    BUILDING THE FOUNDATIONFOR A SUCCESSFUL MAINTENANCE PROGRAM

    By

    Frederick T. Coenen

    Maintenance Management ConsultantCSI Services, Inc., an Emerson Process Management Company

    Have you ever wondered why a large percentage of Maintenance programs either end

    up sitting on a shelf gathering dust or fail to produce the promised results?

    Until recently most of the customers that I have provided consulting services to have

    virtually none or very little in the way of Preventive (PM) (Time Based) or Predictive(PdM) (Conditioned Based) Maintenance programs.

    When I would ask them what percentage of their work was Reactive (Breakdownfighting fires) it would range from 50-90%.

    If they have a PM program, the answer of how much of the PM work that is done on

    schedule, ranged from 40%-60%.

    When the majority of the work is reactive, than the text book answer is implementing

    PM and PdM programs.

    But, before you can move ahead with the PM and PdM programs you have to have a

    solid foundation on which to build these programs.

    For the last year and a half I have been working with a large government agency. Whenthe initial evaluation of their programs was done, it was obvious that they had an

    excellent preventive and predictive program in place. If youve ever had the opportunityto put this type of program in place this was the ideal situation. A separate departmentwas formed with the sole purpose of developing the predictive programs to move from a

    strictly preventive to a combination of preventive and predictive. Starting with VibrationAnalysis, Thermography, Oil Analysis and later adding Ultrasound this was a complete

    program. Excellent training was provided for all of the personnel which includedcertification. Full time technical and administrative support was provided as the

    programs were implemented and evolved.

    With all this in place over a period of 2-3 years you would think the results would be

    obvious. Yes, there were some successes but they were minimal!

    During the initial interviews with the Predictive Technicians, Maintenance Mechanics,

    maintenance management and support personnel a common theme came through. Thepredictive programs were doing exactly what they are supposed to do, identifying a

    problem before it failed, but the equipment was failing anyway. As you would expect not

  • 7/29/2019 Building the Foundation for a Program

    2/5

    RCM

    TPM

    RBM

    Predictive

    Preventive

    Reactive

    1. Consistent Top Management support for the program.2. Standardize Work Flow Process.

    3. Organized to support the Work Flow Process.

    4. CMMS System that supports the Work Flow andOrganization.

    only was this very frustrating to the Predictive Technicians, but the equipment ownerswere really questioning the value of the program.

    The answer was obvious; the foundation for the program was not in place.

    But before we get into that, lets set the stage; approximately 6-7 years ago the

    maintenance department was decentralized and each building became self-sufficientexcept for such trades as: carpentry, elevators, locksmith and machinists. With the

    decentralization came the loss of support personnel, common processes and systems.In short, everybody was doing his or her own thing.

    It was now clear why the identified work was not getting completed, there was not acommon work flow process for the work to be completed. A computerized maintenance

    management system (CMMS) was in place but was used very little and was very slow.If a work order was developed it went in the system, usually got lost or was never

    completed.

    This is a perfect example of what looked like on the surface like a program that wasworking well and producing the expected results. But because the foundation was not inplace the results of the program were less than expected.

    In order to address these issues the following four (4) step plan was put in place:

    1. Gain Top Management support for the program2. Develop and implement a simple work flow process

    3. Develop and implement an organization that supported the work flow process4. Select or develop a CMMS that supports the workflow and the organization.

  • 7/29/2019 Building the Foundation for a Program

    3/5

    In order to gain the consistency and ownership required, teams of cross-functionalmaintenance personnel from the different buildings and crafts were formed to develop

    the work flow process and the organization to support the work flow.

    The workflow must be simple and easy to understand and provide the planning and

    scheduling steps to improve the manpower efficiencies.

    MAINTENANCE WORK PROCESS

    The team defined the detail work required for each step and what function in the

    workflow is responsible to complete the work.

    This plan was presented and accepted by all the maintenance management as the

    overall work flow process.

    Each Maintenance Building Manager and Craft Manager reorganized their departmentsand assigned people to fill the workflow functions. Depending on the workload andnumber of crafts the Planning and Scheduling could be under one person or in some

    cases multiple Planners and Schedulers were required. In every case the Auditresponsibilities fell under the Planners.

    AUDIT

    EXECUTE

    SCHEDULE

    PLAN

    WORK ORDERS

    Packaging the work.

    Who by name will do the

    work and the time and

    date it is scheduled tobecompleted.

    When the work is actually

    completed. What actually got done

    What went well and what

    needs improvement the

    next time we do this work.

    This is the continuousimprovement step.

  • 7/29/2019 Building the Foundation for a Program

    4/5

    A formal Planning and Scheduling class was presented to all the people filling these

    functions.

    The last step in the four- (4) step process was the CMMS program. As luck would have

    it a decision was made to replace the old system. Without going through all the detailsthe final decision was made to develop the system in house using web pages. Having

    been through the in-house development before I was really doubtful that this was agood move.

    The maintenance team did not have any input in that decision and development of theprogram began in a vacuum using the old system, which did not work before, as a

    template.

    Since the group developing the CMMS had not been part of the Work Flow Process itbecame obvious very quickly that the new CMMS was not going to support the

    workflow.

    In order to correct this situation a meeting was held with the CMMS development group

    and the Maintenance Team. The purpose was to explain the Workflow and make surethe new CMMS system supported the work. Needless to say this caused a majorredirection for the CMMS development team.

    Another cross-functional team was formed to provide the CMMS requirements in detail.

    The development of the system progressed fairly quickly and version (1) was put out foruse in approximately 3 months. The advantage of using the web page concept became

    apparent very quickly, making changes to the system is quick and simple. Since wewere really feeling our way along with the system and the people were new in the

    Planning and Scheduling functions, there were numerous requests for changes. Thecross-functional team was required to review, prioritize, and approve all changes. Themajor test for each change: did it support the Maintenance workflow Process?

    The CMMS is a long way from being a complete system, but since the basic system is

    in place and supporting the workflow and the organization, the consisentcy and resultsare starting to be realized.

    As you examine your Maintenance Program make sure you have a strong foundationfor your program:

    Is your Top Management support for the program strong and consistent?

    Do you have a simple workflow process that supports Planning and Scheduling?

    Does it include a continuous improvement step?

    Is the organization designed and manned to support the work?

    Does the CMMS support the work or do you have to change the way you do work to

    fitthe CMMS?

  • 7/29/2019 Building the Foundation for a Program

    5/5

    Finally in order to sustain the management support that you must have for any program,report regularly on the agreed upon metrics.