bridgelink professional tutorials - pgsuper

15
Bridge fro Model eLink Professio Tutorials om BridgeSight Software ling Touch Shor BridgeSight Inc. P.O. Box 19172 South Lake Tahoe, CA 96151 877-441-0346 www.BridgeSight.com onal ring

Upload: others

Post on 01-May-2022

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BridgeLink Professional Tutorials - PGSuper

BridgeLink Professional

from

Modeling

BridgeLink ProfessionalTutorials

from BridgeSight Software

Modeling Touch Shoring

BridgeSight Inc. P.O. Box 19172

South Lake Tahoe, CA 96151 877-441-0346

www.BridgeSight.com

BridgeLink Professional

Touch Shoring

Page 2: BridgeLink Professional Tutorials - PGSuper

Title PGSuper Tutorial – Modeling Touch Shoring Publication No. BS02282011-2

Abstract This document provides a discussion and step-by-step procedure for modeling precast-prestressed girder bridge structures constructed with touch shoring.

Disclaimer The information contained in this publication is believed to be accurate; however, it is being provided for informational purposes only. Publication of this document by BridgeSight Inc. should not be construed as BridgeSight Inc. engaging in or rendering engineering, legal or other professional services. Use of the information contained in this publication should not be considered by the user as a substitute for the advice of a registered professional engineer, attorney or other professional. If such advice is required, it should be sought through the services of a registered professional engineer, licensed attorney or other professional.

Notes

Author Staff – BridgeSight Software Sponsor BridgeSight Inc P.O. Box 19172 South Lake Tahoe, CA 96151

Specification AASHTO LRFD Bridge Design Specifications BridgeLink Professional 2.0 - PGSuper 3.0

Original Publication Date 3/13/2011 Date of Latest Revision 9/9/2017 Version 2.0

Notice of Copyright

Copyright © 2017 BridgeSight Inc. All Rights Reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means (electronic, mechanical, photocopied, recorded, or otherwise), without prior written permission from BridgeSight Inc.

Page 3: BridgeLink Professional Tutorials - PGSuper

1

Introduction This tutorial demonstrates how to model a touch shoring construction scenario with PGSuper. Touch shoring supports precast girders during deck placement to reduce the final stresses in the composite deck and girder system. In this construction scenario, temporary shoring towers are erected before the girders are placed. After the girders are placed, the shoring is adjusted to touch the bottom of each girder without introducing any significant force into the system. Subsequent loads placed on the non-composite girder, such as the deck slab, will be partially supported by the shoring effectively reducing the girder’s span length. At temporary shoring locations, the additional dead load creates negative moment. This reduces the positive bending moment stresses in the bare girder from the subsequent loads applied to the completed structure.

The shoring is removed after the deck slab reaches a specified compressive strength. Any force carried by the temporary shoring tower is then carried by the full span girder, which is now a composite section. This method can reduce total stresses compared to when touch shoring is not utilized.

Scenario Our example is a fictitious design-build construction scenario where the builder has realized a large cost savings by eliminating a bridge from a project. However, six girders for the removed bridge have already been fabricated, and the cost savings would be even greater if these girders can be used in a different bridge.

The six girders are AASHTO Type V with 32 straight and 8 harped strands. They were constructed for a 130 ft span structure (127.33 ft between bearings). The design concrete strengths are f’ ci = 5.9 ksi and f’ c = 6.6 ksi. The bridge where the builder would like to use these girders is also 130 ft long, but slightly wider. The girders would be spaced at 8 ft and the deck would have 4 ft overhangs. The girders were originally designed for a closer spacing and thus might not have adequate capacity.

Page 4: BridgeLink Professional Tutorials - PGSuper

2

Our job is to assess the girders and determine if they can be utilized in a different bridge. The purpose of this tutorial is to describe modeling technique, so we will limit the engineering evaluation to flexural requirements. Of course, a full evaluation must be performed if this were an actual bridge project.

Creating the PGSuper Project Create a PGSuper Project to evaluate the bridge. The fastest way to start a project with AASHTO girders is to use the AASHTO Standard Girder templates published by the Washington State Department of Transportation (WSDOT).

Configure PGSuper for AASHTO Girders This project uses AASHTO girders so begin by configuring PGSuper for AASHTO standard girders.

1. Start BridgeLink 2. Select File > Configure BridgeLink… to activate the configuration wizard 3. The second step in the configuration wizard is the PGSuper configuration. Select

the WSDOT configuration server and the AASHTO Standard Girders from PCI BDM configuration

4. Press [Next>] and proceed to through the wizard. Default configurations for the other BridgeLink applications are acceptable

5. Press [Finish] to end the configuration wizard.

Page 5: BridgeLink Professional Tutorials - PGSuper

Create a New PGSuper Project1. Select File > New 2. Under PGSuper Project Templates, select I3. Press [OK] to create a new project

Describing the BridgeThe bridge in this example can be defined by changing just a parameters.

1. Select Edit > Bridge

3

Create a New PGSuper Project

Under PGSuper Project Templates, select I-Beams and then the Type V to create a new project

Describing the Bridge The bridge in this example can be defined by changing just a few of the default

Bridge

Beams and then the Type V template.

of the default

Page 6: BridgeLink Professional Tutorials - PGSuper

2. On the General Tab input the girder spacing (8 ft)

3. On the Layout tab elength (1+30)

4

On the General Tab input the girder spacing (8 ft)

tab enter the station of Abutment 2 to define the overall

2 to define the overall bridge

Page 7: BridgeLink Professional Tutorials - PGSuper

4. On the Deck Geometry and Materials ta(24ft)

5. The default value for the remaining parameters are sufficient for this Press [OK].

6. In a normal situation, the next step would be to use PGSuper’s bridge model view and girder view to This is covered in other tutorials, so we will skip model validatation and define the girder properties.

Describing the GirdersAll of the girders used in the bridge are the same. parameters to the remaining girders.

1. Select Edit > Girder

5

On the Deck Geometry and Materials tab, enter the left and right deck offset

The default value for the remaining parameters are sufficient for this

In a normal situation, the next step would be to use PGSuper’s bridge model view and girder view to confirm that the bridge’s geometry has been input correctly. This is covered in other tutorials, so we will skip model validatation and define the girder properties.

the Girders All of the girders used in the bridge are the same. Define Girder A and tparameters to the remaining girders.

Girder then edit Span 1, Girder A

enter the left and right deck offset

The default value for the remaining parameters are sufficient for this tutorial.

In a normal situation, the next step would be to use PGSuper’s bridge model view that the bridge’s geometry has been input correctly.

This is covered in other tutorials, so we will skip model validatation and define

efine Girder A and then copy the

Page 8: BridgeLink Professional Tutorials - PGSuper

2. Enter the concrete strength

6

Enter the concrete strength

Page 9: BridgeLink Professional Tutorials - PGSuper

3. Enter the strand configuration

4. The remaining parameters are not of significanceall girders in this span

Press [OK]

Evaluate the Girders for Evaluate a typical interior girder accomplished by creating

7

Enter the strand configuration

The remaining parameters are not of significance for this tutorial. Check the rders in this span box to copy these parameters to all other girders in Span 1.

Evaluate the Girders for Conventional ConstructionEvaluate a typical interior girder for a conventional construction sequence. This

a Spec Check Report for Girder B.

Check the Copy to e parameters to all other girders in Span 1.

Conventional Construction construction sequence. This is

Page 10: BridgeLink Professional Tutorials - PGSuper

1. Select View > Reports 2. Select Span 1 and Girder B. Press [OK]

3. Reviewing the analysis results, we see that the girder does not satisfy the level stress criteria.

NOTE: There are other specifitutorial we are only interested in flexure.

With a conventional construction are not within acceptable service level stress limits. construction as a means of reducing the

Shored ConstructionLet’s see if the final service level stresses can be reduced through the use of shored construction. Shoring towers cannot be explicitly modeled in be simulated with user defined loadare of interest:

• Event 4 : Cast Deck into their final position

• Event 5 : Final without Live Load strength and is composite with the girders. railing system, are applied.

We model the addition of equal to the shoring tower reactions in

8

Reports > Spec Check Report Select Span 1 and Girder B. Press [OK]

eviewing the analysis results, we see that the girder does not satisfy the stress criteria.

NOTE: There are other specification checks that do not pass. For purposes of this tutorial we are only interested in flexure.

conventional construction sequence, these girders have adequate strength but not within acceptable service level stress limits. We will investigate

construction as a means of reducing the service level stresses.

Shored Construction he final service level stresses can be reduced through the use of shored

horing towers cannot be explicitly modeled in PGSuper;user defined loads applied during key construction events

Event 4 : Cast Deck - During this event, the non-composite girders into their final position and carry the deck slab load as simple span membersEvent 5 : Final without Live Load - The deck slab has reached its required strength and is composite with the girders. Superimposed dead loads, such as the railing system, are applied.

touch shoring towers by applying upward userequal to the shoring tower reactions in Event 4. Shoring tower removal is

eviewing the analysis results, we see that the girder does not satisfy the service

cation checks that do not pass. For purposes of this

sequence, these girders have adequate strength but We will investigate shored

he final service level stresses can be reduced through the use of shored PGSuper; however they can

during key construction events. Two events

composite girders are erected le span members.

he deck slab has reached its required Superimposed dead loads, such as the

ing upward user-defined loads horing tower removal is then simulated

Page 11: BridgeLink Professional Tutorials - PGSuper

by applying downward user defined loads loads in Event 5.

Assume the shoring towers located

Slab Loading Start by using PGSuper to by the shoring towers.

Create a Details Report for Girder

1. Select View > Reports 2. Select Span 1, Girder

From the Details Report, the

Compute the Shoring Tower ReactionWhen the shoring towers engage the bottom flange of the girder and the deck is cast, the girder acts as a three span continuous beam.

9

user defined loads that are equal and opposite of the reaction

shoring towers located at the 1/3 and 2/3 points in the span.

to compute the deck slab dead load that will be carried, in part,

Create a Details Report for Girder B, with just the Loading Details chapter.

eports > Details Report Select Span 1, Girder B, and deselect all chapters except for Loading Details

From the Details Report, the total slab load is 0.970 k/ft

Compute the Shoring Tower Reaction When the shoring towers engage the bottom flange of the girder and the deck is cast, the girder acts as a three span continuous beam.

that are equal and opposite of the reaction

at the 1/3 and 2/3 points in the span.

compute the deck slab dead load that will be carried, in part,

just the Loading Details chapter.

, and deselect all chapters except for Loading Details

When the shoring towers engage the bottom flange of the girder and the deck is cast, the

Page 12: BridgeLink Professional Tutorials - PGSuper

A BRA=0.4wl

l

The total span length, between bearings, is 127.33ft.

The shoring tower reaction at B and C is

Modeling the Shoring TowerThe effect of the towers is modeled with two upward Event 4 so the loading activity is assign

User defined load for s1. Select Loads > Add Point Load2. Define the first shoring tower reaction load. Note that positive loads are in the

direction of gravityof the span length.

10

B C D

l l

w

RB=1.1wl RC=1.1wlRD=0.4wl

, between bearings, is 127.33ft.

� � 127.33�3 � 42.44�

ower reaction at B and C is 1.1�� � 1.1 �0.970 ���� �42.44

Modeling the Shoring Tower is modeled with two upward point loads. The deck is cast in

so the loading activity is assigned to this event.

for shoring tower reaction Add Point Load shoring tower reaction load. Note that positive loads are in the

direction of gravity. Enter a load of -45.3 kips. The load is located at the 1/3 point

D

� 44�� � 45.3���

deck is cast in

shoring tower reaction load. Note that positive loads are in the kips. The load is located at the 1/3 point

Page 13: BridgeLink Professional Tutorials - PGSuper

3. Repeat this process to define the shoring tower reaction load at the 2/3 point of the span.

User defined load for Shoring The shoring towers are removed agirder. Removal is modeled with two dupward loads applied in Event 4

The user defined loads can are listed in the Loads window. Select

Evaluate the Girders using Shored ConstructionWe will review the moment diagram to verify that the user defined loads that simulate the shoring towers have the desired effect.

1. Select View > Graphs > Analysis Results2. Select Girder B 3. Select Interval 10: Cast Deck4. Select Moment 5. Hold the CTRL key and sel6. Select Incremental results

11

Repeat this process to define the shoring tower reaction load at the 2/3 point of

oad for Shoring tower removal The shoring towers are removed after the deck cures and becomes composite with the

emoval is modeled with two downward loads that are equal and opposite ofEvent 4. These loads are applied in Event 5.

The user defined loads can are listed in the Loads window. Select Edit > Loads

Evaluate the Girders using Shored ConstructionWe will review the moment diagram to verify that the user defined loads that simulate the shoring towers have the desired effect.

View > Graphs > Analysis Results

Select Interval 10: Cast Deck

Hold the CTRL key and select “Slab”, “Haunch”, “User DC”, and “DC” loadsSelect Incremental results

Repeat this process to define the shoring tower reaction load at the 2/3 point of

fter the deck cures and becomes composite with the and opposite of the

Edit > Loads.

Evaluate the Girders using Shored Construction We will review the moment diagram to verify that the user defined loads that simulate the

ect “Slab”, “Haunch”, “User DC”, and “DC” loads

Page 14: BridgeLink Professional Tutorials - PGSuper

The incremental DC moment diagram mimics that of a three span continuous span. The DC moment is considerablywithout the shoring towers.

Create a specification check report

Upon review of the service level stress checks, we see that the use of touch shoring has reduced the final service levelchecks do not pass, this is ok since we are focusing on reducing flexural stresses in this tutorial).

Further evaluation of exterior girders should be performed to ensure that they are also adequate.

Conclusion These girders can be used level stresses within acceptable limitsfeatures available in PGSuper scenarios quick and easy.

Customizing PGSuperPGSuper Professional has an advanced software architecture that allows third parties to extend and enhance its capabilities. At BridgeSight Software, we can add new analysis capabilities to meet your needs. For details, contact us at

BridgeSight Inc P.O. Box 19172

12

The incremental DC moment diagram mimics that of a three span continuous span. The ly less than the simple span “Slab” + “Haunch” moment

towers.

Create a specification check report for Girder B using the same steps as described

Upon review of the service level stress checks, we see that the use of touch shoring has reduced the final service level stresses to acceptable levels (NOTE: Other specification checks do not pass, this is ok since we are focusing on reducing flexural stresses in this

Further evaluation of exterior girders should be performed to ensure that they are also

hese girders can be used in the new bridge structure. However, to keep the final service level stresses within acceptable limits, touch shoring must be utilized. The advanced features available in PGSuper Professional make modeling these complex constructi

Customizing PGSuper Professional has an advanced software architecture that allows third parties to

extend and enhance its capabilities. At BridgeSight Software, we can add new analysis your needs. For details, contact us at

The incremental DC moment diagram mimics that of a three span continuous span. The less than the simple span “Slab” + “Haunch” moment

using the same steps as described above.

Upon review of the service level stress checks, we see that the use of touch shoring has : Other specification

checks do not pass, this is ok since we are focusing on reducing flexural stresses in this

Further evaluation of exterior girders should be performed to ensure that they are also

o keep the final service The advanced

make modeling these complex construction

has an advanced software architecture that allows third parties to extend and enhance its capabilities. At BridgeSight Software, we can add new analysis

Page 15: BridgeLink Professional Tutorials - PGSuper

13

South Lake Tahoe, CA 96151 877-441-0346 [email protected]