Page 1: Building for Learning Project Photo Progress Report  Month of April 2010

Building for Learning ProjectPhoto Progress Report

Month of April 2010

Project commencement 21st September 2009

Page 2: Building for Learning Project Photo Progress Report  Month of April 2010

Don’t ask a man to do something you wouldn’t do yourself right Kassi !!!

Another Blue-Tongue Lizard saved.

Page 3: Building for Learning Project Photo Progress Report  Month of April 2010

Hang on a minute!!! That’s not right – I’m sure Rod said not to build that

there!!!

Al (Site Foreman), stirred but not shaken,

sought of that ‘James Bond’ 007

temperament about him.

April 2010.

Page 4: Building for Learning Project Photo Progress Report  Month of April 2010

Stairway progressing – roof added.

Page 5: Building for Learning Project Photo Progress Report  Month of April 2010

Toilets and wet areas water proofed.

Page 6: Building for Learning Project Photo Progress Report  Month of April 2010

Lights begin installed – windows cleaned

Page 7: Building for Learning Project Photo Progress Report  Month of April 2010

Plaster added to Lecture Theatre.

Page 8: Building for Learning Project Photo Progress Report  Month of April 2010

New electrical sub-station installed April 2010.

Page 9: Building for Learning Project Photo Progress Report  Month of April 2010

Sign writing and doors trims added.

Page 10: Building for Learning Project Photo Progress Report  Month of April 2010

Scaffolding coming down on High St and Hebel still going at rear

Page 11: Building for Learning Project Photo Progress Report  Month of April 2010

Changes to student classroom adviceTV monitors installed

Page 12: Building for Learning Project Photo Progress Report  Month of April 2010

End