bsc panel 224 - elexon · 2018. 4. 23. · of their activities directly accountable to pab/elexon....
TRANSCRIPT
![Page 1: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/1.jpg)
BSC Panel 249
11 February 2016
![Page 2: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/2.jpg)
Health & Safety
2
![Page 3: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/3.jpg)
Open Session
11 February 2016
![Page 4: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/4.jpg)
Report on Progress of Modification
Proposals
11 February 2016 Adam Lattimore
![Page 5: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/5.jpg)
P332 ‘Revisions to the Supplier Hub
Principle’
11 February 2016 Dean Riddell
249/05
![Page 6: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/6.jpg)
P332 – Revisions to the Supplier Hub Principle Colin Prestwich, Head of Regulatory Affairs
![Page 7: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/7.jpg)
The Proposal
The purpose of this Modification is to revise the nature of the Supplier Hub Principle
by making Agents Signatories to the Code and to make all of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship between customer and supplier and monitoring performance accordingly.
7
![Page 8: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/8.jpg)
The Defect BSC does not take account of the fact that Suppliers do not always have a contractual relationship with the Agents they are supposed to be managing
Approximately 90% of MPANs in the I&C market are under direct contract between customer and DC/DA The Supplier Hub Principle is inappropriate in this instance
There is not sufficient direct accountability for Agent performance
8
![Page 9: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/9.jpg)
Advantages of this modification
Agent performance generally would improve if there were a direct relationship between BSC and Agents and the incentives were in the right place. Supplier Charges need to be revamped anyway with more and more actual HH data available. Customers will be able to appoint their own agent without creating a conflict between Supplier and Agent Agents being able to raise change would widen the base of Parties with this ability and will lead to the introduction of change which facilitates innovation. 9
![Page 10: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/10.jpg)
BSC Objectives
SmartestEnergy believes this modification meets 2 BSC Objectives:
Objective (c) Promoting Effective Competition: Suppliers and Customers will not be treated differently depending on whether there is a direct relationship or not. Objective (d) Promoting Efficiency in the Implementation of the Balancing and Settlement Arrangements : should result in better and more consistent performance from Agents; ability to raise modifications should enhance BSC.
10
![Page 11: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/11.jpg)
P332: Solution
■ Revise the Supplier Hub principle by making Party Agents signatories to the BSC
–Data Collectors
–Data Aggregators
–Meter Operator Agents
–Meter Administrators
■ Proposer’s anticipated changes
–The specified Party Agents become signatories to the BSC
–Accreditation and role contingent on being a signatory
–Agents become directly responsible for relevant BSC/BSCP requirements/standards
–PARMs and Supplier Charges reviewed and changed as appropriate
–Likely changes around performance assurance, qualification, committee constitution, etc.
![Page 12: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/12.jpg)
P332: Solution
■ Possible solution options and considerations
–Could revise Supplier Hub only where no contractual relationship
–Obligate Agents to remain until another is appointed
–Could potentially limit scope to HH Agents only
![Page 13: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/13.jpg)
P332: Areas to Consider
■ P332 specific areas:
–What issues are caused by customers choosing Agents?
–What is the materiality of the issues?
–What means are presently available to address the issues?
–What is the best way in principle to address the issues?
■ Standard areas:
–What changes are needed to BSC documents, systems and processes to support P332 and what are the related costs and lead times?
–Are there any Alternative Modifications?
–Does P332 better facilitate the Applicable BSC Objectives compared with the current baseline?
![Page 14: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/14.jpg)
P332: Proposed Progression
■ Submit P332 to an Assessment Procedure for Workgroup consideration
–Potentially large and complex change – solution and scope not clear
– Initial indicative nine month timetable
–First Workgroup meetings to scope and develop solution
– Impact assessment and consultation
– Indicative date for presentation of Assessment Report to Panel: 10 November 2016
–Keep timetable under review
■ Workgroup membership – individuals with expertise in:
–Supplier role
–Party Agent roles
![Page 15: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/15.jpg)
P332: Recommendations
We invite the Panel to:
a) AGREE that P332 progresses to the Assessment Procedure;
b) AGREE the proposed Assessment Procedure timetable;
c) AGREE the proposed membership for the P332 Workgroup; and
d) AGREE the Workgroup’s Terms of Reference
![Page 16: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/16.jpg)
P333 ‘Inclusion of DSBR volumes into the
cashout price in time for publication after the
end of the Settlement Period’
11 February 2016 Dean Riddell
249/06
![Page 17: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/17.jpg)
00/00/2015 TITRE DE LA PRESENTATION ( MENU "INSERTION / EN-TETE ET PIED DE PAGE") 17
BSC Panel meeting 11th February 2016 BSC Modifications P333 Libby Glazebrook ENGIE
![Page 18: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/18.jpg)
Why these cashout reforms are necessary
00/00/2015 PRESENTATION TITLE ( FOOTER CAN BE PERSONALIZED AS FOLLOW: INSERT / HEADER AND FOOTER") 18
From Ofgem’s Electricity Balancing Significant Code Review
![Page 19: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/19.jpg)
DSBR is a last resort balancing service that can be called by the SO to avoid demand disconnection
Providers specify the reduction in demand they can offer and the settlement periods between 4 and 8pm on winter weekdays (Nov-Feb) that this quantity can be delivered
DSBR is normally dispatched with at least 2 hours notice
When DSBR is called, it is priced for cashout purposes at £3000/MWh
This price and the volume dispatched are currently incorporated in the cashout price for the WD+5 II settlement run
P333 – Demand Side Balancing Reserve (DSBR)
00/00/2015 PRESENTATION TITLE ( FOOTER CAN BE PERSONALIZED AS FOLLOW: INSERT / HEADER AND FOOTER") 19
MP 333
![Page 20: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/20.jpg)
For winter ‘15/16 there is around 500MW of DSBR (when de-rated 177MMW)
On 4th November, a Notification of Insufficient Margin was issued at 13:31 for 16:30 to 18:30,
At 15:16, a DSBR notice was published on the BMRS indicating that DSBR would be dispatched in SPs 35 and 36
Power exchange prices rose to £259/MWh in SP 35
The system out-turned long, estimate that under P305 cashout would have been c. £44/MWh in SP 35
The next day, National Grid notified that 43MW of de-rated DSBR had been dispatched
Use of DSBR
00/00/2015 PRESENTATION TITLE ( FOOTER CAN BE PERSONALIZED AS FOLLOW: INSERT / HEADER AND FOOTER") 20
MP 333
![Page 21: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/21.jpg)
Cashout is meant to provide the principle incentive for demand and supply to be balanced in the short term.
P305 introduces ‘explosive’ cashout where the price can quickly change from tens of pounds to £3000/MWh
The delay in including the volume could lead to a very large positive change in the cashout price reported at WD+5 compared to the one reported immediately after the Settlement Period has ended
The use of DSBR could also create an expectation that prices will rise to £3000/MWh but because of the Net Imbalance Volume (NIV) tagging process this may not happen (ref 4th November).
These actions need to be captured in cashout to provide timely price signals. Knowing what the cashout price is 5WD later can lead to sub optimal real time trading decisions being made and more balancing actions that have to be taken by the SO
Why P333 is needed
00/00/2015 PRESENTATION TITLE ( FOOTER CAN BE PERSONALIZED AS FOLLOW: INSERT / HEADER AND FOOTER") 21
MP 333
![Page 22: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/22.jpg)
Place a specific requirement on the Transmission Company to provide its best estimate of Demand Side Balancing Reserve (DSBR) volumes as part of its Balancing Services Adjustment Data required under paragraph 6.3.1(a) (ii) of BSC Section Q ‘Balancing Mechanism Activities’.
From a BSC perspective, this change is very simple to make
It has the added benefit that it provides certainty of the volume dispatched - with a 2 hour lead time, this is ahead of gate closure
The change would also provide more time to post additional credit cover
The change needs to be in place by November 2016 to ensure that timely cashout prices include use of DSBR in winter 2016/17
Arguably this is a more important change than the modifications in the November 2016 BSC Release
— P297 - Receipt and Publication of New and Revised Dynamic Data Items
— P321 - Publication of Trading Unit Delivery Model
Required BSC changes
00/00/2015 PRESENTATION TITLE ( FOOTER CAN BE PERSONALIZED AS FOLLOW: INSERT / HEADER AND FOOTER") 22
MP 333
![Page 23: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/23.jpg)
Without MP333, cashout prices will continue to lack a timely fundamental scarcity pricing signal
Impact on the Applicable BSC Objectives
00/00/2015 PRESENTATION TITLE ( FOOTER CAN BE PERSONALIZED AS FOLLOW: INSERT / HEADER AND FOOTER") 23
Objective (b) - a 5WD delay in determining the cashout price will not provide a timely signal to the market to maximise plant availability at times of system stress and can also lead to poor trading decisions being made. Removing this delay will improve the is efficient and economic and co-ordinated operation of the GB Transmission System.
Objective (c) –Smaller players may have less resources to estimate the revised cashout price. Implementation will better promote competition in the sale and purchase of electricity as the whole market will have access to the same information
Objective (d) - While there will still be post event cashout changes, this modification will reduce the number of changes. This promotes efficiency in the implementation and administration of the balancing and settlement arrangements
MP 333
![Page 24: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/24.jpg)
P333: Solution
■ Place a requirement on the Transmission Company to provide its best estimate of Demand Side Balancing Reserve volumes in its initial submission of Balancing Services Adjustment Data by the end of the Settlement Period
![Page 25: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/25.jpg)
P333: Areas to Consider
■ P333 specific areas:
– Is a BSC Modification the best way to achieve the aim of P333?
–What is the impact of implementing P333?
–What is the benefit of P333?
■ Standard areas:
–What changes are needed to BSC documents, systems and processes to support P333 and what are the related costs and lead times?
–Are there any Alternative Modifications?
–Does P333 better facilitate the Applicable BSC Objectives compared with the current baseline?
![Page 26: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/26.jpg)
P333: Proposed Progression
■ Submit P333 to a four month Assessment Procedure
–Two/three Workgroup meetings
–Joint industry IA & consultation if possible (may enable earlier report submission)
–Present Assessment Report to the Panel on 9 June 2016
■ Workgroup membership
– Individuals with expertise in imbalance prices and calculation methodologies
–Members of previous relevant groups (P305, P323, Issue 56)
![Page 27: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/27.jpg)
P333: Recommendations
We invite the Panel to:
a) AGREE that P333 progresses to the Assessment Procedure;
b) AGREE the proposed Assessment Procedure timetable;
c) AGREE the proposed membership for the P333 Workgroup; and
d) AGREE the Workgroup’s Terms of Reference
![Page 28: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/28.jpg)
P334 ‘Inclusion of Non-BM STOR costs and volumes into the cashout price in time for publication after the end of
the Settlement Period’
11 February 2016 Dean Riddell
249/07
![Page 29: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/29.jpg)
00/00/2015 TITRE DE LA PRESENTATION ( MENU "INSERTION / EN-TETE ET PIED DE PAGE") 29
BSC Panel meeting 11th February 2016 BSC Modifications P334 Libby Glazebrook ENGIE
![Page 30: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/30.jpg)
National Grid has contracted for c. 2000MW of non BM STOR for this winter, a lot of this is not available during winter peak periods as generation is instead used for TRIAD avoidance
Non BM STOR prices and volumes have been included in the cashout calculation since MP305 was implemented on 5th November 2015
— Currently this is on an aggregated basis due to issues with disaggregation as required under MP 305
Whilst non BM STOR volume are published at the end of the SP, there is currently a 5WD delay in including these and also their offer prices into the cashout calculation
Both the system direction and the cashout price can change once non BM STOR is included
P334 - Non BM STOR
00/00/2015 TITRE DE LA PRESENTATION ( MENU "INSERTION / EN-TETE ET PIED DE PAGE") 30
MP 334
MWh use of Non BM STOR SP 17/11 18/11 19/11 10/1 22/1 15 43 16 3 217 17 143 250 18 164 51 351 19 164 100 352 20 173 162 317 21 259 168 279 22 270 168 236 23 242 150 144 24 78 28 25 1 26 27 28 29 30 31 32 33 17 34 166 35 232 36 163 37 81 38 4 39
![Page 31: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/31.jpg)
Impact of excluding non BM STOR (1)
00/00/2015 PRESENTATION TITLE ( FOOTER CAN BE PERSONALIZED AS FOLLOW: INSERT / HEADER AND FOOTER") 31
Changes in NIV do not match aggregated non BM STOR volume published after end of settlement period Change in the cashout price may be bigger once non BM STOR is disaggregated
MP 334
![Page 32: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/32.jpg)
Impact of excluding non BM STOR (2)
00/00/2015 PRESENTATION TITLE ( FOOTER CAN BE PERSONALIZED AS FOLLOW: INSERT / HEADER AND FOOTER") 32
MP 334
![Page 33: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/33.jpg)
There is almost always a mismatch between on the day reported use of non BM STOR and D+1 reported use in BSAD submission
Potential data quality issue?
00/00/2015 PRESENTATION TITLE ( FOOTER CAN BE PERSONALIZED AS FOLLOW: INSERT / HEADER AND FOOTER") 33
![Page 34: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/34.jpg)
Section 6.3.1 (a) (ii) requires the Transmission Company to submit its best estimate of Balancing Services Adjustment Data as soon as reasonably practicable after Gate Closure for, and in any event not later than the end of, such Settlement Period
6.3.1 (b) requires this information to again be submitted the next day. It is incorporated in the recalculated cashout price in the WD+5 settlement run
This modification would place a specific requirement on the Transmission Company to provide its best estimate of non BM STOR volumes and costs as part of the Balancing Services Adjustment Data required under 6.3.1(a) (ii) (i.e. as soon as reasonably practical after gate closure)
This is a very simple change to the BSC
Required changes to the BSC
00/00/2015 PRESENTATION TITLE ( FOOTER CAN BE PERSONALIZED AS FOLLOW: INSERT / HEADER AND FOOTER") 34
![Page 35: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/35.jpg)
Timely cashout prices provide the reason to trade to minimise disparity between metering and contractual position
Impact on the Applicable BSC Objectives
111/02/16 35
Objective (b) - a 5WD delay in determining the cashout price can lead to poor trading decisions being made. Removing this delay will improve the is efficient and economic and co-ordinated operation of the GB Transmission System.
Objective (c) – Non BM STOR volume are published at the end of the SP so a party can establish the impact on the system direction and estimate (based on previous acceptances) how the cashout price might be affected. Smaller players may have less resources to estimate the revised cashout price. Implementation will better promote competition in the sale and purchase of electricity as the whole market will have access to the same information
Objective (d) - While there will still be post event cashout changes, this modification will reduce the number of changes. This promotes efficiency in the implementation and administration of the balancing and settlement arrangements
MP 334
![Page 36: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/36.jpg)
ELEXON recommendation to reject
00/00/2015 PRESENTATION TITLE ( FOOTER CAN BE PERSONALIZED AS FOLLOW: INSERT / HEADER AND FOOTER") 36
From the P334 IWA
• Agree with ELEXON on the rationale to reject as the BSC requires non BM STOR to be included in the indicative prices
• Currently non BM STOR is not included in these submissions (and even if it was there appear to be data quality issues)
• Is this due to the disaggregation problems and will be resolved soon?
![Page 37: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/37.jpg)
P334: Solution
■ Place a specific BSC requirement on the Transmission Company to provide its best estimate of non BM STOR volumes and costs as part of its initial submission of BSAD by the end of the relevant Settlement Period
![Page 38: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/38.jpg)
P334: ELEXON Assessment
■ The BSC currently requires the Transmission Company to send
– Initial estimated BSAD by the end of a Settlement Period
–Complete BSAD the following day
■ BSAD Methodology Statement currently includes non-BM STOR in estimated BSAD
■ Specifying an element of BSAD in the BSC would not add any additional value
–Would not affect existing obligation to send the non-BM STOR data
–BSC clarification would not add incentive to meet existing obligation
■ Specifying BSAD elements in the BSC is not efficient
– If BSAD is changed or updated then the BSC must also be updated
–Potential inconsistencies and market confusion about source of BSAD information
![Page 39: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/39.jpg)
P334: Proposed Progression
■ Proceed directly to the Report Phase with an initial recommendation to reject
■ Applicable BSC Objectives:
–Objective (a), (b) and (c) – Neutral
–Objective (d) – Detrimental
■ Not Self-Governance
–Potential interactions with the BSAD Methodology Statement mean P334 should be considered by the Authority
■ Report Phase consultation (12 Working Days)
■ Present Modification Report to the Panel on 10 March 2016
![Page 40: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/40.jpg)
P334: Recommendations
We invite the Panel to:
a) AGREE that P334 progresses directly to the Report Phase;
b) AGREE that P334 DOES NOT better facilitate Applicable BSC Objective (d);
c) AGREE an initial recommendation that P334 should be rejected;
d) AGREE an initial Implementation Date of 10 Working Days after an Authority decision is received;
e) AGREE the production of draft legal text; and
f) NOTE that ELEXON will issue the P334 draft Modification Report (including the draft BSC legal text) for a 12 Working Day consultation and will present the results to the Panel at its meeting on 10 March 2016
![Page 41: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/41.jpg)
P329 ‘Changes to REMIT inside
information reporting’
11 February 2016 Simon Fox-Mella
249/08
![Page 42: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/42.jpg)
P329: Background
■ European Union Regulation on Wholesale Energy Markets Integrity and Transparency (REMIT) (Dec 11)
–aims to prevent market abuse in wholesale energy markets
– the Agency for the Co-operation of Energy Regulators (ACER) prefers central reporting platforms
■ P291 ‘REMIT Inside Information Reporting Platform for GB Electricity’ (31 Dec 14)
–made the Balancing Mechanism Reporting Service (BMRS) the common platform for publishing inside information on the electricity market in Great Britain
![Page 43: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/43.jpg)
P329: Issue
■ The ACER published its requirements for the collection of REMIT inside information data from REMIT platforms (30 Sep 15)
– the BMRS to expose a web feed and
– for this to comply with the requirements for collection by ACER
■ BMRS provides a web feed, but it is not aligned with ACER’s requirements
–ACER specified the web feed must be either Rich Site Summary (RSS) or ATOM
![Page 44: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/44.jpg)
P329: Solution
■ P329 proposes to align the BSC and BMRS with the ACER’s requirements to enable it to collect REMIT inside information data
■ In addition, P329 would enable the submission of outage profile information to BMRS (originally raised under Issue 63)
■ Proposed Modification Solution: as above, plus remove MODIS for REMIT submissions
■ Alternative Modification Solution: as above, but retain MODIS for REMIT submissions
![Page 45: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/45.jpg)
P329: REMIT Data Flow (AS IS)
45
ELEXON Portal
User Interface
Web API
National Grid
User Interface
FTP
Industry Participants
REMIT XML
BMRS
REMIT Info
REMIT XML
REMIT XML
REMIT XML
REMIT Info
REMIT XML
REMIT XML
![Page 46: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/46.jpg)
P329: REMIT Data Flow in (Proposed)
46
ELEXON Portal
User Interface
Web API
National Grid
User Interface
FTP
Industry Participants
REMIT XML
BMRS
REMIT Info
REMIT XML
REMIT XML
REMIT XML
REMIT Info
REMIT XML
REMIT XML
Removed
![Page 47: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/47.jpg)
P329: REMIT Data Flow in (Alternative)
47
ELEXON Portal
User Interface
Web API
National Grid
User Interface
FTP
Industry Participants
REMIT XML
BMRS
REMIT Info
REMIT XML
REMIT XML
REMIT XML
REMIT Info
REMIT XML
REMIT XML
Impacted by P329
![Page 48: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/48.jpg)
P329: BMRS changes and Data Flow out (Both)
48
Industry
Participants
BMRS REMIT XML
BMRS Website
UI
ACER ATOM
RESTFul API
Data Push Service
TIBCO
Optional
![Page 49: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/49.jpg)
P329: Impacts and costs
■ P329 is expected to impact
–all participants that use BMRS for REMIT
– the Transmission Company (system changes)
– the Balancing Mechanism Reporting Agent (BMRA), which operates the BMRS
–ELEXON to implement the change
■ The central systems implementation costs are ~£72k.
– this will be reassessed and confirmed during implementation
![Page 50: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/50.jpg)
P329: Transmission Company impacts and costs
■ Proposed Modification
–£100k to £200k
–due to need to remove MODIS
■ Alternative Modification
–£600k to £1.1m
–due to the need to update MODIS and provide participant testing and support
–NGET has indicated implementation risk and issues
■ Neither Proposed nor Alternative Modification change the ongoing operating cost of MODIS
![Page 51: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/51.jpg)
P329: Implementation approach
■ The Workgroup recommends an Implementation Date for P329 of 23 February 2017 as part of the February 2017 BSC Systems Release
–ACER’s Start Date (7 July 2016) would be preferable, but February 2017 is the earliest feasible Release for implementation by ELEXON and NGET
–NGET highlighted significant risks associated with the February 2017 date for Alternative Modification
![Page 52: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/52.jpg)
P329: Views against the Applicable BSC Objectives
52
Applicable BSC Objective (b) Proposed Modification Alternative Modification Beneficial (majority) • Participants will be able to make more informed
decisions due to increased transparency Neutral (minority - one)
• No impact
Beneficial (Unanimous) • As per Proposed Modification
Applicable BSC Objective (c)
Proposed Modification Alternative Modification Beneficial (Unanimous) • Increased transparency may enable participants
to make informed decisions, and the new platform could particularly benefit participants with fewer resources
Beneficial (Unanimous) • As per Proposed Modification
![Page 53: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/53.jpg)
P329: Views against the Applicable BSC Objectives
53
Applicable BSC Objective (d)
Proposed Modification Alternative Modification Detrimental (minority) • Due to the existing investment in MODIS by
participants
Beneficial (majority) • Wide use of the platform may mean
participants are better informed and hence balance their positions more effectively
Detrimental (minority - Proposer) • Due to the risks associated with MODIS
Neutral (minority - one) • No impact
Beneficial (majority) • As per Proposed Modification
Applicable BSC Objective (e)
Proposed Modification Alternative Modification Beneficial (unanimous) • The BMRS is the means for delivering the
national platform (P291), therefore any applicable regulations relating to REMIT are relevant
Beneficial (unanimous) • As per Proposed Modification
![Page 54: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/54.jpg)
P329: Workgroup’s final view
Insert: Document title 54
■ The Workgroup’s unanimous view that both Proposed and Alternative are better than the baseline
■ Workgroup’s majority view that the Alternative is better than the Proposed
–Alternative better facilitates (d) as the impact on participants is reduced by retaining MODIS
– therefore recommends that P329 Alternative should be approved
![Page 55: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/55.jpg)
P329: Proposed progression under Self-Governance
55
■ We believe P329 meets Self-Governance criteria as it has no material impact on
–consumers
–competition
– the Transmission System
–BSC governance
■ There will be no impact on Parties beyond what they are already required to implement under the EU REMIT Implementing Regulation
![Page 56: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/56.jpg)
P329: Approved Timetable under Self-Governance
56
Event Date
Issue High Level Requirements to Workgroup 10 Dec 15
Workgroup Meeting 1 (teleconference) 15 Dec 15
Assessment Procedure Consultation (15 WDs) 21 Dec 15 – 13 Jan 16
Workgroup Meeting 2 18 Jan 16
Present Assessment Report to Panel 11 Feb 16
Report Phase Consultation (10 WD) 12 – 26 Feb 16 Present Draft Modification Report to Panel
10 Mar 16
Publish Final Modification Report 11 Mar 16
Appeal Window (15 WD) 11 Mar – 5 Apr 16
![Page 57: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/57.jpg)
P329: Recommendations (1 of 3)
We invite the Panel to
a) AGREE that the P329 Proposed Modification
–DOES better facilitate Applicable BSC Objective (b)
–DOES better facilitate Applicable BSC Objective (c)
–DOES better facilitate Applicable BSC Objective (d) and
–DOES better facilitate Applicable BSC Objective (e)
b) AGREE that the P329 Alternative Modification
–DOES better facilitate Applicable BSC Objective (b)
–DOES better facilitate Applicable BSC Objective (c)
–DOES better facilitate Applicable BSC Objective (d) and
–DOES better facilitate Applicable BSC Objective (e)
![Page 58: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/58.jpg)
P329: Recommendations (2 of 3)
We invite the Panel to (cont.)
c) AGREE that the P329 Alternative Modification is better than the P329 Proposed Modification;
d) AGREE an initial recommendation that the P329 Alternative Modification should be approved and that the P329 Proposed Modification should be rejected;
e) AGREE an initial Implementation Date for the Proposed Modification of 23 February 2017;
f) AGREE an initial Implementation Date for the Alternative Modification of 23 February 2017
![Page 59: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/59.jpg)
P329: Recommendations (3 of 3)
We invite the Panel to (cont.)
g) AGREE the draft legal text for the Proposed Modification;
h) AGREE the draft legal text for the Alternative Modification;
i) AGREE that P329 is submitted to the Report Phase; and
j) NOTE that ELEXON will issue the P329 draft Modification Report (including the draft BSC legal text) for a 10 Working Day consultation and will present the results to the Panel at its meeting on 10 March 2016
![Page 60: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/60.jpg)
Minutes of Meetings 248 and
Actions arising
11 February 2016 Victoria Moxham
![Page 61: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/61.jpg)
Chairman’s Report
11 February 2016 Michael Gibbons
![Page 62: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/62.jpg)
ELEXON Report
11 February 2016 Mark Bygraves
249/01
![Page 63: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/63.jpg)
Distribution Report
11 February 2016 David Lane
![Page 64: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/64.jpg)
National Grid Report
11 February 2016 Alex Haffner
![Page 65: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/65.jpg)
Ofgem Report
11 February 2016 Rory Edwards
![Page 66: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/66.jpg)
Reports from the ISG, SVG, PAB,TDC
and SRAG
11 February 2016
249/01a-e
![Page 67: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/67.jpg)
Trading Operations: BSC
Operations Headline Report
11 February 2016
249/02
![Page 68: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/68.jpg)
System Price Analysis Report
11 February 2016
249/03
![Page 69: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/69.jpg)
Change Report
11 February 2016
249/04
![Page 70: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/70.jpg)
Approval of BSCCo Business Strategy
2016/17
11 February 2016
249/11
Mark Bygraves
![Page 71: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/71.jpg)
The BSC Panel Report from the
SRAG
11 February 2016
249/13
Kevin Spencer
![Page 72: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/72.jpg)
SRAG Conclusions
Panel 249 72
The SRAG recommends a simplified end-to-end elective HH Settlement process for smart metered customers that includes:
■ Improved data transfer processes for smart meter data from Suppliers to their Agents
■ Removal of processes (such as proving and protocol testing) which are not necessary for smart meters
■ Reduced validation requirements for smart meter data and data estimation processes where initial, or replacement data, is required for Settlement; and
■ Changes to address potential inaccuracies in the precision used in data flows that contain HH data.
![Page 73: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/73.jpg)
SRAG Recommendations (1)
Panel 249 73
■ BSC Changes
It is proposed that two Change Proposals (CPs) are raised in early 2016 for implementation as soon as practicable in 2016/early 2017:
■ A Change Proposal affecting BSCP502 ‘Half - Hourly Data Collection For SVA Metering Systems Registered in SMRS’ (BSCP502)‘– to define new processes and requirements for data validation and data estimation
■ A Change Proposal affecting BSCP601 ‘Metering Protocol Approval and Compliance Testing’ – to indicate that this BSCP is not applicable to Smart Metering Equipment Technical Specifications SMETS 1 and 2 smart Meters.
![Page 74: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/74.jpg)
SRAG Recommendations (2)
Panel 249 74
Related Changes
A number of associated changes to Master Registration Agreement (MRA) Data Transfer Catalogue (DTC) flows will be required to support the improved end-to-end elective HH Settlement process (including increased data precision):
■ MRA Changes to data flows (D0010, D0003, D0275, D0012) to allow the Supplier to send these flows to other Parties
■ Changes to data flow items (J0177, J0021 and J0281) and HH Agent Systems – to allow HH metered values to be declared to the nearest Watt hour (Wh) (i.e. to three decimal places)
These changes will require sponsorship under the MRA. ELEXON, working under the Code Administration Code of Practice, will seek to promote these changes and work with the relevant Code Administrators. SRAG members who are parties to the MRA will also promote these changes.
![Page 75: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/75.jpg)
SRAG Recommendations: Embedded Generation
Panel 249 75
Conclusions
■ The SRAG recognises that spill from embedded generation is currently an issue for Suppliers and for the accuracy of Settlement. It supports ELEXON's view that that export from embedded generation should be metered and settled.
Recommendations: BSC Changes
■ The SRAG recommends that a BSC Party raises a BSC Modification to create new Consumption Component Classes (CCCs) for Aggregated HH Export. This will allow aggregated HH export data to enter Settlement for smaller customers (that are in Measurement Class F ‘Domestic HH Current Transformer (CT) and whole current (WC) Metering Systems’ or Measurement Class G ‘non-domestic HH WC metered Metering Systems’). This change will provide for the interaction of the improved HH settlement processes recommended above and the implementation of new Measurement Classes with Modification P300 in November
![Page 76: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/76.jpg)
SRAG Recommendations: Further Work
Panel 249 76
■ The SRAG proposes that ELEXON conducts a review of the application of Grid Supply Point Group Correction Factors (GSPGCFs) to HH consumption values. This is to investigate, identify and seek to remove any perverse barriers to elective HH Settlement that maybe caused by embedded generation on GSPGCF
■ The SRAG recommends work is conducted on the smart Change of Measurement Class process
■ Work Area 4 should be progressed by Ofgem in its work on HH Settlement
■ The SRAG should be stood down.
![Page 77: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/77.jpg)
SRAG Recommendations: Other considerations
Panel 249 77
Transmission Use of System and Distribution Use of System charging methodologies
■ The SRAG has recommended that both National Grid and Distribution Businesses look at any related adjustments to Transmission Use of System (TNUoS) and Distribution Use of System (DUoS) charging methodologies. This is in light of the potential increase in the number of customers being settled HH and the impact this may have on the current methodologies for setting charges for NHH and HH customers. The recommendation also takes into account the long lead in periods normally applied before changes can be implemented to Network charges
Interactions with Europe
■ Finally, the SRAG recommends that consideration must also be given to any interaction with the review of the Imbalance Settlement Period (ISP) by the Agency for the Cooperation of Energy Regulators (ACER) and this has been highlighted in the report and flagged to Ofgem/DECC.
![Page 78: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/78.jpg)
Panel Recommendations
Panel 249 78
We invite you to: a) NOTE the report and recommendations of the SRAG
b) NOTE that ELEXON will raise the required Change Proposals and MRA DTC changes once the SRAG report has been considered by the BSC Panel
c) NOTE that a BSC Party will need to raise a BSC Modification to create new Consumption Component Classes (CCCs) for Aggregated HH Export and that ELEXON will seek a sponsor for the BSC Modification
d) NOTE that ELEXON will support BSC Parties on the new elective HH settlement processes and will develop associated guidance and communication in line with the proposed changes;
e) NOTE that ELEXON will undertake a review of the application of Grid Supply Point Group Correction Factors (GSPGCFs) to HH consumption values when the BSC Modification is raised NOTE that ELEXON will consider the impacts of the new elective HH settlement process on CoMC/CoT processes and CoP10 following the assessment/implementation of the above changes in 2016/17
f) AGREE that the SRAG be stood down.
![Page 79: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/79.jpg)
Proposed Changes to the CAP process
11 February 2016
249/14
Thomas Routier
![Page 80: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/80.jpg)
Credit Committee meeting 25
80
■ The Credit Assessment Price (CAP) is set at £42/MWh since 24 December 2015
■ The CAP reference price breached the lower Trigger level of £38/MWh on 29 December 2015
■ Parties were consulted on changing the current CAP value to £37/MWh and whether the current Trigger Level (+/- £4/MWh) was appropriate
■ We received two responses, representing nine BSC Parties
■ The Credit Committee met on Tuesday 12 January 2016
![Page 81: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/81.jpg)
The Credit Committee decisions
81
■ Decreased the CAP value from £42/MWh to £38/MWh
■ Keep the CAP Trigger Level at current value of +/- £4/MWh
■ Agreed to implement those values on Tuesday 9 February 2016
![Page 82: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/82.jpg)
Ad Hoc CC meeting 26 - Review of the CAP setting process
82
■ The Credit Committee met on 2 February to review options to improve the CAP review process
■ The CC agreed on changes to send out to industry for consultation
■ These are the changes to the process proposed by the Credit Committee in the consultation:
– Changing the products used to calculate the reference price
– Reducing and moving forward the ‘Reference period’
– Shortening the notice period for implementing a new CAP value
![Page 83: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/83.jpg)
Ad Hoc CC meeting 26 - Review of the CAP setting process
83
■ Products used to calculate the reference price
– the Credit Committee suggested changing the prices used in the calculation from average baseload + peak prices to solely peak prices
■ Reference period
– The Credit Committee recommend changing the current Reference Quarter to account for closer to date data with the next two months
■ Notice period for implementing a new CAP value
– The Credit Committee recommended shortened the period from 20 to 15 Working Days after the notification of a decision
– Would require a Modification to be raised to change BSC Section M1.4.2 b)
![Page 84: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/84.jpg)
Next step…
84
■ With your approval, ELEXON will publish the Consultation document and proforma seeking industry’s views on the proposed changes
■ At the beginning of March, the Credit Committee will meet and will formulate its final recommendations for decision at the next Panel meeting, on 10 March 2016.
![Page 85: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/85.jpg)
Recommendations
We invite the Panel to:
a) NOTE the decisions taken by the Credit Committee at its meeting on 12 January 2016;
b) AGREE that ELEXON perform a consultation on the proposed options on behalf of the Credit Committee; and
c) NOTE that the Credit Committee will review the result of the consultation and make recommendations to the Panel at its meeting on 10 March 2016.
![Page 86: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/86.jpg)
BSC Panel Strategic Work Programme:
Update
11 February 2016
249/10
Victoria Moxham
![Page 87: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/87.jpg)
Review of the BSC Panel Strategic Work Programme
87
■ Document sets out:
–Updates on work undertaken in Q3 (October – December)
–Key milestones and amendments to work streams in Q4 (January - March)
–Some revisions to scheduled work programme (largely to reflect the changes in the December panel paper on delivering strategic activities)
■ Next Review: late April 2016
–Panel to approve any amendments arising from this six-month review in May 2016
![Page 88: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/88.jpg)
PRIORITY 1: Delivery of Core BSC Services
Mod process and doc architecture reviews combined and timescales amended
On hold – timetable amended to reflect this
Nov implementation added
NEW Publication date of findings report added
Actions following lessons learnt added
Timetable amended
![Page 89: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/89.jpg)
PRIORITY 2: Addressing Known Settlement Issues
Revised mod timetable Timetable amended
![Page 90: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/90.jpg)
PRIORITY 3: Efficient Working Practice and Committee Communication
Workstream deferred Review extended Replaces BSC Systems and processes re-design
![Page 91: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/91.jpg)
PRIORITY 4: Addressing Evolving Settlement Risks
Amended to reflect revised timetable for review of Assurance framework for Smart
Moved to accommodate revised timetable for doc architecture review
![Page 92: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/92.jpg)
PRIORITY 5: Future Settlement Design and Development - Drivers for Change
Date added
Date added
NEW - Locational Transmission Losses mod
NEW
![Page 93: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/93.jpg)
PRIORITY 6: Other Considerations
93
Timescale revised to reflect extension of Assessment Phase
![Page 94: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/94.jpg)
Recommendations
94
The BSC Panel is invited to:
a) NOTE the amendments to the Strategic Work Programme; and
b) NOTE that the revised Strategic Work Programme will be published on the ELEXON website following the February Panel meeting
![Page 95: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/95.jpg)
Review of BSC Credit Modifications
11 February 2016
249/15
Elliot Hall
![Page 96: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/96.jpg)
Review of BSC Credit Modifications
Review of BSC Credit Modifications 96
■ ELEXON has undertaken a post-implementation review of Credit Modifications
–Requested by the Panel
–To assess benefits realisation
–Detailed findings were presented at January ISG meeting
■ 14 November 2014 implementation
–P306 ‘Expanding the definition of a ‘Letter of Credit’ to include regulated insurance companies’
■ 25 June 2015 implementation
–P307 ‘Amendments to Credit Default arrangements’
–P310 ‘Revised Credit Cover for Exporting Supplier BM Units’
![Page 97: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/97.jpg)
Summary of Findings
Review of BSC Credit Modifications 97
£5.2m
£7.6m
£6.9m
P310 credit
Credit Withdrawn
Potential Withdrawal
Remaining Credit
■ P306
–Approved Insurance Products not yet utilised by BSC Parties
–Mod has allowed two LoC to be accepted
■ P307
–Analysis spanned 25 June 2015 to 7 January 2016
–28 ‘Level 1’ default notices to 20 individual Parties
–Mod saved two BSC Parties from ‘Level 2’ Credit Default
■ P310
–Analysis spanned 25 June 2015 to 31 December 2015
–11 BSC Parties affected, two withdrew £5.2m credit
–Five BSC Parties could withdraw up to £7.6m
■ ELEXON will bring further update in the summer
![Page 98: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/98.jpg)
Recommendations
We invite the Panel to
a) NOTE the update given on the impact of Modification P306;
b) NOTE ELEXON’s plan to complete a further review of Modifications P307 and P310 in July 2016; and
c) PROVIDE comments on the analysis to ELEXON.
![Page 99: BSC Panel 224 - ELEXON · 2018. 4. 23. · of their activities directly accountable to PAB/ELEXON. or relaxing the Supplier Hub Principle only where there is no contractual relationship](https://reader036.vdocument.in/reader036/viewer/2022081400/605519f57a250f397e736d39/html5/thumbnails/99.jpg)
Next Meeting: 10 March 2016