KALANIANAOLE HIGHWAY ENDS N 0’ 50’ 100’ MATCH LINE A Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple) Existing Driveway (Red) Existing Sidewalk (Yellow) Existing Landscaped Buffer (Green) Existing Driveway (Red) Proposed Raised Median with Landscaping Proposed Berm Median Island Proposed Ramp (Blue) Marked Crossing (White) Proposed Raised Berm Curbing (Red) Proposed Asphalt Path (Light Grey) Existing Bus Stop To be Consolidated Relocated Bus Stop Existing Bus Stop to remain New Road Sign 1 1 of 21 Bus Stop to be Consolidated and Moved • Low existing ridership • Excess stops adds delay to bus route • Existing transit riders may use Flamingo bus stop (~500 feet to east) Bus Stop to be Consolidated and Moved • Low existing ridership • Excess stops adds delay to bus route • Existing transit riders may use Flamingo bus stop (~1000 feet to east)

Upload: others

Post on 02-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

KALANIANAOLE HIGHWAY

ENDS

N0’ 50’ 100’

MATC

H LINE A

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

11 of 21

Bus Stop to be Consolidated and Moved• Low existing ridership

• Excess stops adds delay to bus route

• Existing transit riders may use

Flamingo bus stop (~500 feet to east)

Bus Stop to be Consolidatedand Moved• Low existing ridership

• Excess stops adds delay to bus route

• Existing transit riders may use

Flamingo bus stop (~1000 feet to east)

Page 2: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

KALANIANAOLE HIGHWAY

Flam

ingo S

t

N0’ 50’ 100’

MATC

H LINE A

MATC

H LINE B

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

22 of 21

Bus Stop to be Consolidatedand Moved• Low existing ridership

• Excess stops adds delay to bus route

• Existing transit riders may use

Flamingo bus stop (~500 feet to west) or

Humuniki bus stop (~900 feet to east)

Raised Median with Landscaping• Provides gateway treatment to notify drivers

they are entering residential area

• Reduces vehicle speeds

• Restores greenery to area

• Retains breaks for driveway access

Curb Extensions• Minimizes pedestrian crossing distance

• Aligns curb ramp

Glenn's

Flowers & Plants

Nalowinds

Kennels

Relocated Bus Stop• Provides accessibility to transit riders

within 1/2-mile radius

• Stop at location with raised median

prohibits illegal passing

Retain Bus Stop• Provides accessibility to transit riders

within 1/2-mile radius

Bus Stop to be Moved

Page 3: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

KALANIANAOLE HIGHWAY

Hu

mu

nik

i St

Sad

dle

Cit

y R

d

Kumuhau St

N0’ 50’ 100’

MATC

H LINE B

MAT

CH L

INE

C

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

33 of 21

Install Raised Center Median with Z-Crossing and Pedestrian Crossing Signs

Relocated Bus Stop• Provides accessibility to transit riders

within 1/2-mile radius at protected

pedestrian crossing

• Stop at location with raised median

prohibits illegal passing

Curb Extensions• Minimize Pedestrian Crossing Distance

• Aligns Curb Ramp

• Shortens pedestrian crossing distance

• Provides refuge for pedestrian protected

• Acts as traffic calming measure to slow

speeding vehicles

Weinberg Village

Waimanalo

Bus Stop to be Consolidated and Moved• Excess stops adds delay to bus route

• Existing transit riders may use

Humuniki bus stop (~450 feet to east)

located at protected pedestrian crossing

Page 4: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

KALANIANAOLE HIGHWAY

Hu

mu

nik

i St

Me

kia

St

Hu

gh

es S

t

Poal

ima

St

N0’ 50’ 100’

N

MAT

CH L

INE

C

0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

44 of 21

Restrict Driveway Access• Consolidate vehicle movements

to right-in/right-out only

• Reduces conflicts with pedestrians

along sidewalk

• Reduces vehicle conflicts with

turning traffic on Kalanianaole Hwy

and off Mekia Street

Curb Extensions• Minimizes Pedestrian Crossing Distance

• Aligns Curb Ramp

MAT

CH L

INE

D

Phase I ConstructionLimits

Weinberg Village

Waimanalo

Waimanalo

Town Center

Jack in the box

Shima's Supermarket

L & L Drive-Inn

Waimanalo Feed Supply

7-Eleven

Reconfigure Intersection• Shortens Pedestrian Crossing Distance

Bus Stop to be Moved• Existing transit riders may use

Humuniki bus stop (~200 feet to west)

located at protected pedestrian crossing

Page 5: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

N0’ 50’ 100’ NNNNNNNNNNNNNNN000000’0’000’0’0000000 505050505505 ’’’’’’’’’’’’’’’ 1010101010101001010101101000’0’0’0’’00’00’000’0’0’0’0’’0

Poal

ima

St

MAT

CH L

INE

D

MAT

CH L

INE

E

KALANIANAOLE HIGHWAY

76 Gas Station

Waimanalo

Shopping Center

Install Berm Curbing• Provides continuous physical

protection for pedestrians

• Connects sidewalk gaps

• Delineates pedestrian space

Relocate Crosswalk• Move crosswalk closer to intersection

• Move pedestrian push button and

pedestrian signal

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

55 of 21

Page 6: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

N0’ 50’ 100’ NNNNNNNNNNN0’0’0’0’0’0’0’0’0’0’00 50505050505050505050505050’’’’’’’’’’ 101010101010100000000’0’0’0’0’0’00’0000

N

0’ 50’ 100’

KALANIANAOLE HIGHWAY

Mo

ole

St

• Shortens crossing distance

• Makes pedestrians more visible

MAT

CH L

INE

E

Install 25 mph School Speed Limit Sign In Expanded School Zone

Install Berm Curbing• Provides continuous physical protection

for pedestrians

• Connects sidewalk gaps

• Delineates pedestrian space

Relocate Crosswalk

Relocate “Your Speed is” Sign• Move the sign to not conflict with view

of other signage

Student Accessible Path/Gate

Kuhimana Street

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

66 of 21

MAT

CH L

INE

F

Install Pedestrain Activated Solar RRFB• Install back-to-back pedestrian school crossing signs

and arrows

• Provides warning for safe school crossing

• Three pedestrian collisions over four years (2010-2014)

Page 7: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

77 of 21

MAT

CH L

INE

F

MAT

CH L

INE

G

KALANIANAOLE HIGHWAY

DR

IVE

WA

YD

RIV

EWA

Y

Waimanalo Elementary

and Intermediate school

WaimanaloHealth Center Waimanalo

Fire Station

St George Church

Improve Bus Stop• Add bus stop shelter

pad (Orange)

• Add covered shelter

• Add trash can and

other amenities

Install Berm Curbing• Provides continuous physical

protection for pedestrians

• Connects sidewalk gaps

• Delineates pedestrian space

Install Marked Crossings• Provides access to bus stop and school

Student Accessible Path/Gate

Kuhimana Street

Page 8: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)

Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)

Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

88 of 21

Ino

ao

le S

tre

et

MAT

CH L

INE

G

MAT

CH L

INE

H

Waimanalo Elementary and Intermediate school

Kuahale OhanaPublic Housing

(Hawaii Housing Authority)

Repair “Your Speed is” Sign• The “Your Speed is” sign is currently

not working

• Add speed limit sign to same pole

Relocate Crosswalk and InstallBack-to-Back Signage• Provides direct access to bus stop

• Increases sight distance

• Remove stop bar

Install Berm Curbing and Mark Crossing• Provides continuous physical protection

for pedestrians

• Connects sidewalk gaps

Page 9: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

Waimanalo

Bay Beach Park

Bellows Air

Force Station

Tink

er R

d

KALANIANAOLE HIGHWAY

Remove Stop Bar

MAT

CH L

INE

H

MATCH LIN

E I

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

99 of 21

Page 10: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

Waimanalo

Bay Beach Park

DRI

VEW

AY

Remove Stop Bar

MATCH LIN

E I

MATCH LIN

E J

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

1010 of 21

Page 11: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

McDonald's

Waimanalo

Market

Co-op

‘Ai Love Nalo

ALOIL

OI

KALANIANAOLE HIGHWAY

MAT

CH L

INE

J

MAT

CH L

INE

K

Relocate Crosswalk and InstallBack-to-Back Signage• Shortens crossing distance

• Removes pedestrian conflict with bus pull out

Reconfigure Intersection• Add dedicated left and right turn lanes

• Improves level of service

• Does not warrant traffic signal

Install Berm Curbing• Provides continuous physical protection

for pedestrians

• Connects sidewalk gaps

• Delineates pedestrian space

• Restricts parking at the corner

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

1111 of 21

Page 12: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

EHU

KA

I St

HIH

IMA

NU

St

HIN

ALE

A S

t

KALANIANAOLE HIGHWAY

MAT

CH L

INE

K

MAT

CH L

INE

L

Relocate Crosswalk and Signage• Relocate crosswalk to Hihimanu Street to

provide access to Hihimanu bus stops

• Move pedestrian signs

• Remove Stop bar

Remove Crosswalk, Stop Barand Signage

Install Berm Curbingand Asphalt Path• Provides continuous physical protection

for pedestrians

• Connects sidewalk gaps

• Delineates pedestrian space

Bus Stop to be Consolidatedand Moved• Excess stops adds delay to bus route

• Existing transit riders may use

Aloiloi bus stop (~520 feet to west) or

Hihimanu bus stop (~300 feet to east)

Install Back-to-Back Signage

Bus Stop to be Consolidatedand Moved• Excess stops adds delay to bus route

• Existing transit riders may use

Hihimanu bus stop (~370 feet to west) or

Hilu bus stop (~680 feet to east)

Relocated Bus Stop• Provides accessibility to transit riders

within 1/2-mile radius

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

1212 of 21

Page 13: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

KA

ULU

St

HIL

U S

t

MA

NA

NA

St

KALANIANAOLE HIGHWAY

MAT

CH L

INE

L

MAT

CH L

INE

M

Install Berm Curbingand Asphalt Path• Provides continuous physical protection

for pedestrians

• Connects sidewalk gaps

• Delineates pedestrian space

Relocated Bus Stop• Provides accessibility to transit riders

within 1/2-mile radius

Install Back-to-Back Signage

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

1313 of 21

Page 14: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

Serg's Mexican

Kitchen

Bobby's At

Waimanalo Inc

U.S Post

Office

Keneke's

Bobby's At

Waimanalo InWaimanalo InWW

ALA

IHI S

t

PUU

ON

E St

WA

ILEA

St

KALANIANAOLE HIGHWAY

MAT

CH L

INE

M

MAT

CH L

INE

N

Relocate Crosswalk and Signage• Relocate crosswalk to Alaihi Street

• Move pedestrian signs

• Remove Stop bar

Install Berm Curbingand Asphalt Path• Provides continuous physical protection

for pedestrians

• Connects sidewalk gaps

• Delineates pedestrian space

Install Back-to-Back Signage

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

1414 of 21

Page 15: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

Serg's Mexican

Kitchen

U.S Post

Office

Keneke's

7-Eleven

Waimanalo Beach Park

Waimanalo Kupuna Housing

WA

ILEA

St

Olu

olu S

t

KALANIANAOLE HIGHWAY

NA

KIN

I Str

ee

t

MAT

CH L

INE

N

MAT

CH L

INE

O

Install Berm Curbing• Provides extended physical protection

for pedestrians

• Delineates pedestrian space

• Reduces crossing distance

Reconfigure Intersection• Move Stop bar closer to intersection

• Reduces intersection size to reduce speed

and enable ease of turns

Install Berm Median Island• Reduces pedestrian crossing exposure

Relocate Crosswalk and Signage• Relocate crosswalk and pedestrian signs

• Remove Stop bar

Install Marked Crossings• Provides access to bus stops

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

1515 of 21

Install Pedestrian Activated Solar RRFB• Install pedestrian crossing signs with arrows on roadside and in

median

• Provide warning for safe senior and all pedestrian crossings

Page 16: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

Waimanalo

Beach Park

Waimanalo Beach Park

Parking Lot

MAT

CH L

INE

O

MAT

CH L

INE

P

Relocate Crosswalk and Signage• Relocate crosswalk and

pedestrian signs

• Remove Stop bar

Install Z-Crossing with Raised Berm Median• Reduces pedestrian crossing exposure

Proposed Marked Crossings

Bus Stop to be Consolidatedand Moved• Low existing ridership

• Excess stops adds delay to bus route

• Existing transit riders may use

Nakini bus stop (~400 feet to west)

located at protected pedestrian crossing

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

1616 of 21

Page 17: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

Waimanalo Beach Park

Install “No Parking” Signage• Enables unobstructed pedestrian

and bicycle travel in shoulder

• Future plans to consider wider shoulder

that permits parking and bike/pedestrian

use.

Retain School Crossing Signs

Dri

vew

ay

Hu

li St

ree

t

KALANIANAOLE HIGHWAY

Install Z-Crossing with Raised Berm Median Island• Reduces pedestrian crossing exposure

Blanche Pope Elementary School

MAT

CH L

INE

P

MAT

CH L

INE

Q

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

1717 of 21

Page 18: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

Install “No Parking” Signage• Enables unobstructed pedestrian

and bicycle travel in shoulder

Remove Stop Bars

Nal

u S

tre

et

KALANIANAOLE HIGHWAY

MAT

CH L

INE

Q

MAT

CH L

INE

R

Bus Stop to be Consolidatedand Moved• Low existing ridership

• Excess stops adds delay to bus route

• Existing transit riders may use

Huli bus stop (~750 feet to west)

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

1818 of 21

Page 19: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

Install “No Parking” Signage• Enables unobstructed pedestrian

and bicycle travel in shoulder

Install New Crosswalk withBerms and Back-to-Back Signage • Provides continuous physical protection

for pedestrians

• Connects sidewalk gaps

• Delineates pedestrian space

Be

ll St

ree

t

KALANIANAOLE HIGHWAY

MAT

CH L

INE

R

MAT

CH L

INE

S

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

1919 of 21

Page 20: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

Kaiona Beach Park

Kaiona Beach Park

Parking

Kaiona Beach Park

Kaiona Beach Park

Parking

Dri

vew

ay

KALANIANAOLE HIGHWAY

MAT

CH L

INE

S

MAT

CH L

INE

T

Relocate Crosswalk and InstallBack-to-Back Signage• Relocate crosswalk and pedestrian signs

• Remove Stop bar

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

2020 of 21

Page 21: Bus Stop to be Consolidated and Moved...Conceptual Pedestrian Improvements Kalanianaole Highway Improvements, Phase 1 and Phase 2 Proposed Sidewalk (Orange) Proposed Driveway (Purple)

KALANIANAOLE HIGHWAY

MAT

CH L

INE

T

Bus Stop to be Consolidatedand Moved• Low existing ridership

• Excess stops adds delay to bus route

• Existing transit riders may use

Kainoa Beach Park bus stop

(~600 feet to west)

N0’ 50’ 100’

Conceptual Pedestrian ImprovementsKalanianaole Highway Improvements, Phase 1 and Phase 2

Proposed Sidewalk (Orange)Proposed Driveway (Purple)Existing Driveway (Red)

Existing Sidewalk (Yellow)Existing Landscaped Buffer (Green)Existing Driveway (Red)

Proposed Raised Medianwith Landscaping

Proposed BermMedian Island

Proposed Ramp (Blue)Marked Crossing (White)

Proposed Raised Berm Curbing (Red)Proposed Asphalt Path (Light Grey)

Existing Bus StopTo be Consolidated

Relocated Bus Stop

Existing Bus Stopto remain

New Road Sign

2121 of 21