Burke MountainSchoolDistrictNo.43(Coquitlam)
About the School District
• 70 schools• Elementary, Middle, Secondary• Approx. 30 000 students• Projected growth: approximately 5,000 more students in the next 10‐15 years
• Several growth areas in our District
Accomplishments
• 16 seismically upgraded schools • 5 seismic replacement schoolsJames Park, Pitt River, Centennial, Moody Middle, Banting
• 3 supported seismic projectsMinnekhada, Montgomery, Irvine
• 3 new/replacement schoolsHeritage Woods, Glen, Eagle Mountain
• 9 Additions*Message from Government*
Learning, Land and NeighbourhoodsCommunity DialogueVictoria ParkNovember 19, 2013
LLN PropertiesParkland1.3Acres– COMPLETEDVictoriaPark– LANDEXCHANGEAGREEMENTIN
PLACE• CoronationPark– Inprogress
• CommunityBenefit• MaximizeLandValue
• MoodyElementarySchool• WorkingwithMinistryofEducationtoreceiveSeismicSupportFunds
• NewElementarySchoolonMiddleSchoolSite
Enrolment Demands
Capital Plan1.NewBurkeMountainElementary#1(Smiling
Creek)
2.2– roomadditionatWaltonElementary
3.4‐ roomadditionatGlenElementary
4.2– roomadditionatPanoramaElementary
5.NewBurkeMountainElementary#2(Sheffield)
6.Seismic(replacement)MoodyElementary
Burke Mountain School Sites – Potential (2002)
Evolution of Site Selection• EducationalNeeds
• Philosophy• MarketDemand(Programming)• Economics
• Determination5schools(3elementary,1middle,1secondary)North‐WestBurkeMountainVisioningProcessOutcome
• SiteAnalysis• CommunityStructures• SuitabilityofSites• AppropriateDistribution• PotentialCost
Burke Mountain School Sites – Potential (2002)
Sites
Landissecuredtoaccommodateall5required
schools
Burke Mountain School Sites ‐ Actual4sites&5schools
Smiling Creek Elementary
Smiling Creek Site
• JointSchool/ParkSite• Approximately7acres• AgreementbetweenCityandSDtocompletelandexchange• CityreceivesSDownedlandinVictoriaPark• SDreceivesequalamountofland(Queenston Ave)
Smiling Creek Site
Partington Creek – “Sheffield” Elementary
Sheffield Site
•6acresite• SponsoredCrownGrant•OCPandZoninginplaceaspartofWesbilddevelopmentapplication
Partington Creek – “Marigold” Elementary
Secondary & Middle School Site
Anticipated School Timeline
DesignConstruction Subjecttochangebasedonprogressofdevelopment
School Project 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
Smiling Creek ElementaryPartington Creek Elementary (Sheffield)
Northeast Coquitlam Middle
Burke Mountain Secondary
Marigold Street Elementary
Typical New School Progression• SubmitCapitalPlan• SDsubmitsaProjectIdentificationReport(PIR)• 7stepprocesstoreceiveapprovaltopurchaseland• SDsubmitsanupdatedProjectIdentificationReport(PIR)• OncepreliminarysupportisgrantedSDcompletedaProjectDevelopmentReport(PDR)
• ApprovalisobtainedwithaProjectAgreement(PA)• Neighbourhood LearningCentre(NLC)Consultationtakesplace
• Architectishiredanddesignprocessbegins(10– 12months)
• Construction(18– 24months)
Moving Forward
SmilingCreekElementarySchoolConstructionProcess
FundingProcess‐SubmitaCapitalPlanSDsubmits(PIR)7stepprocesstogetapprovaltopurchaselandUpdatedPIRsubmittedCompleteadetailedreport(PDR)whichincludesacostanalysis
‐ApprovalisobtainedfromMinisty ofEducationthroughaProjectAgreementfollowedbyanOfficialAnnouncement
Moving ForwardSDhashiredaConsultingTeaminadvanceofProjectAgreementDesignProcessisunderwayNeighbourhoood LearningCentre(NLC)ConsultationhasbegunwithsurveyresultsbeingrecordedJune24th NLCPublicConsultationandDesignUpdateatLeighElementarySchoolbeginningat6:00pmApplicationsubmittedonDevelopmentprocess