    Case Study on

    Lean Manufacturing Initiatives at Boeing

  • 7/31/2019 Boeing (71-75)

    2/14

    1916: Airplane manufacturer Boeing Airplane Company was formed by William

    Boeing 1954: The Boeing 707 jet makes its first flight.

    1960: Philadelphia-based Vertol Aircraft Corporation, a maker of military

    helicopters, is acquired.

    1966: Company launches first Lunar Orbiter, which sends photos of the moon back

    to Earth.

    1968: Apollo 8, which takes the first astronauts around the moon, is launched in

    December boosted by a Saturn V rocket, for which Boeing had built the first stage.

    1970: The 747, the first of the 'jumbo jets,' makes its first commercial flight.

    1993: NASA names the company the prime contractor for the International Space

    Station.

    1996: The aerospace and defense units of Rockwell International are acquired.

    1997: McDonnell Douglas, number one in military aircraft and number three in

    commercial aircraft worldwide, is acquired, making Boeing the largest aerospace

    company in the world.

    1999: Company-led consortium successfully launches a commercial

    satellite from a floating platform at sea.

    History

  • 7/31/2019 Boeing (71-75)

    3/14

    How The Journey Started?......

    Boeing airplane company was formed in 1916 by William Boeing and

    George Westerville as Pacific Aero Products company.

    They manufactured aircrafts for US military during the first world war.

    Navy awarded a contract to build a primary trainer(planes for test flights).

    Model 40A mail plane won the US post office contract. BAT was formed to run airmail services, to train pilot, to setup airfields,

    maintenance staff for new service.

    After second world war focus shifted to commercial jets.

    1952 first commercial jet Boeing 707(short range jet).

    1960 first jumbo jet Boeing 747.

    1962 they manufactured Air Force One for American President's use.

  • 7/31/2019 Boeing (71-75)

    4/14

  • 7/31/2019 Boeing (71-75)

    5/14

    Need for Change

  • 7/31/2019 Boeing (71-75)

    6/14

    Primary focus was to eliminate waste in the companys

    business processes in order to :

    i. Maximize operational efficiency

    ii. Improve quality/safety standards

    iii. Eliminate unnecessary motion and inventory

    iv. Save time

    v. Improve employees morale with increased involvement

    Implementation plan (using tools like value stream and

    employee involvement) was formulated

    Boeing relied on people who worked closely with processesand products to remove waste in manufacturing and support

    processes

    Implementation of Lean Manufacturing

  • 7/31/2019 Boeing (71-75)

    7/14

    Production Reform Team was formed

    Carriers had to choose from a limited options. Special requests

    were handled at an extra price

    400 computers were discarded and replaced with 4 inter-

    connected software packages to manage Configuration,

    Manufacturing, Purchasing and Inventory Control

    Accelerated Improvement Workshops (AIW) were held

    Inventory management system- Cribmaster, was installed to

    monitor inventory

    Autonomous Maintenance Workshops (AMW) were conducted

    to improve maintenance of machines

    Lean Manufacturing Assessments and Production Preparation

    Process workshops were also conducted

    Implementation of Lean Manufacturing (contd)

  • 7/31/2019 Boeing (71-75)

    8/14

    PARAMETER RESULTS

    INVENTORY Inventory Turns increased from 2 to 18

    WIP brought down to 30 pieces from 100 pieces

    MANUFACTURING TIME Reduced by 60%

    Time taken to produce individual parts reduced by 95%

    FLOOR SPACE AREA

    Reduced by over 50% Inventory Storage space also reduced

    CAPACITY Increased

    ASSEMBLY TIME Reduced by 50%

    Wing production lead time reduced from 9.5 days to 5 days

    PROCESS TIME Eliminated the need of a second production line

    DEFECT RATE Defects reduced by 48%

    EFFICIENCY Increased- Process that took 2000 minutes was being

    completed in 100 minutes

    Benefits Derived from Lean Mfg.

  • 7/31/2019 Boeing (71-75)

    9/14

    Moving Line Technique

  • 7/31/2019 Boeing (71-75)

    10/14

    Benefits Derived from Moving-Line Technique

    PARAMETER RESULTS

    INVENTORY WIP Inventory reduced as employees could monitor the

    production status at any time

    ASSEMBLY TIME

    30 feeder lines parallel to the main assembly line helped reduce

    assembly time

    An assembly that previously needed 42 hours of work was nowcompleted in just 16 hours

    Further anticipation to reduce the assembly time by 50%

    LEAD TIME Anticipated reduction of order to delivery time to six months

    QUALITY LEVELS Standardized parts and procedures increased the quality

    EFFICIENCY Increase in overall efficiency was observed

    COST The cost of production came down because of various process

    improvements

  • 7/31/2019 Boeing (71-75)

    11/14

    Traditional vs. Moving-Line Approach

    Traditional Approach Moving-Line Approach

  • 7/31/2019 Boeing (71-75)

    12/14

    Lessons Learnt

    Moving Line Technology

    Lean Manufacturing From principle to Practice

    Role of IT in Lean Manufacturing

  • 7/31/2019 Boeing (71-75)

    13/14

    Boeing Current Market outlook 2010 to 2030

    Total Revenues - $ 64,306.0 mn

    Profit - $ 12,463.0 mn

    http://boeing_current_market_outlook_2011_to_2030.pdf/http://boeing_current_market_outlook_2011_to_2030.pdf/http://boeing_current_market_outlook_2011_to_2030.pdf/http://boeing_current_market_outlook_2011_to_2030.pdf/http://boeing_current_market_outlook_2011_to_2030.pdf/http://boeing_current_market_outlook_2011_to_2030.pdf/http://boeing_current_market_outlook_2011_to_2030.pdf/
  • 7/31/2019 Boeing (71-75)

    14/14

    Thank You