boehm-foundation solutions for new tanks

Upload: mortaza7094

Post on 06-Jul-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    1/50

    www.HaywardBaker.com

    Foundation Solutions for New TanksNISTM – 6 th Annual International Aboveground Storage Tank Conference and

    Trade Show – September 19, 2013

    http://www.nistm.org/index.html

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    2/50

    2

    Presentation Outline

    • Some Definitions to set the stage• Design Considerations for Supporting Tanks• Ground Improvement Tank Support Methods

    – Stone Columns – Soil Mixing – Wick Drains – Other Improvement

    • Conclusions

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    3/50

    3

    Presentation Outline

    • Some Definitions to set the stage• Design Considerations for Supporting Tanks• Ground Improvement Tank Support Methods

    – Stone Columns – Soil Mixing – Wick Drains – Other Improvement

    • Conclusions

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    4/50

    4

    Above Ground Storage Tanks are not built on thebest sites, so they offer foundation challenges

    • Soft Compressible Soils – The load is always there – Differential Settlements offer maintenance challenges – Edge stability can lead to catastrophic consequences

    • Mixed bearing soils and placed fills• Foundations available

    – –

    – – Im prov ed Groun d

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    5/50

    5

    Soft soil beneath the tank can consolidatewith time rendering the tank useless

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    6/50

    6

    Lack of sufficient edge stability can create floorplate failure or buckling of shell

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    7/50

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    8/508

    What types of Ground Improvement methods aretank friendly?

    • Stone Columns – Vibro Piers – Aggregate Piers – Geo Piers

    • Wick Drains – Vertical Drains (PVDs) – Need surcharge + time – Using the tank for surcharge is risky

    • Displacement Piles – CMCs, DeWall Piles, CSCs

    •Rigid Inclusions

    • Deep Dynamic Compaction• Soil Mixing – Wet and Dry Methods

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    9/509

    Why does Ground Improvement make sense forTanks?

    • Offers faster site turnover• Predictable long term performance• Higher Tank Capaci t ies

    • Controllable settlements• Usually less expensive than traditional methods• Flexible Designs

    • Very good history in the USA as a widely acceptedpractice

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    10/5010

    Arrangement of Treatment

    • Typically in a square patternunder the floor of the tank

    • Replacement ratios from 10to 50%

    • Placement of elementsdirectly beneath the shell

    • Typically settlement criteriacontrols design

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    11/5011

    The Load Transfer Platform Must ProvideUniform Support of the Load from the Tank

    • Uses a semi rigid transferplatform

    • Designed to limit dishingbetween GI elements

    • Crushed rock isfantastic…but sand willdo

    • Layers of geogrid toincrease efficiency

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    12/5012

    Presentation Outline

    • Some Definitions to set the stage• Design Considerations for Supporting Tanks• Ground Improvement Tank Support Methods

    – Stone Columns – Soil Mixing – Wick Drains – Other Improvement

    • Conclusions

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    13/5013

    Design soil parameters used in the GroundImprovement solution for support of the tank

    13

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    14/50

    14

    Stability check is crucial to the success of thetank foundation project

    14

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    15/50

    15

    Stresses under the tank as well as overlappingstresses from other tanks must be checked

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    16/50

    16

    Numerical model setup to analyze the long termperformance of the Soil Mix support system

    16

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    17/50

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    18/50

    18

    Presentation Outline

    • Some Definitions to set the stage• Design Considerations for Supporting Tanks• Ground Improvement Tank Support Methods

    – Stone Columns – Soil Mixing – Wick Drains – Other Improvement

    • Conclusions

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    19/50

    19

    Vibro-Replacement or Stone Columns:reinforce the ground with aggregate

    Performed in-situ up to 120 feet deep

    Effective above and below the water table

    Performed using wet top-feed method or drybottom-feed method

    Commonly used for seismic responseimprovement

    Vibro Systems

    Vibrocompaction

    Vibro-Replacement StoneColumns

    VibroPiers / Aggregate Piers1

    2

    3

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    20/50

    20

    Typical Boring and design from the tank side ofthe project

    2

    • Stone Columnsdesigned to carry 2/3load from tank

    • Treatment depths just

    into the dense sand• Maximum center

    settlement – 4 inches

    • Maximum perimetersettlement – 3 inches

    • Satisfies all criteria

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    21/50

    21

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    22/50

    22

    Hydrotest Data from Stone Column Supportedtanks…the settlement has been designed

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    23/50

    23

    Presentation Outline

    • Some Definitions to set the stage• Design Considerations for Supporting Tanks• Ground Improvement Tank Support Methods

    – Stone Columns – Soil Mixing – Wick Drains – Other Improvement

    • Conclusions

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    24/50

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    25/50

    25

    Dry Soil mixing methods are utilized in wettersofter soils or where REM is a problem

    25

    Dry binder materials arepneumatically injected into thesoil during the dry mixingprocess

    Bottom up method of soilmixing

    There must be adequate soilmoisture for the binders tofully hydrate often limitingdesign strengths

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    26/50

    26

    Dry or Wet Mixing can be used to treat 100%of the soil to form blocks

    Dust

    Control

    BinderShuttle

    24-TonTanker

    GeofabricSurcharge (2-

    ft)

    20 ft20 ft

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    27/50

    27

    Dry Soil Mixing at Port Everglades to supporttanks in organic soils

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    28/50

    28

    The Project was contracted as design-build andmet the following criteria

    • Design Strength – Allowable bearing capacity of 3,750 lbs/ft 2 for thein-situ soil mass

    • Settlement – Planar tilting not to exceed 8 inches (100-ft

    diameter), 10 inches (125-ft diameter) across thediameter of the tank

    – Center-to-edge dishing not to exceed 5 inches(100-ft diameter), 6 inches (125-ft diameter)

    – Out of Plane Differential not to exceed 3/8 inch inan arc length of 30 feet

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    29/50

    29

    Dry mass mixing is working in block cellarrangement working from platform

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    30/50

    30

    Following Mass mixing, the tank foundation canbe completed using ring beams

    All tanksconstructed on

    shallowfoundations

    Foundation

    elementsconstructed to

    bear directly onsoil mix / or

    compacted fill

    bearing on soilmix

    No relievingplatform is

    required

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    31/50

    31

    Following the work and after the tank is built thehydrotest is monitored from start to finish

    k h d l d

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    32/50

    32

    Supporting tanks with Deep Mixed Columns andMass Mixing can provide an economical solution

    32

    C i f h S il i h fi

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    33/50

    33

    Construction of the Soilcrete Mat is the first stepin the process

    33

    Mass Mix Cap is thefirst element to beinstalled. Designthickness of 10 feet.

    C l i ll d h h h il

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    34/50

    34

    Columns are installed through the soilcrete matto complete the foundation system

    34

    Columns installed in a singlepass depth of 75 feet

    Th h k b i d h

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    35/50

    35

    The three new tanks being constructed over thenew structural support system using Soil Mixing

    35

    M i i h T k f ll h i h d i

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    36/50

    36

    Monitoring the Tank to full height duringhydrotest

    Final HydrotestHeight of 46’- 3”RingwallSettlement wellwithin APItolerances as wellas floor settlement

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    37/50

    37

    Lots of Happy Tanks!

    37

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    38/50

    38

    Presentation Outline

    • Some Definitions to set the stage• Design Considerations for Supporting Tanks• Ground Improvement Tank Support Methods

    – Stone Columns

    – Soil Mixing – Wick Drains – Other Improvement

    • Conclusions

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    39/50

    39

    Wick Drains – The General Idea

    Without Drains

    Clay

    Bedrock

    With Drains

    Bedrock

    How are wick drains installed and how do they

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    40/50

    40

    How are wick drains installed and how do theywork?

    • The Drains can beinstalled to depthsgreater than 100 ft.

    • Very fast installationspeeds

    • The water has to go

    somewhere on site!• Needs surcharge

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    41/50

    41

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    42/50

    42

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    43/50

    43

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    44/50

    44

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    45/50

    45

    Presentation Outline

    • Some Definitions to set the stage• Design Considerations for Supporting Tanks• Ground Improvement Tank Support Methods

    – Stone Columns

    – Soil Mixing – Wick Drains – Other Improvement

    • Conclusions

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    46/50

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    47/50

    47

    Dynamic Compaction for Chemical Storage

    47

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    48/50

    48

    Ground Modification for Asphalt Storage Tanks

    48

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    49/50

    49

    Conclusions

    GI Method Soft Soils,Compressible Soils,

    Organic Soils

    Mixed Soils orUndocumented

    Fills

    Liquefiable Soils orClean Sands

    Sandy Soils

    Wick Drains Excellent-Requires Preload-May require stagedloading

    Good-May require extrameasures to install-Requires Preload-May require stagedloading

    N/A N/A

    Earthquake Drains N/A N/A Good N/A

    Stone Columns orAggregate Piers

    Good-Sufficient settlementreduction may not beachievable

    Very Good Excellent Excellent

    Rigid Inclusions Very Good Very Good N/A Good

    Soil Mixing - Columns Excellent Very Good Excellent Excellent

    Soil Mixing - Mass Excellent Good to N/A-Depending on soil type

    Excellent Good

    h k

  • 8/17/2019 Boehm-Foundation Solutions for New Tanks

    50/50

    Thank You!! Questions?

    Dennis W. Boehm [email protected] Baker www.haywardbaker.com

    509 North Sam Houston Parkway/Houston, Texas

    281-668-1870