Bridging the gap between EIA and procurement
+EIA and then what?
– Client and contractor responses to environmental requirements
Charlotta Faith-Ell, WSP Civils
Berit Balfors, Kristina Lundberg & Annika Varnäs
Royal Institute of Technology
2007-06-05
![Page 2: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/2.jpg)
Road planning in theory and practice
Feasibility study+EIA
Initial study+(EIA)
Project design+EIA
Building document Construction Operation and
maintenance
Initial study+(EIA)
Procurement Procurement
Feasibility study+EIA
Project design+EIA
This presentation
Procurement Procurement Procurement
Building document Construction Operation and
maintenance
![Page 3: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/3.jpg)
The application of environmental requirements in road construction and maintenance contracts
Two different studies
One case study of road maintenance contracts– (interviews, participatory observations, content
analysis, inventories)
– 1997 – 2003
One case study of road construction contracts– (questionnaires and interviews)
– 2005 – 2007
![Page 4: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/4.jpg)
Environmental requirements in road maintenance contracts
Vegetation and fauna
Natural resources
Noise and dust
Pollution of soil and water
Waste
Chemicals and products
Vehicles
Product declaration
Environmental management
![Page 5: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/5.jpg)
Development and implementation of environmental requirements
![Page 6: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/6.jpg)
Client knowledgeand experience
Development of env. req.
![Page 7: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/7.jpg)
Client knowledgeand experience
Development of env. req.
Environmentalrequirements
![Page 8: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/8.jpg)
Client knowledgeand experience
Development of env. req.
Environmentalrequirements
Interpretation by contractors and
client representatives
![Page 9: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/9.jpg)
Intentions behind requirements on mowing
Use of cutting tools, not shredding tools
Removal of cut of material
Late mowing dates
Annual mowing
![Page 10: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/10.jpg)
Operation
Client knowledgeand experience
Development of env. req.
Environmentalrequirements
Interpretation by contractors and
client representatives
Contractor knowledge, economy
and resources
Driver knowledge
![Page 11: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/11.jpg)
Lupinus polyphyllus Lindl. Echium vulgare L.
![Page 12: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/12.jpg)
Operation
Client knowledgeand experience
Development of env. req.
Environmentalrequirements
Interpretation by contractors and
client representatives
Contractor knowledge, economy
and resources
Driver knowledge
Result?
![Page 13: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/13.jpg)
Why is this a problem?
SRA will not be able to verify the impact of most of the environmental requirements
The benefit to the environment by stating environmental requirements on road maintenance is difficult to assess
No follow-up of the EIA
![Page 14: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/14.jpg)
How should the process look like?
![Page 15: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/15.jpg)
Results of the EIA, Environmental objectives,
legislation, problems and research
Development of environmental
requirements, indicators and baseline
Environmentalrequirements
![Page 16: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/16.jpg)
Development of environmental
requirements, indicators and baseline
Implementation
Environmentalrequirements
Environmental training and development of working processes
Results of the EIA, Environmental objectives,
legislation, problems and research
![Page 17: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/17.jpg)
Development of environmental
requirements, indicators and baseline
Implementation
Environmentalrequirements
Environmental training and development of working processes
Operation
Results of the EIA, Environmental objectives,
legislation, problems and research
![Page 18: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/18.jpg)
Development of environmental
requirements, indicators and baseline
Implementation
Environmentalrequirements
Environmental training and development of working processes
Operation
FEEDBACK
Follow-up ofcontractor
performance
Follow-up of environmental effectiveness
Results of the EIA, Environmental objectives,
legislation, problems and researchEIA
![Page 19: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/19.jpg)
Where are we now?
Feasibility study+EIA
Initial study+(EIA)
Project design+EIA
Building document Construction Operation and
maintenance
Initial study+(EIA)
Feasibility study+EIA
Project design+EIA
Procurement Procurement Procurement Procurement Procurement
Building document Construction Operation and
maintenance
![Page 20: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/20.jpg)
What do this mean for EIA in the Swedish context? We are seeing changes in the writing of the
EIS into more specific requirements that can be translated into the tender documents
Some players have introduced ‘Environmental Plans’ that translates the requirements in the EIS to the tender documents
The SRA have started to place requirements on EIA training among the consultants
![Page 21: Bridging the gap between EIA and procurement + EIA and then what? – Client and contractor responses to environmental requirements Charlotta Faith-Ell,](https://reader035.vdocument.in/reader035/viewer/2022081513/56649ebb5503460f94bc3320/html5/thumbnails/21.jpg)
Swedish planning is today lacking people with construction experiences both among engineers and environmentalists. This means that some of the decisions made in the planning might not be feasible during the construction. Early contractor involvement in the planning process might lead to: An increased understanding of the environmental
requirements among the contractors and client representatives and a reduction of the need for interpretation of the requirements
Stronger relationships between different players which might mean an even higher will to avoid conflicts
Increase or decrease in transparency
Conclusion