Page 1: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

IT in Education Section, Education Bureau16 March 2016

Briefing Session for the ICT Sector on the Enhancement of WiFiInfrastructure in Schools

Page 2: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Item Speakers

Progress on ITE4Mr YT LAU

Chief Curriculum Development Officer (IT in Education), Education Bureau

Updates of technical documentsMs Sierra LAM

Senior Curriculum Development Officer (IT in Education), Education Bureau

Support from Hong Kong Education City

Mr Victor CHENGExecutive Director, Hong Kong Education City Limited

Service Management and Schools’ Concerns

Mr Albert WONGChairman, Association of IT Leaders in Education

Introduction on Wi-Fi.HK Mr HO Tze-kin

Senior System Manager, Office of the Government Chief Information Officer

Q & A

Page 3: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Support Scheme for e-Learning in schools(WiFi 100)

Page 4: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

The Fourth Strategy on IT in Education(ITE4)

• Launched on 25 August 2015

Page 5: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

WiFi 900

1st 400• 2015/16 School year• Over 80% adopted subscription mode

2nd 300• 2016/17 School year

3rd 200• 2017/18 School year

Page 6: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Support Measures

Recurrent grant to public sector schools (Except WiFi100 schools) for enhancing WiFi infrastructure of $48,530 to 121,340

One off grant for acquiring mobile computing devices of $69,400 to$173,510

Providing checklist and sample specifications …… Technical Advisory Team to provide consultancy service

Professional Development Programmes …… Strengthen CoE(Centre of Excellence) and setting up communities of practices

Page 7: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

0102030405060708090100

1 2 3 4 5 6 7 8 9 10 >10

No. of schools

No. of Subjects

2017/18Primary

Secondary

Schools’ plan in adopting e‐learning (1)

0102030405060708090100

1 2 3 4 5 6 7 8 9 10 >10

No. of schools

No. of Subjects

2015/16Primary

Secondary

0102030405060708090100

1 2 3 4 5 6 7 8 9 10 >10

No. of schools

No. of Subjects

2016/17Primary

Secondary

Page 8: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

0

50

100

150

200

250

300

CHI ENG MATHS GS IT MUSIC VA 圖書

No. of schools

Subject

Schools’ plan in adopting e‐learning (2)– Primary

2015/16

2016/17

2017/18

Page 9: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

0

50

100

150

200

250

300

No. of schools

Subject

Schools’ plan in adopting e‐learning  (3)– Secondary

2015/16

2016/17

2017/18

Page 10: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

10

Any BYOD Policies? Accumulated (%)

None 50

Aware the issue and formulating 81

Policy formulated but not yet implemented

88

Policy formulated and implemented 96

Have support measures to facilitate BYOD (e.g. AUP, Single sign‐on, charging 

facilities)

100

Are schools ready to implement BYOD?

Page 11: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

WiFi900 1st batch

• 80% schools adopted WiFi subscription service

• Average satisfactory level 2.46 / 4

Unsatisfactory Acceptable Very satisfactory

Excellent

23 143 132 197% 45% 42% 6%

(out of 340 schools for subscription, 317 schools responded this question)

Page 12: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Enhanced measures for WiFi900 (2nd batch)Facilitate schools’ early preparation – briefing sessions organised in Dec 2015, seminars for school leaders in Jan 2016Special workshops on formulating user requirement specifications (Jan to Mar by CUHK)Enhanced technical advisory and support by ITE Section, HKEdCity and collaboration with the Association of I.T. Leaders in Education

Briefing session Special workshop – school visit

Page 13: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Item WiFi 900 –1st batch

WiFi 900 –2nd batch

Remarks

EDB CM, briefing for schools and EOI form submission

Feb to Apr 2015

Briefing for schools and ICT Sector

May 2015 Dec 2015 (Schools)

March 16 (ICT Sector)

Training Jan – Mar 2016

Prepare quotation documents

Apr – May Mar – May Checklist, Sample User RequirementSpecifications and Technical Advisory Service

Quotation procedures and contract award

June – Jul May – Jun

Construction work Jul – Sep Jun – AugProgress update Aug – Oct Aug – Oct

Completion Sep Sep

Progress

Page 14: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

WiFi 900 – 2nd Batch

Collaboration among stakeholders

Page 15: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

WiFi in schools

Schools

EDBIT industry

• Source of funding• Technical advisory

Service

• Total user experience• Clear requirements• Choose vendors

• Clear communication with schools

• Design and build• Support service

Roles and Responsibility

Page 16: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

WiFi100 and WiFi900 experiences

• Service providers shall strengthen communication among sub-contractors and with schools

• Single contact point, e.g. Project Manager

• Service providers shall enhance schedule and resource management

Page 17: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Technical Advisory Service and face-to-face sessions1. Information note2. Sample Requirement specifications3. Sample System Test4. Sample UAT5. Recommended Practices on Information

Security

Page 18: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Information Note

Page 19: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Information Note – Standard Provision• WiFi Internet Connectivity - use IEEE 802.11 a/b/g/n/ac or

above network in a standard classroom. The minimum number of classrooms to be covered should be at least equal to the number of approved classes for the 2016/17 school year.

• Number of Concurrent Connection - commensurate with the maximum number of students, say 40, in a class with at least 1 Mbps upload / download bandwidth per user connection for browsing web pages.

• Authentication Method - use Hong Kong Education City accounts for authentication to save the effort for device registration.

Page 20: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

School Case• At least covering all classrooms of EDB approved number

of classes

• Mobile AP is not acceptable, all those classrooms should be WiFi connected

• Each WiFi connection should have at least 1 Mbps upload and download speed, total bandwidth shall evenly distributed among number of connections

• Suggest school to adopt 2.4GHz or 5GHz according to the environment

Page 21: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Information Note – Standard Provision• Session Control - allow multiple devices per user

account to be authenticated using Hong Kong Education City.

• Internet Content Filtering Service - based on filtering profile commonly adopted by most schools.

• Existing Network Facilities - not rely on any existing network facilities and cabling of the schools, nor interfere with the existing WiFi network of the schools.

• Existing Broadband Network – Use the existing broadband link for the WiFi service.

Page 22: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

School Case

• Contractor shall advise school if existing Conduit / Cable / Trunk / Switch / AP of the school can or cannot be technically feasible for use

• Schools may have other construction work or activities during summer vacations, that may interfere with WiFiconstruction work, detailed project schedule should be agreed once Contract confirmed

Page 23: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Information Note – Standard Provision• Managed Service - operate the WiFi network using

managed service model, provide end-to-end service including provision, monitoring and maintenance service.

• Service Level Agreement - ensure at least 99.7% availability of the WiFi service, support four-hour response time and four-hour service recovery with active monitoring, helpdesk support with support hours from Mon to Sat 8:00 am to 6:00 pm, and provide monthly monitoring reports for School.

Page 24: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Information Note – Add-on Service• WiFi Coverage - to include special rooms and open areas

• Broadband Service - provide broadband service with at least 100Mbps Internet connection at school and allowing upgrade to 1Gbps

• Authentication - user account system being used by school

• Session Control - allow single device per user account or other arrangement to be authenticated if using Hong Kong Education City accounts

• WLAN System Access Control - provide MAC address filtering mechanism, pre-shared key mechanism, etc.

Mutual understanding and agreement on

provision

Page 25: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Information Note – Add-on Service• MAC Address Monitoring – The lists of filtering and filtered mac

addresses are to be monitored by the Contractor or the School.

• Internet Content Filtering Service - specific request on content filtering

• Integration - system integration with existing network

• Internet addresses subscription & configuration – for Internet access to school internal resources.

• Monitoring of WiFi network - specific request on monitoring of WiFinetwork by School

• Redundancy - increase the availability of the WiFi service

• Supporting hours - longer support hours and shorter time recovery

For Information Security, Network

Integration is NOT

recommended

Page 26: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

School Case• School may request extra work, e.g. integration to existing

school LAN network, cabling for other coverage, MAC address filtering tool, etc. Contractor shall obtain detailed requirement from schools and propose appropriate technical solution

Page 27: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Wi-Fi.HK Service• It is outlined here for schools’ reference and consideration on

the related service requirements.• Authentication - landing page with Wi-Fi.HK logo, terms and

conditions and disclaimers but no registration/login is required for use of Wi-Fi.HK; users can use the free Wi-Fi service after accepting the terms and conditions in the landing page

• Content filtering - can also apply to Wi-Fi.HK though it is not mandatory

• Integration - the network for supporting Wi-Fi.HK shall be isolated from the School’s network without direct access; connections via Wi-Fi.HK shall have access to the Internet only

• Helpdesk - service provider will provide hotline service and contact email for public enquiry of its service

Page 28: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Sample Requirement Specification

Page 29: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Remarks - UAT• 4.9 User Acceptance Test•

• 4.9.1 The Contractor shall conduct tests with the School before the service is officially accepted and subscription started. Tests shall include User Acceptance Test for reliability and performance of the hardware and software, and also the monitoring, operation support and all other aspects related to the Service Level Agreement of the Service. At least 14 school working days of trial period is expected for service monitoring after testing.

Page 30: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Remarks – Sub-Contracts

Page 31: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Remarks – Service Level Rebates and Termination of Service

Page 32: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Sample System Test

Page 33: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Sample UAT

Speed Test: OFCA tool, HK Education City

Page 34: Briefing Session for the ICT Sector on the Enhancement of ... · • 4.9 User Acceptance Test • • 4.9.1 The Contractor shall conduct tests with the School before the service is

Enquiry• http://www.edb.gov.hk/ited/wifi900

• Use of Funding: (852) 3698 3606 • Professional Development Programmes: (852) 3698 3610• Technical Advisory Service: (852) 3698 4148 / 3698 3566