bsbpmg504a manage project costs 7.1 estimate costs adapted from pmbok 4 th edition...
TRANSCRIPT
BSBPMG504A Manage Project Costs
7.1 Estimate Costs
Adapted from PMBOK 4th Edition
Initiation Planning Execution Close
Monitor
Control
• The process of developing an approximation of the monetary resources needed to complete project activities
• Cost estimates are a prediction based on the information known at any point in time
• Includes the identification and consideration of costing alternatives to initiate and complete the project
• Cost trade offs and risks need to be considered
• Occurs during Planning
BSBPMG504A Manage Project Costs
7.1 Estimate Costs
• Inputs to Estimate CostsScope Baseline
Cost Management policies and procedures
Project Schedule
Human Resource Plan
Risk Register
• Tools and techniques to Estimate Costs
Adapted from PMBOK 4th Edition
ReserveAnalysis
ExpertJudgementAnalogous
Estimating
ParametricEstimating
Estimating Software
Three-pointEstimates
Bottom-upEstimating
Vendor BidAnalysis
BSBPMG504A Manage Project Costs
7.1 Estimate Costs
• Analogous EstimatingUses previous similar projects to estimate costs
Least costly and least time consuming, also least accurate
Accuracy improved when combined with Expert Judgement
Most common form of cost estimation
• Parametric EstimatingUses statistical relationships between historical project data
and variables for estimation of time and costs
Some industries publish estimating tables, prominent in the construction and engineering industries
Standard cost estimates for activitiesInitiation Planning Execution Close
Monitor
Control
Adapted from PMBOK 4th Edition
BSBPMG504A Manage Project Costs
7.1 Estimate Costs
• Bottom-up EstimatingStarts with the cost of individual activities or work packages
and builds a bottom up estimate
Detailed costs are rolled up to provide the overall budget
Accuracy is influence by the size and complexity of the project
• Three-Point Estimates - PERTCalculates the Expected activity cost based on the weighted
average of the Most Likely, Optimistic and Pessimistic estimates
Often more accurate than other methods and quantifies the range of uncertainty
Initiation Planning Execution Close
Monitor
Control
Adapted from PMBOK 4th Edition
BSBPMG504A Manage Project Costs
7.1 Estimate Costs
• Reserve Analysis
Inclusion of contingency
Can be calculated for each activity
Can be calculated for entire project
Often a percentage based on risk or complexity
• Cost of Quality
Estimates cost of quality control and quality assurance activities
Enables tracking of these costs
More in Project Quality unitInitiation Planning Execution Close
Monitor
Control
Adapted from PMBOK 4th Edition
BSBPMG504A Manage Project Costs
7.1 Estimate Costs
• Project Management Estimating Software
Cost estimating applications, spreadsheets and tools
Becoming widely accepted
• Vendor Bid Analysis
Looks at estimates made by vendors for components of the project
Normally only one component of project cost and other methods required to estimate other activities to provide the total cost
More in Procurement Unit Initiation Planning Execution Close
Monitor
Control
Adapted from PMBOK 4th Edition
BSBPMG504A Manage Project Costs
7.1 Estimate Costs
• Outputs of this process include –Activity Cost Estimates
– Quantitative assessments of the probably cost of the project work
Basis of Estimates – Information supporting the cost estimates
– Assumptions and Constraints
– Range of possible estimates
– Level of confidence in estimates
– Recommendations for contingency amounts
Project Document Updates– Most particularly updates to the Risk Register and Risk Management
Plan
Adapted from PMBOK 4th Edition
Initiation Planning Execution Close
Monitor
Control
BSBPMG504A Manage Project Costs
7.1 Estimate Costs
• Cost estimates often include some form of range of possible results
• Most common form of range is plus or minus - e.g.
$10,000 +/- $500 – the activity could cost between $9,500 and $10,500
$10,000 +/- 20% - the activity could cost between $8,000 and $12,000
Adapted from PMBOK 4th Edition
Initiation Planning Execution Close
Monitor
Control