8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
1/13
VENDOR VENDOR
No Material Item TOTAL PRICE TOTAL PRICE
STANDARD ELEVATED 1 M
A. GENSET FOUNDATION G STD G E1
TOTAL A Rp6,578,336 Rp10,865,691B. MONTHLY / BULK TANK FOUNDATION CAPACITY 1000 L T1 STD T1 E1
TOTAL B Rp3,213,908 Rp6,277,564
C. MONTHLY / BULK TANK FOUNDATION CAPACITY 3000 L T3 STD T3 E1
TOTAL C Rp6,717,189 Rp12,289,342
D. MONTHLY / BULK TANK FOUNDATION CAPACITY 5000 L T5 STD T5 E1
TOTAL D Rp6,717,189 Rp12,289,342
E. DOUBLE GENSET FOUNDATION DG STD DG E1
TOTAL E Rp10,459,065 Rp17,694,286
GRAND TOTAL (A+B+C+D+E) Rp33,685,686 Rp59,416,225
-
8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
2/13
VENDOR
TOTAL PRICE
ELEVATED 2 M
G E2
Rp8,250,152T1 E2
Rp5,769,607
T3 E2
Rp11,388,229
T5 E2
Rp11,388,229
DG E2
Rp11,997,701
Rp48,793,918
-
8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
3/13
BOQ - FOUNDATION - GENERAL DESIGNsites 1
16-Apr 16-Apr
No Material Item TYPE TYPE
A. GENSET FOUNDATION QTY QTY
G STD G E1
1 Site Preparation
a Site Clearing and grubbing, removal of scrubs, grass, and soft trees, 1.00 1.00
b Leveling & benchmark setting 1.00 1.00
2 Foundation Structure
a Soil Excavation & Compaction 6.60 12.71
b Sand fill (Thickness 150 mm) 0.56 0.45
c Aanstamping 1.11 1.29
d Stone masonry 3.44 8.30
e Concrete Floor (K-225) 1.65 1.83
f Land fill (compacted) 1.72 2.48
g Concrete layer (50mm) - -
h Stair (stone masonry) - -
i Finishing with cement plaster & black painting 14.05 19.85
TOTAL A - PER SITE
TOTAL
B. MONTHLY / BULK TANK FOUNDATION CAPACITY 1000 L
1 Foundation Structure
a Soil Excavation & Compaction 3.70 6.34
b Sand fill (Thickness 150 mm) 0.26 0.31
c Aanstamping 0.79 0.92
d Stone masonry 1.41 4.75e Concrete Floor (K-225) 1.20 1.35
f Land fill (compacted) 1.23 2.42
g Concrete layer (50mm) - -
h Stair to shelter (stone masonry) - -
i Finishing with cement plaster & black painting 8.00 13.00
TOTAL B - PER SITE
TOTAL
C. MONTHLY / BULK TANK FOUNDATION CAPACITY 3000 L
1 Foundation Structure
a Soil Excavation & Compaction 6.97 11.95b Sand fill (Thickness 150 mm) 0.50 0.58
c Aanstamping 1.49 1.74
d Stone masonry 2.66 8.96
e Concrete Floor (K-225) 2.80 2.95
f Land fill (compacted) 2.32 7.12
g Concrete layer (50mm) - -
h Stair to shelter (stone masonry) - -
i Finishing with cement plaster & black painting 17.12 24.92
-
8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
4/13
TOTAL C
TOTAL
D. MONTHLY / BULK TANK FOUNDATION CAPACITY 5000 L
1 Foundation Structure
a Soil Excavation & Compaction 6.97 11.95
b Sand fill (Thickness 150 mm) 0.50 0.58
c Aanstamping 1.49 1.74d Stone masonry 2.66 8.96
e Concrete Floor (K-225) 2.80 2.95
f Land fill (compacted) 2.32 7.12
g Concrete layer (50mm) - -
h Stair to shelter (stone masonry) - -
i Finishing with cement plaster & black painting 17.12 24.92
TOTAL D
TOTAL
E. DOUBLE GENSET FOUNDATION
1 Foundation Structurea Soil Excavation & Compaction 9.07 15.55
b Sand fill (Thickness 150 mm) 0.65 0.76
c Aanstamping 1.94 2.27
d Stone masonry 6.80 14.58
e Concrete Floor (K-225) 2.94 3.46
f Land fill (compacted) 3.83 10.24
g Concrete layer (50mm) - -
h Stair to shelter (stone masonry) - -
i Finishing with cement plaster & black painting 22.40 32.58
TOTAL E
TOTAL
GRAND TOTAL (A+B+C+D+E)
TERMS OF PAYMENT
CUBE TEST/MASTER MIX DESIGN
WARRANTY SERVICE
DELIVERY TERM
DELIVERY TIME
-
8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
5/13
UNIT PRICE STANDARD FOUNDATION ELEVATED 1M FOUNDATION
16-Apr 1 1 1
TYPE Unit VENDOR VENDOR VENDOR
QTY UNIT PRICE TOTAL PRICE TOTAL PRICE
G E2 G STD G E1
S1 S1
1.00 ls Rp3,189 Rp3,189 Rp3,189
1.00 ls Rp739,200 Rp739,200 Rp739,200
14.83 m3 Rp30,916 Rp204,043 Rp392,937
0.50 m3 Rp165,150 Rp92,484 Rp74,318
1.24 m3 Rp321,907 Rp356,351 Rp415,743
- m3 Rp680,065 Rp2,342,145 Rp5,646,241
4.59 m3 Rp1,572,000 Rp2,593,800 Rp2,878,725
3.70 m3 Rp26,580 Rp45,809 Rp65,905
- m3 Rp165,150 Rp- Rp-
- m3 Rp680,065 Rp- Rp-
26.02 m2 Rp100,080 Rp1,406,124 Rp1,986,588
Rp7,783,145 Rp12,202,846
SITES Rp7,783,145 Rp12,202,846
T1 STD T1 E1
6.34 m3 Rp30,916 Rp114,264 Rp195,881
0.30 m3 Rp165,150 Rp43,600 Rp50,866
0.90 m3 Rp321,907 Rp254,951 Rp297,442
- m3 Rp680,065 Rp957,532 Rp3,231,6703.73 m3 Rp1,572,000 Rp1,886,400 Rp2,122,200
3.42 m3 Rp26,580 Rp32,747 Rp64,217
- m3 Rp165,150 Rp- Rp-
- m3 Rp680,065 Rp- Rp-
20.00 m2 Rp100,080 Rp800,640 Rp1,301,040
Rp4,090,133 Rp7,263,317
SITES Rp4,090,133 Rp7,263,317
T3 STD T3 E1
14.04 m3 Rp30,916 Rp215,544 Rp369,5030.70 m3 Rp165,150 Rp82,245 Rp95,952
2.10 m3 Rp321,907 Rp480,929 Rp561,084
- m3 Rp680,065 Rp1,806,253 Rp6,096,104
7.04 m3 Rp1,572,000 Rp4,401,600 Rp4,637,400
8.19 m3 Rp26,580 Rp61,772 Rp189,356
- m3 Rp165,150 Rp- Rp-
- m3 Rp680,065 Rp- Rp-
40.12 m2 Rp100,080 Rp1,713,370 Rp2,493,994
-
8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
6/13
Rp8,761,712 Rp14,443,394
SITES Rp8,761,712 Rp14,443,394
T5 STD T5 E1
14.04 m3 Rp30,916 Rp215,544 Rp369,503
0.70 m3 Rp165,150 Rp82,245 Rp95,952
2.10 m3 Rp321,907 Rp480,929 Rp561,084- m3 Rp680,065 Rp1,806,253 Rp6,096,104
7.04 m3 Rp1,572,000 Rp4,401,600 Rp4,637,400
8.19 m3 Rp26,580 Rp61,772 Rp189,356
- m3 Rp165,150 Rp- Rp-
- m3 Rp680,065 Rp- Rp-
40.12 m2 Rp100,080 Rp1,713,370 Rp2,493,994
Rp8,761,712 Rp14,443,394
SITES Rp8,761,712 Rp14,443,394
D STD D1 E1
16.24 m3 Rp30,916 Rp280,466 Rp480,799
0.82 m3 Rp165,150 Rp107,017 Rp124,853
2.46 m3 Rp321,907 Rp625,788 Rp730,086
- m3 Rp680,065 Rp4,627,164 Rp9,915,351
7.09 m3 Rp1,572,000 Rp4,621,680 Rp5,434,797
10.47 m3 Rp26,580 Rp101,908 Rp272,232
- m3 Rp165,150 Rp- Rp-
- m3 Rp680,065 Rp- Rp-
43.20 m2 Rp100,080 Rp2,241,792 Rp3,260,606
Rp12,605,814 Rp20,218,725
SITES Rp12,605,814 Rp20,218,725
Rp42,002,516 Rp68,571,675
-
8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
7/13
ELEVATED 2M FOUNDATION 1.65
1
VENDOR
TOTAL PRICE
G E2
S1
Rp3,189
Rp739,200
Rp458,478
Rp82,575
Rp398,360
Rp-
Rp7,219,017
Rp98,452
Rp-
Rp-
Rp2,604,082
Rp11,603,353
Rp11,603,353
T1 E2
Rp195,881
Rp49,545
Rp289,716
Rp-Rp5,867,490
Rp90,797
Rp-
Rp-
Rp2,001,600
Rp8,495,030
Rp8,495,030
T3 E2
Rp434,055Rp115,605
Rp676,005
Rp-
Rp11,073,168
Rp217,624
Rp-
Rp-
Rp4,015,210
-
8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
8/13
Rp16,531,666
Rp16,531,666
T5 E2
Rp434,055
Rp115,605
Rp676,005Rp-
Rp11,073,168
Rp217,624
Rp-
Rp-
Rp4,015,210
Rp16,531,666
Rp16,531,666
D1 E2
Rp501,946
Rp135,258
Rp790,926
Rp-
Rp11,144,301
Rp278,293
Rp-
Rp-
Rp4,323,456
Rp17,174,179
Rp17,174,179
Rp70,335,895
-
8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
9/13
No Material Item Vol Unit Unit Price Total Price
1 Site Preparation
a1.00 ls Rp3,189 Rp3,189
b Leveling & benchmark setting 1.00 ls Rp739,200 Rp739,200
2 Foundation Structure
a Soil Excavation & Compaction 2.52 m3 Rp30,916 Rp77,907
b Sand fill (Thickness 50 mm) 0.18 m3 Rp165,150 Rp29,727
c Aanstamping 0.54 m3 Rp321,907 Rp173,830
d Stone masonry 1.68 m3 Rp680,065 Rp1,142,510
e Back filling with compaction 1.60 m3 Rp30,916 Rp49,465
f Concrete Floor (K-225) 0.27 m3 Rp1,729,200 Rp466,884
i Finishing with cement plaster & black painting 3.81 m2 Rp100,080 Rp381,305
TOTAL Rp3,064,016
Site Clearing and grubbing, removal of scrubs,grass, and soft trees,
-
8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
10/13
No Material Item Vol Unit Unit Price Total Price
1 Site Preparation
a1.00 ls Rp3,189 Rp3,189
b Leveling & benchmark setting 1.00 ls Rp739,200 Rp739,200
2 Foundation Structure
a Soil Excavation & Compaction 2.44 m3 Rp30,916 Rp75,434
b Sand fill (Thickness 150 mm) 0.48 m3 Rp165,150 Rp79,272
c Aanstamping 0.91 m3 Rp321,907 Rp292,936
d Stone masonry 2.88 m3 Rp680,065 Rp1,958,588
e Concrete Floor (K-225) 0.92 m3 Rp1,572,000 Rp1,440,974
f Land fill (compacted) 1.28 m3 Rp26,580 Rp34,022
gFinishing with cement plaster & black painting 7.81 m2 Rp100,080 Rp781,375
Total Rp5,404,989
Site Clearing and grubbing, removal of scrubs,grass, and soft trees,
-
8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
11/13
1.65
0.92
2.44 1.83
6.6 4.95
7.81
-
8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
12/13
BOQ - CUSTOM FOUNDATION 2x1,5m FOR HCPT
No Material Item QTY Unit UNIT PRICE TOTAL PRICE
1 Site Preparation
a
1.00 ls Rp3,189 Rp3,189
bLeveling & benchmark setting 1.00 ls Rp739,200 Rp739,200
2 Foundation Structure
aSoil Excavation & Compaction 2.64 m3 Rp30,916 Rp81,617
bSand fill (Thickness 50 mm) 0.22 m3 Rp170,000 Rp37,740
c Aanstamping (Thickness 150 mm)0.67 m3 Rp340,000 Rp226,440
d Stone masonry1.21 m3 Rp710,000 Rp857,680
e Concrete Floor (K-225)1.16 m3 Rp1,572,000 Rp1,815,660
f Land fill (compacted) 0.54m3 Rp26,580 Rp14,460
gFinishing with cement plaster & black painting 4.28 m2 Rp100,080 Rp428,342
Total Rp4,204,328
Site Clearing and grubbing, removal of scrubs,
grass, and soft trees,
-
8/14/2019 Boq - Foundation (General Smart) - 16 Apr 09
13/13
HPP PG 135KVA 2,2m x 4,8m
No Material Item QTY Unit UNIT PRICE TOTAL PRICE
1 Site Preparation
a 1.00 ls Rp3,189 Rp3,189
bLeveling & benchmark setting 1.00 ls Rp739,200 Rp739,200
2 Foundation Structure
aSoil Excavation & Compaction 8.45 m3 Rp30,916 Rp261,175
bSand fill (Thickness 50 mm) 0.42 m3 Rp170,000 Rp71,400
c Aanstamping (Thickness 150 mm)1.26 m3 Rp380,000 Rp478,800
d Stone masonry2.27 m3 Rp741,000 Rp1,683,552
e Concrete Floor (K-225)3.38 m3 Rp1,572,000 Rp5,312,102
f Land fill (compacted) 4.50m3 Rp26,580 Rp119,504
gFinishing with cement plaster & black painting 11.96 m2 Rp100,080 Rp1,196,957
Total Rp9,865,879
Site Clearing and grubbing, removal of scrubs,grass, and soft trees,