brown institute of education - amazon...
TRANSCRIPT
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Hawkins\BrownInstitute of Education
MasterplanExecutive Summary
March 2014
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Introduction
What is the Masterplan?The Royal Institute of British Architects (RIBA) sets out the process and protocol for developing a building from appraising the client’s requirements through to post construction. The process is set out as key work stages which describe the activities of the Architect at each of these stages. The other consultants’ work stages run approximately parallel to the RIBA work stages.
This study is the output of RIBA Stage 1 (Preparation). During this phase of work the Design Team will review the Institute of Education’s strategic objectives, develop the initial strategic brief through consultation with key project stakeholders, identify potential constraints on these aspirations and develop design options.
The Masterplan report will collate this information into a single coherent document to enable the client to make an informed decision on whether the project satis�es the client’s strategic objectives, and should proceed to the next stage of design – RIBA Stage 2 (Concept).
Please note that this document references the ‘new’ RIBA Plan of Work 2013 illustrated opposite, introduced in May 2013. This new document replaces the former linear structure with a gridded matrix of activities. This new structure is intended to re�ect the complexities of developing and delivering contemporary construction projects.
Plan of Work 2013
1 2 3 4 5 6 7Preparation Concept Design Developed Design Technical Design Specialist Design Construction Use & Aftercare
Description of Key Tasks
- Identify Project Objectives, the client's Business Case , Sustainability Aspirations and other parameters or constraints and develop the Initial Project Brief.
- Examine Site Information and make recommendations for further information, including surveys, required.
- Preparation of Feasibility Studies and assessment of options to enable the client to decide how to proceed.
- Determine client's Risk Pro�le and agree the Project Programme and preliminary Procurement Strategy.
- Assemble Project Team, agree Scope of Service, Contract Relationship and Design Responsibilities for each participant. Develop BIM and Soft Landings Strategies, Information Exchanges and conclude Appointment Documents.
- Preparation of Concept Design including outline proposals for structural design, services systems, site landscape, outline specifications and preliminary cost plan along with environmental, energy, ecology, access or other Project Strategies.
- Agree developments to Initial Project Brief and issue Final Project Brief.
- Review Procurement Strategy, finalise Deisgn Responsibility including extent of Performance Speci�ed Design and take action where required.
- Prepare Project Manual including agreement of Software Strategy, BIM Execution Plan and extent of Performance Specifed Work.
- Prepare Construction Strategy including review of off-site fabrication, site logistics and H&S aspects.
- Preparation of Developed Design including co-ordinated and updated proposals for structural design, services systems, site landscape, outline specifications, cost plan and Project Strategies.
- Prepare and Submit Planning Application
- Implement Change Control Procedures, undertake Sustainability Assessment and take actions determined by Procurement Strategy. - Review Construction Strategy including H&S aspects.
- Preparation of Technical Design information to include all architectural, structural and mechanical services information and specifications including the Lead Designer 's review and sign-off of all information.
- Performance Speci�ed Work to be developed in sufficient detail to allow development and integration by Specialist Subcontractors during Completed Design stage.
- Take actions determined by Procurement Strategy including issuing in packages where appropriate.
- Prepare and submit Building Regulations Submission
- Review Construction Strategy including sequencing, programme and H&S asepcts.
- Progression of Specialist Design by Specialist Subcontractors including the integration, review and sign-off of Performance Speci�ed Work by the Lead Designer and other designers as set out in Design Responsibility document
- Review Construction Strategy including sequencing and critical path.
- Undertake actions from Procurement Strategy or administration of Building Contract as required.
- Offsite manufacturing and onsite construction in accordance with the Construction Programme
- Regular review of progress against programme and any Quality Objectives including site inspections.
- Administration of Building Contract. .
- Resolution of Design Queries from site as they arise
- Implementation of Soft Landing Strategy including agreement of information required for commissioning, training, handover, asset management, future monitoring and maintenance and ongoing complilation of "as-constructed" information.
- Implementation of Soft Landings Strategy including Post Occupancy Evaluation.
- Conclude administration of Building Contract
- Review of Project Performance in use and analysis of Project Information for use on future projects.
- Updating of Project Information, as required, in response to Asset Management and Facilities Management feedback and modifications.
Procurement
Programme
Planning
The Initial Project Brief The Concept Design including Outline Structural and Mechanical Services Design, associated Design Strategies, Preliminary Cost Information and Final Project Brief.
The Developed Design including the Co-ordinated Architectural, Structural and Mechanical Services Design and Developed Cost Information.
The Technical Design of consultant aspects in sufficient detail to enable construction or Performance Speci�ed Work to commence.
The Specialist Design including the integration of Performance Speci�ed Work.
"As Constructed" Information. "As constructed" Information updated in response to on-going client feedback, Asset Management updates and Facilities Management information.
Government Gateway Information Exchange 1 Information Exchange 2 Information Exchange 3 Information Exchange 6 As Required
© RIBA 2012Royal Institute of British Architects
Figure 3: Draft diagram of the proposed new stages and overall framework
The Plan of Work organises the progress of designing, constructing, maintaining and operating building projects into a number of key Work Stages. The sequence or content of Work Stages may vary or they may overlap to suit the procurement method, the project programme and the clients risk profile.
Key Information
Exchanges(at stage
Completion)
Stage 4, 5 and 6 activities may occur concurrently depending on the Procurement Strategy. Work may also be undertaken in packages to facilitate its development by Specialist Subcontractors. Early package procurement may also occur during stage 3 depending on the procurement route. The Project Programme should set out the timesscales for these overlapping design and, where appropriate, construction stages.
The stage 1, 2, 3 and 4 outputs may be used for tendering and contract purposes depending on the Procurement Strategy as influenced by the clients Risk Pro�le, time, cost and quality aspirations and how Early Contractor Involvement and Specialst Subcontractor input is to be undertaken.
Planning Applications typically be made using the stage 3 (Developed Design ) output, however, certain clients may wish this task to be undertaken earlier. The project or practice specific Plan of Work identifies when the Planning Application is to be made. Certain aspects of the Technical Design may also be required as part of the application or in respond to planning conditions.
RIBA Work Stages
6
IntroductionThe Institute of Education appointed Hawkins\Brown, Turley Associates and Gardiner and Theobald to create the Masterplan in August 2013. The aim of the Masterplan is to review the existing condition of the Estate and propose a spatial strategy that re�ects the short, medium and long term aspirations of the organisation.
Although the Institute has a clearly de�ned Strategic plan, the quality of many of the facilities do not currently embody the ambitions expressed in this document or meet the expectations of users and the standards that should be expected of an organisation of the Institute’s reputation.
The Institute occupies a number of beautiful and architecturally important properties; many of them listed. Historically, Strategic planning has not been carried out in a manner that the quality of the Estate and organisation requires so these properties are, unfortunately, being neglected. Capital projects mainly address a speci�c issue at a speci�c time. There is no framework or aspirational plan within which they can be set or assessed.
It should also be recognised that the Higher Education sector is becoming increasingly competitive. Students expect a good quality service for their fees. The standard of the current Institute Estate is below that of many competitor organisations. This has the potential to adversely impact on the Institute’s ability to fully compete for students and sta�.
Creating a Masterplan for the Institute and it’s facilities will help to set out a framework within which the Institute can move towards achieving its overall vision as articulated in its Strategic plan.
ContentsThis document contains a summary of the consultation process we have undertaken, the �ndings and the agreed priority projects together with some explanatory diagrams and visualisations.
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
ConsultationSummary of consultation undertaken and findings
We have carried out consultation with the following committees and groups in the production of this Masteprlan:
• Estates Committee, Project Board, Strategic Working Group
• Senior Leadership Group
• Student Forums, Teaching Forum, Workspace Forum
• 1:1 interviews held with key staff
• Open consultation afternoon for all staff and students
1. Creating a heart for the Institute in Bedford Way
Universal key findings were:
• The number of staff and students has increased substantially from when the IOE first occupied the building in 1977 and is expected to increase further in the next 5-10 years.
• Students consider there is a lack of appropriate social learning space, group study space and quiet study space.
• The student space currently on level 3 is not easily accessible and is not fit for purpose; students do not like to spend a long time there.
• The demographic of the IOE as a mainly post-graduate Institution means that student facilities and working areas need to be aimed at a more mature student base.
• Students are demanding better facilities for their course fees.
• Staff and students find a lack of good informal meeting spaces.
• There is a bottleneck in the circulation between the Western facade and the grand stair to the Level 1 halls.
2. Improving the student experience
It has been identified that there are two groupings of students that have distinct needs; Doctoral/ PGR students and MA, PGCE, Undergraduate and short course students. PGR students require more permanent workspace in the building that the latter group.
Other issues that the student forums we have held have raised are that there are a number of facilities that need improving, are not provided at all or are not accessible to students:
• More, acoustically separate, group study spaces are needed both within the library and student space so that quiet working is not affected by the PGCE and Undergraduate project work.
• The food offering in the Student Union area is not appropriate or open long enough; therefore the roller shutter in this area makes it feel unwelcoming.
• The demographic of the IOE as a mainly post-graduate Institution
• Lockers are needed for students who travel in from a distance; these should be ‘hot’ lockers for daily use.
• Printing facilities need to be advertised more widely.
• Teaching space needs to be improved, both in quantity and quality.
• Toilet areas are insufficient and poor.
• Computer rooms can be busy when PGCE students are in the building.
This diagram colours the current social and circulation area blue. There is minimal circulation and informal meeting space in the reception area for the demand. Student spaces are not visible or accessible from this space and the Western courtyard is underutilised.
Top: The level 4 entrance does not reflect the aspirations of the IOEBelow: The student area is not easily found from this space; it is at the end of this corridor, down a set of stairs.
Above: The level 3 student area is not inspiring, suffers from competing food offers and students do not like to spend a lot of time there.
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
single office
shared office
SHARED WORKSPACE
open meeting space
storage
central:
printerswastepost collectionrecyclingteapointcommunal room space
meeting spaceshared
office
meeting space
single office
single office
shared office
open meeting space
3. Increasing and improving teaching space
The number of students taught at the IOE has been increasing steadily and is expected to continue to increase.
This means a shortfall of teaching spaces across the campus and we have been working with the timetabling and academic sta� to establish the most common teaching group sizes and the quantity of rooms required to teach this number of students.
The IOE have begun a refurbishment programme and the proposals link to this, so that works have not been abortive.
It has been found that teaching space in the Georgian terraced properties is not heavily used because it is too distant from the main centre of the campus, is not �exible enough and has poor IT and toilet facilities. It is preferable for all teaching space to be located within the 20 Bedford Way building.
We have also reviewed the specialist space provision. One of the issues with allocating this is that the IOE can not determine it’s PGCE student numbers - this is Government de�ned. This is an issue for all subjects, but especially the specialist ones.
4. Creating more e�cient workspaces
This topic has been one of the most widely discussed. We have held a number of 1 to 1 discussions with sta� and Heads of Departments, as well as a workspace forum. We also presented at the Senior Leadership Team event in September to broaden the discussion about work practices and ways of using the increasingly limited space within the Estate more e�ciently.
The current patten of allocating every member of sta� an o�ce has not been sustainable over and number of years and the IOE are �nding it hard to locate people adjacent to those they should be near and to �nd appropriate space for them to work in. A more �exible approach is required, and one that is based on roles rather than pure hierarchy, as has historically been the case.
The desire is to move to more collaborative working with more visual connection between spaces. This needs to be implemented across the Georgian properties that they own as far as possible, as well as Bedford Way. This will aid the cohesive nature of the academic community.
We also need to account for Doctoral student hot desking, based on a 10% provision. Based on 11% growth from 900 to 1000 students in the next 5-10 years, this would be 100 desk spaces.
Above: A diagram representing the �exible working model the IOE would like to implement across their Estate. The key to this would be visual connections between the spaces and the provision of central communal welfare facilities.
Existing teaching spaces require remodelling and a review of their distribution.
Existing workspaces are mainly behind closed doors, located o� corridors; they are not appropriate to modern ways of working.
ConsultationSummary of consultation undertaken and findings
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
6. Usage of the Estate to generate additional income
As well as student fees and research grants the IOE uses its Estate to generate income. There are several ways they currently do this:
• Letting out the level 1 halls for conferences and providing catering
• Renting student residences, and when not in use to conference guests
• Renting office space to third parties who have a related discipline
Some problems have been found with all of the above sources of income:
Level 1
• Circulation routes on level 1 do not facilitate use of the halls simultaneously. External bookings can disrupt teaching. When these spaces are not used for teaching it would be beneficial to be able to let them simultaneously.
• Toilet provision is insufficient and not accessible.
• The accommodation could be of a higher quality, considering it’s prime location in central London.
Student residences
• Many of these are poor quality, especially those in Woburn Square. It is considered this location would be better suited to research academics.
• Endsleigh Gardens is a difficult property to deal with as the lower floors are offices and the upper floors are residences. The staff here should be located with the other Professional Services in Bedford Way.
• The student residences are difficult to manage and do not make a profit.
Office space
• When workspace is so tight for IOE staff and facilities the IOE will review what it rents to external parties. Some of this space could be reserved for specially funded research projects.
5. Dealing with the split campus and buildings of different eras
Unfortunately the IOE has outgrown it’s main home Bedford Way and has spread into a number of historic Georgian properties in the surrounding area. While beautiful, these spaces are often not the most appropriate for creating a collaborative working environment, due to their closed cellular nature and restrictions on working with the listed fabric. However, the academics are very fond of their buildings.
In order to consolidate the campus and become more space efficient the IOE would like to adjust their use of these properties through the following means:
• Increasing use of visual connections either through door vision panels or glazed panels within walls to create a more collaborative environment.
• Improve accessibility.
• Increase the potential use of the buildings, by upgrading IT and opening out rooms, within the sensitivities of working with historic fabric.
• Introduce lateral links where possible to open out the buildings and provide an environment as similar as possible to that in Bedford Way.
• Add cycle parking and associated facilities, such as showers and changing rooms.
• Add central communal facilities, such as teapoints, seating and printers.
• Maintain the local meeting room provision but link these rooms to the central booking system so occupancy can be monitored.
• As noted, centrally bookable teaching space is not appropriate for these properties due to location, flexibility and support facilities.
ConsultationSummary of consultation undertaken and findings
The historic Georgian properties should be used in a way that suits their sensitive historic fabric, but allows them to be useful as modern workspaces for the IOE as well.
The circulation routes and lecture halls needs improving and upgrading on Level 1 of Bedford Way.
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Constraints & Opportunities20 Bedford Way
Level 9 Music teaching requires space for larger groups and practice rooms, with sound-
proofing.
Level 9 Science teaching requires more flexible labs and remodelling of the prep
spaces.
Level 8 Art teaching has good daylight due to studio arrangement, but the spaces are
not large enough for the group sizes. More IT infrastructure is required.
Central teaching and offices are on the upper floors of the building. Departments have been arranged in a disparate fashion due to organic
growth. Faculty administrators are organised in cellular offices, which makes it difficult to find
them.
Level 6 Staff dining area is not open long enough and is not well located. The kitchen is
too small as it also covers conference catering.
Levels 3-5 The Library is well used and popular and access to the archives is
increasing, but more space is needed, especially for group study.
Level 4 Main entrance and reception is on level 4, but accessibility is poor from Bedford
Way. There is little social learning and informal meeting space available.
Level 3 Student Union space is not an inspiring environment. Accessibility to the conference
facilities and Student Union is poor.
Level 2 Estates areas, storage, records archiving need to be re-worked. Cycle storage
is required.
Level 1 circulation is difficult, the green room is in poor repair and wcs are insufficient.
This diagram shows the current organisation with constraints and opportunities of the Bedford Way building.
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
It is considered that the main significance of the listed building is derived externally from its bold expression of its structure and function, distinctive massing and form, and use and quality of materials. It also shares a close architectural relationship with the nearby SOAS building across a shared plaza and landscaped pedestrian route (Queen’s Walk).
The original design concept for the site was not fulfilled with only one of the intended five rear wings being built and the enclosure of the Western entrance plaza incomplete. The Level 5 walkway on this facade was also never utilised due to the wings never being completed.
It is our opinion that the original character of the exterior of the building remains strong, especially along Bedford Way. However the design has been robust enough to successfully accommodate further extension with the addition of the deferential library wing on the West, for example.
Internally there are a number of key elements of the original design, which are described in the listing notice and we feel are part of the special character of the building. These include the key circulation and communal spaces of the two level foyer, main staircase and atrium down to the lecture halls, and the lift and stair cores (A, B and C).
It is worth noting that the entrance sequence was altered during the 1990s as well, with the addition of the external staircase to bring people directly into a main reception on Level 4. We assume this was in response to the fact that most people who know the building will enter onto level 4 from the West. This does however, create accessibility issues, which we have reviewed later in the document.
Other areas we have proposed changes to are the level 3 social area, which is currently occupied by the Student Union, together with its connection to the main reception area and the level 4 area above.
The upper floors, are documented as having been specifically designed to be flexible and we have suggested remodelling these to provide more efficient workspaces and flexible teaching spaces. We feel this is in keeping with the original design intent of the building.
As described above the IOE only occupies the building around the central 3 cores.
History and Status20 Bedford Way
Top and bottom left: Current Bedford Way elevation.
Bottom right: West wing, showing distinctive,
sculptural fire escape
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Top: 1967 Masterplan showing full building with 5 wings to the Western precinct, intended to enclose courtyard spaces of differing characters.Far right: Image from 1977 showing intent of cladding to reflect vertical proportion of surrounding Georgian terracesRight: 1967 Masterplan plan, showing SOAS library in relation to the Bedford Way building
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Design SolutionsImproving the heart of the Institute
Current situationLack of social learning and informal meeting space on
level 4. No visual connection with student space on level 3 and under-utilised Western courtyard,
Phase 1Extend envelope on SE corner level 4 and move
student social learning area to this level. Level 3 can be used for staff dining, supported by a suite of meeting rooms. This can be used to welcome visiting funders
and policy makers.
The glazing on the Western facade is in poor repair. We would seek to replace this sensitively, within the existing proportions, but to integrate sliding panels so the reception space can extend outside in good
weather.
Phase 2Add a double height glazed element to the Western
facade to increase circulation, informal meeting space and usable internal floor space. Improve entrance to
library. This also gives the opportunity of bringing the walkway into use as an internal circulation route; it is
not currently use as the ends are blocked off.
As the original wing was never built to enclose the courtyard it is considered that this mass could be read as a continuation of the library massing. Or it could be
detailed as a clearly separate and distinct new addition. We would welcome discussion.
Showing the underutilised western
courtyard and existing facade
It is considered that extending the envelope at the south east
corner of level 4 would not be detrimental to the overall
massing of the wing.
The current enclosure for the stair into the student social area is not in keeping with the quality
of the main facade, so extending the envelope here would improve
the external appearance.
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Design SolutionsImproving the heart of the Institute
Kitchen large enough to serve 2 areas and cater for conferences
Stair and lift from social learning area level 4. Also connects with level 1 and 2.
Servery area
Dining area for staff and visitors
Suite of meeting rooms to support level 1 conference area or be used for meeting with visiting funders, academics, policy makers etc
Servery, bar and welcome area for student union
Long opening hour cafe for PGCE, master and PGR students
Quiet informal study benches and seatings along south window for PGR and master students
New stair and lift to lower floors
Soft furniture for group study and informal discussion
Student Union reception
Flexible space for temporary functions of events
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Design SolutionsExisting Entrance
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Design SolutionsProposed Entrance
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Design SolutionsProposed New Student Space
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Design SolutionsProposed New Formal Dining Area and Suite of Meeting Rooms
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Design SolutionsImproving the student experience, teaching space and effective space use
increased, and improved specialist teaching for Science, Music and Art
central teaching space (yellow) on top floorsacademic enquiries arranged near teaching
workspaces mainly arranged around levels 5-6 and provided with central communal facilities such as teapoints, seating, post
collection and waste/ recycling areas
minor remodelling in Library space and review of the Thornhaugh Mews
development to see if more space can be made available
student printing to be relocated near the computers
student enquiries retained on level 4
Western courtyard re-landscaped and accessibility improved to all parts of the
building
improved student social learning at level 4with bar, servery and eating space supported
by other services such as shop and events spaces; this will also allow the terraces to be
used more effectively
formal suite of meeting/ committee rooms supported with servery and dining space
lockers and cycle space to be provided at level 2, accessed from the service road
additional wcs and circulation opened out to create more viable lecture theatres at level 1
Project
Drawing
Drawn by
Checked by
Status
Job Number
Date
Scale
Drawing No. & Revision
HB1477
Institute of Education
20 Bedford Way
Copyright Hawkins Brown Architects LLP
No implied license exists. This drawing should
not be used to calculate areas for the purposes
of valuation. Do not scale this drawing. All
dimensions to be checked on site by the
contractor and such dimensions to be their
responsibility. All work must comply with relevant
British Standards and Building Regulations
requirements. Drawing errors and omissions to
be reported to the architect.
RevisionsRevisions
JQ14.01.14
Preliminary
LB
20 Bedford WayLevel 3 Proposed Plan
1477-A-DWG-00-203-P3
1:250 @A1
KITCHEN
STAFF DINING
SUITE OF MEETING ROOMS
SERVERY
LIBRARY
WORK SPACE
CORE C
CORE B
CORE A
ITSUITESTUDIO
BOOKSHOP
SERVER
LIBRARYARCHIVES
PRAYER ROOM
NOTE:This plotfile has been generated from measured survey information received from Ridge.
Centrally bookable teaching/
meeting space
3rd PartyEstates & Facilities
Library/ Library Store
Workspace
KEY:
Plant/ WCs/ Risers
Communal Facilities
IT Services
Circulation
Students' Union
N
No. Date
Comment
Checked By
Drawn By
P1 06.12.13
Issue for Information
LB
JQP2 19.12.13
Issue for Information
LB
JQP3 14.01.14
Issue for Information
LB
JQ
Project
Drawing
Drawn by
Checked by
Status
Job Number
Date
Scale
Drawing No. & Revision
HB1477
Institute of Education
20 Bedford Way
Copyright Hawkins Brown Architects LLP
No implied license exists. This drawing should
not be used to calculate areas for the purposes
of valuation. Do not scale this drawing. All
dimensions to be checked on site by the
contractor and such dimensions to be their
responsibility. All work must comply with relevant
British Standards and Building Regulations
requirements. Drawing errors and omissions to
be reported to the architect.
RevisionsRevisions
JQ06.12.13
Preliminary
LB
20 Bedford WayLevel 4 Proposed Plan
1477-A-DWG-00-204-P1
1:250 @A1NOTE:This plotfile has been generated from measured survey information received from Ridge.
Centrally bookable teaching/
meeting space
KEY:
Plant/ WCs/ Risers
Computer Area
Library
Circulation
DirectorateDoctoral School
Socail
Kitchen
Workspace
N
No. Date
Comment
Checked By
Drawn By
P1 06.12.13
Issue for Information
LB
JQ
Project
Drawing
Drawn by
Checked by
Status
Job Number
Date
Scale
Drawing No. & Revision
HB1477
Institute of Education
20 Bedford Way
Copyright Hawkins Brown Architects LLP
No implied license exists. This drawing should
not be used to calculate areas for the purposes
of valuation. Do not scale this drawing. All
dimensions to be checked on site by the
contractor and such dimensions to be their
responsibility. All work must comply with relevant
British Standards and Building Regulations
requirements. Drawing errors and omissions to
be reported to the architect.
RevisionsRevisions
JQ06.12.13
Preliminary
LB
20 Bedford WayLevel 5 Proposed Plan
1477-A-DWG-00-205-P1
1:250 @A1NOTE:This plotfile has been generated from measured survey information received from Ridge.
Centrally bookable teaching/
meeting space
KEY:
Plant/ WCs/ Risers
Computer Area
Library
Circulation
Workspace
Socail
N
No. Date
Comment
Checked By
Drawn By
P1 06.12.13
Issue for Information
LB
JQ
Project
Drawing
Drawn by
Checked by
Status
Job Number
Date
Scale
Drawing No. & Revision
HB1477
Institute of Education
20 Bedford Way
Copyright Hawkins Brown Architects LLP
No implied license exists. This drawing should
not be used to calculate areas for the purposes
of valuation. Do not scale this drawing. All
dimensions to be checked on site by the
contractor and such dimensions to be their
responsibility. All work must comply with relevant
British Standards and Building Regulations
requirements. Drawing errors and omissions to
be reported to the architect.
RevisionsRevisions
JQ06.12.13
Preliminary
LB
20 Bedford WayLevel 6 Proposed Plan
1477-A-DWG-00-206-P1
1:250 @A1NOTE:This plotfile has been generated from measured survey information received from Ridge.
KEY:
General Storage
Workspace
Circulation
Socail
Plant/ WCs/ Risers
Centrally bookable teaching/
meeting space
N
No. Date
Comment
Checked By
Drawn By
P1 06.12.13
Issue for Information
LB
JQ
MALEWCFEMWC
WCFEM
MALEWC
MALEWC
FEMWC
New doors vision panel/ Saltolock
11 teaching spaces
Project
Drawing
Drawn by
Checked by
Status
Job Number
Date
Scale
Drawing No. & Revision
RevisionsRevisions
JQ19.12.13
Preliminary
LB
20 Bedford WayLevel 1 Proposed Plan
1477-A-DWG-00-201-P2
1:250 @A1NOTE:This plotfile has been generated from measured survey information received from Ridge.
N
Centrally bookable teaching/
meeting spaceCirculation
KEY:
General StoragePlant/ WCs/ Risers
Kitchen
Student FacilitiesThis diagram shows the proposals for reorganising the Bedford Way building to provide more accessible services, teaching and workspaces.
Teaching SpaceThe plans opposite contain the teaching space now required to serve the student body.
Science (level 9)We will be maintaining the current lab provision, but improving the prep areas and adding a fume hood.
Music (level 9)Music practice rooms will be added and teaching remodelled so that a larger space is available.
Art (level 8)The storage and support spaces will be remodelled to increase the size of the current studios.
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Design SolutionsCampus principles
The concept is to re-focus as much activity as possible around the Bedford Way building to re-introduce a core into the campus. Residential units within Woburn Square can be renovated into office space for research groups. This and the building of Thornhaugh Mews can free up space to move the staff in Endsleigh Gardens back to the main campus core.
©Hawkins\Brown Institute of Education - Masterplan Executive Summary - March 2014
Next StepsPriority Projects
As discussed with the Project Board there are a number of priority projects.
• Improved social learning and meeting spaces - New stair and lift to connect levels 1-4 - Central kitchen on level 3 - Level 3 and 4 staff and student social and meeting space
• 24-28 Woburn Square and 10-18 Woburn Square
• A pilot scheme for the workspace proposals
• Level 1 conference facilities
• Thornhaugh Mews
• Improving accessibility to the main Bedford Way entrance
• Western courtyard landscaping
The Final Recommendations from the study included:
• IOE to develop a management strategy to ensure internal and external resources are in place to deliver the Masterplan and Priority Projects
• Research external decant opportunities so that workspace and teaching space can be refurbished
• Detailed Project Programme to be drawn up in line with expected cash flow and critical times of year for the IOE
• Appoint a full design team to progress the Priority Projects to detailed planning and Listed Building Consent
• Review areas for further investigation
• Heritage Partnership Agreement to be developed for the Bedford Way buildings