building information modeling

42
Building Information Modeling What Does it Mean for the Electrical Engineer? John Griffiths PE Geoff Gunn PE Anthony Fresquez

Upload: michaeljmack

Post on 14-Jan-2017

91 views

Category:

Engineering


0 download

TRANSCRIPT

Building Information Modeling

What Does it Mean for the Electrical Engineer?

John Griffiths PE Geoff Gunn PE Anthony Fresquez

2

Presentation Overview

� BIM Overview

� BIM in Detail

� BIM Project Management

� Question and Answer

� BIM Demonstration

3

Evolution

4D, 5D, ?

6

� What is BIM?

� Building Information Modeling

“digital representation of physical and functional characteristics of a facility”

National Institute of Building Sciences, Model Standard 22 (2007)

7

� What is BIM?

� Building Information Modeling

� BIM means radically different things to different people

� Use often limited to 3D drafting

9

Building Information Modeling

Load, voltage, type

3D - size, location, routing

10

BIM to an Owner

� Opportunity to take advantage of new technology and skills to add value to their projects

- Build more for less- Opportunity Reduce Risk- Control Cost- Manage Schedule- Use BIM model throughout the life of the building

11

BIM to a Design Engineer

� Allow the engineer to combine all the design process and information a single model to streamline the creation and production of designs

� Better coordinated designs� Faster response to design changes� Increase accuracy (schedules)� Sustainability

12

BIM to a Contractor

� Allows the contractor to improve efficiencies and streamline the construction process

- Encourages collaboration- Reduce risk and improve construction predictability- Allows for better examination of alternates- More efficient layouts and networks- Compatible with LEAN

“most effective when contractor engaged early and often in the design phase”

13

Turning Expectations into Reality

� Understand the Value Point for all stakeholders

� Clearly define expectations and deliverables early in process

� Be realistic about capabilities and limitations of the BIM delivery method

14

Turning Expectations into Reality

� Clearly define expectations and deliverables early in process

� Understand the Value Point for all stakeholders

� Be realistic about capabilities and limitations of the BIM delivery method

well….doesn't Revit do that?

15

Define Expectations

“This project will utilize Building Information Management (BIM) strategies and protocols, to assist in the design and construction process”

Extract from a recent RFP

Big BIM or Little BIM?

16

Standards & Guidelines

17

BIM – In Detail

� Geoff Gunn PE

18

BIM – In Detail

� Capabilities Overview

� “How BIM’s supposed to work”

� Case Study

� “How BIM actually works”

19

BIM – Software Setup

Electrical Project Database (EPD)

Smart Panels Drawing

Power & Signal

Lighting Fire Alarm

Smart Panels Drawing

ANTHONY TO CHANGE

AutoCAD MEP Revit MEP

20

BIM – 3D Modeling

21

BIM – Intelligent Devices

22

BIM - Really Intelligent Devices

23

BIM - Intelligent Device Circuiting

24

BIM - Intelligent Drawings

25

BIM - Intelligent Panels

Smart Panels Drawing

26

BIM - Intelligent Schedules� Generates Panelboard schedules that are directly linked to your design.

� As your design changes schedules are automatically updated`

� Reduces potential for errors

Architects: Anshen + Allen

27

BIM – Case Study – UCSF Medical Center

Architects: Stantec

HospitalOutpatient

BuildingFuture

Outpatient

Cancer

Building

Energy Center

28

BIM – Case Study – UCSF Medical Center

Energy Center

� Statistics� 3 Buildings� Hospital – 289 patient beds� Outpatient building� Energy Center� Total Building Area – 878,000 sf

� Total Electrical Load – 16.5MW

29

BIM – Case Study – Project Timeline� 2007 Project Start

� SD phase completed� Design started in AutoCAD MEP 2008

� 2008� DD phase completed

� 2009� 50% CD completed� Project “upgraded” to AutoCAD MEP 2010

� 2010� 100% CD completed

� 2011� OSHPD permit received

30

BIM – Case Study – File Setup

� Working drawings limited to

approx 20k sf due to

computer speed.

31

BIM – Case Study – File Setup

Electrical Project Database (EPD)and Smart Panels

24Power

Drawings

23Lighting Drawings

Hospital

Electrical Project Database (EPD)and Smart Panels

17Power

Drawings

15Lighting Drawings

Hospital

Electrical Project Database (EPD)and Smart Panels

3Power

Drawings

3Lighting Drawings

Hospital

� No way to link EPDs together from each building

� 88 total BIM drawings

32

BIM – Case Study – Complications

� AutoCAD MEP 2008� Our version was heavily customized in order to realize

maximum BIM potential� Maximum size of EPD file due to 64-bit computers not being

supported

� AutoCAD MEP 2010� Automatic Transfer Switches are not supported� Panelboard schedules did not meet OSHPD requirements out

of the box� No way to link EPD files from different projects� Some circuit loads were mis-recorded

33

BIM – Case Study – Lessons Learned

� Proper project setup essential� All devices, demand factor styles, file structures, etc. should

be properly setup before any circuiting is started

� Slow and Steady work flow� Adding extra BIM technicians and Engineers to meet a

deadline often results in crashes or corrupted files

� Hardware and Software limitations� Limits due to hardware or software performance should be

reviewed in advance

34

BIM – Management

Anthony Fresquez

35

BIM ManagementManaging Arup BIM Team

4 Electrical BIM Technicians3 Mechanical BIM Technicians3 plumbing BIM Technicians4 Structural BIM Technicians90+ SMEP Engineers

University of California, Davis Physical Sciences Expansion – Perkins & Will Architects

Release 9

36

BIM Management

�Work Culture�Communication�Challenges�Time Management�Software�Hardware�Next Steps

37

Work Culture

� Transition from 2D CAD to 3D Modeling

� Performing design within software

� Increased roles and responsibility performing 3D coordination

� Due to design skill specialization staff cannot switch easily between disciplines

� Hiring profile change seeking people with design experience

� Recognizing some people may not make the transition

38

Communication� Communication is critical and occurs at a higher level within

design team.- Entire team must understand engineering concepts - Team members are not easily replaceable.

� Model is very sensitive, because it is dynamic, which necessitates more reviews and back checks.

� Not just hard clashes, also soft checking

Demand Factors, Loads, Voltage

Challenges

39

BIM Management

� Time management� Training

- Formal training is recommended. Train the trainer method not beneficial.

� Resourcing- Plan ahead to avoid last minute allocation of resources as it’s

difficult to find contract resources with BIM skills. � Workflow

- Multiple users saving to EPD file caused software to crash with AutoCAD MEP 2010. Issued resolved with AutoCAD MEP 2011

� Trouble shooting - Plan on it you’re going to spend plenty of time solving problems,

especially around deadlines.

40

BIM Management

� Software� Constantly releasing new versions

- Autodesk has committed to releasing a new version of the every year which can present a problem as projects can continue for 5+ years

- Difficulty upgrading to the new release as upgrading to new could impact the display of AEC objects or new drawing format.

� Licenses, various platforms, support- Distributed server configuration - Suite base products AutoCAD and Revit Structure, AutoCAD

MEP and Revit MEP plus we also use Navisworks. - Autodesk Subscription online support- Autodesk reseller ‘Ideate’ training, user groups and support.

41

BIM Management

� Hardware� HP Z400 Workstation, Genuine Windows® 7 Professional 64-bit OS10,000RPM 320gb Hard DriveIntel® Xeon® 23350 3.06, 8MB/1066 QC CPU16GB (4x4gb) DDR3-1333 MHz/PC3 10600-unbuffered- ECC RAM NVIDIA Quadro FX3800 1GB Graphics Card

� Dual Monitors is essential when working within the model environment.

42

Next Steps� Revit MEP

- Recognized as industry standard for design firms

� Capture I in BIM- Information is key - Superior scheduling functionally - Single model allows better design processes

� More capabilities - Ideal workflow with architectural revit model- More efficient 3D coordination and production tool- Content development from manufacturers

� Link to e-Specs- Interfaces with Revit's parametric database, instantly updating your project

specifications to the requirements of the building model

43

Building and Maintaining Relationships

Beta-Testing program:- Revit Structure- AutoCAD MEP- Revit MEP- Navisworks- Microstation Structural Triforma

�Working with Software Designer to ensure software meets the demands of the design industry

44

Summary

� Great potential� Increased accuracy� Increased productivity

� Major Challenges� Steep learning curve� High entry cost

- Training - Software & Hardware

� BIM is here to stay!

45

Questions and Comments

[email protected]@[email protected]