bow lake wind project - bluearth...
TRANSCRIPT
![Page 1: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/1.jpg)
Community Liaison Committee September 28, 2015
Bow Lake Wind Project
![Page 2: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/2.jpg)
Construction Activities
Phase I interconnection to the provincial
electrical grid completed communications system commissioning
completed testing and commissioning of the wind
turbines completed site restoration works initiated 17 bat roosting boxes were installed on
the project site this phase of the project was
commissioned in August
![Page 3: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/3.jpg)
Construction Activities
Phase II Negick Creek Bridge upgrade
completed (replaced old wooden bridge)
project roads completed wind turbine erection completed and
commissioning works nearing completion
collector and communications systems installation completed
O&M building construction initiated
![Page 4: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/4.jpg)
Transformer Station
![Page 5: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/5.jpg)
O&M Building
![Page 6: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/6.jpg)
Project Roads Negick Bridge
![Page 7: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/7.jpg)
Viewscape Changes
![Page 8: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/8.jpg)
Viewscape Changes
![Page 9: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/9.jpg)
Public Roads
• public use / access via Dump Rd. will be possible once the project is commissioned – this is a shared public road so as always use with caution
• It is not presently the project’s intention to plough and sand Dump Rd. during the heart of winter, unless operational or safety needs require such
• The intersection of 67 Rd and Trim Lake Rd will not be ploughed
![Page 10: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/10.jpg)
Project Site
![Page 11: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/11.jpg)
Hunting Restrictions
A hunting restriction, approved by the Ministry of Natural Resources and Forestry, was enacted in the vicinity of the Project
Hunting is prohibited from September 15 to December 31, 2015 in the areas adjacent to the project
![Page 12: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/12.jpg)
Thank You!
• As this will be the final meeting of the Bow Lake CLC, we wanted to express our thanks!
• We appreciate your participation and contributions over the past two years!
![Page 13: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/13.jpg)
Contact
1-844-214-2578 [email protected]
We remain committed to being a good neighbour. If you have any questions or comments about the project as we move in to the operations phase, please feel free to contact us.
![Page 14: Bow Lake Wind Project - BluEarth Renewablesbluearthrenewables.com/wp-content/uploads/2018/12/Bow...September 28, 2015 Bow Lake Wind Project Construction Activities Phase I interconnection](https://reader033.vdocument.in/reader033/viewer/2022042001/5e6d7843d4d2573a0a352709/html5/thumbnails/14.jpg)
Questions?