1 Administrative and Fiscal Services 336-506-4410 FAX 336-578-3964 1247 Jimmie Kerr Road P.O. Box 8000 Graham, NC 27253-8000 www.alamancecc.edu Buildings and Grounds Committee November 9, 2017 Proposed County Bond and Connect NC Bond Project List Proposed Changes Background: The purpose of this memo is to summarize changes made to the proposed 2018 county bond project list and the Connect NC state bond project list. Connect NC Bond On June 13, 2016, the Alamance Community College Board of Trustees approved how the College would utilize the $6.1M in Connect NC state bonds allocated to the College. Following is a brief summary of what was approved. Project Cost Facilities Master Plan Backfill $1,872,839* Powell Building Design Work $562,500 Student Center Design Work $465,000 Performance Contracting HVAC and Satellite Locations $1,500,000 Culinary Expansion and Renovation $1,700,000 Total: $6,100,339 *Amount in June 2016 was $1,858,875; final amount per NCCCS $1,872,839 College Administration proposes the following changes to align 2018 county bond and NC Connect bond projects with predicted funds to ensure the College’s facilities master plan is fully implemented over the next 10

Upload: others

Post on 14-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Buildings and Grounds Committee November 9, 2017 Proposed … · 2017. 11. 8. · Connect NC Bond On June 13, 2016, the Alamance Community College Board of Trustees approved how the

1

Administrative and Fiscal Services 336-506-4410

FAX 336-578-3964 1247 Jimmie Kerr Road

P.O. Box 8000 Graham, NC 27253-8000

www.alamancecc.edu

Buildings and Grounds Committee November 9, 2017

Proposed County Bond and Connect NC Bond Project List Proposed Changes

Background:

The purpose of this memo is to summarize changes made to the proposed 2018 county bond project list and the

Connect NC state bond project list.

Connect NC Bond

On June 13, 2016, the Alamance Community College Board of Trustees approved how the College would utilize

the $6.1M in Connect NC state bonds allocated to the College. Following is a brief summary of what was

approved.

Project Cost

Facilities Master Plan Backfill $1,872,839*

Powell Building Design Work $562,500

Student Center Design Work $465,000

Performance Contracting HVAC and Satellite Locations $1,500,000

Culinary Expansion and Renovation $1,700,000

Total: $6,100,339

*Amount in June 2016 was $1,858,875; final amount per NCCCS $1,872,839

College Administration proposes the following changes to align 2018 county bond and NC Connect bond

projects with predicted funds to ensure the College’s facilities master plan is fully implemented over the next 10

sbwaters544
Typewritten Text
IV.B.7 / IV.B.8
Page 2: Buildings and Grounds Committee November 9, 2017 Proposed … · 2017. 11. 8. · Connect NC Bond On June 13, 2016, the Alamance Community College Board of Trustees approved how the

2

years. The major change from the original list is transferring design work for the Powell Building renovation and

Student Center new construction to the proposed county bond, transferring satellite location development to the

proposed county bond and/or county capital allocation, increasing the scope of the original backfill project, and

reducing the culinary renovation/expansion project scope.

Project Cost

Facilities Master Plan Backfill:

Early/Middle College Dedicated Facility Upgrade

Former Automotive Building Retrofit and Renovation

Food Service Expansion, Classrooms, and

Administrative/Multipurpose Retrofit

Total Backfill

$2,521,245

$1,414,125

$1,064,969

$5,000,339

Culinary Expansion and Renovation $1,100,000

Total: $6,100,339

Action Required: Be it resolved that the Building and Grounds Committee recommends to the College’s Board

of Trustees to approve the revised above facilities improvement projects in the aggregate amount of $6,100,339

to be funded by means of Connect NC Bond funds.

Proposed Alamance County Bond Referendum

On April 4, 2017, and April 7, 2017, the Alamance Community College Building and Grounds Committee and

Finance Committee met and approved the following expansion projects utilizing proposed a 2018 County Bond

Referendum. The Alamance Community College Board of Trustees approve the projects on April 11, 2017. The

2018 Alamance County Bonds were to be allocated to the College as follows:

Project Cost

Powell Building Expansion: Construction Work $6,937,500

New Student Learning and Development Center: Construction Work $5,735,000

Center of Excellence: Build and Design $5,400,000

Modernize Early Childhood Learning Lab/Daycare, Update Early

Childhood Classrooms and Main Building Classrooms

$1,290,000

Convert and Modernize Vacated Gee Building First Floor to

Multipurpose

$1,309,500

Rework Entrance and Promenade $300,000

Parking Deck/Transportation Center: Build and Design $10,080,000

Page 3: Buildings and Grounds Committee November 9, 2017 Proposed … · 2017. 11. 8. · Connect NC Bond On June 13, 2016, the Alamance Community College Board of Trustees approved how the

3

Project (Cont.) Cost

Update and Modernize Vacated Main Building (convert old bookstore):

Food Service, Multipurpose Rooms, and Classrooms

$1,053,300

Library and Learning Resource Center: Build and Design $5,500,000

Modernize Vacated Third Floor Gee Building $2,046,375

Total: $39,651,675

Due to reassessed needs, updates have been made regarding expending the $39.6M in 2018 Alamance County

Bond Referendum funds if passed in November 2018. The goal of the bond is to upgrade college facilities that

prepare students for jobs and university transfer by modernizing academic and job-training classrooms and

facilities, creating a Public Safety Training Center, expanding the Natural and Life Science Facilities, building a

new Student Services Learning and Development Center, and constructing a Student Vehicle Center. Major

changes from the original list include adding the Public Safety Training Center, removing the new library from the

bond measure, decreasing the scope of Natural and Life Science Facilities, decreasing the scope of the Multi-

Deck Student/Visitor Vehicle Center, and adding Satellite Campus Development. The project updates are as

follows:

Project Cost

Natural and Life Science Facilities Expansion & Renovation $9,100,000

New Student Services Learning and Development Center $6,200,000

Childcare Facility/Early Childhood Education Center Renovation $1,000,000

Public Safety Training Center $10,428,200

Multi-Deck Student/Visitor Vehicle Center $8,460,000

Modernize Academic Classrooms, Labs, Student Support Spaces, and

Learning Facilities Improvements and Expand Campus Technology

$3,463,475

Satellite Locations Development-East/West $1,000,000

Total: $39,651,675

Action Required: Be it resolved that the Building and Grounds Committee recommends to the College’s Board

of Trustees to approve the above revised facilities improvement projects in the aggregate amount of

$39,600,000 to be funded by means of a public Alamance County bond referendum.