britannia’s low rate well strategy - alrdc egwdc... · © 2012 britannia operator limited...
TRANSCRIPT
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
Britannia’s Low Rate Well
Strategy
Eduard Nederlof Britannia Operator Limited 7th European Conference on Gas Well Deliquification, Groningen, September 26th 2012
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
2
Introduction
Low Rate Well Strategy
Challenges
Lessons Learned & Best Practices
Outline
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
3
One of the largest gas-condensate
fields developed on the UKCS
• IGIP 4 TCF
• At plateau contributed 10% of
total UK gas supply
Operated by Britannia Operator Ltd.
(BOL):
• 50% ConocoPhillips
• 50% Chevron
Britannia Field – Location Map
58.65% 32.38%
8.97%
Conoco
Phillips Chevron
BP Britannia
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
4
Britannia Field – Installations
Britannia
Steel Jacket Platform
43 wells
Subsea Centre at 15 km
9 subsea wells
Satellites
Callanish at 25 km
4 Oil wells
Brodgar at 41 km
2 Gas condensate wells
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
5
Fladen Ground
Spur
16/26 16/27a
15/30 15/29a
stratigraphic pinch-out
Gas-liquid-contact
Britannia Field
Witch Ground
Graben B01 B02
B03
B04
B05
B31
B12 B35
B10
B27
B14 B08
B29 B20 B11Z
B15
B33
B06
B21
B28
B17 B23Z B07
B19
B13Z B30
B26 B16
B34
B22 B09Z B25Z
B32 B24 16/26-23
16/26-26
16/26-5 16/26-9
16/27A
-6
16/26-24 16/26-16
B36
B38Z
B37 B18
B40
16/26-2
16/26-29
16/27B-4
Z
16/27A-
7
16/26-21Z
16/26-21 15/30-13
M06
M04
M08
M01
M03
M02
M09
M07
M05Z
M10
15/30-3
15/30-9
15/30-6
15/30-7
15/30-12
15/30-2
15/29A-5
15/29A-14 15/29A-7
15/29A-3
15/29A-8 15/29-2
15/29A-6 15/29A-11
15/29B-4Z
15/30-4
16/26-1
16/26-4 16/26-19
B41Z
B40Z
16/27a-3
B45
B44
Platform Area
Sub-sea Centre
Depth (x1000ft) -13 -12.5 -12 -11.5 -11
Britannia Field – Top Structure Map
0 2 4 km
Geology/Static Properties
Crest at 11,800 ft TVDSS
Average reservoir thickness 300 ft
Average porosity 15%
Average permeability 20 mD
Fluids/Reservoir Properties
Initial CGR 70-100 bbl/MMscf
Initial pressure 5,990 psia
Dew point 5,600 psia
Temperature 275 oF
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
6
Low Rate Well Strategy
Inflow Performance
• Re-Perforation
• Solvents
• Acidizing
• Hydraulic Fracturing
Vertical Lift Performance
Composite Performance
• Compression
• Wet Gas Metering
• Jet Pump Use
• Production Optimization
Applied / trialled / engineered / ready for application
Pending projects being analyzed / progressed
Being considered
• Cap Strings + Foam
• Isolation Plugs
• Velocity Strings
• Plunger Lift
Rejected
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
7
Inflow Performance
• Re-perforating wells (since 2007)
Vertical Lift Performance
• Batch foamer treatments (since 2008)
• Continuous foam injection (SPE 130672) (since 2009)
Composite performance
• Production Optimization - cycling wells (since 2007)
• Compressor Re-wheel (2009)
Opportunities Realized
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
8
Well Cycling & Batch Foamer Treatments
0
10
20
30
40
50
60
70
80
28-A
ug
-10
30-A
ug
-10
01-S
ep
-10
03-S
ep
-10
05-S
ep
-10
07-S
ep
-10
09-S
ep
-10
11-S
ep
-10
13-S
ep
-10
15-S
ep
-10
17-S
ep
-10
19-S
ep
-10
21-S
ep
-10
23-S
ep
-10
25-S
ep
-10
We
llh
ea
d P
res
su
re [
bar]
0
10
20
30
40
50
60
70
80
Flo
wli
ne
Te
mp
era
ture
[d
eg
C]
Liquid loading well -
frequent low pressure
routing necessary
(cycling)
Liquid loading well post-batch foamer treatment -
less frequent low pressure routing necessary
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
9
Capillary String Installation Options
Wellhead Modification
Option:
•Install tubing bonnet with
injection mandrel
•Lock out TRSV – primary
control line
•Run lower cap string
•Connect WISV to lower cap
string and set
•Run upper cap string and
sting into WISV
Primary control line obsolete
Secondary control line controls
WISV
Legend:
Tubing
Primary control line
Secondary control line
Capillary string
Safety Valve
Safety Valve Cut Option:
•Lock out TRSV
•Make cut in TRSV body
•Run lower cap string
•Connect WISV to lower cap
string and set – seals both
control lines separately
Primary control line to inject foam
Secondary control line to operate
WISV
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
Alternative to capillary string
Advantages
Lower Opex
Interventions/ logging possible
Batch foamer
Disadvantages
Reduced rate
More complex and challenging installation
10
Velocity String
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
11
Composite performance, medium term
• Facilities upgrade, lower topsides pressure to ~6-7 bar
Vertical Lift performance, long term
• Low rate wells workover development
(capillary / velocity strings)
Potential satellite tie-in
Future Opportunities
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
12
Production Prediction
Time
Ga
s R
ate
Low Rate Well Work Over Development
Long Term Compression
2010 New Wells
2011 Capillary Strings
Cycling
Base
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
13
1. Assessing effect of individual well solutions on
neighboring wells in a well connected field
2. Adapting and implementing “new technology”
3. Changing operating philosophy
4. Modeling liquid loading
Challenges
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
14
1. Consider technologies/strategies early in field life to
delay liquid loading problems
2. Develop and implement a range of remedial solutions to
address liquid loading
3. Well design to consider well interventions
4. Implement easy, low cost/high impact solutions
Lessons Learned & Best Practices
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
Britannia Operator Limited
– Peter Fowler, Richard Reverol, Bruce Bremner, Linda van der Bol
Conocophillips
BP
Chevron
15
Acknowledgements
© 2012 Britannia Operator Limited CONFIDENTIAL – This information is proprietary to BOL and is to be used, disclosed or reproduced only under
permission granted by BOL. All rights reserved.
QUESTIONS?