Booster and PS LIU workunits
EPC Project Meeting 06-09-2011Serge Pittet
TE EPC
The LIU Project
“The LHC Injectors Upgrade should plan for delivering reliably to the LHC the beams required for reaching the goals of the HL-LHC. This includes LINAC4, the PS booster, the PS, the SPS, as well as the heavy ion chain.”
06/09/2011 TE-EPC - Serge Pittet 2
TE EPC
D. Nisbet D. Nisbet (inj.)S. Pittet
S.Pittet
Project leaderR. Garoby
Linac4M. Vretnar
PSBK. Hanke
PSS. Gilardoni
SPSB. Goddard
Deputy M. Meddahi
LIU Project status
• RCS option studied and rejected.
• LIU project approved in the 24th of august LMC.• Official date for project start on 1st of September 2011.• TDR to be completed by the end of 2011.• Startup of upgraded machines at the end of LS2 (2017?).
• Some budget codes already funded.• WBS and WUs will soon be transferred in APT.
06/09/2011 TE-EPC - Serge Pittet 3
TE EPC
Provisional planning
06/09/2011 TE-EPC - Serge Pittet 4
TE EPC
Manpower request overview
06/09/2011 TE-EPC - Serge Pittet 5
TE EPC
LIU-PSB 5.2 - Booster MPS
• Civil engineering included. To be done in LS1 as far as possible.
06/09/2011 TE-EPC - Serge Pittet 6
TE EPC
Provide Booster MPS Trims
Holder [email protected]
Budget code 99327 (not active yet)
Budget 700kCHF
unit(s) 3
Deadline LS2
Provide Booster MPS
Holder [email protected]
Budget code 99327 (not active yet)
Budget 15MCHF
unit(s) 1
Deadline LS2
POPS based Baseline
06/09/2011 TE-EPC - Serge Pittet 7
TE EPC
Benefits• Overall voltage available increases and would allow a
reduction of the RMS current using a faster ramping.• The capacitor bank totally absorbs the peak power
on the 18kV network. Meyrin SVC would then become optional.
• Spare sharing between MPS A and B and eventually with POPS.
• Only a few new cables needed between the reference magnet (BCER) and the MPS.
• New B-field regulation to minimize eddy currents and saturation effects impact at higher current and acceleration rate.
Drawbacks• Cost estimation 14MCHF using POPS module.
Reference magnet
Ring 2&3
GND
MPS B2500V5500A
QFO600V450A
QDE600V450A
GND
MPS A2500V5500A
DC3
DC
DC +
-
MAGNETS
V_F3
UdcF3
AC
CC1
AC
MV7308
DC
DIP+QF+REF
DC3
DC
DC +
-
V_F3
UdcF3
AC
CC1
AC
MV7308
DC
DIP+QD+REF
DC3
DC
DC +
-
UdcF3
AC
CC1
AC
MV7308
DC
64 BHZ Rings 1&4
128 QFO Rings 1,2,3&4
64 QDE Rings 1,2,3&4
64 BHZ Rings 2&3
Reference magnet
Ring 1&4
Ring 1 B-filedmeasurement
Ring 2 B-filedmeasurement
Layout of MPS new building
06/09/2011 TE-EPC - Serge Pittet 8
TE EPC
New
MPSB
(2 GeV)
(26m x 16m)
TT
6
Cap bank #1 Cap bank #2 Cap bank #3
Control roomLocal for Cooling& Air Conditioning
AC/DC3 spare (1.2m x 10m) DC/DC3 floating (1.2m x 10m)
AC/DC1 (1.2m x 10m) AC/DC2 (1.2m x 10m)
DC/DC1 (1.2m x 10m) DC/DC2 (1.2m x 10m)
Out
put c
ubic
le
QF QD QS16
m
26m
4m4m
• 420m2 required, only 190m2 available in bdg. 271 ground floor.• Only 200kg/m2 allowed in bdg. 271 first floor.• No space left in bdg. 361.
With this new building:• We can install and commission during Booster operation.• We have a backup power supply during the first years.• Easy connection to existing cables and cooling services.
LIU-PSB 5.2 – ALG1&2
• The linear stage can handle the new rated current.
• The capacitor bank size needs to be increased.
06/09/2011 TE-EPC - Serge Pittet 9
TE EPC
Perform ALG1&2 upgrade
Holder [email protected]
Budget code 99327 (not active yet)
Budget 200kCHF
unit(s) 4
Deadline LS2
LIU-PSB 5.2 - Mididiscaps
• Design and production from Linac 4 project.
06/09/2011 TE-EPC - Serge Pittet 10
TE EPC
Provide Mididiscaps
Holder [email protected]
Budget code 99327 (not active yet)
Budget 50kCHF
unit(s) 5
Deadline LS2
LIU-PSB 5.2 – Beam Transfer
• Optimization still need to be done: pulsing converters and keep existing magnets, BT.BHZ10 magnet design, 2GeV quadrupoles optic, reuse of some converters or spares
06/09/2011 TE-EPC - Serge Pittet 11
TE EPC
Provide Transfer Bendings
Holder [email protected]
Budget code 99327 (not active yet)
Budget 3.2MCHF
unit(s) About 13 (+15 for Isolde?)
Deadline LS2
LIU-PS 5 – CBE
• Specification under study with OP.
• ACAPULCO power design with FGC3 and RegFGC3.
06/09/2011 TE-EPC - Serge Pittet 12
TE EPC
DHZ&DVT Power Converters
Holder [email protected]
Budget code 99263 PS Upgrade: Converters
Budget 560kCHF
unit(s) 75
Deadline LS1
QN&QSK Power Converters
Holder [email protected]
Budget code 99263 PS Upgrade: Converters
Budget 740kCHF
unit(s) 85
Deadline LS1
LIU-PS 5 – PI.SMH42
• 2 aimants en série• R bobinage:
2·0.08mOhms ≈ 0.2 mOhms
• L aimant: 2·0.9uH ≈ 2uH
• Inom: 31kA• Forme: Demi sinus+ 3ème harmonique + filtre actif• Largeur pulse demi sinus: 3ms
06/09/2011 TE-EPC - Serge Pittet 13
TE EPC
Manufacture and commission PI.SMH42 Power Converter
Holder [email protected]
Budget code 99263 PS Upgrade: Converters
Budget 400kCHF
unit(s) 2
Deadline LS2
LIU-PS 5 – PI.BSM42• R bobinage: 0.5 mOhms• L aimant: 1uH• Inom: 28kA• Forme: Demi sinus
+ 3ème harmonique + filtre actif
• Largeur pulse demi sinus: 0.8ms
• Temps de descente du courant: 0.4ms
• Pas de faisceau sur la portion de montée en courant.
• La descente en courant des 4 bumpers doit être aussi proche que possible.
06/09/2011 TE-EPC - Serge Pittet 14
TE EPC
Manufacture and commission PI.BSM42 Power Converter
Holder [email protected]
Budget code 99263 PS Upgrade: Converters
Budget 300kCHF
unit(s) 2
Deadline LS2
LIU-PS 5 – PI.BSM40, 43 & 44• R bobinage:
0.41 mOhms (20 tours)• L aimant: 0.5mH• Inom: 1.1kA• Largeur pulse demi sinus:
0.8ms• Temps de descente
du courant: 0.4ms
• Le nombre de tour peut encore être modifié ([email protected])
• Pas de faisceau sur la portion de montée en courant.• La descente en courant des 4 bumpers doit être aussi proche que possible.
06/09/2011 TE-EPC - Serge Pittet 15
TE EPC
Upgrade and commission PI.BSM40, 43 & 44 Power Converters
Holder [email protected]
Budget code 99263 PS Upgrade: Converters
Budget 360kCHF
unit(s) 4
Deadline LS2
Related consolidation
06/09/2011 TE-EPC - Serge Pittet 16
TE EPC
• Some consolidation items which are essential for the LIU project have been pushed/advanced.
• They have not been transferred and stay in S.Baird project.
status code 2011 kCHF
2012kCHF
2013kCHF
2014kCHF
2015kCHF
2016kCHF
started 68215 PS Main Ring
started 68217 PS Gamma Transition
started 68251 PSB Multipole/Dipole 16 92
Approv. EPC.04 SVC Meyrin Filter 647
Approv. EPC.03 Canada, BI.QNO, BIX.QNO 1118
Approv. EPC.05 PS Septum 16 & 26 527
Approv. EPC.16 East area 647
Approv. EPC.06 TT2 3835
Organization
• Bi-weekly LIU PSB project meetings followed by linkman.• Bi-weekly LIU PS project meetings followed by linkman.
• EPC LIU project meetings in January, May and September with a shot presentation by each WU holder.
• WU specific meetings when needed.
06/09/2011 TE-EPC - Serge Pittet 17
TE EPC
Documentation
• Detailed information still available on TE-EPC-LPC website: http://te-epc-lpc.web.cern.ch/te-epc-lpc/general.stm
06/09/2011 TE-EPC - Serge Pittet 18
TE EPC
LIU-PSB Work Units
06/09/2011 TE-EPC - Serge Pittet 19
TE EPC
wu v1.0 Generated: 10-Feb-2011 11:19
cmd wu WU ID Baseline Status Description WBS Holders EMail Start Date Finish Date Comments
cmd Pxx # Skill [Missing] Email or Profile Org Code [Recharging] Duration Unit (M.WK, %) Start Date Finish Date Comments
cmd PSx # JobType Skill [Missing] Email or Profile Org Code [Recharging] Duration Unit (M.WK, %) Start Date Finish Date Comments
cmd PBU # Expenditure Description Org Code [Recharging] Amount Currency Start Date Finish Date Comments
cmd Mxx # Expenditure Description Org Code [Recharging] Amount Currency Start Date Finish Date Comments
cmd de # Weight Deliverable description Actual Qty Total Qty Unit Start Date Finish Date Comments
Specify command N, M, D; Commands: N (New ), M (Modify), D (Delete)
wu D2 Provide Booster MPS LIU-PSB 5.2 [email protected] 1-Jan-2011 30-Jun-2014
MSP 10 Budget 99327 15,000,000 CHF
de 10 1 Design & Specif ication 0 1 U 1-Jan-2011 31-Dec-2012
de 20 0 Market survey 0 1 U 1-Apr-2012 30-Jun-2012
de 30 0 Call for tender 0 1 U 1-Jul-2012 31-Dec-2012
de 40 10 Converter manufacturing 0 1 U 1-Jan-2013 31-Dec-2014
de 50 2 Civil engineering 0 1 U 1-Jan-2013 31-Dec-2015
de 60 2 Installation and commissioning 0 1 U 1-Jan-2014 31-Mar-2016
wu D2 Provide Booster MPS Trims LIU-PSB 5.2 [email protected] 1-Jan-2011 30-Jun-2014
MSP 10 Budget 99327 700,000 CHF
de 10 100 Design & Specif ication 0 1 U 1-Jan-2011 31-Dec-2012
de 20 0 Market survey 0 1 U 1-Apr-2012 30-Jun-2012
de 30 0 Call for tender 0 1 U 1-Jul-2012 31-Dec-2012
de 40 400 Converter manufacturing 0 1 U 1-Jan-2013 31-Dec-2014
de 50 200 Installation and commissioning 0 1 U 1-Jan-2015 31-Mar-2016
wu D2 Perform ALG1&2 upgrade LIU-PSB 5.2 [email protected] 1-Jan-2011 30-Jun-2014
MSP 10 Budget 99327 200,000 CHF
de 10 10 Design & Specif ication 0 1 U 1-Jan-2011 31-Dec-2012
de 20 150 Component supplies 0 1 U 1-Jan-2013 30-Jun-2014
de 30 40 Installation and commissioning 0 1 U 1-Jan-2015 31-Mar-2016
wu D2 Provide MidiDiscap LIU-PSB 5.2 [email protected] 1-Jan-2011 30-Jun-2014
MSP 10 Budget 99327 50,000 CHF
de 10 0 Design & Specif ication 0 1 U 1-Jan-2011 31-Dec-2012 from linac 4 project
de 20 0 Market survey 0 1 U 1-Apr-2012 30-Jun-2012 from linac 4 project
de 30 0 Call for tender 0 1 U 1-Jul-2012 31-Dec-2012 from linac 4 project
de 40 45 Converter manufacturing 0 5 U 1-Jan-2014 31-Dec-2014
de 50 5 Installation and commissioning 0 5 U 1-Jan-2015 31-Mar-2016
wu D2 Provide Transfer bendings LIU-PSB 5.2 [email protected] 1-Jan-2011 30-Jun-2014
MSP 10 Budget 99327 3,200,000 CHF
de 10 320 Design & Specif ication 0 1 U 1-Jan-2011 31-Dec-2012
de 20 0 Market survey 0 1 U 1-Apr-2012 30-Jun-2012
de 30 0 Call for tender 0 1 U 1-Jul-2012 31-Dec-2012
de 40 2240 Converter manufacturing 0 1 U 1-Jan-2013 31-Dec-2014
de 50 640 Installation and commissioning 0 1 U 1-Jan-2015 31-Mar-2016
LIU-PS Work Units
06/09/2011 TE-EPC - Serge Pittet 20
TE EPC
cmd wu WU ID Status Description WBS Holders EMail Start Date Finish Date
cmd Pxx # Skill [Missing] Email or Profile Org Code [Recharging] Duration Unit (M.WK, %) Start Date Finish Date
cmd PSx # JobType Skill [Missing] Email or Profile Org Code [Recharging] Duration Unit (M.WK, %) Start Date Finish Date
cmd PBU # Expenditure Description Org Code [Recharging] Amount Currency Start Date Finish Date
cmd Mxx # Expenditure Description Org Code [Recharging] Amount Currency Start Date Finish Date
cmd de # Weight Deliverable description Actual Qty Total Qty Unit Start Date Finish Date
Specify command N, M, D; Commands: N (New ), M (Modify), D (Delete)
wu D2
Design and specify Low Energy Quadrupoles (QN&QSK) power converters LIU-PS 5 [email protected] 1-Jan-2011 31-Dec-2011
MSP 10 Budget 99263 70,000 CHF
de 10 70 Pow er converters designed and specif ied 0 1 U 1-Jan-2011 31-Dec-2011
wu D2
Prototype and order Low Energy Quadrupoles (QN&QSK) power converters LIU-PS 5 [email protected] 1-Jan-2012 31-Oct-2012
MSP 10 Budget 99263 30,000 CHF
de 10 30 Prototype validated 0 1 U 1-Jan-2012 30-Jun-2012
de 20 0 Market survey completed 0 1 U 1-Apr-2012 30-Jun-2012
de 30 0 Call for tender completed 0 1 U 1-Jul-2012 31-Oct-2012
wu D2
Manufacture Low Energy Quadrupoles (QN&QSK) power converters LIU-PS 5 [email protected] 1-Nov-2012 31-Dec-2013
MSP 10 Budget 99263 530,000 CHF
de 10 530 Pow er converters manufactured 0 85 U 1-Nov-2012 31-Dec-2013
wu D2
Install and commission Low Energy Quadrupoles (QN&QSK) power converters LIU-PS 5 [email protected] 1-Jan-2014 31-Mar-2014
MSP 10 Budget 99263 110,000 CHF
de 10 110 Pow er converters installed and commissioned 0 85 U 1-Jan-2014 31-Mar-2014
wu D2
Design, specify Low Energy Dipoles (DHZ&DVT) Power Converters LIU-PS 5 [email protected] 1-Jan-2011 31-Dec-2011
de 10 0 Pow er converters designed and specif ied 0 1 U 1-Jan-2011 31-Dec-2011
wu D2
Prototype and order Low Energy Dipoles (DHZ&DVT) Power Converters LIU-PS 5 [email protected] 1-Jan-2012 31-Oct-2012
de 10 0 Prototype validated 0 1 U 31-Dec-2011 30-Jun-2012
de 20 0 Market survey completed 0 1 U 1-Apr-2012 30-Jun-2012
de 30 0 Call for tender completed 0 1 U 1-Jul-2012 31-Oct-2012
wu D2
Manufacture Low Energy Dipoles (DHZ&DVT) Power Converters LIU-PS 5 [email protected] 1-Dec-2012 31-Dec-2013
MSP 10 Budget 99263 470,000 CHF
de 10 470 Pow er converters manufactured 0 75 U 1-Nov-2012 31-Dec-2013
wu D2
Install and commission of Low Energy Dipoles (DHZ&DVT) Power Converters LIU-PS 5 [email protected] 1-Jan-2014 31-Mar-2014
MSP 10 Budget 99263 90,000 CHF
de 10 90 Pow er converters installed and commissioned 0 75 U 1-Jan-2014 31-Mar-2014
wu D2
Design, specify and order PI.SMH42 Power Converter LIU-PS 5 [email protected] 1-Jan-2011 31-Dec-2013
MSP 10 Budget 99263 60,000 CHF
de 10 60 Pow er converters designed and specif ied 0 1 U 1-Jan-2011 31-Dec-2013
de 20 0 Market survey completed 0 1 U 1-Apr-2013 30-Jun-2013
de 30 0 Call for tender completed 0 1 U 1-Jul-2013 31-Dec-2013
wu D2
Supply PI.SMH42 Power Converter conponents LIU-PS 5 [email protected] 1-Jan-2014 31-Dec-2014
MSP 10 Budget 99263 200,000 CHF
de 10 200 Component supplied 0 2 U 1-Jan-2014 31-Dec-2014
wu D2 LIU-PS 5 [email protected] 1-Jan-2015 31-Dec-2016
MSP 10 Budget 99263 100,000 CHF
de 10 100 Pow er converters manufactured 0 2 U 1-Jan-2015 31-Dec-2016
wu D2 LIU-PS 5 [email protected] 1-Jan-2017 31-Dec-2017
MSP 10 Budget 99263 40,000 CHF
de 10 40 0 2 U 1-Jan-2017 31-Dec-2017
wu D2 LIU-PS 5 [email protected] 1-Jan-2011 31-Mar-2016
MSP 10 Budget 99263 60,000 CHF
de 10 60 Pow er converters designed and specif ied 0 1 U 1-Jan-2011 31-Dec-2013
de 20 0 Market survey completed 0 1 U 1-Apr-2013 30-Jun-2013
de 30 0 Call for tender completed 0 1 U 1-Jul-2013 31-Dec-2013
wu D2 LIU-PS 5 [email protected] 1-Jan-2014 31-Dec-2014
MSP 10 Budget 99263 100,000 CHF
de 10 100 Component supplied 0 2 U 1-Jan-2014 31-Dec-2014
wu D2 LIU-PS 5 [email protected] 1-Jan-2015 31-Dec-2016
MSP 10 Budget 99263 100,000 CHF
de 10 100 Pow er converters manufactured 0 2 U 1-Jan-2015 31-Dec-2016
wu D2 LIU-PS 5 [email protected] 1-Jan-2017 31-Dec-2017
MSP 10 Budget 99263 40,000 CHF
de 60 40 0 2 U 1-Jan-2017 31-Dec-2017
wu D2 LIU-PS 5 [email protected] 1-Jan-2011 31-Dec-2013
MSP 10 Budget 99263 100,000 CHF
de 10 100 Linear stage designed and specif ied 0 1 U 1-Jan-2011 31-Dec-2013
de 20 0 Integration study completed 0 1 U 1-Jan-2011 31-Dec-2013
de 30 0 Market survey completed 0 1 U 1-Apr-2013 30-Jun-2013
de 40 0 Call for tender completed 0 1 U 1-Jul-2013 31-Dec-2013
wu D2 LIU-PS 5 [email protected] 1-Jan-2014 31-Dec-2014
MSP 10 Budget 99263 80,000 CHF
de 10 80 Component supplied 0 4 U 1-Jan-2014 31-Dec-2014
wu D2 LIU-PS 5 [email protected] 1-Jan-2015 31-Dec-2016
MSP 10 Budget 99263 80,000 CHF
de 10 80 Linear stage manufactured 0 4 U 1-Jan-2015 31-Dec-2016
wu D2 LIU-PS 5 [email protected] 1-Jan-2017 31-Dec-2017
MSP 10 Budget 99263 100,000 CHF
de 10 100 0 4 U 1-Jan-2017 31-Dec-2017
cmd Pxx # Skill [Missing] Email or Profile Org Code [Recharging] Duration Unit (M.WK, %) Start Date Finish Date
cmd PSx # JobType Skill [Missing] Email or Profile Org Code [Recharging] Duration Unit (M.WK, %) Start Date Finish Date
cmd PBU # Expenditure Description Org Code [Recharging] Amount Currency Start Date Finish Date
cmd Mxx # Expenditure Description Org Code [Recharging] Amount Currency Start Date Finish Date
Specify command N, M, D; Commands: N (New ), M (Modify), D (Delete)
wu D2 LIU-PS 5 [email protected] 1-Jan-2011 31-Dec-2011
MSP 10 Budget 99263 70,000 CHF
de 10 70 Pow er converters designed and specif ied 0 1 U 1-Jan-2011 31-Dec-2011
wu D2 LIU-PS 5 [email protected] 1-Jan-2012 31-Oct-2012
MSP 10 Budget 99263 30,000 CHF
de 10 30 Prototype validated 0 1 U 1-Jan-2012 30-Jun-2012
de 20 0 Market survey completed 0 1 U 1-Apr-2012 30-Jun-2012
de 30 0 Call for tender completed 0 1 U 1-Jul-2012 31-Oct-2012
wu D2 LIU-PS 5 [email protected] 1-Nov-2012 31-Dec-2013
MSP 10 Budget 99263 530,000 CHF
de 10 530 Pow er converters manufactured 0 85 U 1-Nov-2012 31-Dec-2013
wu D2 LIU-PS 5 [email protected] 1-Jan-2014 31-Mar-2014
MSP 10 Budget 99263 110,000 CHF
de 10 110 0 85 U 1-Jan-2014 31-Mar-2014
wu D2 LIU-PS 5 [email protected] 1-Jan-2011 31-Dec-2011
de 10 0 Pow er converters designed and specif ied 0 1 U 1-Jan-2011 31-Dec-2011
wu D2 LIU-PS 5 [email protected] 1-Jan-2012 31-Oct-2012
de 10 0 Prototype validated 0 1 U 31-Dec-2011 30-Jun-2012
de 20 0 Market survey completed 0 1 U 1-Apr-2012 30-Jun-2012
de 30 0 Call for tender completed 0 1 U 1-Jul-2012 31-Oct-2012
wu D2 LIU-PS 5 [email protected] 1-Dec-2012 31-Dec-2013
MSP 10 Budget 99263 470,000 CHF
de 10 470 Pow er converters manufactured 0 75 U 1-Nov-2012 31-Dec-2013
wu D2 LIU-PS 5 [email protected] 1-Jan-2014 31-Mar-2014
MSP 10 Budget 99263 90,000 CHF
de 10 90 0 75 U 1-Jan-2014 31-Mar-2014
wu D2 LIU-PS 5 [email protected] 1-Jan-2011 31-Dec-2013
MSP 10 Budget 99263 60,000 CHF
de 10 60 Pow er converters designed and specif ied 0 1 U 1-Jan-2011 31-Dec-2013
de 20 0 Market survey completed 0 1 U 1-Apr-2013 30-Jun-2013
de 30 0 Call for tender completed 0 1 U 1-Jul-2013 31-Dec-2013
wu D2
Supply PI.SMH42 Power Converter conponents LIU-PS 5 [email protected] 1-Jan-2014 31-Dec-2014
MSP 10 Budget 99263 200,000 CHF
de 10 200 Component supplied 0 2 U 1-Jan-2014 31-Dec-2014
wu D2
Manufacture PI.SMH42 Power Converter LIU-PS 5 [email protected] 1-Jan-2015 31-Dec-2016
MSP 10 Budget 99263 100,000 CHF
de 10 100 Pow er converters manufactured 0 2 U 1-Jan-2015 31-Dec-2016
wu D2
Install and commission PI.SMH42 Power Converter LIU-PS 5 [email protected] 1-Jan-2017 31-Dec-2017
MSP 10 Budget 99263 40,000 CHF
de 10 40 Pow er converters installed and commissioned 0 2 U 1-Jan-2017 31-Dec-2017
wu D2
Design, specify and order PI.BSM42 Power Converter LIU-PS 5 [email protected] 1-Jan-2011 31-Mar-2016
MSP 10 Budget 99263 60,000 CHF
de 10 60 Pow er converters designed and specif ied 0 1 U 1-Jan-2011 31-Dec-2013
de 20 0 Market survey completed 0 1 U 1-Apr-2013 30-Jun-2013
de 30 0 Call for tender completed 0 1 U 1-Jul-2013 31-Dec-2013
wu D2
Supply PI.BSM42 Power Converter component LIU-PS 5 [email protected] 1-Jan-2014 31-Dec-2014
MSP 10 Budget 99263 100,000 CHF
de 10 100 Component supplied 0 2 U 1-Jan-2014 31-Dec-2014
wu D2
Manufacture PI.BSM42 Power Converter LIU-PS 5 [email protected] 1-Jan-2015 31-Dec-2016
MSP 10 Budget 99263 100,000 CHF
de 10 100 Pow er converters manufactured 0 2 U 1-Jan-2015 31-Dec-2016
wu D2
Install and commission PI.BSM42 Power Converter LIU-PS 5 [email protected] 1-Jan-2017 31-Dec-2017
MSP 10 Budget 99263 40,000 CHF
de 60 40 Pow er converters installed and commissioned 0 2 U 1-Jan-2017 31-Dec-2017
wu D2
Design, specify, integrate and order PI.BSM40, 43 & 44 Power Converters LIU-PS 5 [email protected] 1-Jan-2011 31-Dec-2013
MSP 10 Budget 99263 100,000 CHF
de 10 100 Linear stage designed and specif ied 0 1 U 1-Jan-2011 31-Dec-2013
de 20 0 Integration study completed 0 1 U 1-Jan-2011 31-Dec-2013
de 30 0 Market survey completed 0 1 U 1-Apr-2013 30-Jun-2013
de 40 0 Call for tender completed 0 1 U 1-Jul-2013 31-Dec-2013
wu D2
Supply PI.BSM40, 43 & 44 Power Converters component LIU-PS 5 [email protected] 1-Jan-2014 31-Dec-2014
MSP 10 Budget 99263 80,000 CHF
de 10 80 Component supplied 0 4 U 1-Jan-2014 31-Dec-2014
wu D2
Manufacture PI.BSM40, 43 & 44 Power Converters LIU-PS 5 [email protected] 1-Jan-2015 31-Dec-2016
MSP 10 Budget 99263 80,000 CHF
de 10 80 Linear stage manufactured 0 4 U 1-Jan-2015 31-Dec-2016
wu D2
Upgrade PI.BSM40, 43 & 44 Power Converters and commission systems LIU-PS 5 [email protected] 1-Jan-2017 31-Dec-2017
MSP 10 Budget 99263 100,000 CHF