Page 1: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

Brookland Middle School

Community Meeting

November 16, 2013

Page 2: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

AGENDA

• Introductions

• Design Update

• Schedule & Work Hours Update

• Construction Update

• Affect on DPR Facilities

• Next Steps

Page 3: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

SITE PLAN

Page 4: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

DESIGN UPDATE

SCHOOL SITE

Page 5: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

DESIGN UPDATE

EXTERIOR RENDERING

Page 6: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

SCHEDULE & WORK HOURS

UPDATE

SCHEDULE

• Students and staff to occupy building 2015-16 school year

• Construction to complete in January 2015

WORK HOURS

• Work to take place during standard DCRA work hours

7AM-7PM Monday through Saturday

• No applications for extended work hours

Page 7: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

CONSTRUCTION UPDATE

ACTIVITY SCHEDULE

COMPLETE

• Building demolition

• Ground improvements

ONGOING & UPCOMING

• Concrete foundations and

waterproofing

• Steel structure

• Geothermal Well Drilling (Requires closure of baseball

field and track from December 1, 2013 – April 15, 2014)

Page 8: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

CONSTRUCTION UPDATE

PARK USAGE

WORK ACTIVITY TIMEFRAME

Ongoing DPR modernization of Turkey Thicket park Present –

December 2013

Baseball field and track closed during geothermal well drilling and

field restoration

December 2013 –

April 2014

Basketball courts closed during expansion of Turkey Thicket

parking lot and basketball court relocation

April 2014 –

May 2014

Two (2) Tennis courts closest to school not in use during school

structure and façade work

Present –

October 2014

All eight (8) tennis courts closed during court re-surfacing October 2014

Page 9: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

CONSTRUCTION UPDATE

CONSTRUCTION ACTIVITY

STRUCTURE / SKIN

Present – December 2013

Two (2) Tennis courts closest to

school not in use during school

structure and façade work

(Present – October 2014)

Page 10: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

CONSTRUCTION UPDATE

CONSTRUCTION ACTIVITY

GEOTHERMAL & FACADE

December 2013 – April 2014

Two (2) Tennis courts closest to

school not in use during school

structure and façade work

(Present – October 2014)

Baseball field and track closed during

geothermal well drilling and field

restoration (Present – October 2014)

Page 11: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

CONSTRUCTION UPDATE

CONSTRUCTION ACTIVITY

INTERIORS

May 2013 – January 2015

Tennis courts get resurfaced

in October 2014

Parking lot expanded and basketball

courts relocated during April & May 2014

Page 12: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

NEXT STEPS

• Next SIT Meeting in December 2013

• Focus on interior finishes and design

• Resume “envelope” meetings

• Monthly updates to be e-mailed at end of each

month

• Community Meeting in February 2014

Page 13: Brookland Middle School Community Meeting (November 16, 2013)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013