box girder 2
TRANSCRIPT
-
7/28/2019 Box Girder 2
1/8
Vol . 39 No. 2 2006Augu st
72
1. Introduction
New Carquinez Bridge was planned to replace the
First Carquinez Bridge constructed in 1927 as a part of
measures to improve the earthquake resistance of the
bridges around San Francisco Bay. The official name of
the new bridge is The Alfred Zampa Memorial Bridge.
It is a 3-span continuous suspension bridge with a
center span of 728 m and a total length of 1 055 m. Its
main tower is made of reinforced concrete, and the girder
is an orthotoropic box with steel (hereinafter called
OBG). The construction of this bridge was ordered by the
California Department of Transportation (hereinaftercalled Caltrans), and the order for the entire construction
was received by FCI Constructor Inc., Cleveland Bridge
California Inc., a joint venture (hereinafter called JV). IHI
received the order for fabrication and transportation of the
OBG from JV. Twenty-four units (standard unit mass
570 t, total OBG mass 12 722 t) divided in accordance
with the JV erection plan were fabricated at our Aichi
Works and transported to the site by sea.
This paper reports on the fabrication/transportation of
the OBG of this bridge undertaken by IHI.
2. Work outline
2.1 Project background
The New Carquinez Bridge completed in 2003 was a
third bridge constructed in parallel to the 2 cantilevertruss bridges (Fig. 2, Fig. 3) constructed in 1927 and
1958, respectively, over the Carquinez Strait (Fig. 1),
which is located approx. 30 km northeast of San
Francisco. California encountered such disasters as the
Sylmar Earthquake in 1971, the Loma Prieta Earthquake
in 1989, and the Northridge Earthquake in 1994. For this
reason, it conducted seismic analyses on all the bridges in
the state, including the two above-mentioned existing
bridges. It was concluded that the second bridge
constructed in 1958 could be used by reinforcing it to be
Fabrication and Transportation of Orthotropic Box Girder
for New Carquinez Bridge
YANAGIHARA Masahiro : Manager, Overseas Project Department, Bridge & Road Construction
Division, Logistics Systems & Structures
KIDA Akihiro : Manager, Manufacturing Department, Chita Works, IHI SA Technology
Co., Ltd.
YAMANE Mitsuhiro : Messina Project Department, Bridge & Road Construction Division,
Logistics Systems & Structures
NAKAYAMA Takeshi : Overseas Project Department, Bridge & Road Construction Division,
Logistics Systems & Structures
MURATA Shinji : Manufacturing Department, Aichi Works, Manufacturing Division,
Logistics Systems & Structures
IHI obtained the subcontract for fabrication and delivery to the site of orthotropic box girders for the suspension
bridge, which was constructed to replace the existing bridge over the Carquinez Strait in the vicinity of San Francisco. A
total of 12 700 t steel structures was fabricated in Aichi works and transported across the Pacific Ocean. With technical
trials and investigations, IHI succeeded in fulfilling the clients high quality requirements and won satisfaction from the
general contractor and the owner. With regards to ocean transportation, which was done with double stacking of heavy
units and across the Pacific Ocean in winter, all three voyages were successful to deliver on time with no problem.
Fig. 1 Site location
ErectionLocation
-
7/28/2019 Box Girder 2
2/8
earthquake-resistant but that the first bridge constructed
in 1927 would not have sufficient earthquake resistance
even with reinforcement. It was therefore decided to
replace it with the third bridge. As a replacement, the
same cantilever truss bridge as the old bridge, a double-arch type, and a cable-stay type were cited as candidates,
but finally the 3-span continuous suspension bridge was
adopted. It was the first modern suspension bridge
constructed in the U.S. after the Chesapeake Bridge
was built in 1973.
The new bridge was named after Mr. Alfred Zampa,
who made remarkable contributions as an iron worker to
the bridge construction work in this area, including the
Oakland Bay Bridge, the Benecia Bridge, the
Richmond San-Rafael Bridge, and the Golden Gate
Bridge since the construction of the First Carquinez
Bridge in 1927.2.2 Bid
The schedule from the date of invitation for bids to
ordering is shown below.
Date advertised August 23, 1999
Bid open January 13, 2000
Lowest price $187 837 346
Date order placed with general contractor
January 28, 2000Date fabrication order placed with IHI
April 15, 2000
This construction work was paid for out of only the
state and local budgets without any federal funds. For this
reason, the Buy America provisions were not applied to
the steel products, including the OBGs and cables.
2.3 Contract outline
The main contractors of this construction work are shown
below. In concluding the agreement, Caltrans made it
mandatory for JV to provide a 50% performance bond
and a 50% payment bond.(1) JV issued a 100% payment
bond exclusively to IHI, and IHI issued a 100%performance guarantee to JV.
Owner Caltr ans (California Department of
Transportation)
Designer Deleuw Cather, OPAC, Steinman
General contractor
FCI Constructor Inc., Cleveland Bridge
California Inc., a JV
Fabrication of OBG
Ishikawajima-Harima Heavy Industries
Co., Ltd.
Transportation
Ishikawajima-Harima Heavy IndustriesCo., Ltd.
Delivery terms of IHI Subcontract
DDP, Incorterms 2000(2)
The California State Public Contract Code (1) prohibits
placing an order with a subcontractor without a
performance capability. The general contractor must
submit the company names of the main subcontractors.
2.4 Bridge outline(3),(4)
Figure 4 shows the general drawing of the bridge, and the
bridge specifications are shown below.
Bridge type 3-span continuous suspension bridge
Span length 183 m + 728 m + 148 mEffective width
25 m (4 lanes + side strip + sidewalk)
Main tower Made of reinforced concrete, 131 m in
height, installed through multi-tiered
self-climbing form system, 1 cycle = 4 m
in height, shortest term 2 days/cycle
Cable Wire 5 mm in diameter (made in U.K.)
8 584 wires/cable, 232 wires/strand,
mass about 1 t/coil. The aerial spinning
method was used, and wires were
pulled out during spinning so that 15%
of the dead weight was loaded on thecatwalk. The wire tension was
controlled by a computer.
Fig. 3 Site photo after demolishment of1st Carquinez Bridge
Fig. 2 Site photo after completion ofNew Carquinez Bridge
New Carquinez Bridge First Carquinez Bridge Second Carquinez Bridge
New Carquinez Bridge Second Carquinez Bridge
73
Vol . 39 No . 2 2006Au gu st
-
7/28/2019 Box Girder 2
3/8
Vol . 39 No. 2 2006Augu st
74
Wrapping Galvanized round steel wire of 3.5 mm
Coating Zinc paste + acrylic polymer coating
(3 layers)
Girder Orthotropic steel deck mono-box girder
(total mass: 12 722 t)
The OBG was the first of its type to be
used for a U.S. suspension bridge
Foundation Steel pipe piles
Diameter 3 m. Total length 6 030 m.
Bedrock abou t --50 m. Fo oting is
precast footing manufactured at afactory near the site.
Pavement Waterproof layer + Trinidad lake
asphalt
2.5 Construction schedule
Table 1 shows the entire construction schedule of this
work.
3. Design
3.1 Design outline(4),(5)
The design outline is shown below. The detailed design
was made by Deleuw Cather, OPAC, Steinman as
described above, and IHI was not directly involved in thedetailed design.
(1) Design method
For the OBG and main tower, the AASHTO LRFD
(load and resistance factor design method) was
adopted, and for the cables, ASD (allowable stress
design method) was adopted.
(2) Design live load
The design live load was based on the standards of
AASHTO (American Association of State Highway
and Transportation Officials).
(3) Earthquake-resistant design
No damage by earthquake of recurrence interval300 years and traffic secured against earthquake of
1 000 to 2 000 years.
(4) Wind resistance design
No damage by wind of recurrence interval 100
years.
(5) Fatigue design characteristics
For trough rib welding, penetration of 80 to 100%
was secured (melt-through was not allowed). The
shape of trough rib scallop is devised.
(6) Painting
Waterborn inorganic zincrich of painting 100 to 200
m was used for the inner surface, and waterborninorganic zincrich painting 100 to 200 m + latex
Fig. 4 General drawing of the bridge (unit : mm)
147 000 728 000
1 056 000
181 000
2000 2001 2002 2003 2004
1 2 3 4 5 6 7 8 9 1011 12 1 2 3 4 5 6 7 8 9 1011 12 1 2 3 4 5 6 7 8 9 1011 12 1 2 3 4 5 6 7 8 9 1011 12 1 2 3 4 5
Foundation, tower
Cable erection
Fabrication of OBG
Erection of OBG
On-deck work
Year
Itemmonth
Table 1 Construction schedule
-
7/28/2019 Box Girder 2
4/8
(rubber type) paint 100 to 200 m for the outer
surface.
3.2 Shop drawing
IHI received orders for both the fabrication and
transportation for this project and prepared the shop
drawings. Figure 5 shows the procedure for preparing theshop drawing.
The U.S. shop drawing is the last document to be
approved by the Engineer before fabrication was started,
and the inspection for the full-size drawing in Japan was
not conducted. Data for weld shrinkage and accessories
installation had to be included in the shop drawings.
Another characteristic of the American shop drawing is
that it contains the data of assembling sequence. Adding
such data, about 1 300 shop drawings were prepared in
this work.
4. Fabrication
4.1 Outline
The OBG was fabricated at our Aichi Works. The factory
was required to be qualified for major bridges, fracture
critical, and sophisticated paint of the categories of
American Institute of Steel Construction (AISC) and to
pass a Caltrans audit. In accordance with the erection
plan, the OBG was divided into 24 units. Segments with
the size of 1/3 unit were fabricated in the shop and
welded/bolted together into one unit on a leveled stage in
the shop yard. Then units were trial-assembled. From 4 to
8 Caltrans engineers and inspectors, and 1 to 3 JV
engineers were always at the workshop to inspect/controlthe work during the whole fabrication period.
4.2 Fabrication standards
The following specifications were applied to the project.
Standard specifications
State of California Business, Transportation and
Housing Agency Department of Transportation
1999.
Special Provisions for Construction on State
Highway in San Francisco County in San Francisco
from 0.6 km to 1.3 km East of the Yerba Buena
Tunnel East Portal
AWS D1.5 (1996)
4.3 Steel
The main steel is ASTM A709M Gr345T2 (JIS :
SM490Y equivalent). Check samples were cut out and
tested for each plate thickness and heat to confirm
mechanical property of the steel.
4.4 Welding, heat straightening4.4.1 Approval of welding
The specifications and AWS code were strictly applied to
the welding work. To meet the specifications QCP
(Quality Control procedures) had to be submitted for the
owners approval. This includes the procedures of
welding, inspection and non-destructive test for every
welding method. Especially AWS D1.5 was strictly
applied to the welding method. WPS (Welding Procedure
Specification) was required for all the welding operations.
Welding tests for obtaining the essential WPS variables
and for supporting WPS were executed. The results of
latter were recorded as PQR (Procedure QualificationRecord). Since the welding procedure depend on the
welding location, welding process and welding position,
124 tests for WPS and 62 tests for PQR were conducted.
These will be valuable assets for Aichi Works in future
projects. Welder qualification tests were also performed
in accordance with AWS D1.5. A total of 130 welders
including tack welders got qualification eventually.
4.4.2 Welding quality control
During the whole fabrication period severe quality control
was required especially for welding. Four resident
welding inspectors dispatched from Caltrans were present
in the workshop to check all welding activities. Since thespecifications required that an AWS-CWI, certified
welding inspector, and an AWS-CAWI, certified assistant
welding inspector, control the welding operation at the
workshop without leaving for more than 30 minutes,
some people needed to get such qualifications quickly
prior to commencement of the project. Five people
obtained CWI qualifications and controlled welding work
together with CAWI.
4.4.3 Heat straightening
Welding distortion was minimized by providing pre-
camber with the components prior to welding to minimize
heat input during heat straightening operations. Theamount of deformation of all components (approx. 1 300
pieces) was surveyed and recorded before/after heat
straightening. Moreover the actual heat locations had to
be recorded.
4.5 Panel assembly
For the trough rib welding to the both deck and bottom
plates, 80% penetration for the trough rib plate thickness
was required. Since melt through was not acceptable,
welding penetration had to be controlled to between 80
and 100%. To satisfy this requirement, welding tests were
repeated. One year was spent to obtain the owners
approval, including coping with the additional qualityrequirements. As the non-destructive inspection, 15% of
the welding length was inspected by UT (Ultrasonic
Fabricationprocedure
Approval
Weldingprocedure
Specificationclarification (RFI)
Welding data(shrinkage, WPS)
description
Solution of designproblems
Panel dimensionsdescription
Start of shopdrawing work
Development fromassembly drawing to
single-component
Fig. 5 Procedure of shop drawing
75
Vol . 39 No . 2 2006Au gu st
-
7/28/2019 Box Girder 2
5/8
Vol . 39 No. 2 2006Augu st
76
Test). But if a defect was found, 100% of the welding
length was required to be inspected by UT for all the
trough ribs of the panel where the defect was found. A
smooth weld profile was required, and the allowable
underfill value of less than 0.25 mm was specified.
Figure 6 shows a welding macro. Trough rib welding wasexecuted after the trough ribs were tack welded to the
skin plate with a gap of less than 0.6 mm. Since tack
welds interfered with the penetrations of the final
welding, resulting in incomplete penetration, the size of
tack weld was reduced to the extent that no tack weld
would be cracked due to the welding distortion during the
final welding, and tack welds were ground off to be thin
enough before the final welding. As to the welding
process, various experiments and tests were repeated,
confirming that SAW (Submerged Arc Welding) satisfied
the aforementioned specifications and owners
requirements. Figure 7 shows the welding work. Panel-to-panel seam-welding was done by one side submerged
arc welding (FCB method). Since this welding method
was not in the AWS code, many tests and documents
were required to obtain the owners approval. High
evaluation was finally obtained from the owner because
FCB welding method does provide less distortion, fewer
defects and stable quality.
4.6 Shop yard assembly, trial assembly
It had to be proved that no effect of twisted deformation
remained in the OBG unit after three segments were
welded together at the unit assembly stage. The welding
sequence was set to minimize twisted deformation andsuch deformation was monitored by a system to display
real-time reaction fluctuation at 24 supporting points
during welding. This monitoring confirmed that through
dimensional control and reaction control the amount of
twisted deformation was kept within the allowable range
and proved that there were no ill effects. To keep the
temperature difference within 4 throughout a unit
during works, temporary tent-roofs were installed.Temperature rises of the OBG due to the direct rays of the
sun were minimized, and the OBG temperature became
stable in shorter time in the evening. That enabled us to
continue the work on the night shift in allowable
temperature conditions. To obtain the root gap of the site
joint and unit length within the specified range in the trial
assembly, the site joint area was required to be trimmed
after completion of shop assembly for each unit. The
trimming amount and trimming lines was checked in the
presence of the JV inspectors before the trial assembly.
During the trial assembly, Caltrans inspectors
independently took a survey the unit using threedimensional measuring equipment at the same time and
measuring points as IHIs. They checked if the difference
of survey results between Caltrans and IHI was within 1
mm (maximum 2 mm). After confirming that the
difference was within allowable range, the site joint
portion of trough ribs was allowed to be drilled. The
necessary numbers of drift pins had to be driven into
holes before dawn. Then the root gap of the site joint and
joint fitting were inspected by the JV inspectors under
the very tight schedule. By strictly implementing the
welding sequence, dimensional control, reaction control
and temperature control, the accuracy of deck elevationand longitudinal alignment, and elevation at the center of
the pin hole for hanger fixing were kept within 2.5
mm/50 m and 3.0 mm/100 m, respectively, meeting the
owners requirements.
4.7 Painting
The use of water-based paint was specified in terms of the
regulation of VOC (Volatile Organic Compound). The
first coat of waterborne inorganic zinc rich paint (100 -
200 m) was applied to the interior and exterior surfaces
at the shop. Painting work was performed in a paint shop
whose atmospheric conditions were controlled to satisfy
the severe requirements such as 7 to 29 for the ambienttemperature limit. Four MPa for the required minimum
value of adhesion was successfully obtained eventually.Fig. 6 Photo of cross section of trough rib welding (unit : mm)
Trough rib24 850
88
Underfill:notmorethan0.2
Controlledwithin1.6
Melt-through: not allowed
305
8
356
Penetration: 6.4 or higher (not more than 8)
Fig. 7 Welding work on panel assembly
-
7/28/2019 Box Girder 2
6/8
5. Transportation
5.1 Outline
The total number of OBG units was 24, and 8 units were
transported at one time at the owners request. To
minimize transportation cost, the OBG units were double-stacked, upper and lower, so that 8 units per voyage could
be transported by one ship. Since the owners
specification prohibited direct stacking of OBG units,
special frames were installed on the hull deck to separate
the upper and lower tier (Fig. 8).
Because of the owners delivery time requirement, it
was difficult to use one ship for 3 voyages, and 3 ships
were therefore chartered from ZPMC Shipping affiliated
with ZPMC in Shanghai (China). The order for the
fabrication of the transportation frames was given to
ZPMC. Forwarder services in Japan and the U.S., a ship
chartering agency service and mooring work wereundertaken by Giyu Kaium Co., Ltd. (Japan).
The average number of navigation days per ship was
about 20.
5.2 Shipping
The OBG of standard unit mass 570 t was loaded by dual
lift of 2 goliath cranes of Aichi Works. Since the trial
assembly direction was different from the loading
direction on the hull, each unit was turned 90 with 4
dollies. Figure 9 and Fig. 10 show the loading and
turning, respectively.
The OBG units were lashed using fastening jigs
installed as part of the frames around the receiving pointof all the transportation frames.
5.3 Marine transportation
The OBG units were each 29 m wide 49.6 m long, and
each unit was loaded sideways across the hull in order to
stack 8 units per ship in two tiers. As a result, the OBG
units overhung about 9 m from both sides of the hull, and
there was the possibility of the overhung portion being
damaged by waves during transportation. For this reason,
the OBG units were raised 6 m above the hull deck by
means of a transportation frame structure, and the Hawaii
route, where waves are relatively mild, was selected.
Hull movement during transportation was numerically
analyzed with the cooperation of IHIs Research
Laboratory, and then we reported on the effects on the
OBGs during transportation with the loading method and
transportation route to the owner for their prior approval.
Figure 11 shows the transportation routes of the 3 ships.
To prevent corrosion of the inner surface of the OBGs
due to waves and wind/rain, the openings at both ends ofthe OBGs was closed watertight with a canvas sheet
capable of withstanding wind velocity of 60 m/s in
consideration of stormy weather and long transportation
period.
5.4 Mooring at site and erection
The OBG units were directly unloaded from the
transportation ship and erected except for some OBG
units requiring transhipping onto smaller barges because
of the inaccessibility to unloading point for the ships.
Thus each time a unit was erected, the transportation ship
was brought under the bridge from the standby site and
moored with 4 anchors installed in advance in the seaarea. For this mooring operation, winches were locally
installed on the hull deck. Since the ships were moored inFig. 8 Transportation ship with deck units doubly stacked
(first shipment)
Fig. 10 Horizontal turning of unit
Fig. 9 Loading unit onto ship
77
Vol . 39 No . 2 2006Au gu st
-
7/28/2019 Box Girder 2
7/8
Vol . 39 No. 2 2006Augu st
78
a navigation channel, a local pilot boarded the ships, and
they were positioned using a tugboat and moored in
accordance with his instructions. During mooring, theposition was checked by JV by means of optical
surveying instruments from the land. Figure 12 shows the
releasing of anchor lines.
The erection was made at low tide when the tide was
starting to rise. This was done to avoid hull movement
during hoisting operation and prevent the OBG load from
being unintentionally loaded on to the hoisting equipment
when the hull lowers due to the ebbing of the tide. Since
the OBG units were installed on the hull at a narrow
clearance of 1.5 m, hoisting guides were provided to
prevent collision during erection. But neither hoisted unit
nor hull moved horizontally during hoisting, because theships were positioned with high accuracy.
Because the coast guard did not allow the
transportation ship to be moored under the bridge for
standby within the navigation channel, they moved after
every erection to an open mooring area near the site for
standby. At the standby site, they were kept moored with
4 anchors as a safety measure for other marine traffic
because the space was limited.
The erection undertaken by JV was made using 4
strand jacks installed in advance on the OBG at the
standby site. After the erection was completed, strand
jacks were transported by barge to the standby site toprepare for the erection of the following OBG unit.
Figure 13 shows the erection of OBG. For the erection
operation, the mooring position was checked first, and
then the strand end of each jack was picked up from the
catwalk by means of a winch and fixed to the temporary
clamps installed in advance on the main cable, and the
ship position was checked again. Then the OBG was
hoisted through jack operation while the load balance was
checked.
Four strand jacks and all the equipment including
power pack were placed on the OBG, and the hoisting
operation was done in a concentrated way by means of awired remote controller from the transportation ship or
catwalk. For one strand jack, 19 galvanized PC steel
strands of 18 mm in diameter were used. Some units weremoved horizontally in the air because of site conditions.
This horizontal movement was made by means of load
shifting between 2 sets of strand jacks (2 4 uni ts)
(Fig. 14).
6. Conclusion
The fabrication and transportation of OBG for the New
Carquinez Bridge were outlined above. Under a severe
delivery schedule, we, including factory workers and
project group, united to perform the operations, and as a
result made the delivery on schedule. We intend to utilize
the technologies and experiences accumulated through thesevere conditions and schedule for this project for our
future overseas projects.
150E 165E 180E40N
35N
30N
165W 150W 135W
Japan
U.S.
20N
Tropic of cancer
: First ship
: Second ship
: Third ship
Fig. 12 Releasing of anchor lines with tug boats
Fig. 11 Sea transportation routes (actual)
Fig. 13 Lifting up of unit
-
7/28/2019 Box Girder 2
8/8
Acknowledgments
In implementing this project, we received much guidance
and cooperation from people both inside and outside IHI.
We hereby express our heartfelt thanks to them.
REFERENCES
(1) State of California, Department of Transportation :Standard Specification 1999 (1999)
(2) International Chamber of Commerce : International
Commercial Terms 2000 (2000)
(3) California Department of Transportation : Spanning
the Carquinez Strait (2003)
(4) M. Marquez, R. W. Wolfe and E. Thimmhardy :
New Carquinez Strait Suspension Bridge, San
Francisco, California, Structural Engineering
International Vol.13 No.2 (2003)
(5) Thomas Spoth and H. Ohashi : Design of the New
Carquinez Bridge, Bridge and Foundation
Engineering Vol.35 No.6 June 2001 pp.17-25
79
Vol . 39 No . 2 2006Au gu st
Fig. 14 Traversing status of unit performed by load shifting
under hoisted condition