    THE BUSINESS PROCESSES OF SAM

    The business processes required to implement Strategic Asset Management (SAM).

    James W. Davis, PE, Vice PresidentStrategic Asset Management Inc

    Voice: 610-861-7472 E-mail:[email protected]

    INTRODUCTIONIn the last few years many companies have begun to realize the importance of Strategic Asset Management (SAM) as an enterprisestrategy that, properly implemented, will improve financial performance. Typical results of an effective Strategic Plan for AssetManagement include a 20% - 50% reduction in maintenance cost accompanied by a 15% - 20% increase in real capacity, with nocapital investment in production equipment. The tangible results include a significant increase in profitability accompanied by adramatic reduction in unit cost. One of the key concepts required for successful development and implementation of SAM is theconcept of Business Processes. The SAM Business Processes are used to define and measure the means by which we implementthe best practices that lead to significant, sustainable financial performance improvement.

    The Business Processes of SAM are cross-functional as shown in Figure 1. This means that developing and implementing SAMrequires the involvement of key individuals from Production, Engineering, Logistics and Senior Management as well as Maintenance.

    Many so-called Maintenance Improvement programs have failed to achieve sustainable results when we have failed to recognize thiscritical aspect.

    The processes typically break-down at the intersections between the various stovepipe organizations. These organizations often are

    focused on strategies and objectives that are conflicting and competitive in nature. The operations organization is so intent onrunning that they push the maintenance organization to make quick fixes rather than to effect appropriate, lasting repairs.Engineering is tasked with reducing capital expense and controlling construction time rather than considering reliability, availability,maintainability (RAM) and life cycle costs when designing and constructing new facilities. Procurement is rewarded for acquiringparts and materials at least cost, often resulting in substandard items that have a negative impact on overall cost.

    The Vice President of Southern Area Manufacturing for Saudi ARAMCO admonished me that, in our plant, the Production andMaintenance organizations were too friendly. In his words we were In bed together. He viewed this as an unhealthyrelationshipand said that he believed there must be a certain level of animosity between these two groups in order for Operations to push Maintenance to meet their needs. Our performance record eventually proved that the old dinosaur was wrong, but we took a lotof heat for awhile.

    CapacityPlan

    &Manage

    AssetHealthcare

    LogisticsMa

    nagement

    ProductionMa

    nagement

    Asset Management Processes"Asset Management Processes"

    Figure 1: Business Processes of SAM

  • 8/11/2019 Business Procsses

    2/19

    James Davis Page 2

    Studies have shown that among industrial companies in North America:

    The average Maintenance wrench time (hands-on work) is less than 30%.

    The typical level of Preventable Maintenance (repairs that could have been avoide by better process) is approximately70%

    The norm for Asset Utilization (level of on spec production) is averaging 65%.

    These issues point to the need for designing appropriate integrated Business Processes to insure that we manage our critical assetsto the optimum capability.

    WHAT IS SAM

    SAM is an aggressive vision of the future and a related three to five year operational strategy. Key roles are identified anddefined in each element of the strategy. Performance standards are established for critical Business Processes. Key performanceindicators (KPIs) and standard definitions are in place and used for decision making. An effective change management plan isdeveloped and documented. An integrated set of Business processes is designed and implemented to establish a standard ofperformance including a plan for achieving the standard and realizing benefits.

    The Strategy is a cross functional tool that identifies roles and expectations for all elements of the Asset ManagementProcesses. It becomes a prioritizing device that causes us to attack first things first. It enables us to develop a thrust ofcommonality across the enterprise.

    In a recently published paper titled The Future of Asset Management Brad Peterson, President of SAMI, stated, This articleexplores a broader vision for asset management than has been previously articulated and brands this vision

    Strategic Asset

    Management (SAM). Based on successful experience with our clients, SAM is an integrated set of processes that systematicallyderive the highest value from plant assets, through a consistent philosophy, plans and objectives, and cooperative involvement byeveryone in the plant. SAM represents a higher level of performance than is currently practiced or even recognized by themanufacturing community today.

    Any useful model to guide action will have several characteristics:

    Simplicity: All of the greatest ideas are simple in concept. If not kept simple, they are not fully understood orremembered, and fail as guiding principles.

    Intuitive: Readers should be able to understand the underlying principles without guidance.

    Utility:The model should work consistently in application.

    Completeness:All necessary elements of success should be contained.

    Our experience with the SAM model indicates these criteria are met. However, you as the reader will need to make your own

    judgments.

    We will explore the SAM Model and its applications in detail in a subsequent paper.

    Figure 2: The SAM Model

  • 8/11/2019 Business Procsses

    3/19

    James Davis Page 3

    WHY CONSIDER DESIGNED PROCESSES

    An associate, Dr. Carol Vesier, once said to me, Business Processes always exist. However, in most cases, management doesntknow what they are. We came to refer to these as Virtual Processes. They are in use throughout your facilities, usually inseveral varying versions, but they are not well defined and often create issues and conflicts. Employees are free to adjust them oreven create new ones as required to do their assignments as they understand them.

    A good example of a Virtual Process occurs when Employee Joe has a problem with his computer but is unable to get support

    from the IT Department for whatever reason. Joe happens to know that Brenda, another Maintenance Employee is good withPCs, so he gives her a call and she comes over to solve his problem. After all, they have to get t heir jobs done in spite ofmanagement.

    Mark Buchanan said in an article in The New Scientist, employees muck up or ignore about one out of every four or fivecommands that come down from their bosses - its a universal principle.

    This implies that a Senior Vice President can expect employees on the shop floor to implement about 25% - 30% of hisstandards. The graphic in Figure 3 shows how it works.

    The typical plant environment in the absence of well-defined, integrated processes goes something like; Business is triggered bya need. >> Something happens (transfer of information) >> Work is accomplished by someone >> Some Procedure is followed>> Informal network business process occurs (Who can help?) >> Results are evaluated >>>>>>>>> Good, bad, redo, trysomething else. The result is inefficiency at best and impending disaster at worst.

    In the absence of well-engineered business processes, employees are going to create their own in order to get through the day.Unfortunately, their limited view of the landscape often causes these ad hoc processes to be inadequate and even detrimental tothe overall mission.

    A managing system where the core business processes are left to the imagination of employees frequently becomes a quid pro

    quo arrangement. Favors are traded and results are heavily dependant on the popularity and relationships of the employee.Because the Business Processes of SAM are nearly always cross-functional as is depicted in Figure 1, process failures often occurdue to conflicting priorities and adversarial relationships between the various organizations.

    Figure 3: Employee Implementation of Standards

  • 8/11/2019 Business Procsses

    4/19

    James Davis Page 4

    BUSINESS PROCESS CONCEPTS

    In order to have effective business processes, The Six Sigma Way by Peter Pande tells us that we need to understand thecomponents or characteristics required for defining a business process. The following diagram depicts these requirements.

    The SIPOC model is defined as:

    Supplier - the person or group providing key information, materials, or other resource to the process

    Input - the thing provided

    Process - the set of steps that transforms - and ideally, adds value to - the Input

    Output - the final product of the process

    Customer - the person, group, or process that receives the output

    Process Measures and Service Requirements

    These consist of:

    A work flow diagram that models the process and identifies roles for each step in the process, and identifies interfacesto other processes

    Definitions of the roles and terms used in the process model

    Measures or performance indicators to measure the process

    Definition of the inputs / suppliers and

    Clear specification of output and service requirements

    In managing your business processes it is important to avoid the mushroom syndrome and to keep the customers informed. Asan example, insure that the operations or production management dont feel like Maintenance Work Orders fall into a BlackHole once they are initiated. Establish effective reporting systems that provide the information needed to inform and inspireconfidence in the customer of your Business Processes.

    Some examples in the Asset Healthcare arena might include:

    Work order backlog management

    Equipment with defects

    Service Requirements:

    What are the standards for how we interact

    with & treat customers?

    Output Requirements:

    What features or

    characteristics of our final

    product or service are key to

    customer satisfaction?

    Customers

    OutputsInputs

    Process

    Suppliers

    Customer

    Interface

    Figure 4: SIPOC Model

  • 8/11/2019 Business Procsses

    5/19

    James Davis Page 5

    PM/PdM completion

    Clearly list the expected results from each process and identify quality requirements and specifications. Specify delivery andturnover procedures for the customer of each process. Create and use measures to manage process output quality

    Some examples in Asset Healthcare and Logistics management may include::

    Turnover completed repairs to production

    Accept new MRO equipment, parts, materials

    BUSINESS PROCESSES VS. BEST PRACTICES

    In many so-called Maintenance Excellence and other programs such as TPM and Lean Manufacturing, proponents focus onimplementing best practices. This approach almost invariably fails to achieve dramatic improvements that are sustainable in thecompany culture. Best practices focus on the what we should be doing while Business Processes define how we will do ourcritical work.

    The Core Business Processes

    There are nine Core or high level Business Processes that are addressed in SAM. The following section provides an overviewparagraph and two or three examples of each of these. Table 1 provides a partial list of the database that we have developed and

    used in implementing business processes in several industries

    The author has provided a detailed example of the Maintenance Work Management Process at Appendix I.

    Strategic Management

    Strategic Management processes define the way in which we establish and communicate the future of the company involvingstakeholders at all levels within the organization.

    Strategy development and planning process

    Goal setting and tracking process

    Results measurement and process validation process

    Information Management

    Information Management incorporates all of the processes and tools that are used to store and retrieve information that is used to

    support decision making based on hard data.

    Repair tracking and reporting process

    Informations systems evaluation and selection process

    Reliability Management

    Equipment Criticality 4.1.1 Assigning Equipment Criticality

    4.1.2 Revising Equipment Criticality

    Equipment Taxonomy

    Equipment MaintenanceStrategies

    4.3.1 Maintenance Strategy

    4.3.2 Create Corporate Generic MaintenanceStrategies

    4.3.3 Revising Corporate Generic Maintenance

    Strategies

    4.3.4 Applying a Maintenance Strategy to anEquipment Unit

    4.3.5 Revising a Maintenance Strategy to an

  • 8/11/2019 Business Procsses

    6/19

    James Davis Page 6

    Equipment Unit

    Standard Repair Procedures 4.4.1 Standard Maintenance Repair Plans

    Acceptance Testing 4.5.1 Identifying Special Acceptance Testing

    Equipment Condition

    Monitoring

    4.6.1 Condition Monitoring

    4.6.2 Define Condition Monitoring Tools forEquipment

    Failure Analysis and Response 4.7.0 Failure Analysis Core Process

    4.7.1 Historical Data Analysis

    4.7.2 Basic Failure Analysis

    4.7.3 Advanced Failure Analysis

    4.7.4 Implement Corrective Actions

    Total Equipment Ownership

    Cost

    4.8.1 Life Cycle Costing.vsd

    4.8.2 Applying Selection Criteria for PurchasingNew Equipment

    Parts Management and

    Inventory Control

    4.9.1 Parts Management

    4.9.2 Reviewing Part Historical Data

    4.9.3 Implement Vendor Stocking Programs

    Resource Management

    Applying Criticality 5.1.1 Applying Equipment Criticality

    Work Management (Reactive

    Maintenance)

    5.2.0 Reactive Maintenance Core Process

    5.2.1 Execute Emergency Work

    5.2.2 Identify Contingency Work

    Work Management (Planning,

    Scheduling and ExecutingWork)

    5.3.0 Maintenance Work Core Process

    5.3.1 Identify Work

    5.3.2 Plan Work

    5.3.3 Schedule Work

    5.3.4 Execute Work

    5.3.5 Execute PM/PdM Work

    5.3.6 Document Work

    5.3.7 Backlog Management

  • 8/11/2019 Business Procsses

    7/19

    James Davis Page 7

    5.3.8 Record Event Info Needed for FailureAnalysis

    Shutdown Management 5.5.0 Maintenance Shutdown Core Practice

    5.5.1 Develop Shutdown Scope of Work5.5.2 Create Preliminary Shutdown Schedule

    Table 1

    Organization Management

    Organization Management involves establishing the Asset Management process management organization and defining the rolesof personnel involved in working with the reliability and maintenance business processes in all organizations. It defines ourManaging System business processes.

    Managing cross-functional processes process management organization

    Defining roles and responsibilities for processes

    Capacity and Capital Management

    Capacity Management processes address the methods by which we acquire or dispose capacity and manage capital investment. Itincludes all of the aspects of incorporating reliability, maintainability, and operability into the design and installation of new

    systems and equipment or modifications to existing.

    Reliability, Availability, Maintainability assessment of systems and equipment

    Life cycle cost assessment

    Capital equipment procurement data for reliability

    Production Management

    Production Management includes all of the processes necessary for establishing and maintaining proper process controls as well

    as those required for day to day management of the production process. This process includes critica l equipment operatingprocedures, quality management, environmental compliance, and more.

    Process quality assurance management

    Critical equipment start-up and shutdown-processes

    Environmental compliance assurance process

    Resource Management

    Resource Management includes all of the planning and supervision activities that go in to allocating manpower, materials, toolsand contractors to the accomplishment of the day to day function of the manufacturing site.

    Daily work management

    Major work and capital projects

    Contractor and contract labor management

    Reliability Management

    Reliability Management involves the work processes and activities that focus on ensuring and enhancing reliability of the plantsproduction assets, the manufacturing equipment. It includes proactive activities like preventive and predictive maintenance andanalysis activities and record keeping.

    Creating and implementing maintenance strategies

    Equipment failure analysis and corrective action

  • 8/11/2019 Business Procsses

    8/19

    James Davis Page 8

    Preventive and predictive maintenance processes and follow-up

    Logistics Management

    Logistics Management includes all of the planning and day to day management processes the manufacturing reliability missionand objectives. Storehouse management, procurement of supplies and parts, and vendor management are all elements ofLogistics Management.

    Vendor evaluation and consolidation

    Crtical spare parts management

    Material quality assurance

    Change Management

    Change Management includes all of the work processes and activities required for communicating the SAM objectives to theworkforce, to motivate them to take ownership of the SAM, to achieve success, and to maintain state of the art work processes.

    Craft reliability reward process

    SAM Key Performance Indicator tracking and results management

    SAM communication process

    Appendix one contains a sample set of Business Processes for the function of managing maintenance work. As an interestingexercise, see if you can identify the following characteristics for each process:

    Supplier

    Inputs

    Process As given.

    Outputs

    Customer

    KPI

    As you can see, it is not always easy to identify the specific characteristics for a given process. In my next article, we willaddress the Value Proposition for SAM.

    References:

    Title Author Copyright Publisher

    The Future of Asset Management S Bradley Peterson 2003 Strategic AssetManagement, Inc.

    Improving Profitability Through Reliability Carol Vesier, PhD 2001 RonaMax

    The Six Sigma Way Peter Pande et al 2000 McGraw-Hill

    Uptime: Strategies for Excellence John Dixon Campbell 1995 Productivity Press

    Article Mark Buchanan 1997 The New Scientist

  • 8/11/2019 Business Procsses

    9/19

    APPENDIX I - SAMPLE BUSINESS PROCESS WORK MANAGEMENT

    James Davis Page 1

    5.3.0 Maintenance Work Core Proces

    Rev: Date: 02/20/02

    Backlog

    Management

    Process - 5.3.7

    Identify Work

    Process - 5.3.1

    Plan Work

    Process - 5.3.2

    Schedule Work

    Process - 5.3.3

    Execute Work

    Process - 5.3.4

    Document Work

    Process - 5.3.6

    Execute PM/ PdM

    Work

    Process - 5.3.5

  • 8/11/2019 Business Procsses

    10/19

    APPENDIX I - SAMPLE BUSINESS PROCESS WORK MANAGEMENT

    James Davis Page 2

    Identify Work Item Create Work Request

    Anyone

    5.3.1.1

    Select Work Priority

    Anyone

    5.3.1.2

    Is this an emergency?

    Create Work Order

    Maintenance Planner

    5.3.1.5

    Is design change required?

    Capture Minimum Event

    Data

    Maintenance Planner

    5.3.1.6

    Plan Work

    Process - 5.3.2

    5.3.1 Identify Work

    Rev: 4

    Identify as Design Change

    Maintenance Planner

    5.3.1.7Reactive

    Maintenance Process

    Process - 5.2.0

    Is this a failure event?

    Review Work Request

    Maintenance Planner

    5.3.1.4

    Review Work Request

    Shift Superintendent

    5.3.1.3

    Is this an emergency?

    Design Change

    Process

    Process -

    YES

    YES

    NO

    NO

    YES

    NO

    YES

    Date: 02/20/02

  • 8/11/2019 Business Procsses

    11/19

    APPENDIX I - SAMPLE BUSINESS PROCESS WORK MANAGEMENT

    James Davis Page 3

    5.3.2 Plan Work

    Rev: 4

    Identify Work

    Process - 5.3.1

    Is archived plan available?

    Define & Sequence Job

    Tasks

    Maintenance Planner

    5.3.2.4

    Define Resource

    Requirements

    Maintenance Planner

    5.3.2.5

    Review Job Plan

    Maintenance Planner

    5.3.2.2

    Is plan complete?

    Assemble Work Package

    Maintenance Planner

    5.3.2.8

    Schedule Work

    Process - 5.3.3

    Revise Job Plan

    Maintenance Planner

    5.3.2.3

    Is material available?

    Initiate Procurement

    Maintenance Planner

    5.3.2.6

    YES

    YES

    NO

    Obtain Materials

    Buyer

    5.3.2.7

    Sort Work Orders By

    Priority

    Maintenance Planner

    5.3.2.1

    YES

    NO

    Date: 02/20/02

    NO

  • 8/11/2019 Business Procsses

    12/19

    APPENDIX I - SAMPLE BUSINESS PROCESS WORK MANAGEMENT

    James Davis Page 4

    Sort Planned Work Orders

    by Priorit y

    Maintenance Scheduler

    5.3.3.1

    Compare Available

    Resources With

    Requirements

    Maintenance Scheduler

    5.3.3.2

    Create Job Schedule

    Maintenance Scheduler

    5.3.3.3

    Review Job Schedule

    Planning & Scheduling

    Team

    5.3.3.4

    Did the schedule change?

    Issue Job Schedule

    Maintenance Scheduler

    5.3.3.8

    Execute Work

    Process - 5.3.4

    5.3.3 Schedule Work

    Rev: 4

    Review Planned Backlog

    Planning & Scheduling

    Team

    5.3.3.5

    Expedite resources? Expedite Resources

    Maintenance Planner

    5.3.3.7

    Revise Job Schedule

    Maintenance Scheduler

    5.3.3.6

    YES

    YES

    NO

    NO

    Plan Work

    Process - 5.3.2

    Date: 02/20/02

    Identify Contingency

    Work

    Process - 5.2.2

  • 8/11/2019 Business Procsses

    13/19

    APPENDIX I - SAMPLE BUSINESS PROCESS WORK MANAGEMENT

    James Davis Page 5

    Schedule W ork

    Process - 5.3.3

    Review Work Package

    Maintenance Supervisor

    5.3.4.1

    Receive Parts and

    Materials

    Craft Person

    5.3.4.4

    Obtain Work Permits

    Craft Person

    5.3.4.6

    Lock Out/Tag Out Work

    Area

    Craft Person

    5.3.4.7

    Execute Work

    Craft Person

    5.3.4.8

    Release to Operations

    Craft Person

    5.3.4.9

    Document Work

    Process - 5.3.6

    5.3.4 Execute Work

    Rev: 4

    Verify Resources

    Maintenance Supervisor

    5.3.4.2

    Assign Personnel

    Maintenance Supervisor

    5.3.4.3

    Send parts or core back

    to warehouse?

    Conduct Site Visit

    Craft Person

    5.3.4.5

    New defects? Should it be f ixed now?

    Fix It

    Craft Person

    5.3.4.11

    Return Parts To

    Warehouse

    Craft Person

    5.3.4.10

    Identify Work

    Process - 5.3.1

    YES

    YES

    NODate: 02/20/02

    Execute Emergency

    Work

    Process - 5.2.1

    YES

    NO

    NO

  • 8/11/2019 Business Procsses

    14/19

    APPENDIX I - SAMPLE BUSINESS PROCESS WORK MANAGEMENT

    James Davis Page 6

    Schedule Work

    Process - 5.3.3

    Review PM/ PdM Work

    Order

    PM/ PdM Supervisor

    5.3.5.1

    Receive Equipment and orTools

    PM/ PdM Person

    5.3.5.4

    Execute Work

    PM/ PdM Person

    5.3.5.5

    Document Work

    Process - 5.3.6

    5.3.5 Execute PM /PdM

    Rev: 4

    Verify Resources

    PM/ PdM Supervisor

    5.3.5.2

    Assign Personnel

    PM/ PdM Supervisor

    5.3.5.3

    Ne w def ect s? NO

    Should it be fixed now?

    YE S

    Obtain Resources

    Craft Person

    5.3.5.7

    NO

    NOClean/ Store Equipment

    and or Tools

    PM/ PdM Person

    5.3.5.6

    YE S

    Identify Work

    Process - 5.3.1

    Fix It

    Craft Person

    5.3.5.8

    Date: 02/20/02

  • 8/11/2019 Business Procsses

    15/19

    APPENDIX I - SAMPLE BUSINESS PROCESS WORK MANAGEMENT

    James Davis Page 7

    Execute Work

    Process - 5.3.4

    Should work package be

    archived?Archive Work Package

    Maintenance Planner

    5.3.6.1

    Document Maintenance

    History

    Maintenance Planner

    5.3.6.3

    Close Work Order

    Maintenance Planner

    5.3.6.4

    Mark-up Work Package

    Craft Person

    5.3.6.5

    Update Work Package

    Maintenance Planner

    5.3.6.6

    Was RCFA single eventtrigger reached?

    Record Event

    Information Needed

    for Failure Analysis

    Process - 5.3.8

    END

    YES

    YES

    NO

    Was work package

    adequate?YES

    NO

    Identify Work Performed

    Craft Person

    5.3.6.2

    NO

    5.3.6 Document Work

    Rev: 4Date: 02/20/02

  • 8/11/2019 Business Procsses

    16/19

    APPENDIX I - SAMPLE BUSINESS PROCESS WORK MANAGEMENT

    James Davis Page 8

    Begin AnalysisPrepare Backlog

    Exception Reports

    Backlog Auditor

    5.3.7.2

    Review Backlog and

    Reports

    Backlog Management

    Team

    5.3.7.3

    Prepare Backlog Aging

    Reports

    Backlog Auditor

    5.3.7.1

    Valid Work Order? Priority Appropriate? Ready to be Scheduled?

    Obtain Necessary

    Resources

    Maintenance Planner

    5.3.7.6

    Cancel the Work Order

    Backlog Auditor

    5.3.7.4

    YES YES

    Adjust the Priority

    Backlog Auditor

    5.3.7.5

    Schedule Work

    Process - 5.3.3

    NO

    5.3.7 Backlog Management

    Rev: 1

    YES

    End

    End

    Date: 02/20/02

    NO

  • 8/11/2019 Business Procsses

    17/19

    APPENDIX I - SAMPLE BUSINESS PROCESS WORK MANAGEMENT

    James Davis Page 9

    Document Work

    Process - 5.3.5

    Notify Reliability

    Engineer

    Area Supervisor

    5.3.8.1

    Classify Work

    Notification as RCFAEvent

    Area Supervisor

    5.3.8.2

    Document Additional

    Data on Template/Checklist

    Craft Person

    5.3.8.3

    Validate that Appropriate

    RCFA Data is Captured

    Reliability Engineer

    5.3.8.4

    Advanced Failure

    Analysis

    Process - 4.7.3

    5.3..8 Record Event Information Needed

    for Failure Analysis

    Rev: 0

  • 8/11/2019 Business Procsses

    18/19

    APPENDIX I - SAMPLE BUSINESS PROCESS WORK MANAGEMENT

    James Davis Page 10

  • 8/11/2019 Business Procsses

    19/19

    Hugh R. Smith, P.Eng, PMPPrincipalR-Tech Technology Inc.4319 Valencia AvenueNorth Vancouver, BC

    CanadaV7N 4A7

    (604) 728-0473

    Hugh is a Mechanical Engineer (University of Alberta, 1987) and spent 10 years with the Cominco / Agrium family ofcompanies working in Operations and Maintenance. In his final years with Agrium, he was the business lead for aproject to reengineer maintenance and operating processes, implement RCM, and implement SAP Plant Maintenanceacross all of Agriums operations. For the last seven years, Hugh has worked as a management consultant initially

    with Cap Gemini Ernst and Young, and more recently with his own consulting company helping various clients withmajor projects to reengineer operations, maintenance, and work management processes and implement supportingapplications. He continues to use tools such as the Deviant Cost Model to help clients develop appropriatemaintenance strategies, and most recently has worked with distribution utilities to apply the cost model and risk-basedmaintenance techniques to distributed asset bases. Hugh has written and delivered highly acclaimed courses onmaintenance methods, and has written and presented numerous articles on related subjects.