0
18.0
Median
max.
60 minutes
7.2% max. 5%
95th Percentile
max.
15 minutes
MON10
Stroke IndicatorLow15.1
95th Percentile
max.
18.3 weeks
Low
MON09.V
A&E - Left Without
Being Seen2
Medium
Very LowVery Low
n/a Not known
0.5
Not Set
Compliant
Not Set
Not applicable
1.0
0.5 for each
indicator
failure
capped at a
maximum of
1.0
0.5
Not Set
Not Set
Not Yet Defined Not Set
2 MON09.I to MON09.V - Following amendments to the 2011/12 Operating Framework Monitor sent a letter to Foundation Trusts on the 2nd August 2011 with the subject Changes to A&E indicator in the 2011/12 Compliance Framework which stated that the A&E performance will be assessed on the number
of patients treated within 4 hours but unlike the previous A&E target this would become site specific. The 5 Clinical Indicators for A&E will still need to be monitored but are now no longer part of the Compliance Framework.
Not Set Not Set
MediumMON09
A&E - 4 Hour Target96.0% min. 95% 1.0 Medium
Integrated Performance Report Wednesday 29 February 2012 Page 23 of 35
Code Target Jan-12 Q1 Q2 Q3 Q4 Weighting PositionRisk for
Quarter
Risk for
Year
MON01 74 7 (7) 27 (18) 26 (18) 17 (19) 7 (19) 1.0 Achieving High High
MON02 3 0 (0) 0 (1) 1 (1) 0 (1) 0 (0) 1.0 Achieving Medium Medium
surgeryMON03.I 94%
100.0%
(0 of 17)
97.4%
(4 of 153)
98.8%
(2 of 162)
96.8%
(4 of 125)
100.0%
(0 of 17)Low Medium
anti cancer drug
treatmentsMON03.II 98%
100.0%
(0 of 88)
99.5%
(1 of 203)
99.6%
(1 of 225)
100.0%
(0 of 200)
100.0%
(0 of 88)Low Medium
radiotherapyMON03.III 94%
96.5%
(5 of 143)
99.0%
(3 of 314)
98.8%
(4 of 320)
99.4%
(2 of 344)
96.5%
(5 of 143)Low Medium
from urgent GP referral to
treatment MON04.I 85%
85.0%
(15.5 of
103.5)
86.1%
(41 of
294.5)
85.9%
(38.5 of
273.5)
85.9%
(40 of 283)
85.0%
(15.5 of
103.5)
Medium Medium
from consultant screening
service referralMON04.II 90%
94.4%
(1 of 18)
94.9%
(2 of 39.5)
92.9%
(3 of 42)
91.7%
(4 of 48)
94.4%
(1 of 18)Medium Medium
admitted pathways MON05 23 weeks 18.9 19.3 18.0 18.1 18.9 1.0 Achieving High Medium
non-admitted pathways MON06 18.3 weeks 15.1 14.0 14.3 14.9 15.1 1.0 Achieving Low Low
MON07 96%96.9%
(6 of 195)
98.1%
(12 of 639)
98.0%
(12 of 598)
98.5%
(8 of 545)
96.9%
(6 of 195)0.5 Achieving Low Low
all cancers
MON08.I 93%92.1%
(60 of 763)
96.3%
(93 of 2484)
94.7%
(124 of
2357)
95.0%
(121 of
2435)
92.1%
(60 of 763)Low Very Low
for symptomatic breast
patients (cancer not
initially suspected)
MON08.II 93%96.1%
(2 of 51)
100.0%
(0 of 136)
99.2%
(1 of 123)
98.3%
(2 of 116)
96.1%
(2 of 51)Very Low Very Low
MON09 95% 96.0% 96.5% 95.8% 93.7% 96.0% 1.0 Achieving Medium Medium
A&E Clinical Quality Indicators 2 Total time in A&E (95th
percentile)MON09.I ≤4 hrs 4.0 4.8 4.3 5.0 4.0
Not Yet
ImplementedNot Set Not Set
Time to initial assessment
(95th percentile)MON09.II ≤15 mins 18.0 29.0 22.0 19.0 18.0
Not Yet
ImplementedNot Set Not Set
Time to treatment decision
(median)MON09.III ≤60 mins 37.0 45.0 41.0 40.0 37.0
Not Yet
ImplementedNot Set Not Set
Unplanned reattendance
rateMON09.IV ≤5% 7.2% 8.2% 7.3% 7.5% 7.2%
Not Yet
ImplementedNot Set Not Set
Left without being seenMON09.V ≤5% 1.7% 2.8% 2.6% 2.7% 1.7%
Not Yet
ImplementedNot Set Not Set
MON10 tbc 0.5 Not Known Not Set Not Set
Patient
experienceMON11 n/a 0.5 Achieving Very Low Very Low
Quality
Monitor Targets Detail - January 2012
Indicator
Clostridium Difficile – meeting the Clostridium Difficile objective1
MRSA – meeting the MRSA objective
Not yet defined
Safety
Quality
Referral to treatment waiting times – (95th
percentile)
Patient
experience
All cancers: 62-day wait for first treatment
Stroke Indicator
Achieving
Achieving
Currently Not
Achieving
1.0
1.0
All cancers: 31-day wait for second or subsequent
treatment
2 MON09.I to MON09.V - Following amendments to the 2011/12 Operating Framework Monitor sent a letter to Foundation Trusts on the 2nd August 2011 with the subject Changes to A&E indicator in the
2011/12 Compliance Framework which stated that the A&E performance will be assessed on the number of patients treated within 4 hours but unlike the previous A&E target this would become site
specific. The 5 Clinical Indicators for A&E will still need to be monitored but are now no longer part of the Compliance Framework.
The position for Cancer targets is subject to change when the data is uploaded to the National Cancer Waiting Times Database 6 weeks after month end.1MON01 - Clostridium Difficile - The Department of Health are currently reviewing the impact of increased testing. This target may be subject to change.
All cancers: 31-day wait from diagnosis to first treatment
Cancer: two week wait from referral to date first
seen
0.5
Certification against compliance with requirements regarding access to
healthcare for people with a learning disabilityCompliant
0.5 for each indicator
failure capped at a
maximum of 1.0
4 Hour Target A&E
Integrated Performance Report Wednesday 29 February 2012 Page 24 of 35
Data Appendices – Finance
Actual Surplus YTD Plan Surplus YTD Spend YTD Planned Spend YTD
£3.5m £2.9m £10.7m £12.3m
Forecast Surplus Y/E Plan Surplus Y/E Forecast Y/E Spend Planned Y/E Spend
£2.8m £3.5m £15.6m £16.7m
Actual Efficiency* Planned Efficiency*
0.80% 1.03%
Other Ratios Plan YTD Actual YTD Plan Y/E Forecast Y/E
Trade Creditor Days 6.3 8.7 6.4 6.2
NHS Trade Debtor Days 9.7 9.6 8.9 9.4
Debt to Asset Ratio 6.5% 6.6% 6.3% 6.5%
Other items £ £ £ £
Revenue available for debt service 19.8m 20.6m 23.9m 23.1mDebt 20.8m 20.8m 20.2m 20.2m
Total Assets 319.8m 318.1m 321.9m 309.3m
Cash in hand and at bank £55.3m
Working Capital Facility £0m
Cash invested @ Month End £43.0m
*(planned surplus / planned operating income *100)
*(forecast surplus / forecast operating income *100)
4. Cash 6. WTE
RD&E Financial Overview as at 31st january (YTD - Month 10)1. I&E 3. Capital 5. Ratios/Risk Rating
Graph – Capital Plan Vs Actual and forecast spend
2. CIP
Graph – Actual, Forecast & Plan
AP
PE
ND
IX 1
CIP Plan v Actual
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
Apr
ilM
ayJu
neJu
ly
Aug
ust
Septe
mbe
r
Oct
ober
Nov
embe
r
Dec
embe
r
Janu
ary
Febru
ary
Mar
ch
Month
£m
CIP Plan
CIP Actual
CIP Forecast
Contracted WTE, Worked WTE & Funded WTE
4700
4800
4900
5000
5100
5200
5300
5400
M7-
10/1
1
M8-
10/1
1
M9-
10/1
1
M10
-10/
11
M11
-10/
11
M12
-10/
11 M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
Month
WT
E
Worked WTE
Contract WTE
Funded WTE
Annual Plan
WTE
Risk Ratings
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
EBITDA Margin
EBITDA % Achieved
ROA
I&E Surplus Margin
Liquidity
Overall Rating
Plan YTD Actual YTD Plan Y/E Forecast Y/E
Comparison of actual cumulative net surplus/deficit compared to plan
-3,000
-2,000
-1,000
0
1,000
2,000
3,000
4,000
5,000
Apr
ilM
ay
June Ju
ly
Aug
ust
Sep
tem
ber
Octob
er
Nov
embe
r
Dec
embe
r
Janu
ary
Febru
ary
Mar
ch
Month
£
Actual
Plan0
2
4
6
8
10
12
14
16
18
£M
Month
Capital Spend
Capital Plan 11/12
Actual Capital Spend
Forecast Capital Spend
(20)
(10)
-
10
20
30
40
50
60
70
80
Ap
r-1
1
Ma
y-1
1
Ju
n-1
1
Ju
l-11
Au
g-1
1
Sep
-11
Oc
t-11
No
v-11
Dec-11
Ja
n-1
2
Fe
b-1
2
Ma
r-1
2
£M
Month
12 Month forecast cashflow v plan
Plan
Actual
Forecast
Commited Facility
Integrated Performance Report Wednesday 29 February 2012 Page 25 of 35
Overall : Year to Date 1% down compared to similar period in 1011
OP 1st Attendances ● Current Month 6% below plan. Daycase 1st FCEs ● Current Month 11% above plan
●4% higher than the same month last year ●11% higher than the same month last year
● 16% higher than previous month ●21% higher than the previous month
● Year to Date same as same period in 1011
● Year to Date 4% above than same period in
1011.
● Year to date 9% below plan. ● Year to date 4% above plan.
Elective IP 1st
FCEs ● Current Month 17% below plan.
Non Elective IP 1st
FCEs ● Current Month 5% below plan.
●17% lower than the same month last year ● 4% lower than same month last year
● 1% lower than previous month ● 5% lower than previous month
● Year to Date 17% lower than the same
period in 1011.
● Year to Date 2% lower than same period in
1011.
● Year to date 12% below plan. ● Year to date 1% below plan.
RD&E Activity Overview as at 31 January 2012 (YTD - Month 10)
Day Case 1st FCEs
2000
2500
3000
3500
4000
4500
5000
5500
6000
Jan
-09
Mar
-09
May
-09
Jul-
09
Sep
-09
No
v-0
9
Jan
-10
Mar
-10
May
-10
Jul-
10
Sep
-10
No
v-1
0
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
Plan Actual
Non-Elective IP 1st FCEs
1500
1750
2000
2250
2500
2750
3000
3250
Jan
-09
Mar
-09
May
-09
Jul-
09
Sep
-09
No
v-0
9
Jan
-10
Mar
-10
May
-10
Jul-
10
Sep
-10
No
v-1
0
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
Plan Actual
Elective IP 1st FCEs
500
700
900
1100
1300
1500
1700
1900
2100
Jan
-09
Mar
-09
May
-09
Jul-
09
Sep
-09
No
v-0
9
Jan
-10
Mar
-10
May
-10
Jul-
10
Sep
-10
No
v-1
0
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
Plan Actual
OP 1st Attendances
6000
6500
7000
7500
8000
8500
9000
9500
10000
10500
11000
Jan
-09
Mar
-09
May
-09
Jul-
09
Sep
-09
No
v-0
9
Jan
-10
Mar
-10
May
-10
Jul-
10
Sep
-10
No
v-1
0
Jan
-11
Mar
-11
May
-11
Jul-
11
Sep
-11
No
v-1
1
Jan
-12
Plan Actual
Integrated Performance Report Wednesday 29 February 2012 Page 26 of 35
Royal Devon & Exeter NHS Foundation Trust Prior Yr
Actual Budget Actual Annual Actual Actual Budget Actual Annual Actual Mar-11
Income Statement Variance Plan Variance Variance Plan Variance Actual
Period ending 31/01/2012 to Budget to Plan to Budget to Plan
Month 10 Fav./(Adv.) Fav./(Adv.) Fav./(Adv.) Fav./(Adv.) Fav./(Adv.) Fav./(Adv.)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000
Income
NHS Clinical Income 237,703 237,814 (111) 1 232,691 5,012 284,674 285,459 (785) 1 278,936 5,738 1 287,191
Private patient income 826 952 (126) 954 (128) 1,025 1,151 (126) 1,150 (125) 1,142
Research and Development 10,901 10,607 294 10,541 360 12,720 12,720 0 12,649 71 13,071
Education and Training 11,543 11,536 7 10,874 669 13,842 13,834 8 12,982 860 14,231
Other income 29,650 29,301 349 28,998 652 35,193 35,096 97 34,806 386 35,035
Total income 290,623 290,210 413 284,057 6,566 347,454 348,260 (806) 340,524 6,930 350,670
Expense
Employee Benefits Expenses (Pay) (167,798) (168,114) 316 2 (165,834) (1,964) (202,103) (202,001) (103) 2 (198,588) (3,516) (203,420)
Drug Costs (24,604) (24,887) 283 (24,187) (417) (29,537) (29,718) 181 (29,120) (417) 2 (27,777)
Clinical Supplies (29,893) (29,586) (307) 3 (32,368) 2,476 (35,731) (35,420) (311) (38,858) 3,127 2 (40,253)
Non Clinical Supplies (4,362) (4,114) (248) (3,694) (668) (5,155) (4,845) (310) (4,364) (791) (4,432)
Research & Development Expenses (10,171) (9,942) (229) (10,718) 547 (11,948) (11,948) 0 (12,861) 913 (13,009)
Misc. Other Operating Expenses (32,411) (31,799) (612) 4 (27,586) (4,825) (38,128) (37,488) (640) 3 (33,016) (5,112) 3 (36,505)
Reserves (1,000) (2,453) 1,453 0 (1,000) (2,028) (3,123) 1,095 0 (2,028) 0
Total Costs (270,239) (270,894) 655 (264,386) (5,853) (324,630) (324,542) (88) (316,806) (7,824) 7 (325,396)
EBITDA 20,384 19,316 1,068 19,672 712 22,824 23,718 (894) 23,718 (894) 25,274
Profit / loss on asset disposals (103) 0 (103) 0 (103) (140) 0 (140) 0 (140) (2,841)
Exceptional Income/ Costs & Impairments **
Total Depreciation (9,935) (9,951) 16 (9,949) 14 (11,955) (11,995) 40 (11,994) 39 (10,499)
Total operating surplus (deficit) 10,346 9,365 981 9,723 623 10,729 11,723 (994) 11,723 (994) 11,934
227 162 65 163 64 260 195 65 195 65 247
Total interest payable on Loans and leases (860) (843) (17) (843) (17) (1,007) (1,007) 0 (1,007) 0 (1,072)
PDC Dividend (6,176) (6,176) 0 (6,176) (0) (7,192) (7,411) 219 (7,411) 219 (7,048)
Net Surplus/(deficit) 3,537 2,508 1,029 2,867 670 2,790 3,500 (710) 3,500 (710) 4,061
YTD KEY MOVEMENTS FORECAST KEY MOVEMENTS
1 Year to date income has improved by £0.4m compared to last months report, mainly due to non-elective work in ICU and Maternity. 1
2 Pay expense has improved by £324k but additional spend on Nursing continues
3 2
4
3
Year to Date Outturn
Total interest receivable/ (payable) - inc
committed WC facilities
AP
PE
ND
IX 3
Overperformances within W&C Health, Medicine and Critical Care and
underperformances on Cancer, Trauma & Orthopaedics and Surgery
Clinical supplies spend mainly within Radiology, W&C Health and Medicine due to activity. Pay is forecasted to deteriorate due to additional nursing spend expected in the
remaining part of the year.Miscellaneous expense overspend on electricity and maintenance contractors.
Misc. expense is overspending mainly on electricity, maintenance contractors and
other services received.
Integrated Performance Report Wednesday 29 February 2012 Page 27 of 35
Royal Devon & Exeter NHS Foundation Trust Prior Yr
Actual Budget Actual Annual Actual Actual Budget Actual Annual Actual Mar-11
Statement of Financial Position Variance Plan Variance Variance Plan Variance
Period ending 31/01/2012 to Budget to Plan to Budget to Plan
Month 10 Fav./(Adv.) Fav./(Adv.) Fav./(Adv.) Fav./(Adv.) Fav./(Adv.) Fav./(Adv.)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000
Assets, Non-Current
Intangible Assets, Net 1,289 362 927 362 927 326 326 0 326 0 544
Property, Plant and Equipment, Net 238,695 241,355 (2,660) 241,355 (2,660) 241,388 254,072 (12,684) 254,072 (12,684) 238,779
Non NHS Trade Receivables, Non-Current 1,014 838 176 838 176 1,000 838 162 838 162 966
Assets, Non-Current, Total 240,998 242,555 (1,557) 1 242,555 (1,557) 242,714 255,236 (12,522) 255,236 (12,522) 240,289
Assets, Current
Inventories 4,588 4,502 86 4,502 86 4,624 4,624 0 4,624 0 4,592
Trade and Other Receivables, Net, Current 17,229 14,840 2,389 2 15,199 2,030 13,280 12,642 638 12,642 638 11,009
Non Current Assets held for sale 0 0 0 0 0 0 0 0 0 0 0
Cash 55,256 55,759 (503) 55,759 (503) 48,657 47,644 1,013 47,644 1,013 53,583
Other Assets - Current Assets Held by Charitable Funds 0 0 0 1,800 (1,800) 0 0 0 1,800 (1,800) 0
Assets, Current, Total 77,073 75,101 1,972 77,260 (187) 66,561 64,911 1,651 66,711 (150) 69,184
Liabilities, Current
Loans, non-commercial, Current (DH, FTFF, NLF, etc) (1,270) (1,270) 0 (1,270) 0 (1,270) (1,270) 0 (1,270) 0 (1,270)
Trade and Other Payables, Current (11,763) (9,627) (2,137) 3 (9,627) (2,138) (10,007) (10,007) 0 (10,007) 0 (10,262)
Deferred Income, Current (2,052) (3,853) 1,801 (3,853) 1,801 (1,575) (1,620) 45 (1,620) 45 (1,520)
Provisions, Current (1,368) (193) (1,175) 4 (193) (1,175) (193) (193) 0 (193) 0 (1,368)
Current Tax Payables (4,272) (4,275) 3 (4,275) 3 (4,276) (4,276) 0 (4,276) 0 (5,083)
Other Financial Liabilities, Current (15,251) (17,698) 2,448 5 (17,698) 2,448 (11,315) (11,315) 0 (11,315) 0 (10,893)
Liabilities, Current, Total (35,976) (36,917) 941 (36,917) 941 (28,636) (28,681) 45 (28,681) 45 (30,396)
NET CURRENT ASSETS (LIABILITIES) 41,097 38,185 2,913 40,343 754 37,925 36,230 1,696 38,030 (105) 38,788
TOTAL ASSETS LESS CURRENT LIABILITIES 282,095 280,740 1,355 282,899 (803) 280,639 291,466 (10,827) 293,266 (12,627) 279,077
Liabilities, Non-Current
Loans, Non-Current, non-commercial (DH, FTFF, NLF, etc) (19,578) (19,577) (1) (19,577) (1) (18,942) (18,942) 0 (18,942) 0 (20,213)
Other Creditors, Non-Current 0 (84) 84 (84) 84 0 (78) 78 (78) 78 (123)
Provisions, Non-Current (418) (346) (72) (346) (72) (346) (346) 0 (346) 0 (346)
TOTAL ASSETS EMPLOYED 262,099 260,733 1,366 262,892 (792) 261,351 272,100 (10,749) 273,900 (12,549) 258,395
TAX PAYERS' EQUITY
Public dividend capital 149,715 149,715 0 149,715 0 149,715 149,715 0 149,715 0 149,715
Retained Earnings (Accumulated Losses) 53,031 47,729 5,302 6 48,088 4,943 52,561 49,145 3,416 49,145 3,415 43,949
Charitable Funds 0 0 0 1,800 (1,800) 0 0 0 1,800 (1,800) 0
Revaluation Reserve 59,353 59,928 (575) 6 59,928 (575) 59,076 69,924 (10,848) 69,924 (10,848) 61,200
Donated Asset Reserve 0 3,361 (3,361) 6 3,361 (3,361) (0) 3,316 (3,316) 3,316 (3,316) 3,531
TOTAL TAX PAYERS' EQUITY 262,099 260,733 1,366 262,892 (792) 261,351 272,100 (10,749) 273,900 (12,549) 258,395
OUTTURN KEY MOVEMENTS
1
2
3
4
5
6
Year to Date Outturn
AP
PE
ND
IX 4
Capital spend is £1.6m lower than plan, see appendix 6 for further details.
Receivables are £2.4m higher than budget and £2m higher than plan, see narrative in performance report for further information.
Actual payables are higher than the estimate on the annual plan, this is off-set with other financial liabilities being lower than plan.
Plan assumed a provision would be settled by the end of September 2011, settlement negotiations continue.
Actual accruals are lower than the estimate on the annual plan.
Prior year adjustments due to change in accounting treatment to comply with Government's alignment project. I&E reserve increased by £4.1m, Donated asset reserve removed £3.5m, Revaluation reserve reduced by £0.4m and
deferred income liabilities reduced by £0.2m.
Integrated Performance Report Wednesday 29 February 2012 Page 28 of 35
Royal Devon & Exeter NHS Foundation Trust Prior Yr
Actual Budget Actual Annual Actual Actual Budget Actual Annual Actual Mar-11
Cash Flow Statement Variance Plan Variance Variance Plan Variance
Period ending 31/01/2012 to Budget to Plan to Budget to Plan
Month 10 Fav./(Adv.) Fav./(Adv.) Fav./(Adv.) Fav./(Adv.) Fav./(Adv.) Fav./(Adv.)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000
NET CASH INFLOW/(OUTFLOW) FROM OPERATING ACTIVITIES
Surplus/(deficit) after tax 3,537 2,508 1,029 2,867 670 2,790 3,500 (711) 3,500 (710) 4,061
Non-cash flows in operating surplus/(deficit)
Finance (income)/charges 633 681 (48) 680 (47) 747 812 (65) 812 (65) 825
Depreciation and amortisation 9,935 9,951 (16) 9,949 (14) 11,955 11,995 (40) 11,994 (39) 10,499
Impairment 0 0 0 0 0 0 0 0 0 0 2,806
PDC dividend expense 6,176 6,176 0 6,176 0 7,192 7,411 (219) 7,411 (219) 7,048
Other increases/(decreases) to reconcile to profit/(loss) from operations 103 (234) 337 (232) 335 139 (278) 417 (278) 417 (238)
Non-cash flows in operating surplus/(deficit), Total 16,847 16,574 273 16,573 274 20,033 19,940 93 19,940 93 20,940
Increase/(Decrease) in working capital
(Increase)/decrease in inventories 4 90 (86) 90 (86) (32) (32) 0 (32) 0 15
(Increase)/decrease in NHS Trade Receivables (2,030) (1,624) (406) (1,982) (48) (1,842) (1,204) (638) (1,204) (638) 974
(Increase)/decrease in Non NHS Trade Receivables (888) 71 (959) 71 (959) 71 71 0 71 0 163
(Increase)/decrease in other receivables (295) (276) (19) (276) (19) (276) (276) 0 (276) 0 749
(Increase)/decrease in accrued income (745) (758) 13 (758) 13 (208) (208) 0 (208) 0 187
(Increase)/decrease in prepayments (2,262) (1,245) (1,017) (1,245) (1,017) (16) (16) 0 (16) 0 (250)
Increase/(decrease) in Deferred Income (excl. Donated Assets) 577 2,333 (1,756) 2,333 (1,756) 100 100 0 100 0 (730)
Increase/(decrease) in provisions 72 (1,175) 1,247 (1,175) 1,247 (1,175) (1,175) 0 (1,175) 0 1,288
Increase/(decrease) in Trade Creditors 2,035 (280) 2,315 (280) 2,315 (200) (200) 0 (200) 0 (139)
Increase/(decrease) in tax payable (811) (808) (3) (808) (3) (807) (807) 0 (807) 0 1,035
Increase/(decrease) in Other Creditors (75) (55) (19) (55) (19) (55) (55) 0 (55) 0 88
Increase/(decrease) in accruals 1,814 4,267 (2,453) 4,267 (2,453) 684 684 0 684 0 (1,037)
Increase/(Decrease) in workling capital, Total (2,604) 541 (3,145) 182 (2,786) (3,757) (3,119) (638) (3,119) (638) 2,343
Net cash inflow/(outflow) from investing activities
Property - new land, buildings or dwellings (6,173) (3,549) (2,624) (3,549) (2,624) (4,434) (4,434) 0 (4,434) 0 (3,555)
Property - maintenance expenditure (997) (2,622) 1,625 (2,622) 1,625 (3,042) (3,042) 0 (3,042) 0 (8,851)
Plant and equipment - Information Technology (1,691) (1,201) (490) (1,201) (490) 712 (1,451) 2,163 (1,451) 2,163 0
Plant and equipment - Other (1,848) (4,971) 3,123 (4,971) 3,123 (7,723) (7,723) 0 (7,723) 0 0
Proceeds on disposal of property, plant and equipment 14 0 14 0 14 0 0 0 0 0 6,081
Increase/(decrease) in Capital Creditors (459) (300) (159) (300) (159) 0 0 0 0 0 (242)
Other cash flows from financing activities 0 63 (63) 63 (63) 0 63 (63) 63 (63) 0
Net cash inflow/(outflow() from investing activities, Total (11,154) (12,581) 1,426 (12,581) 1,426 (14,487) (16,587) 2,101 (16,587) 2,101 (6,568)
Net cash inflow/(outflow) from financing activities
PDC Dividends paid (3,968) (3,968) (0) (3,968) (0) (7,454) (7,673) 219 (7,673) 219 (6,502)
PDC Dividend Received 0 0 0 0 0 0 0 0 0 0 0
Interest (paid) on commercial loans (524) (513) (11) (514) (11) (1,007) (1,007) 0 (1,007) 0 (1,072)
Interest received on cash and cash equivalents 227 162 65 163 64 260 195 65 195 65 247
Repayment of non-commercial loans (635) (636) 1 (636) 1 (1,271) (1,271) 0 (1,271) 0 (1,271)
(Increase)/decrease in non-current receivables (48) 128 (176) 128 (176) (34) 128 (162) 128 (162) (128)
Increase/(decrease) in non-current payables 0 (39) 39 (39) 39 (0) (45) 45 (45) 45 34
Net cash inflow/(outflow) from financing activities, Total (4,948) (4,866) (83) (4,865) (83) (9,506) (9,673) 167 (9,673) 167 (8,692)
Net increase/(decrease) in cash and cash equivalents 1,678 2,177 (499) 2,177 (499) (4,927) (5,939) 1,012 (5,939) 1,013 12,085
Opening cash and cash equivalents 53,583 53,583 0 53,583 0 53,583 53,583 0 53,583 0 41,498
Closing cash and cash equivalents 55,261 55,760 (499) 55,760 (499) 48,656 47,644 1,012 47,644 1,013 53,583
Year to Date Outturn
AP
PE
ND
IX 5
Integrated Performance Report Wednesday 29 February 2012 Page 29 of 35
Royal Devon and Exeter NHS Foundation Trust
Capital expenditure
Period ending 31/01/2012
Month 10 Column B Column C Column D Column E Column F Column G Column H
YTD planned
expenditure per
annual plan
YTD actual
expenditure
YTD variance
slippage /
(overspend)
Forecast future
capital
expenditure for
the year
Forecast total
capital
expenditure for
the year
Full year
expenditure per
annual plan
11/12 forecast
slippage /
(overspend)
Expenditure
approved by the
Exec Group
Total expenditure
forecast for the
scheme
Scheme variance
under spend /
(overspend)
( B - C) (C + E) (G - F)
£'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000
FBC 1,443 2,091 ( 648) 525 2,616 2,251 ( 365) 8,344 8,344 - 31-Mar-15
OBC 301 844 ( 544) 237 1,081 378 ( 703) 7,900 7,900 - 31-Mar-15
FBC 2,261 2,016 245 412 2,428 2,261 ( 167) 6,200 5,897 303 30-Jun-12
Approved 100 91 9 347 438 165 ( 273) 5,000 5,000 - 31-Mar-14
FBC - 9 ( 9) 8 16 - ( 16) 3,126 3,126 - Occupied
FBC ( 22) ( 19) ( 3) - ( 19) ( 22) ( 3) 2,370 1,924 446 Complete
FBC 515 254 262 24 278 527 249 2,207 2,193 14 31-Mar-14
FBC 47 29 18 - 29 77 48 1,366 1,104 262 Complete
FBC - 60 ( 60) - 60 - ( 60) 1,248 1,346 ( 98) Occupied
Note 1 (CAP1 rec'd) 188 - 188 - - 267 267 1,175 1,175 - 31-Mar-15
Approved 6,126 2,822 3,304 2,342 5,164 8,613 3,449
10,959 8,196 2,763 3,895 12,091 14,516 2,425
FBC 1,036 1,264 ( 228) 418 1,683 1,484 ( 198) 4,014 4,014 - 31-Mar-15
Note 1 134 - 134 50 50 250 200 2,787 2,787 - 31-Mar-14
Note 1 214 - 214 - - 400 400 1,440 1,440 - On hold
1,384 1,264 120 468 1,733 2,134 402
12,343 9,460 2,883 4,363 13,824 16,650 2,826
Note 2 - 1,249 ( 1,249) 508 1,757 - ( 1,757) 13,848 13,848 - 31-Mar-15
12,343 10,710 1,634 4,872 15,581 16,650 1,069
Approval Level Key
OBC Outline business case
FBC Full business case
SOC Strategic outline case
Note 1 Subject to Board approval of full business cases (SOC, OBC, FBC)
Note 2 Full cost of RILD scheme capitalised during the construction period. When asset is brought into use the cost of the university's element will be offset against their contribution received. There is no loss anticipated.
Annual plan schemes <£1 million includes some schemes that have bow been classed as revenue expenditure schemes. The to date figures includes £450k and the forecast for the year includes £585k.
Research, Innovation, Learning and Development (RILD)
Increasing radiotherapy capacity(3rd LINACC)
Expected completion
date
Actual expenditure to date compared to budget on
annual plan
Total expenditure forecast for the year compared to the budget on the
annual plan
Total expected expenditure compared to the value
approved by the Exec Group.
Schemes over £1 million in progress or planned
Scheme Approval level
Priority 1
Rebuild CIVAS unit and equip.
Priority 2 schemes - £2,768k allocated below plus £184k
allocated to priority 1 Durbin Ward refurbishment
Electronic document management
Estates infrastructure (for capital schemes moved to revenue
please see below)
Pain management (inc. physio)
Renal Heavitree
Order comms and e-prescribing IT systems
Procurement of third CT scanner
Nursery expansion
Core network upgrade
Other schemes < £1m and contingency
Priority 1 total
Priority 2
Replacement PAS,CDM & ward whiteboard
North Devon expansion and central water processing plant
Priority 2 total
AP
PE
ND
IX 6
Total Priority 1 and Priority 2
RILD - University of Exeter element
(The University's RILD capital additions were not included on the Annual Plan, these
additions are suppressing the Trust's actual capital slippage, excluding them the Trust's
capital slippage would be £2.9 million to date)
Grand total
Integrated Performance Report Wednesday 29 February 2012 Page 30 of 35
Royal Devon & Exeter NHS Monitor YTD Target CY Target
Foundation Trust Actual Plan Variance Actual Plan Variance Actual Plan Variance Forecast
to Budget (target) to Budget to Plan
Cost Improvement Programme Fav./(Adv.) Fav./(Adv.) Fav./(Adv.)
Period ending 31/01/2012
Month 10 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 R/A/G R/A/G
Work Stream
Bed Utilisation (235) (235) 0 1,576 (280) (280) 0 (280) 0 (269) 821 (1,090) (269) G G
Theatre Utilisation 807 848 (41) 770 1,040 1,090 (50) 1,128 38 1,359 1,342 17 1,658 G G
Outpatients 679 437 241 1,064 840 575 265 868 293 911 923 (12) 923 G G
Workforce 670 724 (54) 1,248 812 979 (168) 862 (117) 861 2,204 (1,343) 1,997 A A
Medical Staffing 559 679 (120) 2,754 706 926 (220) 926 (0) 995 1,471 (476) 1,146 A G
Nursing & AHP Staff 514 601 (87) 1,358 640 846 (206) 703 (143) 755 1,409 (654) 1,135 A A
Procurement 649 734 (85) 1,630 827 1,287 (460) 1,296 9 995 1,673 (678) 1,401 A G
Diagnostics 603 546 57 861 780 764 16 764 (0) 948 1,179 (231) 1,179 G G
Pharmacy 474 490 (16) 581 581 636 (55) 636 0 642 747 (105) 747 G G
Back Office 903 772 131 995 1,056 966 90 1,090 124 1,253 1,357 (104) 1,733 G G
5,623 5,598 26 12,837 7,002 7,789 (787) 7,993 204 8,449 13,126 (4,677) 11,652
RESTOT Central Plans 6,761 6,056 705 8,553 9,337 (784) 9,133 (204) 2,687 2,687 0 2,887 G G
RESTOT Unidentified 0 1,256 (1,256) 1,314 (1,314) 2,587 G G
12,384 12,910 (525) 12,837 15,555 17,126 (1,571) 17,126 (0) 11,136 17,127 (5,991) 17,126
Key
580
Red > 20% variance to plan
Amber > 5 % variance to plan
Green < 5% variance to plan
YTD Plan Forecast CY Forecast
Variance Fav /
(Adv)
Year to Date - Achieved Current Year - Achieved Current Year - Forecast Full Year - Achieved
Confidence
Rating
Confidence
Rating
AP
PE
ND
IX 7
CIP Achievement Current Year
(0) 50
(265)
168 220 206460
(16)55
(90)(11)(319)
(70)
(49) (115) (168) (168)
(269)
911
861995
755995
948
(289) (61)(197)
1,359
642
1,253
-100%
-80%
-60%
-40%
-20%
0%
20%
40%
60%
80%
100%
Bed Utilisation Theatre Utilisation Outpatients Workforce Medical Staffing Nursing & AHP
Staff
Procurement Diagnostics Pharmacy Back Office
Work Streams
Ach
iev
emen
t
To be Achieved Non-Recurrent
Recurrent
Integrated Performance Report Wednesday 29 February 2012 Page 31 of 35
Royal Devon & Exeter NHS Foundation Trust
Surplus / (Deficit) by Directorate based on SLR reporting
Medicine Critical Care
Orthopaedic
s Surgery I
Specialist
Surgery
Women &
Child Health
Cancer
Services Diagnostics
Professional
Services Other Trust
£'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000
Patient Income -PbR 48,252 1,081 23,985 23,446 18,478 20,701 5,085 58 1 0 141,086
Patient Income - Non PbR 20,550 5,651 1,591 866 3,050 11,185 12,785 7,432 7,961 602 71,673
Total Clinical Income 68,802 6,732 25,576 24,312 21,528 31,886 17,871 7,490 7,961 602 212,759
Admin Secretarial Support 2,105 59 757 833 747 1,189 260 0 0 0 5,951
Anaesthetics 166 0 1,517 1,602 1,402 862 14 0 0 0 5,563
Devices 3,510 453 2,968 229 356 92 0 0 0 0 7,608
Other Departments 3,554 15 732 642 1,011 4,111 892 330 615 289 12,192
Diabetes services 817 0 0 0 0 0 0 0 0 0 817
Dialysis 2,754 4 0 0 0 0 0 0 0 0 2,757
Medical Staffing 10,764 975 3,559 3,671 4,783 6,463 1,582 0 0 0 31,796
Mobility Centre 0 0 0 0 0 0 0 0 6,026 0 6,026
Nuclear Medicine 102 0 39 193 37 24 131 4 24 0 554
Oncology Centre 0 0 0 0 0 0 2,194 0 0 0 2,194
Professions Allied to Medicine 2,095 130 479 492 346 245 98 0 1,101 0 4,986
Pathology 2,334 198 314 1,265 384 1,406 1,290 5,085 24 0 12,300
Pharmacy 5,210 305 1,351 882 2,353 529 6,188 2 164 0 16,982
Radiology 3,357 58 736 1,243 577 417 1,098 386 167 0 8,039
Health Records 513 17 574 139 237 198 133 0 77 0 1,889
R.T. Physics 0 0 0 0 0 0 937 0 0 0 937
Theatres 4,314 326 6,726 5,977 5,329 2,300 141 0 0 0 25,114
Wards / Nursing 28,030 2,995 4,798 7,626 3,981 13,941 3,024 6 0 0 64,401
Total Expense 69,627 5,534 24,550 24,795 21,543 31,778 17,981 5,812 8,198 289 210,106
Surplus / Deficit -825 1,198 1,026 -483 -15 108 -111 1,678 -237 313 2,653Margin % -1.2% 17.8% 4.0% -2.0% -0.1% 0.3% -0.6% 22.4% -3.0% 52.0% 1.2%
AP
PE
ND
IX 8
Period ending 30 December 2011
Month 9
Integrated Performance Report Wednesday 29 February 2012 Page 32 of 35
MONITOR PROPOSED FURTHER INDICATORS FOR FRR - COMPLIANCE FRAMEWORK CONSULTATION
Proposed indicator Potential financial weakness Criteria to measure against
Unplanned decrease in EBITDA margin in two consecutive quarters Deteriorating trend in operating
performance and cashflow
generation Variance to planned EBITDA margin NO 112.61% NO 105.95% NO 103.24% NO 107.96%
Quarterly self-certification by trust that FRR may be less than 3 in the next 12
months
Identified risk of potential
financial breach within the next
year
Forecast financial risk rating for the next 12
months NO 3+ NO 3+ NO 3+ NO 3+
FRR 2 for any one quarter In year deterioration in financial
performance Current period Financial Risk Rating NO 4 NO 4 NO 4 NO 3
Debtors more than 90 days past due account for more than 5% of total debtor
balances
Potential for payment / debtor
collection concerns
% of Debtors more than 90 days past due
account NO 1.46% NO 0.79% NO 1.04% NO 2.06%
Creditors more than 90 days past due account for more than 5% of total creditor
balances
Potential for build up in creditors,
resulting in future liquidity
concerns
% of Creditors more than 90 days past due
account NO 0.05% NO 0.00% NO 0.00% NO 0.00%
Capital expenditure is less than 75% of plan for the year to date Capital expenditure plans are
delayed to conserve cash Capital expenditure variance to plan YES 65.26% YES 73.39% NO 81.44% NO 88.36%
Quarter end cash balance less than 10 days of operating expenses Potential liquidity concerns and
ability to meet liabilities as they
fall due Liquidity days at period end NO 63.07 NO 62.36 NO 55.61 NO 62.39
Working capital facility (WCF) agreement includes default clause. This will
require all trusts to review their WCF agreements.
Risk that WCF, whilst included in
calculation of liquidity days for
the purpose of FRR, may not be
available if and when required
(eg: FRR 1 or 2). Review of WCF NO NO NO NO NO NO NO NO
Interim Finance Director in place over more than one quarter end Absence of permanent /
substantive appointment to key
position NO NO NO NO NO NO NO NO
Two or more changes in Finance Director in a twelve month period Multiple changes in a short
period of lead financial officer NO NO NO NO NO NO NO NO
Notes / Explanations
AP
PE
ND
IX 9
31/10/2011 30/11/2011 31/12/2011 31/01/2012
Integrated Performance Report Wednesday 29 February 2012 Page 33 of 35
Data Appendices – Quality
Green
TrustProcess - Pressure Sores Assessment Process - MUST, MST, STAMP Score Process - Hand Hygiene
General (Green)
Outcome - MUST Score
Green
Red
Green
Outcome - Pressure Sores Outcome - New MRSA Isolates Identified > 72 Hours After Admission
Initial (Red)
Threshold - 95% Threshold - 85%
Threshold - 0.8% Threshold - 0 cases
0
10
20
30
40
50
60
70
80
90
100
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
0
10
20
30
40
50
60
70
80
90
100
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
Initial compliance with MUST Screening on Admission
General compliance with MUST Screening at Weekly Review
0
10
20
30
40
50
60
70
80
90
100
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
0%
5%
10%
15%
20%
25%
30%
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
0
1
2
3
4
5
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
Average SPC +1sd
Indicator to be developed
Integrated Performance Report Wednesday 29 February 2012 Page 34 of 35
GreenOutcome - C.Difficile Infections Identified > 72 Hours After Admission Outcome - Inpatient Slips, Trips & Falls Outcome - Cardiac Arrest Calls
Process - Housekeeping & Equipment Cleaning Process - Falls Risk Assessment Process - EWS CallsHousekeeping (Green) Equipment (Green)
Trust
Threshold - Housekeeping 90% Equipment 90% No Threshold
Green
Threshold - 6 cases No Threshold No Threshold
0
5
10
15
20
25
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
Actual Cases Trust Theshold
80
82
84
86
88
90
92
94
96
98
100
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
Housekeeping Equipment
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Sep-11 Oct-11 Nov-11 Dec-11 Jan-12
0
5
10
15
20
25
30
35
40
45
50
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
0
20
40
60
80
100
120
140
160
180
200
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-120
5
10
15
20
25
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
Integrated Performance Report Wednesday 29 February 2012 Page 35 of 35
Outcome - Thromboprophylaxis Audit Outcome - Estimated Date of Discharge met Outcome - Incidents & Complaints/Concerns
Process - Bank & Agency WTE Staff Usage
Trust
No Threshold No Threshold
Green
Threshold - 100% Threshold - 40% No Threshold
Process - Electronic VTE Risk Assessment Process - Estimated Date of Discharge Red
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
100.0%
Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12
0
10
20
30
40
50
60
70
80
90
100
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
0
20
40
60
80
100
120
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
Bank Assigned Agency Assigned
Indicator to be developed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
0
50
100
150
200
250
300
350
400
450
500
Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12
Complaints/Concerns Incidents