PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 1 of 31
Building Multidimensional Standardized Work Breakdown Structure, Cost Breakdown Structure, and Cost Estimation of The Battery
Laboratory Project 1
Tony Noorwicaksono ABSTRACT
The Company, as an energy provider, has the intention to engage in the battery manufacturing
business by setting up a battery laboratory. Building the laboratory needs a standardized Work
Breakdown Structure (WBS) or cost breakdown structure (CBS) to make better estimates, project
execution plan, and reliable database.
This paper aims to build multidimensional standardized WBS/CBS, cost estimation of battery laboratory, and cost breakdown for contractors. The method used to determine the selection of tables on the international WBS/CBS standard (OmniClass) uses chip voting. The cost estimation uses steps from the GAO Cost Estimating & Assessment Guide and templates from the Cost Estimating Requirements Handbook in the National Park Service (NPS). The result shows that the OmniClass tables used in WBS/CBS are tables 11, 13, and 22. The estimate obtained to build this battery lab is $ 1,049,591, with an area of 600m2 and the cost breakdown for the contractor using class A from the NPS template. The Company is recommended to use a standardized WBS/CBS to generate more organized and reliable data used in the next project. Key words: Cost Estimate, WBS, CBS, Laboratory, OmniClass, Chip Voting, GAO, NPS
INTRODUCTION
1. 1. Lithium-Ion Battery
"A team of global scientists started to create what would become the lithium-ion battery in the late 1970s, a form of rechargeable battery that would ultimately power anything from portable electronics to electric cars and cell phones."2
For their work in creating this battery, three scientists, John B. Goodenough, M. Stanley Whittingham, and Akira Yoshino, were awarded the 2019 Nobel Prize in Chemistry. "The
1 How to cite this paper: Noorwicaksono, T. (2020). Building Multidimensional Standardized Work Breakdown
Structure, Cost Breakdown Structure, and Cost Estimation of The Battery Laboratory Project; PM World Journal,
Vol. X, Issue I, January. 2 Liu, Z., Says, M., Chaney, M., Says, M., Lumayag, M., Says, R., & Chhabda, R. (2019, October 11). The
History of the Lithium-Ion Battery. Retrieved November 14, 2020, from
https://www.thermofisher.com/blog/microscopy/the-history-of-the-lithium-ion-battery/
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 2 of 31
lightweight, rechargeable, and the efficient battery is now used in everything from cell phones to laptops and electric vehicles. It can also store significant amounts of energy from solar and wind power, making possible a fossil fuel-free society."3
In Indonesia, to accelerate the implementation of an electric vehicle for road transport, the government issued Presidential Regulation No 55 in August 2019, providing incentives fiscal and non-fiscal for electric vehicle manufacturing, components industry, and end-user / customer. Since the battery is a primary component in Electric Vehicles (EV), which contributes around 40-50% of EV's total cost, these incentives will benefit battery manufacturing to improve business economics.
Figure 1. Driver for Entering Lithium-Ion Battery Business4
Based on the battery business shown in Figure 1, There are four key drivers for the Company to enter it, namely:
1) In the automotive application, It is a high growth potential. Additionally, Indonesia's
strategic advantages also provide an additional driver to enter the business (to be
discussed further in the supply section)
2) To support the government's ambition of developing the EV and Electric Motor Cycle
(EMC) industry in Indonesia, along with the entire value chain (including batteries)
3) To diversify the business to be a world-class energy company
4) To hedge against the risk of oil and gas decline/price fluctuation and decrease the
dependence on imported oil as a fuel source.
3 Ibid 4 ADL. (2019). Battery Cell Manufacturing in Indonesia Report.
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 3 of 31
Besides four key drivers above and supporting the Government program, the Company as an energy provider has the intention to engage in the battery manufacturing business by setting up a pilot Li-ion battery manufacturing plant. To implement that project, the Company will build a battery laboratory to enhance skill and knowledge in the business battery.
1. 2. Laboratory
"Build a laboratory has differences with a conventional building, office, or academic facility.
Some of these distinctions include; schedule, Floor elevations, environmental requirements,
equipment space, water treatment, floor structure, air circulation, system redundancy, cost"5.
1) Schedule. For research or laboratory buildings, the construction schedule may take an
average of six months longer to complete than the standard academic building. It depends
on program size and the complexity of the facility. Plan and include this additional time frame
in the development schedule and the project's first planning model. Consult with industry
experts (architects and construction managers) to obtain the project requirements' best
knowledge. Do not depend on the rules of thumb when detailed project knowledge is
inaccessible.
2) Floor elevations. More air ductwork and plumbing services are needed for supply and return.
The floor-to-floor heights for a research facility are more significant than for a typical
academic building.
3) Environmental Requirements. The research facility must comply with stringent
environmental standards for the filtration of air sources, handling exhaust air, the storage of
solvents and chemical elements, and the treatment of laboratory wastewater and unique
wastewater systems.
4) Equipment Space. Depending on the particular construction program, a traditional university
building may or may not have a basement. A research facility typically needs a deep
basement—20 feet or more below ground level—to house electrical and mechanical
equipment, including large air handling units, boilers, electrical switchgear, chillers, and
emergency generators.
5) Water treatment. Nontraditional plumbing features, such as storm drainage systems and
sanitary, laboratory drainage, domestic and non-potable hot and cold water systems, and
filtered water systems, are typically required by a research facility. Simultaneously, there will
only be sanitary and storm drainage systems and hot/cold domestic water for a typical
academic building.
5 Lab Buildings Pose Tests. (2008, January 01). Retrieved November 14, 2020, from
https://www.facilitiesnet.com/educationalfacilities/article/Lab-Buildings-Pose-Tests--8066
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 4 of 31
6) Floor structure. Laboratory buildings call for rigid structural floor design to mitigate vibration
problems for sensitive instruments and experiments. There would be a more relaxed
vibration requirement for a traditional academic building, which results in less structural
framing and thinner floor slabs.
7) Air circulation. The academic building uses devices that re-circulate the air supply back to
the air handling facility, re-temperate, and return to the classroom. The supply air of a
research facility cannot be re-circulated due to the potential for pollutants. As a result, a
massive amount of air must be heated and cooled and then exhausted into the atmosphere.
8) System redundancy. The research facility needs to be fitted with fully redundant systems. If
one power source is disabled, it will automatically turn to the other, and there will be no loss
of power to the facility. Likewise, for critical loads such as boilers, chillers, air handling units,
fume hoods, vivarium systems, construction automation, emergency lighting, large
emergency generators can provide electrical power backup.
9) Cost. There's no way around that. A study building would most likely cost a little more than
a traditional academic structure. "Construction costs will vary from $350 to $500 per gross
square foot for a research building, depending on the program compared to $150 to $250
for a traditional academic building." It's a good idea to hang on to a budget for construction
costs too early. Collect as much data as possible on ongoing programs that are similar to the
proposed project. Create an account based on historical expense data as practicable and
have at least 15% contingency for a healthy owner.
1. 3. The Work Break Down Structure and Cost Estimating
The Work Breakdown Structure (WBS) is a breakdown of deliverables and project work into
smaller components that can be better managed. Then, making WBS is a process of describing
deliverables and project works in the form of individual elements in top-down lists and
hierarchically explaining the components to be built and the work associated with it. Each of the
WBS represents an increasingly detailed work item. In another meaning, "WBS is a structure that
separates the project into manageable work packages, components or WBS elements to provide
a standard mechanism for scheduling scope, costs, distribution of responsibilities,
communication, risk assessment, monitoring, and control."6
Furthermore, many companies having difficulties building and having a database for the project.
That why standardizing the WBS is the best way to get a reliable database. By standardizing the
WBS, the Company can collect and share data between programs. Then, it will produce a better
6 Al Farizi, S., & Latief, Y. (2018). Development of Standardized WBS (Work Breakdown Structure) For
Planning The Schedule Based On Risk In Steel Bridge Construction Projects. Retrieved from
http://www.ieomsociety.org/ieom2018/papers/167.pdf
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 5 of 31
estimate of the cost, allowing the data to be shared across the Company and lead to more
efficient project execution.
The study from Joko Wisnugroho (2020) that "GAO Cost Estimating and Assessment Guide (GAO)
can be selected as the best alternative standards compare to other standards; GUILD of Project
Control Compendium and Reference, AACE, and PMI."7 Figure 2 shows that following the overall
cost estimating process stated in best practices such as established, repeatable, comprehensive,
accurate, replicated, and updated can produce accurate and credible estimates. In this paper,
the author chooses GAO as a reference for selecting the best practices recommended for
companies.
Figure 2. The Cost Estimating Process8
1. 4. Problem Statement
In this paper, the author demonstrates cost estimating to battery laboratory project by adopting the best practice standard; GAO Cost Estimating and Assessment Guide, and building the multidimensional standardized WBS using OmniClass standard.
This research should find the answers to the questions below: • The multidimensional WBS or CBS level 3 using OmniClass • Class C construction cost estimate
7 Wisnugroho, Joko. (2020). Indonesia Oil & Gas Cost Estimating vs International “Best-Tested and Proven”
Practices – A Benchmarking Study. Retrieved from
https://pmworldlibrary.net/wp-content/uploads/2020/02/pmwj90-Feb2020-Wisnugroho-benchmarking-indonesia-
og-cost-estimating-vs-international3.pdf 8 The United States. Government Accountability Office. (2009, March). GAO Cost Estimating and Assessment
Guide: Best Practices for Developing and Managing Capital Program Costs. Washington, DC: Government Printing
Office. Retrieved from https://www.gao.gov/new.items/d093sp.pdf
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 6 of 31
• The cost breakdown class A for the contractor
METHODOLOGY
2.1. OmniClass, The Standardized WBS
"The OmniClass Construction Classification System (recognized as OmniClass or OCCS) is one of
the international accredited WBS standards, which developed to organize and retrieve
construction industry information."9
The organization may use OmniClass for applications, such as filing physical materials or
organizing project details. Still, its chief application is to provide a classification structure for
electronic databases and software, enriching the data used in those resources.
To provide a structured framework for the classification of knowledge needs to develop
Omniclass. The North American Architectural, Engineering, and Construction (AEC) industry over
the facility's full life cycle creates and uses it, from design to demolition or re-use, and
encompassing all the various forms of construction that make up the built environment.
OmniClass is intended to organize, sort, and retrieve information and derive relational computer
applications.
OmniClass provides a framework for classifying the full built environment over the life cycle of
the project. It consists of 15 hierarchical tables, covering various aspects of construction details.
Serving a specific project or topic can use each table separately or in combination. The table
below shows the 15 hierarchical tables.
9 OmniClass. (2020). About Omniclass. Retrieved from
https://www.csiresources.org/standards/omniclass/standards-omniclass-about
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 7 of 31
Table 1. The Fifteen Tables of OmniClass10
2.2. Chip Voting
“The chip voting system works by providing participants with a list of choices that they can vote
to in the form of chips based on the importance they give to a list of choices."11 In this paper,
10 OmniClass. (2020). Introduction and User’s Guide. Retrieved from
https://www.csiresources.org/standards/omniclassv 11 Daren, A, Olsen, J.D., Richard, A. B. (2010). The “Chip Voting System”: Bridging the Gap Between Industry
and Faculty During a Curriculum Revision.
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 8 of 31
selecting the Omniclass tables for developing WBS or the Cost Breakdown Structure (CBS) should
do Stakeholder analysis using the chip voting method. Building the four-dimensional WBS / CBS
will choose the four tables. Chip voting will hold a minimum of 7 persons from project teams.
Selecting 5 of 15 OmniClass tables12 gives five chips for Each person. We can see the summary
of votes in Table 2.
Table 2. The Vote Summary13
Figure 3. The Vote Scoring and Raking14
12 OmniClass. (2020). Introduction and User’s Guide. Retrieved from
https://www.csiresources.org/standards/omniclass 13 Author 14 Ibid
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 9 of 31
Determining the ranking of the OmniClass Table from each person's vote makes a scoring system.
The vote scoring from 1st, 2nd, 3rd, 4th, and 5th are 100, 80, 60, 40, and 20. We can see the final
rank of the OmniClass Table in Figure 3.
2.3. SELECTION CRITERIA
For further analysis, building multidimensional WBS or CBS takes chip voting results from Figure 3. The four highest scores of OmniClass tables are Table 11-construction entities by function, Table 13-space by function, table 22-work result, and table 31-phases. Subsequently, the cost estimate process will describe following the GAO Cost Estimating and Assessment Guide step 1 until step 7. The table below summarizes cost estimating steps.
STEP DESCRIPTION ASSOCIATED TASK
1 Define estimate's purpose Determine estimate' purpose, the required level of detail,
and scope
2 Develop estimating plan Develop a master schedule and the estimated timeline
3 Define program characteristics Technical baseline description document; identify the
program's purpose and its system and performance
characteristics and all system configurations
4 Determine estimating structure Define a work breakdown structure (WBS)
5 Identify ground rules and
assumptions
-Clearly define what the estimate includes and excludes;
-Identify global and program-specific assumptions, such
as the estimate's base year, including time-phasing and
life cycle;
-Identify program schedule information by phase and
program acquisition strategy;
-Identify any schedule or budget constraints, inflation
assumptions, and travel costs.
6 Obtain data -Build a data collection plan with a focus on gathering
current and applicable technical and cost information;
-Investigate possible data sources;
-Collect data and normalize them for cost accounting,
inflation, learning, and quantity adjustments;
7 Develop a point estimate and
compare it with an objective cost
estimate
Develop a cost model, estimate each WBS element, use
the best methodology from the data collected, and make
all estimation assumptions.
Table 3. Summary of GAO's Steps15
15 The United States. Government Accountability Office. (2009, March). GAO Cost Estimating and Assessment
Guide: Best Practices for Developing and Managing Capital Program Costs. Washington, DC
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 10 of 31
FINDINGS
3.1. Standardizing WBS
Standardizing WBS is a critical step before estimating, or project scheduling starts. This paper
uses OmniClass tables 11, 13, 22, and 31 builds the four-dimensional WBS. The hierarchical
structural WBS is defined by OmniClass table 13 (Space by function)16 , and we can see the
structural WBS in the figure below.
Figure 4. The 4 Dimensional WBS 17
After building WBS, using the Cost Estimating Requirement Handbook18 will arrange the Cost Breakdown Structure (CBS), as shown in Figure 4. The client or project owner build the CBS using level 2 WBS. The bid participants will create the Budgeted Cost of Work Scheduled (BCWS) using level 3 WBS and the example in Figure 4 using OmniClass Table 2119 level 1. Figure 5 is a sample of a bid line-item cost summary built after the winner is selected. The field execution BCWS is build using level 5 WBS with detailed cost material, labor, and equipment.
16 OmniClass. (2020). Spaces by Function - Table 13. Retrieved from
https://www.csiresources.org/standards/omniclass 17 Author 18 National Park Service. (2011). Cost Estimating Requirements Handbook. Retrieved from
https://www.nps.gov/dscw/upload/CostEstimatingHandbook_2-3-11.pdf 19 OmniClass. (2020). Elements - Table 21. Retrieved from https://www.csiresources.org/standards/omniclass
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 11 of 31
Table 4. Sample of Cost Breakdown Structure Class A20
Table 5. Sample of Bid Line Item Cost Summary213.2. Cost Estimate
To build the cost estimation, it will follow the GAO Cost Estimating and Assessment Guide using
step one until seven, shown in Table 3.
Step 1. Define estimate's purpose
Establish cost estimation Class C construction cost estimate for battery laboratory building. The
scope of construction describes using OmniClass Standard Table 2222 - Work Result shown in
the table below:
20 National Park Service. (2011). Cost Estimating Requirements Handbook. Retrieved from
https://www.nps.gov/dscw/upload/CostEstimatingHandbook_2-3-11.pdf 21 National Park Service. (2011). Cost Estimating Requirements Handbook. Retrieved from
https://www.nps.gov/dscw/upload/CostEstimatingHandbook_2-3-11.pdf 22 OmniClass. (2020). Work Results - Table 22. Retrieved from https://www.csiresources.org/standards/omniclass
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 12 of 31
Table 6. Scope of Work Using OmniClass23
Step 2 Develop estimating plan
The overall duration of the project is 12 months, with the following detail
1. Permit duration 140 days and
2. Construction duration of 12 months
Figure 5 shows the summary schedule's activity using OmniClass table 3124-Phase.
23 Author 24 OmniClass. (2020). Phases - Table 31. Retrieved from https://www.csiresources.org/standards/omniclass
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 13 of 31
Figure 5. Master Schedule25
Step 3 Define program characteristics
The total area of the battery laboratory is 600m2, with the detailed room as follow
Figure 6. General Layout26
25 Author 26 Ibid
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 14 of 31
The OmniClass Standard Table 1127 dan 1328 describes the construction entities and space's
function showing on the table below.
Table 7. Constructions Entities and Spaces By Function Using OmniClass29
The Laboratory Area is Clean Room Class 7, consist of :
1. Mixing Room (13-49 15 23.001) : 85m2
2. Cathode & Anode Room (13-49 15 23.002) : 126 m2
3. Assembly Room (13-49 15 23.003) : 95m2
4. Formation & Grading Room (13-49 15 23.004) : 75m2
5. Electrical & Instrument Room (13-49 15 23.005) : 35m2
27 OmniClass. (2020). Construction Entities by Function - Table 11. Retrieved from
https://www.csiresources.org/standards/omniclass 28 OmniClass. (2020). Spaces by Function - Table 13. Retrieved from
https://www.csiresources.org/standards/omniclass 29 Author
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 15 of 31
6. Material Analysis Room (13-49 15 23.006) : 35m2
Those rooms need a superior HVAC system because the room considers it has to be a
cleanroom. The detailed requirement is:
1. Target Temperature: 23C ±2 C
2. The humidity 40% – 50% ±5 C
2. ACH 40-60
3. Fresh Air: Min 20%
4. HEPA Filter (99, 99% Efficiency) for Mixing, Cathode & Anode and Assembly Room
5. Heat Gain from equipment 20W/m2
6. Static pressure; Cathode & Anode Room, Assembly Room > Mixing Room > Other rooms
7. Floor height 4m
Non Laboratory Area
1. Office (13-55 11 17) : 46 m2
2. Toilet (13-65 13 13) : 33 m2
3. Corridor (13-25 11 11) : 70 m2
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 16 of 31
Step 4 Determine estimating structure
The WBS used in this study using three levels, as seen in the figure below
Figure 7. WBS of Battery Laboratory30
Step 5 Identify ground rules and assumptions
The general rules and assumptions made for estimation:
1) The analysis only for the laboratory facility, not including the lab. equipment
2) The overall duration of the project is 12 months or one year
3) The project will start in 2021
4) The inflation assumptions used average BI Rate data from 2015 to 2020 is 3.28%31
5) Exchange rate US Dollar to Rupiah is 14,663.0032
30 Author 31 Bank Indonesia. (2020). Inflasi. Retrieved from https://www.bi.go.id/id/moneter/inflasi/data/Default.aspx 32 Bank Indonesia. (2020). Informasi Kurs. Retrieved from https://www.bi.go.id/id/moneter/informasi-
kurs/transaksi-bi/Default.aspx
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 17 of 31
Step 6. Obtain data
The data obtained from the previous project is shown in the table below and analyzed using
P50 and P90. P50 value is the target of cost estimate with contingency successful 50%. Depend
on the confidence level of each Company or management decision, and the Company may
increase the contingency to 90% with P90.
Table 8. Data Analyzing Using P50 and P90 33
Step 7. Develop point estimate
The point estimation is built for the project year in 2021 using P50 data in Table 8 and template
from Cost Estimating Requirement Handbook with Class C Construction Class Estimate34. The
result of cost estimating can be seen in Table Table 9 and 10. The detail of cost estimating can
be seen in the Appendix.
33 Author 34 National Park Service. (2011). Cost Estimating Requirements Handbook
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 18 of 31
Table 9. Project Cost Summary35
Table 10. Line Item Cost Summary of Clean Room Class 736
35 Author 36 Ibid
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 19 of 31
3.3 Cost Breakdown Class A
The bidding process uses the template cost breakdown class A from Cost Estimating
Requirement Handbook and includes in the bid package. All bidders are required to submit with
the template (Table 8) and showing only the total cost of the bid item. When the winning bidder
is selected either through auction, low bid wins, or negotiated contract, the winning bidder is
required to submit the detailed cost breakdown shown in Table 9. The winning bidder data is
real cost estimation data that the next project can use it. We can see The rest of the detail of the
line-item cost summary class.
Table 11. Bid Item Cost Summary No. 1 and 237
37 Author
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 20 of 31
Table 12. Bid Item Cost Summary No. 3, 4 and Total Estimated38
2. CONCLUSION
As mentioned in the Problem Statement of this paper, the study should find the answers to the
question below:
• The multidimensional WBS or CBS level 3 using OmniClass tables?
• Using three WBS or CBS levels with OmniClass Table 11, 13, and 22, we can see the WBS
or CBS in the figure below.
38
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 21 of 31
Figure 8. WBS or CBS of Battery Laboratory39
• Class C construction cost estimate?
The estimated data and summary of cost estimate class C shown in Table 12 and 13. P50 is
used to generate cost estimate class C with contingency successful 50%. The contingency of
success will increase to 90% with P90 depend on the confidence level of each Company or
management decision.
39 Author
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 22 of 31
Table 13. Estimation Data Using P50 and P9040
Table 14. Project Cost Summary of Battery Laboratory41
• The cost breakdown class A for the contractor
The cost breakdown class A for the contractor can be seen in Table 12, and the rest of the
details of the line item cost summary class A can be seen in the Appendix. The contractor's cost
breakdown will be delivered after the winning bidder selected from the template included in
40 Author 41 Ibid
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 23 of 31
the bid package. The winner's data is real cost estimate data that can be used for the next
project by the Company.
FOLLOW ON RESEARCH
Further research should be done on WBS's risk analysis that may affect the project cost and schedule. Moreover, for developing the cost estimate, refer to GAO Cost Estimating and Assessment Guide. It should conduct sensitivity analysis and risk and uncertainty analysis.
BIBLIOGRAPHY
1. Bank Indonesia. (2020). Inflasi. Retrieved from https://www.bi.go.id/id/moneter/inflasi/data/Default.aspx
2. Bank Indonesia. (2020), Informasi Kurs. Retrieved from https://www.bi.go.id/id/moneter/informasi-kurs/Contents/Default.aspx
3. Compassinternational. (2020). 2020 International Construction Benchmark Yearbook
4. Compassinternational. (2020). 2020 Front End/Conceptual Estimating Yearbook
5. OmniClass. (2020). Introduction and User's Guide. Retrieved from https://www.csiresources.org/standards/omniclass
6. OmniClass. (2020). Construction Entities by Function - Table 11. Retrieved from https://www.csiresources.org/standards/omniclass
7. OmniClass. (2020). Spaces by Function - Table 13. Retrieved from https://www.csiresources.org/standards/omniclass
8. OmniClass. (2020). Elements (includes Designed Elements) - Table 21. Retrieved from https://www.csiresources.org/standards/omniclass
9. OmniClass. (2020). Work Results - Table 22. Retrieved from https://www.csiresources.org/standards/omniclass
10. OmniClass. (2020). Phases - Table 31. Retrieved from https://www.csiresources.org/standards/omniclass
11. Wisnugroho, Joko. (2020). Indonesia Oil & Gas Cost Estimating vs International "Best-Tested and Proven" Practices – A Benchmarking Study; PM World Journal, Vol. IX, Issue II, February. https://pmworldlibrary.net/wp-content/uploads/2020/02/pmwj90-Feb2020-Wisnugroho-benchmarking-indonesia-og-cost-estimating-vs-international3.pdf
12. ADL. (2019). Battery Cell Manufacturing in Indonesia Report.
13. GUILD OF PROJECT CONTROLS COMPENDIUM and REFERENCE (CaR). (2019). Managing Project Cost Estimating & Budgeting. Retrieved from http://www.planningplanet.com/guild/gpccar/introduction-to-managing-planning-andscheduling
14. Presidential Regulation No 55. (2019). Accelerating Implementation of Electric Vehicle for Road Transport.
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 24 of 31
15. Liu, Z., Says, M., Chaney, M., Says, M., Lumayag, M., Says, R., & Chhabda, R. (2019, October 11). The History of the Lithium-Ion Battery. Retrieved November 14, 2020, from https://www.thermofisher.com/blog/microscopy/the-history-of-the-lithium-ion-battery
16. Al Farizi, S., & Latief, Y. (2018). Development Of Standardized Wbs (Work Breakdown Structure) For Planning The Schedule Based On Risk In Steel Bridge Construction Projects. Retrieved from http://www.ieomsociety.org/ieom2018/papers/167.pdf
17. Chatfield, C., Johnson, T .(2016). Microsoft Project 2016 Step by Step
18. Sullivan, W. G., Wicks, E. M., & Koelling, C. P. (2014). Engineering Economy 16th ed.
19. National Park Service. (2011). Cost Estimating Requirements Handbook. Retrieved from https://www.nps.gov/dscw/upload/CostEstimatingHandbook_2-3-11.pdf.
20. Daren, A, Olsen, J.D., Richard, A. B. (2010). The "Chip Voting System": Bridging the Gap Between Industry and Faculty During a Curriculum Revision. Retrieved from http://ascpro0.ascweb.org/archives/cd/2010/paper/CEUE163002010.pdf
21. The United States. Government Accountability Office. (2009). GAO Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Capital Program Costs. Washington, DC: Government Printing Office. Retrieved from https://www.gao.gov/new.items/d093sp.pdf
22. The United States. Government Accountability Office. (2009). Schedule Assessment Guide: Best Practices for Project Schedule. Washington, DC: Government Printing Office.
23. Facilitiesnet. (2008). Lab Buildings Pose Tests. Retrieved from https://www.facilitiesnet.com/educationalfacilities/article/Lab-Buildings-Pose-Tests--8066#:~:text=A%20research%20building%20will%20most,for%20a%20typical%20academic%20building" https://www.facilitiesnet.com/educationalfacilities/article/Lab-Buildings-Pose-Tests--8066#:~:text=A%20research%20building%20will%20most,for%20a%20typical%20academic%20building
LIST OF TABLES
Table 1 The Fifteen Tables of OmniClass Pg. 6 Table 2 The Vote Summary Pg. 7 Table 3 Summary of GAO’s Steps Pg. 8 Table 4 Sample of Cost Breakdown Structure Class A Pg. 10 Table 5 Sample of Bid Line Item Cost Summary Pg. 11 Table 6 Scope Of Work Using OmniClass Pg. 12
Table 7 Constructions Entities and Spaces By Function Using OmniClass Pg. 14 Table 8 Data Analyzing Using P50 and P90 Pg. 17 Table 9 Project Cost Summary Pg.18 Table 10 Line Item Cost Summary Sample of Clean Room Class 7 Pg. 18
Table 11 Bid Item Cost Summary No. 1 and 2 Pg. 20 Table 12 Table 13 Table 14
Bid Item Cost Summary No. 3, 4 and Total Estimated Estimation Data Using P50 and P90 Project Cost Summary of Battery Laboratory
Pg. 21 Pg. 23 Pg. 23
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 25 of 31
LIST OF FIGURES
Figure 1 Driver for Entering Lithium-Ion Battery Business Pg. 2
Figure 2 The Cost Estimating Process Pg. 4 Figure 3 The Vote Scoring and Raking Pg. 7 Figure 4 The 4 Dimensional WBS Pg. 9 Figure 5 Master Schedule Pg. 13 Figure 6 General Layout Pg. 13 Figure 7 WBS of Battery Laboratory Pg. 16
Figure 8 WBS or CBS of Battery Laboratory Pg. 22
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 26 of 31
APPENDICES
Appendix I:
Project Cost Summary and Line Project Cost Summary with Class C Construction Class Estimate
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 27 of 31
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 28 of 31
Appendix II:
Line Item Cost Summary with Class A Construction Class Estimate
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 29 of 31
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 30 of 31
PM World Journal (ISSN: 2330-4480) The Battery Laboratory Project
Vol. X, Issue I – January 2021 by Tony Noorwicaksono
www.pmworldjournal.com Featured Paper
© 2021 Tony Noorwicaksono www.pmworldlibrary.net Page 31 of 31
About the Author
Tony Noorwicaksono Jakarta, Indonesia
Tony Noorwicaksono is a project engineer with ten years of professional experience
in the oil and gas sectors. Currently, he works as an analyst Facilities at Research
Facility & Support, Innovation & New Ventures Department, PT Pertamina. Several
project have been completed, such as CNG station, pipeline, CNG converter kit and
laboratory building. He holds a bachelor degree in Civil Engineering from Gadjah Mada
University and a master degree in Civil Engineering from National University of
Malaysia. He is attending a distance learning mentoring course, under tutorage of Dr
Paul D. Giammalvo, CDT, CCE, MScPM, MRICS, GPM-m Senior Technical Advisor,
PT Mitrata Citragraha, to attain Certified Cost Professional certification from AACE
International. He lives in Jakarta, Indonesia and can be contacted at