Brunswick High School
Feasibility Study – Meeting #02
January 24, 2019
![Page 2: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/2.jpg)
Today’s Agenda
1. Welcome
2. Schedule
3. Assessment Findings
4. Building Zones
5. Site Analysis
Q+A
![Page 3: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/3.jpg)
AprMarFebJan
Design Phase
May
Data Collection
Report Preparation
Committee Meetings
Community Meetings
Mtg #2 Jan 24th
Final Report
Preliminary Report Draft Report
Project Schedule
BHS Site Visit Jan 14th
Feb 7th Mar 7th Apr 24th
![Page 4: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/4.jpg)
MEETING DATE TIME LOCATION AGENDA
FS Committee Meeting #1 1/10/2019 2:00pm FCPS Building Project Kick-off
FS Committee Meeting #2 1/24/2019 2:00pm FCPS Building Assessment Findings
Student Workshop 2/7/2019 1:00pm Brunswick HS - TBDProject Introduction, Stakeholder
Input
FS Committee Meeting #3 2/7/2019 2:00pm Brunswick HS - TBD Ed Spec Review
Community Meeting #1 2/7/2019 6:00pm BHS AuditoriumProject Introduction, Stakeholder
Input
FS Committee Meeting #4 2/21/2019 2:00pm FCPS Building Concept Options - initial
Preliminary Report to FCPS 2/28/2019
FS Committee Meeting #5 3/7/2019 2:00pm FCPS Building Concept Options - refinement
Community Meeting #2 3/7/2019 6:00pm BHS Auditorium Concept Options – feedback
FS Committee Meeting #6 3/21/2019 2:00pm FCPS Building Concept Options - refinement
FS Committee Meeting #7 4/4/2019 2:00pm FCPS Building Review Draft Report
Community Meeting #3 4/24 or 4/25 6:00pm BHS AuditoriumPresent Final Options and
recommendations
Draft Report to FCPS 4/10/2019
FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required)
Final Report to FCPS 4/24/2019
BOE Due Date 5/1/2019 FCPS Building
BOE Meeting 5/22/2019 FCPS Building
Project Schedule
![Page 5: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/5.jpg)
1. What one thing would make your new high school a success?
Stakeholder Engagement
1
Themes:
• Modern facility
• Optimize learning
opportunities
• Prepare students for success
![Page 6: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/6.jpg)
2. What is unique about the existing Brunswick High that should be considered in this study?
Stakeholder Engagement
1
Themes:
• History
• CTE programs
• The caboose
• Scale / Feel
![Page 7: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/7.jpg)
3. What are your hopes + aspirations for this feasibility process?
Stakeholder Engagement
1
Themes:
• Collaborative Process
• Listen to Community
• Address the Issues
![Page 8: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/8.jpg)
Brunswick HS Improvements Timeline
1963 Original Building
1965 Year Occupied
1977 Stadium Press Box
1979 Vo-Tech Shop Addition
1982 Vo-Tech Addition
1989 Fire Sprinkler
1990 Auditorium Renovations
1991 Stadium Bleachers
1992 Gymnasium Addition
1993 Concession Stand + Restrooms
1998 Roof Replacement
2002 Boiler Replacement
2003 Technology Cabling / Voice-Data Network
2005 Gymnasium Roof
2009 Chiller/Cooling Tower Replacement
2011 HVAC Piping Replacement
2013 Security Vestibule
2015 Unit Ventilator Replacement
2016 Stadium Lighting
2017 Tennis Court Replacement
2017 Parking Improvements
2019 System upgrades?
![Page 9: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/9.jpg)
Building Assessment Findings
EXTERIOR WALL ITEMS
• 2” rigid insulation, no cavity
• Original single-pane windows
• No evidence of air + vapor barrier
• Steel columns+ channels exposed
• Researching investigative testing
![Page 10: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/10.jpg)
Building Assessment Findings
ROOF ITEMS
• Gypsum deck on rigid foam board
spanning bulb tee supports
• Originally 1” insulation
• Roof replaced in 1989
• FCPS 2018 roof report scores
2.5 – 3.0 out of 4, no leaks
![Page 11: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/11.jpg)
Building Assessment Findings
CODE + LIFE SAFETY ITEMS
• Building is fully sprinklered
• Stairs are not rated exit enclosures
• Handrails + guardrails not compliant
• Open risers
![Page 12: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/12.jpg)
Building Assessment Findings
ADA / ACCESSBILITY ITEMS
• Mechanical/CTE wing access
• Clearances @ door swings
• Door hardware
• Sound room not accessible
• Music room tiers not accessible
![Page 13: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/13.jpg)
Building Assessment Findings
TOILET ROOM ITEMS
• Typical fixtures not ADA-compliant
• Stalls recently replaced
• No accessible stalls
• Locker rm showers non-compliant
![Page 14: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/14.jpg)
Building Assessment Findings
STRUCTURAL ITEMS
• Structural steel exposed to exterior
• No vertical reinforcing in masonry
walls
• No expansion joints in floor; cracking
@ intersections
• Seismic/earthquake code
compliance - analysis
![Page 15: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/15.jpg)
Building Assessment Findings
MECHANICAL ITEMS
• Boiler + chiller capacity
• Plant has no room to expand
• Air handling equip @ at end of life
• High humidity problems due to
incompatible equipment
• Sewage backups @ locker rooms.
![Page 16: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/16.jpg)
Building Assessment Findings
ELECTRICAL ITEMS
• Main switchboard and most
branch panel boards are past
useful life
• Space/clearance in electrical room
• Lighting systems all original
• Older fire alarm system
![Page 17: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/17.jpg)
Building Assessment Findings
SITE ITEMS
• Flooding in loading/service area
• Insufficient site lighting
• Mixing of cars and busses at exit
• Backup at the light at Point of
Rocks Road
• Non-ADA compliant pedestrian
pathways + railings
![Page 18: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/18.jpg)
First Floor Plan
Existing Floor Plan
Second Floor Plan
![Page 19: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/19.jpg)
ACADEMIC
PHYS ED
PERF ARTS
CTE/MECHDINING
Existing Building Zones
![Page 20: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/20.jpg)
ACADEMIC
Existing Building Zones
ACADEMIC BLOCK
• Remedy stairs
• Internal rooms @ core
• Undersized Media Center
• ADA upgrades @ doors
• Toilet rooms
• Classroom inventory
• 13’-10” floor to floor
![Page 21: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/21.jpg)
Existing Building Zones ACADEMIC BLOCK
![Page 22: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/22.jpg)
DINING
Existing Building Zones
DINING BLOCK
• Undersized dining room
• Inadequate serving lines
• Aged kitchen equipment
• Trash + deliveries @
loading dock
• Courtyard is a plus
• Landlocked in plan
![Page 23: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/23.jpg)
Existing Building Zones DINING BLOCK
![Page 24: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/24.jpg)
PHYS ED
Existing Building Zones
PHYS ED BLOCK
• Gym < 30 years old
• Access to fields
• Underutilized lobby space
• Health Room location
• No wrestling room
• Room to grow on site
• Locker/shower updates
![Page 25: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/25.jpg)
Existing Building Zones PHYS ED BLOCK
![Page 26: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/26.jpg)
PERF ARTS
Existing Building Zones
PERFORMING ARTS BLOCK
• Separate back of house
• Limitations to theater
• Music Rooms split
• Access to sound booth
![Page 27: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/27.jpg)
Existing Building Zones PERFORMING ARTS BLOCK
![Page 28: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/28.jpg)
CTE/MECH
Existing Building Zones
CTE/MECHANICAL BLOCK
• Separate building, 2’ lower
• Supervision challenge
• Mech rm below grade
• Woodworking + digital arts
![Page 29: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/29.jpg)
Existing Building Zones CTE/MECHANICAL BLOCK
![Page 30: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/30.jpg)
Space
No. of
Spaces Net Sq. Ft.
Total Net
Sq. Ft.
Total Dept.
Sq. Ft.
No.
Teaching
Stations
General 23025
General Purpose Classroom 25 775 19375 25
Storage 3 350 1050
Conference/Planning Room 3 200 600
Collaborative Learning Spaces (Study) 10 200 2000
Restroom (Boys) (Existing) 0 0 0
Restroom (Girls) (Existing) 0 0 0
Resource Center Office / Seminar (Existing) 0 0 0
Science 14040
Lab, Biology 3 1360 4080 3
Lab, Chemistry 2 1360 2720 2
Lab, Physics 2 1360 2720 2
Lab, Physical Science 2 1360 2720 2
Preparation Area 2 200 400
Storage Room 4 300 1200
Chemical Storage Room 1 200 200
Technical Education
Foundations 14140
Foundations Lab 2 1900 3800 2
Storage 2 200 400
Classroom (Existing) 0 0 0
Foundations Support Rooms (Existing) 0 0 0
Restroom (Boys) (Existing) 0 0 0
Restroom (Girls) (Existing) 0 0 0
Restroom (Unisex) (Existing) 0 0 0
Computer Business Education
Computer Lab 1 1060 1060 1
Storage 1 100 100
Animal Science
Labs 1 1280 1280 1
Storage 1 200 200
Horticulture
Lab 1 1400 1400 1
Storage 1 200 200
Head House 1 300 300
Green House 1 1200 1200
Seminar Room (Existing) 0 0 0
Horticulture Support (Existing) 0 0 0
Auto Shop
Shop 1 3400 3400 1
Parts and Tools Storage 1 350 350
Classroom 1 450 450
Business Education 2050
Transition Education
Classroom 1 775 775 1
Storage 1 200 200
Business Program
Classroom/Lab 1 975 975 1
Storage 1 100 100
Family and Consumer Science/Life Skills 2575
Food Lab 1 975 975 1
Child Development Lab 1 1200 1200 1
Storage 1 300 300
Office 1 100 100
Living Room (Existing) 0 0 0
Grooming (Existing) 0 0 0
General Purpose (Existing) 0 0 0
General Purpose Toilet (Existing) 0 0 0
Draft BHS - 1300 SRC
Educational Specifications
Existing Building
Current Enrollment: 741
Current SRC: 893
Current GSF: 166,000
Ed Spec Assumptions
Target SRC: 1300
Target GSF: 204,540
Core Spaces Designed
for future expansion:
• Dining
• Media
• Auditorium
• Gym
![Page 31: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/31.jpg)
ACADEMIC
PHYS ED
PERF ARTS
CTE/MECHDINING
Existing Building Zones
Which Zones have the
highest value?
• Program
• Functionality
• Location
• Condition
• Other Factors?
![Page 32: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/32.jpg)
Feasibility Study Options
Renovation + Minimal Addition
Renovation /Modernization + Addition
Full Demolition + Replacement
![Page 33: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/33.jpg)
Site Plan
![Page 34: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/34.jpg)
Traffic Patterns
![Page 35: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/35.jpg)
BuildableAreas
Relatively flat, access thru PE
Sloped area, caboose, restroom bldg
Impacts service access
Flat area, displaces bus loop
![Page 36: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/36.jpg)
Space
No. of
Spaces Net Sq. Ft.
Total Net
Sq. Ft.
Total Dept.
Sq. Ft.
No.
Teaching
Stations
General 23025
General Purpose Classroom 25 775 19375 25
Storage 3 350 1050
Conference/Planning Room 3 200 600
Collaborative Learning Spaces (Study) 10 200 2000
Restroom (Boys) (Existing) 0 0 0
Restroom (Girls) (Existing) 0 0 0
Resource Center Office / Seminar (Existing) 0 0 0
Science 14040
Lab, Biology 3 1360 4080 3
Lab, Chemistry 2 1360 2720 2
Lab, Physics 2 1360 2720 2
Lab, Physical Science 2 1360 2720 2
Preparation Area 2 200 400
Storage Room 4 300 1200
Chemical Storage Room 1 200 200
Technical Education
Foundations 14140
Foundations Lab 2 1900 3800 2
Storage 2 200 400
Classroom (Existing) 0 0 0
Foundations Support Rooms (Existing) 0 0 0
Restroom (Boys) (Existing) 0 0 0
Restroom (Girls) (Existing) 0 0 0
Restroom (Unisex) (Existing) 0 0 0
Computer Business Education
Computer Lab 1 1060 1060 1
Storage 1 100 100
Animal Science
Labs 1 1280 1280 1
Storage 1 200 200
Horticulture
Lab 1 1400 1400 1
Storage 1 200 200
Head House 1 300 300
Green House 1 1200 1200
Seminar Room (Existing) 0 0 0
Horticulture Support (Existing) 0 0 0
Auto Shop
Shop 1 3400 3400 1
Parts and Tools Storage 1 350 350
Classroom 1 450 450
Business Education 2050
Transition Education
Classroom 1 775 775 1
Storage 1 200 200
Business Program
Classroom/Lab 1 975 975 1
Storage 1 100 100
Family and Consumer Science/Life Skills 2575
Food Lab 1 975 975 1
Child Development Lab 1 1200 1200 1
Storage 1 300 300
Office 1 100 100
Living Room (Existing) 0 0 0
Grooming (Existing) 0 0 0
General Purpose (Existing) 0 0 0
General Purpose Toilet (Existing) 0 0 0
Draft BHS - 1300 SRC
Educational
Specifications
![Page 37: Brunswick High School Feasibility Study Meeting #02 ... · 1/24/2019 · FS Committee Meeting #8 4/18/2019 2:00pm FCPS Building Review Final Report (if required) Final Report to](https://reader033.vdocument.in/reader033/viewer/2022042306/5ed1b4627dccd150e82adcaf/html5/thumbnails/37.jpg)