building structure fettucine bridge

41
TUTOR: MS. ANN CHUAH SAY YIN 0315301 CHRISTINE YEAP ZHE XING 0316294 KHOR XIN SUAN 0316230 NG WEI YING 0316366 WANG PUI YEE 0316283 5-7-2015 ARC 2523 BUILDING STRUCTURES PROJECT 1: FETTUCCINE TRUSS BRIDGE SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN, TAYLOR’S UNIVERSITY LAKESIDE CAMPUS

Upload: chuah-say-yin

Post on 18-Aug-2015

41 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BUILDING STRUCTURE FETTUCINE BRIDGE

TUTOR: MS. ANN CHUAH SAY YIN 0315301 CHRISTINE YEAP ZHE XING 0316294 KHOR XIN SUAN 0316230 NG WEI YING 0316366 WANG PUI YEE 0316283 5-7-2015

ARC 2523 BUILDING STRUCTURES

PROJECT 1: FETTUCCINE TRUSS BRIDGE SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN, TAYLOR’S UNIVERSITY LAKESIDE CAMPUS

Page 2: BUILDING STRUCTURE FETTUCINE BRIDGE

1 | P a g e

CONTENT Page 1.0 Introduction 2

1.1Project Intention 1.2Report Overview 2.0 Methodology 3 2.1 Aim of Study 2.2 Learning Outcomes 2.3 Precedent Study 2.4 Materials and Equipment Testing 2.5 Model Making 2.6 Structural Analysis 2.7 Bridge Efficiency Calculation 3.0 Precedent Study 5 4.0 Material and Equipment 9 4.1 Material 4.2 Equipment 5.0 Modal Making 14 5.1 Process 5.2 Precautions 6.0 Structural Analysis 26 6.1 Member Analysis 6.2 Design Analysis 7.0 Conclusion 38 8.0 Appendix 39 9.0 References 40 10.0 Exercise: Truss Analysis 41

Page 3: BUILDING STRUCTURE FETTUCINE BRIDGE

2 | P a g e

1.0 Introduction 1.1 Project intention and research In a group of 5, we were required to design and construct a truss bridge with fettuccine. The bridge requirement include a clear span of 750mm and maximum weight of 200g. The fettucine structure will be tested to fail. The bridge must be of high efficiency by using the least material to sustain the higher load. The intention of designing this bridge is to investigate and understand the tension and compressive strength of construction materials. In this case, it's the fettucine. We are required carry out research on precedent studies of bridges with different truss system. There 6 types of bridges identified through extensive research. Namely, the Beam bridge, Truss Bridge, Arch Bridge, Suspension bridge and Cantilever Bridge. For this project, only truss bridge is needed to be analyzed as the project requirement is to build a truss bridge with high efficiency. Materials are being experimented to differentiate its strength. Several brands and types of adhesives are used in the test to determine its strength and properties. Through this project we are able to identify which member in the truss system needs to be strengthen so that the load apply will be distributed evenly throughout the entire system. 1.2 Report Overview The report started off with a precedent study carried out on a truss bridge. Analysis of load distribution and how it affects its member. The report also recorded down the several designs we had tried out before the deciding on the final design. These test bridges were improved and developed further based on previous test results and analysis to increase its efficiency. A set of analysis regarding the strength of the bridge structure and its reason of failure had been done. Individual case studies calculations are attached at the end of the report.

Page 4: BUILDING STRUCTURE FETTUCINE BRIDGE

3 | P a g e

2.0 Methodology 2.1 Aim of Study The aim of this projects is to develop student's understanding of tension and compressive strength of construction materials as well as the force distribution in a truss. This project aims to enable students to design a perfect truss bridge which fulfills the aesthetic value and minimum construction material required. 2.2 Learning Outcomes By the end of this project, students are able to:

- Evaluate, explore and improve attributes of construction materials - Explore and apply understanding of load distribution in a truss - Evaluate and identify tension and compression members in a truss structure - Explore different arrangement of members in a truss structure

2.3 Precedent Study We had opted to carry out our case study on the Cicero Avenue Cal-Sag Bridge. This bridge is the closest to what we had for our fettucine bridge in terms of design and truss member arrangement. Further elaboration and findings will be in the Precedent Study section later. 2.4 Materials and Equipment Testing We had experimented with different brands and types of fettuccine to examine its tension and compressive strength before deciding to select a specific brand to proceed with our bridge building. The brand of fettucine we had selected in this project is San Remo. Various types of adhesive are being used in the experiment and were observed how they affect the joints and connecting members of the bridge. In the end, we settled on super glue (3 seconds glue). 2.5 Model Making The model making process was an on-going process as we had to keep revising and improving the Fettuccine Bridge after load testing to achieve higher efficiency. A total of 6 bridges with various designs and improvements were built for this project. After testing, the strength of each bridge will be maintained and the weakness will be eliminated for further development.

Page 5: BUILDING STRUCTURE FETTUCINE BRIDGE

4 | P a g e

2.6 Structural Analysis Structural Analysis is the determination on the effects of load on the Fettuccine Bridge and its members by calculation. 2.7 Bridge Efficiency Calculation The efficiency of the bridge tested is calculated using the formula:

bridge of Weight

Load MaximumE,Efficiency

2

Page 6: BUILDING STRUCTURE FETTUCINE BRIDGE

5 | P a g e

3.0 PRECEDENT STUDY

CICERO AVENUE CAL-SAG BRIDGE

Cicero Avenue Cal-Sag Bridge is a truss bridge through Calumet Sag Channel at Cicero Avenue,

Illinois. It was built in the year 1938 and was rehabilitated on year 1963. It is one of the oldest

existing metal truss bridges among the truss bridges on Calumet Sag Channel and Little Calumet

River. According to the bit letting in November 2011, the bridge is planned to be rehabilitated

again of which the works include painting, repair of gusset plate connections, joints repair, etc.

The truss bridge function as a four lane vehicular bridge with 2 pedestrian passage at each side.

Figure 3.1: West Elevation and Top View of the Bridge

The type of this truss bridge is warren truss. It is the type of truss that contain a series of

isosceles or equilateral triangles. In the case of Cicero Avenue Cal-Sag Bridge, vertical members

Page 7: BUILDING STRUCTURE FETTUCINE BRIDGE

6 | P a g e

are added to increase the span of the bridge. The total length of this bridge is 115.2m with the

span of 82.3m, deck width of 13.3m and vertical member of 5.3m. Besides, top chord and end

post is also riveted with an additional plate as shown in box A in figure 2 to strengthen the its

box beam.

Figure 3.2: Connections of Top Chord, Bottom Chord, Vertical Member and Diagonal Member

Figure 3.3

A

B

B C

Figure 3.3 is showing from the interior view of the bridge

the part labelled as B in Figure 3.2. It is the connection

joint among diagonal members, vertical member, struts

and lateral bracing son the top as well as top chord or

bottom chord. They are joined together by riveting to

gusset plates.

Page 8: BUILDING STRUCTURE FETTUCINE BRIDGE

7 | P a g e

Figure 3.4

Figure 3.5: Interior View of the Bridge

Figure 3.6

Figure 3.4 is showing the part labelled as C in figure 3.2. It

is the connection joint of the vertical member to the top

chord.

Figure 3.6 is showing the part labelled as A in figure 3.5. It

is the connection joint of the lateral bracings and struts

through gusset plate.

B

A

Page 9: BUILDING STRUCTURE FETTUCINE BRIDGE

8 | P a g e

Figure 3.7

Figure 3.7 is showing the part labelled as B in figure 3.5. It

is the connection joints of the members of portal bracings.

Its connection system is the same with sway bracings

except having different arrangement of the truss.

Page 10: BUILDING STRUCTURE FETTUCINE BRIDGE

9 | P a g e

4.0 Material and Equipment

4.1 Materials

Table 4.1.1

Initially, we use both UHU and 3 seconds glue as we think that both are able to counter the

compression and tension we might need flexibility in certain members and used 3 seconds

glue on horizontal members at the base to have the best strength to hold the whole bridge

together. Then we switch to UHU super glue as flexibility in using UHU is unnecessary and is

less efficient. Finally, we have chosen to use only 3 second glue as it dries faster which could

save up a lot of time in model making as this project need us to test on multiple bridge

design before finalizing on the selection of design.

Type of Adhesives Advantages Disadvantages

UHU Glue

- Able to adjust position of connection as it dries slower - Flexiblele connection - Easy to use

-Causes the bridge to weight more -Needs more amount to stick the members tightly

UHU Superglue

-Efficient -Easy to use

-Does not hold the members tightly

3 Seconds Glue (Superglue)

-Highest efficiency -Firm and stiff connection - Easy to use

-More brittle: broken easily if fettuccini is not stacked in multiple layers

Page 11: BUILDING STRUCTURE FETTUCINE BRIDGE

10 | P a g e

We had selected two different brands of fettucine to carry out the material load testing

before selecting one of it for the bridge construction later. The difference between San

Remo brand fettucine and Kimball brand fettucine is the width. Sam Remo fettucine is

measured at 5mm whereas Kimball fettucine is measured at 4mm. Load testing is then

carried out to determine the tension and compressive strength of each brand.

Figure 4.1.2 San Remo Fettucine Figure 4.1.3 Kimball Fettucine

Material Load Testing Results:

San Remo Fettucine Weight

I-beam One pail and 600 g

Laminated truss One pail and 200 g

Kimball Fettucine Weight

I-beam One pail

Load testing results proved that San Remo’s fettuccini is stronger than Kimball’s fettuccini. It

is compared in the condition where the glue used and the way of lamination is the same.

San Remo brand is selected in the end.

Page 12: BUILDING STRUCTURE FETTUCINE BRIDGE

11 | P a g e

4.2 Equipment

Figure 4.2.1 Penknife Figure 4.2.2 Scissors

Penknife is able to cut precisely and accurately compared to using scissors. Fettucine are

prone to breakage as it is very brittle. Therefore, penknife is a better choice for cutting

Figure 4.2.3 Nylon String Figure 4.2.4 Raffia String

Nylon string is chosen to hang the pail of water from the bridge rather than raffia because it

is more durable.

Figure 4.2.5 T-Square Figure 4.2.6 Set Squares

Page 13: BUILDING STRUCTURE FETTUCINE BRIDGE

12 | P a g e

Figure 4.2.7 Metal Rule

Set squares were used to ensure the vertical member sticking to the horizontal member is at right angle. T-square and metal rule are used to mark the measurement as it can reach longer length, which increase the accuracy of the measurement

Figure 4.2.8 Sand Paper

Sand paper is used to mill the edge of the fettuccini in case it is not cut well. This is

important as the contact surface of fettuccini should be maximum as it could affect the load

it could carry and the better the joint connection, the more stable it could be.

Page 14: BUILDING STRUCTURE FETTUCINE BRIDGE

13 | P a g e

Figure 4.2.9 Pail Figure 4.2.10 S-hook

Pail is used to fill the water which act as load pulling downwards from the bridge with an S-

hook connecting to the bridge.

Figure 4.2.11 Electronic balance

An electronic balance is used to get a more accurate weight measurement.

Page 15: BUILDING STRUCTURE FETTUCINE BRIDGE

14 | P a g e

5.0 Model making

5.1 Process

1. Categorize the fettucine into usable and non-usable. (bent or straight)

2. Draft out the design of the bridge in AutoCAD and print out the drawings of the bridge.

3. Measure the fettucine and cut them into the specific lengths.

4. Make all the components and turn them into I-beams or laminated truss with adhesive.

Figure 5.1.1 I-beams and laminated trusses are constructed precisely

5. Join the vertical components to the base strip as seen in 5.1.2

Figure 5.1.2

Page 16: BUILDING STRUCTURE FETTUCINE BRIDGE

15 | P a g e

6. Place the bracings in between the vertical components.

Figure 5.1.3

7. Stick the top chord for both sides of the bridge.

Figure 5.1.4

Page 17: BUILDING STRUCTURE FETTUCINE BRIDGE

16 | P a g e

8. Connect both sides of the bridge horizontal I-beams.

Figure 5.1.5

9. Continue by fixing horizontal components on top to hold both sides of the bridge.

Figure 5.1.6

Page 18: BUILDING STRUCTURE FETTUCINE BRIDGE

17 | P a g e

10. Place the two major supporting beams in the middle.

Figure 5.1.7

11. Weight the bridge.

Figure 5.1.8

Page 19: BUILDING STRUCTURE FETTUCINE BRIDGE

18 | P a g e

12. Test the bridge.

Figure 5.1.9

13. Identify the weakness and problems.

Figure 5.1.10

14. Repeats the steps above until the final model.

Page 20: BUILDING STRUCTURE FETTUCINE BRIDGE

19 | P a g e

Model 1

Figure 5.1.11

Model 2

Figure 5.1.12

Page 21: BUILDING STRUCTURE FETTUCINE BRIDGE

20 | P a g e

Model 3

Figure 5.1.13

Model 4

Figure 5.1.14

Page 22: BUILDING STRUCTURE FETTUCINE BRIDGE

21 | P a g e

Model 5

Figure 5.1.15

Page 23: BUILDING STRUCTURE FETTUCINE BRIDGE

22 | P a g e

5.2 Precautions

Overall aspects:

1. Quality controls is needed for fettucine. There are twisted and bended fettucine which

will affect the stability and strength of the bridge.

Figure 5.2.1 shows the examples of a straight and bended fettucine

2. In order to make sure the bridge functions as how we plan, we need to build the model

as perfect as the drawing. We can use setsquares to make sure the fettucine are joined

perpendicular to one another.

3. Place cardboard on the table when using 3 seconds glue in order to prevent the glue

from staining the table.

4. When using 3 seconds glue, make sure the position of joint and stick it quick and

accurately. Remember try not to readjust the position because when there is a layer of

glue on the fettucine, it will be tricky to stick them precisely again.

5. Make sure the finger is not near to the place where u apply glue because when

removing the finger after holding the fettucine in its position might cause destruction of

the joints of the fettucine itself.

Page 24: BUILDING STRUCTURE FETTUCINE BRIDGE

23 | P a g e

6. Reapply glue to every joint.

7. Test the completed bridge a day after construction to make sure the glue has set in.

Joints:

a) Make sure the fettucine join firmly with each other. Use sand paper to make sure the

end of the fettucine is flat and even in order to prevent the uneven surface of the

fettucine when joining to one another which would affect the strength of joints.

b) When assemble the components into a bridge, it is better to have four people so that

those components can be held in position and join firmly.

c) In order to make sure the fettucine joins firmly, it is better to join it in a way which the

two fettucine members have the most surface contact. Diagrams below are the

examples.

Example 1:

(a) (b)

Joint (a) will sustain the weight solely based on the glue whereas joint (b) will transfer the load

through the connection. Therefore, joint (b) is a better choice.

Page 25: BUILDING STRUCTURE FETTUCINE BRIDGE

24 | P a g e

Example 2:

(a) (b)

Joint (a) has larger contact surface area compares to joint (b) which make it a better choice for

making the bridge.

Example 3:

(a) (b)

Joint (b) has larger contact surface area compares to join (a) which enable it to hold both of the

bottom strip together firmer than join (a).

Page 26: BUILDING STRUCTURE FETTUCINE BRIDGE

25 | P a g e

Example 4:

(a) (b)

Joint (a) has more contact surface area and a more flat contact surface compare to joint (b)

which mean it can be join much more firmly. Therefore, it is better to choose joint (a) over joint

(b) as this is an important joint for bracing which is an important member in supporting the

bridge.

Page 27: BUILDING STRUCTURE FETTUCINE BRIDGE

26 | P a g e

6.0 Structural Analysis

6.1 Member Analysis

Experiment of various designs of Fettuccini members’ tension and compressive

strength with load. The members were tested to bear with load for 10 seconds

during each experiment. Each members had 160mm clear span and 350mm resting

on table at each end.

Type of member Weight

C beam 300 g 500 g

Broken -

Bent Bent

Bent Bent

Bent Broken

Laminated

Broken -

Bent Broken

Bent Bent

I- beam

Bent Broken

Bent Bent

Bent Broken

L- beam

Broken -

Bent Bent

Triangular

Bent Broken

Table 6.1.1

In conclusion, the double layered I-beam is the most stable although it contributes

the most weight.

d

d d d

d d d

d

d

D

z

D

d

d

D

z

D

d

d

d d

d

d d

d

Page 28: BUILDING STRUCTURE FETTUCINE BRIDGE

27 | P a g e

Further experiments are then carried out to test how different choice of adhesive

affect the performance of the truss. Double layered I-beam of 160mm clear span is

used in this experiment.

Table 6.1.2

The test is carried out further with double layered I-beam with clear span of 160mm

placing vertically on both side of the desks. The adhesive used to construct the I-

beam is 3 seconds glue

800g 900g 1000g 1100g 1200g

Not bent Not bent Bent Bent Broken

Table 6.1.3

Adhesive 800g 900g 1000g 1100g

3 seconds glue Bent Bent Bent+ broken (18s)

-

UHU + 3 seconds glue

Bent Bent Bent Bent+ broken (7s)

Page 29: BUILDING STRUCTURE FETTUCINE BRIDGE

28 | P a g e

6.2 Design Analysis

Fettuccine Truss Bridge Design 1

Figure 6.2.1 (a)

*Assumption Made

Figure 6.2.1 (b)

Total Length: 950mm

Weight of Bridge: 230g

Clear Span: 750mm

Load Sustain: < 1400g

Efficiency: < 8.522 Figure 6.2.1 (c) Cross section

Page 30: BUILDING STRUCTURE FETTUCINE BRIDGE

29 | P a g e

Figures 6.2.2

Problems encountered:

1) Too many members at one joint does not help to transfer load.

2) The bridge is overweight with low efficiency.

3) The upper members are not strong enough to overcome compression.

Solutions:

1) Change the connection of slanted members with vertical members.

2) Reduce the length of connecting beams to reduce weight of the bridge which does

not exceed 200g.

3) Replace two-layer laminated with I-beam for upper members and vertical members

to increase the strength.

Page 31: BUILDING STRUCTURE FETTUCINE BRIDGE

30 | P a g e

Fettuccine Truss Bridge Design 2

Figure 6.2.3 (a)

*Assumption Made

Figure 6.2.3 (b)

Total Length: 950mm

Weight of Bridge: 233g

Clear Span: 750mm

Load Sustain: < 1000g

Page 32: BUILDING STRUCTURE FETTUCINE BRIDGE

31 | P a g e

Efficiency: < 4.292 Figure 6.2.3 (c) Cross Section

Figure 6.2.4

Problems Encountered:

1) The internal bracings are too long and weak to resist force.

2) Failure on joints.

3) Horizontal members broken. The surface in contact with vertical member is low

therefore load cannot be transferred.

4) Upper members are too weak to sustain load.

Solutions:

1) Reduce the length and increase the thickness of internal bracing.

2) Perfect edges on fettuccine to allow perfect joining.

3) Change the orientation of I-beams.

4) Replace two-layer laminated with I-beam for upper members and vertical members

to increase the strength.

5) Change the orientation of slanted members for better load distribution.

Page 33: BUILDING STRUCTURE FETTUCINE BRIDGE

32 | P a g e

Fettuccine Truss Bridge Design 3

Figure 6.2.5 (a)

*Assumption Made

Figure 6.2.5 (b)

Total Length: 950mm

Weight of Bridge: 340g

Clear Span: 750mm

Load Sustain: 3860g

Efficiency: 43.822 Figure 6.2.5 (c) Cross section

Page 34: BUILDING STRUCTURE FETTUCINE BRIDGE

33 | P a g e

Figure 6.2.6

Changes made refer to previous designs:

1) Vertical and upper members are changed to I-beams.

2) Length of connecting beams reduced. (shown in section)

3) Height of the truss bridge reduced.

4) Internal members increases.

Problems Encountered:

1) Connecting beams could not sustain higher load.

2) Weight of the structure exceeds 140g.

3) The efficiency is still not satisfying.

Solutions:

1) Replace some of the members with two-layer laminated to reduce the weight.

2) Increase the spacing of the internal members to reduce material used.

3) Add horizontal beams onto connecting beams to sustain higher load.

Page 35: BUILDING STRUCTURE FETTUCINE BRIDGE

34 | P a g e

Fettuccine Truss Bridge Design 4

Figure 6.2.7 (a)

*Assumption Made

Figure 6.2.7 (b)

Total Length: 950mm

Weight of Bridge: 354g

Clear Span: 750mm

Load Sustain: 5200g

Efficiency: 76.384 Figure 6.2.7 (c) Cross Section

Page 36: BUILDING STRUCTURE FETTUCINE BRIDGE

35 | P a g e

Figure 6.2.8

Changes made refer to previous designs:

1) Height of truss bridge reduced.

2) Internal members reduced.

3) Horizontal beams added onto connecting beams.

4) Length of connecting beams reduced.

Problems encountered:

1) Failure on joints.

2) The structure has sustain its maximum load but efficiency still not satisfying.

3) Weight of the structure still exceeds 154g.

Solutions:

1) Have all the connecting beams join directly perpendicular to the vertical members to

improve load distribution.

2) Reduce the number of layers in less critical members.

3) Reduce the height and length of connecting beams.

Page 37: BUILDING STRUCTURE FETTUCINE BRIDGE

36 | P a g e

Fettuccine Truss Bridge Design 5 (Final Design)

Figure 6.2.9 (a)

*Assumption Made

Figure 6.2.9 (b)

Total Length: 950mm

Weight of Bridge: 225g

Clear Span: 750mm

Load Sustain: 5750g

Efficiency: 146.944

Page 38: BUILDING STRUCTURE FETTUCINE BRIDGE

37 | P a g e

Figure 6.2.9 (c) Cross Section

Figure 6.2.10

Apparently, the efficiency of our last design is the highest among the previous truss bridges.

Page 39: BUILDING STRUCTURE FETTUCINE BRIDGE

38 | P a g e

7.0 Conclusion

By the end of this project, we had constructed a total of 5 fettucine bridges to achieve the

highest efficiency possible. The precedent study of Cicero Avenue Cal-Sag Bridge had help us

to understand how load is distributed in a truss bridge system.

Our final model of the bridge is constructed in perfect frame system and achieved the

highest efficiency among the 5 bridges. The efficiency calculated for our final bridge testing

is 146.944. This project has made us understand more about load distribution in a structure.

We also learned to calculate the efficiency and type of force applied in each structural

member.

We had also experimented with various truss and beam deigns in order to select the best

one for our bridge construction. We understood the importance of the diagonal bracing

member. Therefore, these members are heavily strengthen using double layered I-beams.

The precision of each connecting joints were achieved as we had built the bridge based on

the computer aided drawing we had prepare. Each connecting point were milled evenly

using sand paper to prevent imperfect connecting joints.

This project required quite a period of time as we had to go through a couple of trial-error.

The bridge building process was long and tedious and required lots of patience putting the

whole thing together. But it never fail to amaze us how a non-construction material like the

fettucine is able to withstand load after proper designing and structural analysis. All in all, it

was a great learning process, regardless of how tedious the building process might be. We

learnt a great deal in proper structural design and it will definitely us in creating a building

with proper building structure for future projects.

Page 40: BUILDING STRUCTURE FETTUCINE BRIDGE

39 | P a g e

8.0 Appendix

A group photo taken during final load testing.

Page 41: BUILDING STRUCTURE FETTUCINE BRIDGE

40 | P a g e

9.0 References

Cicero avenue cal-sag bridge. (2011). Retrieved from

http://historicbridges.org/bridges/browser/?bridgebrowser=illinois/cicerosag/

Kathy , W. (2007, 2 27). Cicero avenue cal-sag bridge. Retrieved from

http://bridgehunter.com/il/cook/calsag-cicero/

Vincent T. H, C. (n.d.). What are the differences among warren truss, howe truss and pratt

truss?. Retrieved from http://www.engineeringcivil.com/what-are-the-differences-among-

warren-truss-howe-truss-and-pratt-truss.html