boq for productivity rate

Upload: dick-anthony-mabao

Post on 02-Jun-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 BOQ for Productivity Rate

    1/7

    Project : BellaVita Tapia

    Subject : Cost Estimate for Duplex Units Using Wall Form Tiles (JJM)

    Floor Area sqm

    Qty Unit

    Unit Cost Amount Unit Cost Amount

    I Preliminaries1.00 Preliminaries 1.00 lot - - 3,000.00 3,000.

    Sub-total I - 3,000.0

    II Site Works

    1.00 Clearing 24.00 sqm - - 12.00 288.

    2.00 Lay-out/Staking 24.00 sqm 20.00 480.00 5.00 120.

    3.00 Excavation 5.18 cum - - 350.00 1,813.

    4.00 Backfilling 3.88 cum - - 180.00 698.4

    Sub-total II 480.00 2,919.4

    III Structural Works

    1.00 Footings

    Gravel Bedding 0.26 cum 803.57 208.93 44.64 11.

    Reinforcement 74.00 kgs 3.57 264.

    Concrete 2.59 cum

    Cement 23.31 bags 44.64 1,040.Sand 1.30 cum 741.07 959.69 178.57 231.

    Gravel 2.59 cum 803.57 2,081.25 178.57 462.

    2.00 Slab

    Gravel Bedding 0.53 cum 803.57 425.89 44.64 23.

    Reinforcement 57.50 kgs 3.57 205.

    Concrete 1.58 cum - -

    Cement 14.22 bags 44.64 634.

    Sand 0.79 cum 741.07 585.45 178.57 141.

    Gravel 1.58 cum 803.57 1,269.64 178.57 282.

    Floor Finishing/Topping 21.00 sqm 22.32 468.

    3.00 Formworks 3.20 sqm 89.29 285.71 35.71 114.

    Sub-total III 5,816.56 3,880.3

    IV Masonry Works

    1.00 Wall SystemWall System (Including mortar & Rebars) 80.00 sqm - -

    Wall Form Tiles 735.00 pcs 51.07 37,537.50 28.42 20,892.

    Cement (For Form Tiles Production) 50.00 bags - -

    GI Studs 84.21 pcs 75.89 6,390.94 22.32 1,879.

    Reinforcement 218.15 kgs 3.57 779.

    Cement (For Form Tiles Laying) 25.00 bags 44.64 1,116.

    Sand 2.23 cum 741.07 1,652.59 178.57 398.

    Gravel 4.46 cum 803.57 3,583.93 178.57 796.4

    Plastering at Corners 15.20 l.m. 53.57 814.

    Reinforcement 56.00 kgs 3.57 200.

    Concrete cum - -

    2.00 Formworks - sqm - -

    Sub-total IV 49,164.96 26,875.8

    Labor Cost

    24.00

    DescriptionNo

    OSM

    OSM

    OSM

    OSM

    OSM

    OSM

    Material Cost

    OSM

    OSM

    OSM

  • 8/10/2019 BOQ for Productivity Rate

    2/7

  • 8/10/2019 BOQ for Productivity Rate

    3/7

    Project : BellaVita Tapia

    Subject : Cost Estimate for Multipod Units Using Wall Form Tiles (JJM)

    Floor Area sqm

    I Preliminaries

    1.00 Preliminaries 4.00 lot

    Sub-total I

    II Site Works

    1.00 Clearing 90.00 sqm 10.00 4.00 40.00

    2.00 Lay-out/Staking 90.00 sqm 30.00 3.00 90.00

    3.00 Excavation 19.20 cum 1.33 8.00 10.64

    4.00 Backfilling 11.52 cum 3.87 8.00 30.96

    Sub-total II

    III Structural Works

    1.00 Footings

    Gravel Bedding 0.80 cum 3.87 1.00 3.87

    Reinforcement 280.00 kgs 112.00 8.00 896.00

    Concrete 10.00 cum 0.91 10.00 9.10

    Cement 90.00 bags

    Sand 5.00 cum

    Gravel 10.00 cum

    2.00 Slab

    Gravel Bedding 2.00 cum 3.87 1.00 3.87

    Reinforcement 230.00 kgs 112.00 8.00 896.00

    Concrete 6.32 cum 0.91 10.00 9.10

    Cement 56.88 bags

    Sand 3.16 cum

    Gravel 6.32 cum

    Floor Finishing/Topping 78.80 sqm 20.00 8.00 160.00

    3.00 Formworks 12.80 sqm 2.70 6.00 16.20

    Sub-total III

    IV Masonry Works

    1.00 Wall System

    Wall System 234.24 sqm

    Wall Form Tiles 2,372.00 pcs 20.00 10.00 200.00

    Cement (For Form Tiles Production) 160.00 bags

    GI Studs 272.00 pcs 10.00 10.00 100.00

    Reinforcement 704.00 kgs 112.00 3.00 336.00

    Cement (For Form Tiles Laying) 80.00 bags 0.91 10.00 9.10

    Sand 7.20 cum 0.08 10.00 0.75

    Gravel 14.40 cum 0.16 10.00 1.60

    Plastering at Corners 42.40 l.m. 1.33 10.00 13.30

    Reinforcement 180.00 kgs 1.33 10.00 13.30

    Concrete cum 0.91 10.00 9.10

    2.00 Formworks - sqm 2.70 12.00 32.40

    Sub-total IV

    V Metal Works

    1.00 Roof Framing 4.00 lot 0.25 4.00 1.00

    Sub-total V

    VI Architectural Works

    1.00 Roofing Works 1.00 lot 0.04 10.00 0.35

    2.00 Doors

    D-1 (2.10 x 0.80m) Steel Door(4 set) 72.24 sq.ft 20.00 4.00 80.00

    D-2 (2.10 x 0.70m) Steel Door(4 set) 63.21 sq.ft 20.00 4.00 80.00

    D-3 (2.10 x 0.60m) PVC Door(4 set) 55.72 sq.ft 20.00 4.00 80.00

    3.00 Windows

    W-1(1.40 x 1.70m) SCW w/ 3mm thick glass(4 set) 102.34 sq.ft 75.00 4.00 300.00

    W-2(1.00 x 1.70m) SCW w/ 3mm thick glass(2 set) 36.55 sq.ft 75.00 4.00 300.00

    W-3(1.00 x 1.15m) SCW w/ 3mm thick glass(2 set) 24.72 sq.ft 75.00 4.00 300.00

    W-4(0.60 x 0.40m) SCW w/ 3mm thick glass(4 set) 10.32 sq.ft 75.00 4.00 300.00

    4.00 Hardwares

    Cylindrical Keyed Lockset (Main & Service) 8.00 set 5.00 2.00 10.00

    Productivity Rate

    Capability Rate

    (per Day)

    Productivity Rate

    (per Day)

    No. of

    Manpower

    QtyNo UnitDescription

    90.00

  • 8/10/2019 BOQ for Productivity Rate

    4/7

    1.00 Water Lines 4.00 lot 0.25 4.00 1.00

    2.00 Sewer Lines 4.00 lot 0.25 4.00 1.00

    3.00 Plumbing Fixtures

    Water Closet and Lavatory 4.00 set 0.25 4.00 1.00

    Kitchen Sink 4.00 set 0.50 4.00 2.00

    Shower/Valve/Faucet 4.00 set 1.00 4.00 4.00

    Hose Bibb 4.00 pcs 1.00 4.00 4.00

    Water Meter 4.00 pcs 1.00 4.00 4.00

    4.00 Septic Tank 4.00 lot 0.25 4.00 1.00

    Sub-total VII

    VIII Electrical Works

    1.00 Pipes and Conduits 4.00 lot 0.25 4.00 1.00

    2.00 Wires and Cables 4.00 lot 0.25 4.00 1.00

    3.00 Electrical Fixtures 4.00 lot 0.50 4.00 2.00

    4.00 Panel Board 4.00 lot 1.00 2.00 2.00

    5.00 Service Entrance 4.00 lot 0.25 8.00 2.00

    Sub-total VIII

    Total Direct Cost

    Cost/sqm

    Total Cost + VAT

  • 8/10/2019 BOQ for Productivity Rate

    5/7

    Project : BellaVita Tapia

    Subject : Cost Estimate for Multipod Units Using Wall Form Tiles (JJM)

    Floor Area sqm

    I Preliminaries

    1.00 Preliminaries 4.00 lot

    Sub-total I

    II Site Works

    1.00 Clearing 90.00 sqm 10.00 3.00 30.00

    2.00 Lay-out/Staking 90.00 sqm 30.00 2.00 60.00

    3.00 Excavation 19.20 cum 1.33 6.00 7.98

    4.00 Backfilling 11.52 cum 3.87 1.00 3.87

    Sub-total II

    III Structural Works

    1.00 Footings

    Gravel Bedding 0.80 cum 3.87 1.00 3.87

    Reinforcement 280.00 kgs 112.00 8.00 896.00

    Concrete 10.00 cum 0.91 10.00 9.10

    Cement 90.00 bags

    Sand 5.00 cum

    Gravel 10.00 cum

    2.00 Slab

    Gravel Bedding 2.00 cum 3.87 1.00 3.87

    Reinforcement 230.00 kgs 112.00 8.00 896.00

    Concrete 6.32 cum 0.91 10.00 9.10

    Cement 56.88 bags

    Sand 3.16 cum

    Gravel 6.32 cum

    Floor Finishing/Topping 78.80 sqm 20.00 8.00 160.00

    3.00 Formworks 12.80 sqm 2.70 6.00 16.20

    Sub-total III

    IV Masonry Works

    1.00 Wall System

    Wall System 234.24 sqm

    Wall Form Tiles 2,372.00 pcs 20.00 10.00 200.00

    Cement (For Form Tiles Production) 160.00 bags

    GI Studs 272.00 pcs 10.00 10.00 100.00

    Reinforcement 704.00 kgs 112.00 3.00 336.00

    Cement (For Form Tiles Laying) 80.00 bags 0.91 10.00 9.10

    Sand 7.20 cum 0.08 10.00 0.75

    Gravel 14.40 cum 0.16 10.00 1.60

    Plastering at Corners 42.40 l.m. 1.33 10.00 13.30

    Reinforcement 180.00 kgs 1.33 10.00 13.30

    Concrete cum 0.91 10.00 9.10

    2.00 Formworks - sqm 2.70 12.00 32.40

    Sub-total IV

    V Metal Works

    1.00 Roof Framing 4.00 lot 0.25 4.00 1.00

    Sub-total V

    VI Architectural Works

    1.00 Roofing Works 1.00 lot 0.04 10.00 0.35

    2.00 Doors

    D-1 (2.10 x 0.80m) Steel Door(4 set) 72.24 sq.ft 20.00 4.00 80.00

    D-2 (2.10 x 0.70m) Steel Door(4 set) 63.21 sq.ft 20.00 4.00 80.00

    D-3 (2.10 x 0.60m) PVC Door(4 set) 55.72 sq.ft 20.00 4.00 80.00

    3.00 Windows

    W-1(1.40 x 1.70m) SCW w/ 3mm thick glass(4 set) 102.34 sq.ft 75.00 4.00 300.00

    W-2(1.00 x 1.70m) SCW w/ 3mm thick glass(2 set) 36.55 sq.ft 75.00 4.00 300.00

    W-3(1.00 x 1.15m) SCW w/ 3mm thick glass(2 set) 24.72 sq.ft 75.00 4.00 300.00

    W-4(0.60 x 0.40m) SCW w/ 3mm thick glass(4 set) 10.32 sq.ft 75.00 4.00 300.00

    4.00 Hardwares

    Cylindrical Keyed Lockset (Main & Service) 8.00 set 5.00 2.00 10.00

    90.00

    No Description Qty Unit Capability Rate

    (per Day)

    No. of

    Manpower

    Productivity Rate

    (per Day)

    Productivity Rate

  • 8/10/2019 BOQ for Productivity Rate

    6/7

    1.00 Water Lines 4.00 lot 0.25 4.00 1.00

    2.00 Sewer Lines 4.00 lot 0.25 4.00 1.00

    3.00 Plumbing Fixtures

    Water Closet and Lavatory 4.00 set 0.25 4.00 1.00

    Kitchen Sink 4.00 set 0.50 4.00 2.00

    Shower/Valve/Faucet 4.00 set 1.00 4.00 4.00

    Hose Bibb 4.00 pcs 1.00 4.00 4.00

    Water Meter 4.00 pcs 1.00 4.00 4.00

    4.00 Septic Tank 4.00 lot 0.25 4.00 1.00

    Sub-total VII

    VIII Electrical Works

    1.00 Pipes and Conduits 4.00 lot 0.25 4.00 1.00

    2.00 Wires and Cables 4.00 lot 0.25 4.00 1.00

    3.00 Electrical Fixtures 4.00 lot 0.50 4.00 2.00

    4.00 Panel Board 4.00 lot 1.00 2.00 2.00

    5.00 Service Entrance 4.00 lot 0.25 8.00 2.00

    Sub-total VIII

    Total Direct Cost

    Cost/sqm

    Total Cost + VAT

  • 8/10/2019 BOQ for Productivity Rate

    7/7

    ITEM Description

    Working

    Days Precedes

    A Clearing 2 B

    B Lay-out/Staking 1 C , E

    C Excavation 3 D

    D Backfilling & Compaction 3 f

    E Cutting and Bending of Rebars 5 -

    F Rough-Ins Plumbing, Water, & Electrical 4 G

    GInstallation of Rebars and Polyethylene Sheets

    for Footing & Slab3 H

    H Concrete Pouring 1 I

    I Masonry walls ( WFT ) 14 J , K , R

    J Installation of Battens 4 L

    K Installation of Rafters 4 L

    L Installation of Fascia Board 6 M , P , Q

    M Roofing Installation 3 N

    N Ceiling installation 8 OO Application Stucco & Skim coat Finish 8 S , T , U

    P Installaion Electrical Fixtures 16 V

    Q Installation of Plumbing Fixtures 11 V

    R Septic Tank 6 V

    S Painting Works 12 V

    T Installation of Windows 8 V

    U Installation of Doors 8 V

    V FINISH - -

    Week 1 Week 2 Week 3 Week 4 Week 5 W