box girder 2

Upload: steelage

Post on 03-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Box Girder 2

    1/8

    Vol . 39 No. 2 2006Augu st

    72

    1. Introduction

    New Carquinez Bridge was planned to replace the

    First Carquinez Bridge constructed in 1927 as a part of

    measures to improve the earthquake resistance of the

    bridges around San Francisco Bay. The official name of

    the new bridge is The Alfred Zampa Memorial Bridge.

    It is a 3-span continuous suspension bridge with a

    center span of 728 m and a total length of 1 055 m. Its

    main tower is made of reinforced concrete, and the girder

    is an orthotoropic box with steel (hereinafter called

    OBG). The construction of this bridge was ordered by the

    California Department of Transportation (hereinaftercalled Caltrans), and the order for the entire construction

    was received by FCI Constructor Inc., Cleveland Bridge

    California Inc., a joint venture (hereinafter called JV). IHI

    received the order for fabrication and transportation of the

    OBG from JV. Twenty-four units (standard unit mass

    570 t, total OBG mass 12 722 t) divided in accordance

    with the JV erection plan were fabricated at our Aichi

    Works and transported to the site by sea.

    This paper reports on the fabrication/transportation of

    the OBG of this bridge undertaken by IHI.

    2. Work outline

    2.1 Project background

    The New Carquinez Bridge completed in 2003 was a

    third bridge constructed in parallel to the 2 cantilevertruss bridges (Fig. 2, Fig. 3) constructed in 1927 and

    1958, respectively, over the Carquinez Strait (Fig. 1),

    which is located approx. 30 km northeast of San

    Francisco. California encountered such disasters as the

    Sylmar Earthquake in 1971, the Loma Prieta Earthquake

    in 1989, and the Northridge Earthquake in 1994. For this

    reason, it conducted seismic analyses on all the bridges in

    the state, including the two above-mentioned existing

    bridges. It was concluded that the second bridge

    constructed in 1958 could be used by reinforcing it to be

    Fabrication and Transportation of Orthotropic Box Girder

    for New Carquinez Bridge

    YANAGIHARA Masahiro : Manager, Overseas Project Department, Bridge & Road Construction

    Division, Logistics Systems & Structures

    KIDA Akihiro : Manager, Manufacturing Department, Chita Works, IHI SA Technology

    Co., Ltd.

    YAMANE Mitsuhiro : Messina Project Department, Bridge & Road Construction Division,

    Logistics Systems & Structures

    NAKAYAMA Takeshi : Overseas Project Department, Bridge & Road Construction Division,

    Logistics Systems & Structures

    MURATA Shinji : Manufacturing Department, Aichi Works, Manufacturing Division,

    Logistics Systems & Structures

    IHI obtained the subcontract for fabrication and delivery to the site of orthotropic box girders for the suspension

    bridge, which was constructed to replace the existing bridge over the Carquinez Strait in the vicinity of San Francisco. A

    total of 12 700 t steel structures was fabricated in Aichi works and transported across the Pacific Ocean. With technical

    trials and investigations, IHI succeeded in fulfilling the clients high quality requirements and won satisfaction from the

    general contractor and the owner. With regards to ocean transportation, which was done with double stacking of heavy

    units and across the Pacific Ocean in winter, all three voyages were successful to deliver on time with no problem.

    Fig. 1 Site location

    ErectionLocation

  • 7/28/2019 Box Girder 2

    2/8

    earthquake-resistant but that the first bridge constructed

    in 1927 would not have sufficient earthquake resistance

    even with reinforcement. It was therefore decided to

    replace it with the third bridge. As a replacement, the

    same cantilever truss bridge as the old bridge, a double-arch type, and a cable-stay type were cited as candidates,

    but finally the 3-span continuous suspension bridge was

    adopted. It was the first modern suspension bridge

    constructed in the U.S. after the Chesapeake Bridge

    was built in 1973.

    The new bridge was named after Mr. Alfred Zampa,

    who made remarkable contributions as an iron worker to

    the bridge construction work in this area, including the

    Oakland Bay Bridge, the Benecia Bridge, the

    Richmond San-Rafael Bridge, and the Golden Gate

    Bridge since the construction of the First Carquinez

    Bridge in 1927.2.2 Bid

    The schedule from the date of invitation for bids to

    ordering is shown below.

    Date advertised August 23, 1999

    Bid open January 13, 2000

    Lowest price $187 837 346

    Date order placed with general contractor

    January 28, 2000Date fabrication order placed with IHI

    April 15, 2000

    This construction work was paid for out of only the

    state and local budgets without any federal funds. For this

    reason, the Buy America provisions were not applied to

    the steel products, including the OBGs and cables.

    2.3 Contract outline

    The main contractors of this construction work are shown

    below. In concluding the agreement, Caltrans made it

    mandatory for JV to provide a 50% performance bond

    and a 50% payment bond.(1) JV issued a 100% payment

    bond exclusively to IHI, and IHI issued a 100%performance guarantee to JV.

    Owner Caltr ans (California Department of

    Transportation)

    Designer Deleuw Cather, OPAC, Steinman

    General contractor

    FCI Constructor Inc., Cleveland Bridge

    California Inc., a JV

    Fabrication of OBG

    Ishikawajima-Harima Heavy Industries

    Co., Ltd.

    Transportation

    Ishikawajima-Harima Heavy IndustriesCo., Ltd.

    Delivery terms of IHI Subcontract

    DDP, Incorterms 2000(2)

    The California State Public Contract Code (1) prohibits

    placing an order with a subcontractor without a

    performance capability. The general contractor must

    submit the company names of the main subcontractors.

    2.4 Bridge outline(3),(4)

    Figure 4 shows the general drawing of the bridge, and the

    bridge specifications are shown below.

    Bridge type 3-span continuous suspension bridge

    Span length 183 m + 728 m + 148 mEffective width

    25 m (4 lanes + side strip + sidewalk)

    Main tower Made of reinforced concrete, 131 m in

    height, installed through multi-tiered

    self-climbing form system, 1 cycle = 4 m

    in height, shortest term 2 days/cycle

    Cable Wire 5 mm in diameter (made in U.K.)

    8 584 wires/cable, 232 wires/strand,

    mass about 1 t/coil. The aerial spinning

    method was used, and wires were

    pulled out during spinning so that 15%

    of the dead weight was loaded on thecatwalk. The wire tension was

    controlled by a computer.

    Fig. 3 Site photo after demolishment of1st Carquinez Bridge

    Fig. 2 Site photo after completion ofNew Carquinez Bridge

    New Carquinez Bridge First Carquinez Bridge Second Carquinez Bridge

    New Carquinez Bridge Second Carquinez Bridge

    73

    Vol . 39 No . 2 2006Au gu st

  • 7/28/2019 Box Girder 2

    3/8

    Vol . 39 No. 2 2006Augu st

    74

    Wrapping Galvanized round steel wire of 3.5 mm

    Coating Zinc paste + acrylic polymer coating

    (3 layers)

    Girder Orthotropic steel deck mono-box girder

    (total mass: 12 722 t)

    The OBG was the first of its type to be

    used for a U.S. suspension bridge

    Foundation Steel pipe piles

    Diameter 3 m. Total length 6 030 m.

    Bedrock abou t --50 m. Fo oting is

    precast footing manufactured at afactory near the site.

    Pavement Waterproof layer + Trinidad lake

    asphalt

    2.5 Construction schedule

    Table 1 shows the entire construction schedule of this

    work.

    3. Design

    3.1 Design outline(4),(5)

    The design outline is shown below. The detailed design

    was made by Deleuw Cather, OPAC, Steinman as

    described above, and IHI was not directly involved in thedetailed design.

    (1) Design method

    For the OBG and main tower, the AASHTO LRFD

    (load and resistance factor design method) was

    adopted, and for the cables, ASD (allowable stress

    design method) was adopted.

    (2) Design live load

    The design live load was based on the standards of

    AASHTO (American Association of State Highway

    and Transportation Officials).

    (3) Earthquake-resistant design

    No damage by earthquake of recurrence interval300 years and traffic secured against earthquake of

    1 000 to 2 000 years.

    (4) Wind resistance design

    No damage by wind of recurrence interval 100

    years.

    (5) Fatigue design characteristics

    For trough rib welding, penetration of 80 to 100%

    was secured (melt-through was not allowed). The

    shape of trough rib scallop is devised.

    (6) Painting

    Waterborn inorganic zincrich of painting 100 to 200

    m was used for the inner surface, and waterborninorganic zincrich painting 100 to 200 m + latex

    Fig. 4 General drawing of the bridge (unit : mm)

    147 000 728 000

    1 056 000

    181 000

    2000 2001 2002 2003 2004

    1 2 3 4 5 6 7 8 9 1011 12 1 2 3 4 5 6 7 8 9 1011 12 1 2 3 4 5 6 7 8 9 1011 12 1 2 3 4 5 6 7 8 9 1011 12 1 2 3 4 5

    Foundation, tower

    Cable erection

    Fabrication of OBG

    Erection of OBG

    On-deck work

    Year

    Itemmonth

    Table 1 Construction schedule

  • 7/28/2019 Box Girder 2

    4/8

    (rubber type) paint 100 to 200 m for the outer

    surface.

    3.2 Shop drawing

    IHI received orders for both the fabrication and

    transportation for this project and prepared the shop

    drawings. Figure 5 shows the procedure for preparing theshop drawing.

    The U.S. shop drawing is the last document to be

    approved by the Engineer before fabrication was started,

    and the inspection for the full-size drawing in Japan was

    not conducted. Data for weld shrinkage and accessories

    installation had to be included in the shop drawings.

    Another characteristic of the American shop drawing is

    that it contains the data of assembling sequence. Adding

    such data, about 1 300 shop drawings were prepared in

    this work.

    4. Fabrication

    4.1 Outline

    The OBG was fabricated at our Aichi Works. The factory

    was required to be qualified for major bridges, fracture

    critical, and sophisticated paint of the categories of

    American Institute of Steel Construction (AISC) and to

    pass a Caltrans audit. In accordance with the erection

    plan, the OBG was divided into 24 units. Segments with

    the size of 1/3 unit were fabricated in the shop and

    welded/bolted together into one unit on a leveled stage in

    the shop yard. Then units were trial-assembled. From 4 to

    8 Caltrans engineers and inspectors, and 1 to 3 JV

    engineers were always at the workshop to inspect/controlthe work during the whole fabrication period.

    4.2 Fabrication standards

    The following specifications were applied to the project.

    Standard specifications

    State of California Business, Transportation and

    Housing Agency Department of Transportation

    1999.

    Special Provisions for Construction on State

    Highway in San Francisco County in San Francisco

    from 0.6 km to 1.3 km East of the Yerba Buena

    Tunnel East Portal

    AWS D1.5 (1996)

    4.3 Steel

    The main steel is ASTM A709M Gr345T2 (JIS :

    SM490Y equivalent). Check samples were cut out and

    tested for each plate thickness and heat to confirm

    mechanical property of the steel.

    4.4 Welding, heat straightening4.4.1 Approval of welding

    The specifications and AWS code were strictly applied to

    the welding work. To meet the specifications QCP

    (Quality Control procedures) had to be submitted for the

    owners approval. This includes the procedures of

    welding, inspection and non-destructive test for every

    welding method. Especially AWS D1.5 was strictly

    applied to the welding method. WPS (Welding Procedure

    Specification) was required for all the welding operations.

    Welding tests for obtaining the essential WPS variables

    and for supporting WPS were executed. The results of

    latter were recorded as PQR (Procedure QualificationRecord). Since the welding procedure depend on the

    welding location, welding process and welding position,

    124 tests for WPS and 62 tests for PQR were conducted.

    These will be valuable assets for Aichi Works in future

    projects. Welder qualification tests were also performed

    in accordance with AWS D1.5. A total of 130 welders

    including tack welders got qualification eventually.

    4.4.2 Welding quality control

    During the whole fabrication period severe quality control

    was required especially for welding. Four resident

    welding inspectors dispatched from Caltrans were present

    in the workshop to check all welding activities. Since thespecifications required that an AWS-CWI, certified

    welding inspector, and an AWS-CAWI, certified assistant

    welding inspector, control the welding operation at the

    workshop without leaving for more than 30 minutes,

    some people needed to get such qualifications quickly

    prior to commencement of the project. Five people

    obtained CWI qualifications and controlled welding work

    together with CAWI.

    4.4.3 Heat straightening

    Welding distortion was minimized by providing pre-

    camber with the components prior to welding to minimize

    heat input during heat straightening operations. Theamount of deformation of all components (approx. 1 300

    pieces) was surveyed and recorded before/after heat

    straightening. Moreover the actual heat locations had to

    be recorded.

    4.5 Panel assembly

    For the trough rib welding to the both deck and bottom

    plates, 80% penetration for the trough rib plate thickness

    was required. Since melt through was not acceptable,

    welding penetration had to be controlled to between 80

    and 100%. To satisfy this requirement, welding tests were

    repeated. One year was spent to obtain the owners

    approval, including coping with the additional qualityrequirements. As the non-destructive inspection, 15% of

    the welding length was inspected by UT (Ultrasonic

    Fabricationprocedure

    Approval

    Weldingprocedure

    Specificationclarification (RFI)

    Welding data(shrinkage, WPS)

    description

    Solution of designproblems

    Panel dimensionsdescription

    Start of shopdrawing work

    Development fromassembly drawing to

    single-component

    Fig. 5 Procedure of shop drawing

    75

    Vol . 39 No . 2 2006Au gu st

  • 7/28/2019 Box Girder 2

    5/8

    Vol . 39 No. 2 2006Augu st

    76

    Test). But if a defect was found, 100% of the welding

    length was required to be inspected by UT for all the

    trough ribs of the panel where the defect was found. A

    smooth weld profile was required, and the allowable

    underfill value of less than 0.25 mm was specified.

    Figure 6 shows a welding macro. Trough rib welding wasexecuted after the trough ribs were tack welded to the

    skin plate with a gap of less than 0.6 mm. Since tack

    welds interfered with the penetrations of the final

    welding, resulting in incomplete penetration, the size of

    tack weld was reduced to the extent that no tack weld

    would be cracked due to the welding distortion during the

    final welding, and tack welds were ground off to be thin

    enough before the final welding. As to the welding

    process, various experiments and tests were repeated,

    confirming that SAW (Submerged Arc Welding) satisfied

    the aforementioned specifications and owners

    requirements. Figure 7 shows the welding work. Panel-to-panel seam-welding was done by one side submerged

    arc welding (FCB method). Since this welding method

    was not in the AWS code, many tests and documents

    were required to obtain the owners approval. High

    evaluation was finally obtained from the owner because

    FCB welding method does provide less distortion, fewer

    defects and stable quality.

    4.6 Shop yard assembly, trial assembly

    It had to be proved that no effect of twisted deformation

    remained in the OBG unit after three segments were

    welded together at the unit assembly stage. The welding

    sequence was set to minimize twisted deformation andsuch deformation was monitored by a system to display

    real-time reaction fluctuation at 24 supporting points

    during welding. This monitoring confirmed that through

    dimensional control and reaction control the amount of

    twisted deformation was kept within the allowable range

    and proved that there were no ill effects. To keep the

    temperature difference within 4 throughout a unit

    during works, temporary tent-roofs were installed.Temperature rises of the OBG due to the direct rays of the

    sun were minimized, and the OBG temperature became

    stable in shorter time in the evening. That enabled us to

    continue the work on the night shift in allowable

    temperature conditions. To obtain the root gap of the site

    joint and unit length within the specified range in the trial

    assembly, the site joint area was required to be trimmed

    after completion of shop assembly for each unit. The

    trimming amount and trimming lines was checked in the

    presence of the JV inspectors before the trial assembly.

    During the trial assembly, Caltrans inspectors

    independently took a survey the unit using threedimensional measuring equipment at the same time and

    measuring points as IHIs. They checked if the difference

    of survey results between Caltrans and IHI was within 1

    mm (maximum 2 mm). After confirming that the

    difference was within allowable range, the site joint

    portion of trough ribs was allowed to be drilled. The

    necessary numbers of drift pins had to be driven into

    holes before dawn. Then the root gap of the site joint and

    joint fitting were inspected by the JV inspectors under

    the very tight schedule. By strictly implementing the

    welding sequence, dimensional control, reaction control

    and temperature control, the accuracy of deck elevationand longitudinal alignment, and elevation at the center of

    the pin hole for hanger fixing were kept within 2.5

    mm/50 m and 3.0 mm/100 m, respectively, meeting the

    owners requirements.

    4.7 Painting

    The use of water-based paint was specified in terms of the

    regulation of VOC (Volatile Organic Compound). The

    first coat of waterborne inorganic zinc rich paint (100 -

    200 m) was applied to the interior and exterior surfaces

    at the shop. Painting work was performed in a paint shop

    whose atmospheric conditions were controlled to satisfy

    the severe requirements such as 7 to 29 for the ambienttemperature limit. Four MPa for the required minimum

    value of adhesion was successfully obtained eventually.Fig. 6 Photo of cross section of trough rib welding (unit : mm)

    Trough rib24 850

    88

    Underfill:notmorethan0.2

    Controlledwithin1.6

    Melt-through: not allowed

    305

    8

    356

    Penetration: 6.4 or higher (not more than 8)

    Fig. 7 Welding work on panel assembly

  • 7/28/2019 Box Girder 2

    6/8

    5. Transportation

    5.1 Outline

    The total number of OBG units was 24, and 8 units were

    transported at one time at the owners request. To

    minimize transportation cost, the OBG units were double-stacked, upper and lower, so that 8 units per voyage could

    be transported by one ship. Since the owners

    specification prohibited direct stacking of OBG units,

    special frames were installed on the hull deck to separate

    the upper and lower tier (Fig. 8).

    Because of the owners delivery time requirement, it

    was difficult to use one ship for 3 voyages, and 3 ships

    were therefore chartered from ZPMC Shipping affiliated

    with ZPMC in Shanghai (China). The order for the

    fabrication of the transportation frames was given to

    ZPMC. Forwarder services in Japan and the U.S., a ship

    chartering agency service and mooring work wereundertaken by Giyu Kaium Co., Ltd. (Japan).

    The average number of navigation days per ship was

    about 20.

    5.2 Shipping

    The OBG of standard unit mass 570 t was loaded by dual

    lift of 2 goliath cranes of Aichi Works. Since the trial

    assembly direction was different from the loading

    direction on the hull, each unit was turned 90 with 4

    dollies. Figure 9 and Fig. 10 show the loading and

    turning, respectively.

    The OBG units were lashed using fastening jigs

    installed as part of the frames around the receiving pointof all the transportation frames.

    5.3 Marine transportation

    The OBG units were each 29 m wide 49.6 m long, and

    each unit was loaded sideways across the hull in order to

    stack 8 units per ship in two tiers. As a result, the OBG

    units overhung about 9 m from both sides of the hull, and

    there was the possibility of the overhung portion being

    damaged by waves during transportation. For this reason,

    the OBG units were raised 6 m above the hull deck by

    means of a transportation frame structure, and the Hawaii

    route, where waves are relatively mild, was selected.

    Hull movement during transportation was numerically

    analyzed with the cooperation of IHIs Research

    Laboratory, and then we reported on the effects on the

    OBGs during transportation with the loading method and

    transportation route to the owner for their prior approval.

    Figure 11 shows the transportation routes of the 3 ships.

    To prevent corrosion of the inner surface of the OBGs

    due to waves and wind/rain, the openings at both ends ofthe OBGs was closed watertight with a canvas sheet

    capable of withstanding wind velocity of 60 m/s in

    consideration of stormy weather and long transportation

    period.

    5.4 Mooring at site and erection

    The OBG units were directly unloaded from the

    transportation ship and erected except for some OBG

    units requiring transhipping onto smaller barges because

    of the inaccessibility to unloading point for the ships.

    Thus each time a unit was erected, the transportation ship

    was brought under the bridge from the standby site and

    moored with 4 anchors installed in advance in the seaarea. For this mooring operation, winches were locally

    installed on the hull deck. Since the ships were moored inFig. 8 Transportation ship with deck units doubly stacked

    (first shipment)

    Fig. 10 Horizontal turning of unit

    Fig. 9 Loading unit onto ship

    77

    Vol . 39 No . 2 2006Au gu st

  • 7/28/2019 Box Girder 2

    7/8

    Vol . 39 No. 2 2006Augu st

    78

    a navigation channel, a local pilot boarded the ships, and

    they were positioned using a tugboat and moored in

    accordance with his instructions. During mooring, theposition was checked by JV by means of optical

    surveying instruments from the land. Figure 12 shows the

    releasing of anchor lines.

    The erection was made at low tide when the tide was

    starting to rise. This was done to avoid hull movement

    during hoisting operation and prevent the OBG load from

    being unintentionally loaded on to the hoisting equipment

    when the hull lowers due to the ebbing of the tide. Since

    the OBG units were installed on the hull at a narrow

    clearance of 1.5 m, hoisting guides were provided to

    prevent collision during erection. But neither hoisted unit

    nor hull moved horizontally during hoisting, because theships were positioned with high accuracy.

    Because the coast guard did not allow the

    transportation ship to be moored under the bridge for

    standby within the navigation channel, they moved after

    every erection to an open mooring area near the site for

    standby. At the standby site, they were kept moored with

    4 anchors as a safety measure for other marine traffic

    because the space was limited.

    The erection undertaken by JV was made using 4

    strand jacks installed in advance on the OBG at the

    standby site. After the erection was completed, strand

    jacks were transported by barge to the standby site toprepare for the erection of the following OBG unit.

    Figure 13 shows the erection of OBG. For the erection

    operation, the mooring position was checked first, and

    then the strand end of each jack was picked up from the

    catwalk by means of a winch and fixed to the temporary

    clamps installed in advance on the main cable, and the

    ship position was checked again. Then the OBG was

    hoisted through jack operation while the load balance was

    checked.

    Four strand jacks and all the equipment including

    power pack were placed on the OBG, and the hoisting

    operation was done in a concentrated way by means of awired remote controller from the transportation ship or

    catwalk. For one strand jack, 19 galvanized PC steel

    strands of 18 mm in diameter were used. Some units weremoved horizontally in the air because of site conditions.

    This horizontal movement was made by means of load

    shifting between 2 sets of strand jacks (2 4 uni ts)

    (Fig. 14).

    6. Conclusion

    The fabrication and transportation of OBG for the New

    Carquinez Bridge were outlined above. Under a severe

    delivery schedule, we, including factory workers and

    project group, united to perform the operations, and as a

    result made the delivery on schedule. We intend to utilize

    the technologies and experiences accumulated through thesevere conditions and schedule for this project for our

    future overseas projects.

    150E 165E 180E40N

    35N

    30N

    165W 150W 135W

    Japan

    U.S.

    20N

    Tropic of cancer

    : First ship

    : Second ship

    : Third ship

    Fig. 12 Releasing of anchor lines with tug boats

    Fig. 11 Sea transportation routes (actual)

    Fig. 13 Lifting up of unit

  • 7/28/2019 Box Girder 2

    8/8

    Acknowledgments

    In implementing this project, we received much guidance

    and cooperation from people both inside and outside IHI.

    We hereby express our heartfelt thanks to them.

    REFERENCES

    (1) State of California, Department of Transportation :Standard Specification 1999 (1999)

    (2) International Chamber of Commerce : International

    Commercial Terms 2000 (2000)

    (3) California Department of Transportation : Spanning

    the Carquinez Strait (2003)

    (4) M. Marquez, R. W. Wolfe and E. Thimmhardy :

    New Carquinez Strait Suspension Bridge, San

    Francisco, California, Structural Engineering

    International Vol.13 No.2 (2003)

    (5) Thomas Spoth and H. Ohashi : Design of the New

    Carquinez Bridge, Bridge and Foundation

    Engineering Vol.35 No.6 June 2001 pp.17-25

    79

    Vol . 39 No . 2 2006Au gu st

    Fig. 14 Traversing status of unit performed by load shifting

    under hoisted condition