Page 1: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

{

Bradley J. Heigel, P.E.Chief Engineer

PA Turnpike Commission

Page 2: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM
Page 3: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM
Page 4: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM
Page 5: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

Program Category FY2015 FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 FY2024 Total FINAL PLAN

Highway Roadway/Safety 98,811,000 62,008,452 67,176,941 92,104,311 59,681,103 125,783,223 138,746,758 109,675,606 121,684,404 90,816,432 966,488,230

Highway Bridge, Tunnel & MiscStructure 88,552,026 98,799,026 87,883,239 63,943,747 58,825,181 162,554,981 136,651,282 136,125,791 139,526,837 143,519,904 1,116,382,014

Highway Total Reconstruction 273,917,000 319,370,738 279,552,481 272,722,034 402,172,159 206,532,255 188,569,393 285,500,742 263,188,242 291,810,272 2,783,335,318

Highway Interchanges (with AET) 84,778,000 136,364,174 140,564,871 136,384,834 47,011,235 84,968,705 117,463,848 50,071,234 57,702,478 48,526,780 903,836,159

Highway Highway Miscellaneous 44,740,667 31,098,178 36,379,251 34,788,514 27,194,975 20,310,812 18,944,837 19,332,221 19,071,880 19,202,385 271,063,720

Total 590,798,693 647,640,568 611,556,783 599,943,440 594,884,654 600,149,976 600,376,118 600,705,595 601,173,841 593,875,773 6,041,105,441

FEMO Re-capitalization 700,000 513,400 1,052,088 410,646 190,593 469,387 0 0 0 0 3,336,114

FEMO Sustainment 10,650,000 8,111,720 9,910,591 10,176,195 9,893,124 10,158,260 10,430,501 9,386,326 9,637,879 9,896,174 98,250,771

FEMO Compliance 1,980,000 2,412,980 3,162,955 3,247,722 3,334,761 3,424,132 3,515,899 3,610,125 3,706,877 3,806,221 32,201,672

FEMO New Energy Initiative 1,865,835 1,197,079 1,176,445 1,021,032 1,000,428 1,027,240 1,054,770 1,083,038 1,112,063 1,141,866 11,679,796

FEMO Facilities Design 28,307,557 26,570,736 26,935,172 14,344,105 3,612,658 4,613,980 3,808,891 3,910,969 4,015,783 4,123,406 120,243,256

Total 43,503,392 38,805,915 42,237,252 29,199,700 18,031,563 19,692,998 18,810,061 17,990,458 18,472,602 18,967,668 265,711,609

Fleet Fleet Equipment 16,031,814 13,419,781 15,920,778 14,214,773 16,288,976 20,175,503 17,812,122 18,315,302 18,831,948 13,276,317 164,287,314

IT Functional Software 13,000,986 13,628,427 12,048,395 12,457,427 13,177,592 13,552,150 14,095,977 15,188,330 15,235,263 14,532,863 136,917,410

IT Infrastructure HW/SW 8,580,000 5,963,914 6,649,616 6,429,353 3,894,751 3,999,130 3,913,635 4,018,521 4,126,217 3,773,229 51,348,365

IT Toll Collection/Ops 9,760,000 14,708,910 11,492,069 1,623,861 1,667,380 1,712,066 1,757,950 1,805,063 1,853,438 1,522,488 47,903,225

Total 31,340,986 34,301,251 30,190,079 20,510,640 18,739,723 19,263,346 19,767,562 21,011,914 21,214,918 19,828,580 236,169,000

Grand Total (PSEXP) 681,674,885 734,167,515 699,904,892 663,868,554 647,944,916 659,281,824 656,765,863 658,023,268 659,693,310 645,948,338 6,707,273,364

Federally Funds (-) 52,000,000 20,000,000 25,850,000 30,850,000 40,000,000 18,800,000 0 0 0 0 187,500,000

Grand Total (PSNET) 629,674,885 714,167,515 674,054,892 633,018,554 607,944,916 640,481,824 656,765,863 658,023,268 659,693,310 645,948,338 6,519,773,364

FY15 10‐Year Capital Plan

Page 6: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

FY15 Highway Program

Page 7: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

$0

$100,000,000

$200,000,000

$300,000,000

$400,000,000

$500,000,000

$600,000,000

$700,000,000

$0

$10,000,000

$20,000,000

$30,000,000

$40,000,000

$50,000,000

$60,000,000

$70,000,000

$80,000,000

$90,000,000

$100,000,000

JUNE AUGUST OCTOBER DECEMBER FEBRUARY APRIL

Capital Plan Status ‐ Highway Program2015 Fiscal Year to Date (September 23, 2014)

Adopted Plan Reforecast Plan Actual

Page 8: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

The PTC will begin using PennDOT's Engineering and Construction Management System (ECMS) for the advertisement of RFPs and the receipt of Statements of Interest for engineering services by early 2015. At that time, all firms (including subconsultant team‐members) must be registered business partners with PennDOT in ECMS in order to submit a Statement of Interest.

Please note that certain facility‐related or non‐highway program‐related engineering/architectural services may still be advertised outside of ECMS on the PTC's website until further notice.

Procurement of Professional Services

Page 9: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

Technical Evaluation Team (TET)

Professional Services Procurement Committee (PSPC)

Commission Selection

Highly Recommended

Page 10: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

Professional Services

As of the end of September 2014, 151 active Engineering services agreements with 80

different firms.

Total contract value of $1,003,950.92

Balance remaining of $517,803.78

2011 15 Contracts 15 Firms2012 40 Contracts 36 Firms2013 22 Contracts 22 Firms2014 19 Contracts 18 Firms

96 Contracts 71 Firms

Page 11: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

Improves Process for Documenting Performance Standardizes Evaluations Creates a Database for Performance History Provides Quantifiable Data for Selection Process

Professional Services Evaluations

Page 12: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

Evaluations: PS&E (Design) and Post‐Construction (Design & CM/CI) Required for all projects that result in a project on the 12Q 

Planning schedule Interim evaluations as necessary or directed Final evaluation required on all agreements, i.e. open ends

Professional Services Evaluations

Short Term Interim  Long Term

Access Data  Momentum ?Base Study

October 8th

Page 13: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

1st Five Quarters is our Letting Schedule

Page 14: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

Requires signature by Design Consultant and Design Manager (if applicable)

Requires a REASON Code

Page 15: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

Construction Contracts

As of the end of September 2014, 99 active construction contracts with 45 different 

contractors.

Total contract value of $1,500,000,000

Balance remaining of $841,000,000

Engineering Estimates for:CY13: 17.3%

CY14: 4.9%

Page 16: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

Construction Contracts

Construction Operations Manual (COM) Update:

Contractor Cash Drawdowns

Change Order Management

Design Errors/Design Omissions

Page 17: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

{

Page 18: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

{

Page 19: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

{

Page 20: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

{

Page 21: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

{

Page 22: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

{

Page 23: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

{

Page 24: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

CM/CI Tuscarora Tunnel RehabFee: $ 6,500,000 

CI Services MP. 319‐326 Total Recon.Fee: $ 20,000,000 

CI Services MP. A31‐A44 TR (2 contr.)Fee: $10,000,000  each

CM MP. 149‐155 Total Recon.Fee: $8,000,000  

Page 25: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

CM/CI Services MP. 28‐31 Total Recon.Fee: $ 7,500,000 

CI Services Southern Beltway US22‐I79Fee: $13,000,000

Page 26: Bradley J. Heigel, P.E. - ASHE Harrisburg Section · Bradley J. Subject: Presentation Created Date: 10/9/2014 8:05:54 AM

Open‐End Design (2 contracts)Fee: $ 950,000 each

Open‐End QA Inspection & TestingFee: $ 1,500,000 

Open‐End CI – West (2 contracts)Fee: $1,500,000  each

Open‐End Coating ConsultantFee: $1,500,000  