c. required port facilities and equipment for major ports · c. required port facilities and...
TRANSCRIPT
TThhee SSttuuddyy oonn tthhee RReedd RRiivveerr IInnllaanndd WWaatteerrwwaayy TTrraannssppoorrtt SSyysstteemm MMaarrcchh 22000033 // FFiinnaall
66
C. Required Port Facilities and Equipment for Major Ports (1) Required length and depth of berth
129. In order to handle increasing cargoes at major ports of Hanoi, Khuyen
Luong, New North and New East, 1.5 km of berth (additional length: 0.8km) and 3.0
km of berth (additional length: 2.3km) will be required in 2010 and in 2020
respectively (see Figure VI-6).
130. Required water depth of berth is 2.5m below the 95% water level for
vessels/barge trains deployed in the RRD by 2010 and 3.6m for Sea-cum-river
vessels by 2020.
(2) Required handling equipment
131. For handling bulk cargoes, quayside mobile crane, grab bucket, shovel
loader, bulldozer and dump truck will be used and for non-bulk cargoes, quayside
mobile crane, forklift, truck and pallet will be needed. For handling containers,
quayside mobile crane (heavy type), forklift (heavy type), tractor and trailer will be
used.
(3) Required land space
132. Space for storage yard (construction material and coal), warehouse, road,
utility and reserve area is required. And in a port handling containers, ICD (inland
container/clearance depot) consisting of CY (container yard), CFS (container
freight station) and DC (distribution center) is also needed.
(4) Required number of access road lanes
133. Access roads between major ports and dyke road or Ring Road No.3 will
have to be constructed. Two lanes will be required for all major ports.
(5) Required elevation of port facilities
134. Crown elevation of berths in major ports shall be set at a level slightly higher
than Warning Water Level III (+11.5m at Hanoi Station). Ground elevation of roads,
storage yards and warehouses shall be set at a level higher than that of berths in
order to avoid traffic blockade and/or degradation of commodity value due to
flooding.
TThhee SSttuuddyy oonn tthhee RReedd RRiivveerr IInnllaanndd WWaatteerrwwaayy TTrraannssppoorrtt SSyysstteemm MMaarrcchh 22000033 // FFiinnaall
67
Source) JICA Study Team
Figure VI-6 Location of Ports/Berths (2001, 2010, 2020)
THANG LO
NG BRIDGE
LONG BIEN BRIDGE
CHUONG DUONG BRIDGE
N
km+ 0
km+ 10
km+ 30
km+ 40
21 cranes 7 cranes
Lung Lo Military PortPassenger berth at Chuong Duong Do
5 cranes
Hanoi Port2001: 568m(cargo)2010: 568m(cargo) 100m(PAX)2020: 648m(cargo) 100m(PAX)
Thanh Tri Berths 9 cranes
Bat Trang Bank 17 steps
Passenger berth forBat Trang Ceramic Village
4 steps
Khuyen Luong Port2001: 106m2010: 326m2020: 926m
Ferry berth
Ferry berth
New North Port2010: 280m2020: 760m
0km 5km 10km
Duc Giang Berths5 cranes
8 cranes
New East Port2010: 360m2020: 720m
Duon
g Bri
dge
Phu
Dong
Brid
ge
Chem Berths2001: 800m2010: 800m2020: 800m
Passenger berth forChem Communal House
Passenger berthfor Bo De Pagoda
km+ 20
Passenger berth for Phu Dong Village
Main passenger terminal in Hanoi Port
Than
h Tri B
ridge
Note) Temporary cargo Berths located in the Red River segment between Thang Long Bridge and Thanh Tri Bridge shall be removed and transferred to the outside by 2010 in principle.
TThhee SSttuuddyy oonn tthhee RReedd RRiivveerr IInnllaanndd WWaatteerrwwaayy TTrraannssppoorrtt SSyysstteemm MMaarrcchh 22000033 // FFiinnaall
68
D. Hanoi Port
135. Development direction of Hanoi Port is proposed as follows:
- Hanoi Port shall handle non-bulk and bulk cargoes as well as cargoes of
SRV (2020), and serve mainly for Citadel districts. Bulk cargo, however, shall
be decreased taking into account environmental preservation.
- Length of newly planned berths shall be 80m for cargo vessels (by 2020)
and 100m for passenger boats (by 2010).
- Out-dated handling equipment shall be replaced.
- Road of low elevation shall be improved.
136. Master plan and short-term development plan of Hanoi Port are shown in
Table VI-2, Table VI-3, Figure VI-7 and Figure VI-8.
Table VI-2 Master Plan of Hanoi Port (2020)
Table VI-3 Short-term Development Plan of Hanoi Port (2010)
Item DescriptionPort Owner/Investor MOT (small-scale investment: port operator)Port Operator Hanoi Port under NOWATRANCOFacing IW Corridor Corridor 1 (Quang Ninh - Hai Phong - Hanoi - Viet Tri)
Corridor 4 (Sea - Hanoi)Hinterland Citadel districtsDesign Capacity 1.2 million tons (Bulk: 0.3, Non-bulk: 0.5, SRV: 0.4)Length of Waterfront 1.8km (Additional bank protection upstream of T4: 900m)Berth Property Existing: 568m for cargo
(partial repair work is needed at berths No.4-6)Newly planned: [email protected] (+11.5m) for SRV [email protected] (+12.0m) for PAX
Land Area Total: 7ha (Storage yard: 0.6ha, Warehouse: 1.6ha for port related use and 1.1ha for other use)(Newly planned warehouse: 1.4ha)
Handling Equipment Quayside mobile crane: 9 units (8tons)Grab bucket: 2 units (3cu.m), Forklift: 23 units (3tons)Shovel loader: 1 unit (2cu.m), Bulldozer: 1 unit (5tons)Dump Truck: 3 units (10tons), Truck: 15 units (7tons)Pallet: 2,700 units (1.2mx1.8m)
Passenger Terminal 1 unit Access Road 2 lanes to be linked to Dyke road (for Ring Road No.2)
Planned: Elevation improvement to +12.0m (L=2.6km)
Item DescriptionPort Owner/Investor MOT (small-scale investment: port operator)Port Operator Hanoi Port under NOWATRANCOFacing IW Corridor Corridor 1 (Quang Ninh - Hai Phong - Hanoi - Viet Tri)
Corridor 4 (Sea - Hanoi)Hinterland Citadel districtsDesign Capacity 0.8 million tons (Bulk: 0.6, Non-bulk: 0.2)Length of Waterfront 1.8km (Additional bank protection upstream of T4: 900m)Berth Property Existing: 568m for cargo
(partial repair work is needed at berths No.4-6)Newly planned: [email protected] (+12.0m) for PAX
Land Area Total: 3ha (Storage yard: 1.1ha, Warehouse: 0.4ha for port related use and 0.9ha for other use)
Handling Equipment Quayside mobile crane: 5 units (8tons)Grab bucket: 3 units (3cu.m), Forklift: 6 units (3tons)Shovel loader: 2 unit (2cu.m), Bulldozer: 1 unit (5tons)Dump Truck: 5 units (10tons), Truck: 4 units (7tons)Pallet: 700 units (1.2mx1.8m)
Passenger Terminal 1 unit Access Road 2 lanes to be linked to Dyke road (for Ring Road No.2)
Planned: Elevation improvement to +12.0m (L=2.6km)
TThhee SSttuuddyy oonn tthhee RReedd RRiivveerr IInnllaanndd WWaatteerrwwaayy TTrraannssppoorrtt SSyysstteemm MMaarrcchh 22000033 // FFiinnaall
69
Figure VI-7 Master Plan of Hanoi Port (2020)
Figure VI-8 Short-term Development Plan of Hanoi Port (2010)
Warehouse B
War ehouse A
Vinafaco
6
510
4
1
22
Lang
Yen STR
EET
8
21
20
23
19
19
2
241
18
1
1717
1614
13
1
3
19
7
22
War
ehou
se D
Wa
reh
ou
se
G
19
War
ehou
se C
Red River
0
100
200
300
400
500
600
700
800900
10001100 1200
1300 1400 15001600
1700
5
9
12
B2L=20m+8.5m
B4L=18m+8.5m
Berth No.1L=65m+11.5mBerth No.2L=65m+11.5m
Berth No.3L=65m+11.5m T4L=12m+8.0m Berth No.4L=56m+11.5m
Berth No.7L=50m+9.0m
T8L=14m+8.5m
Berth No.8L=40m+9.5m
500m400m300m200m100m0m
B3L=50m+11.5m
Berth No.5L=56m+11.5m
Berth No.6L=56m+11.5m
New Berth L=80m +11.5m
Road ElevationImprovementto +12.0mL=1.8km+0.8km
New Passenger Berth
L=100m +12.0m
2 Pontoon
Wa
reh
ou
se E
Bank ProtectionL=0.9km
New Warehouse6 units, S=1.4 ha+13.0m
Warehouse B
Warehouse A
Vinafaco
6
510
4
1
22
Lang
Yen STR
EET
8
21
20
23
19
19
2
241
18
1
171716
14
13
1
3
7
22
War
ehou
se D
Wa
re
ho
us
e G
19
War
ehou
se C
Red River
0
100
200
300
400
500
600
700
800900
10001100 1200
1300 1400 15001600
1700
5
9
12
B2L=20m+8.5m
B4L=18m+8.5m
Berth No.1L=65m+11.5mBerth No.2L=65m+11.5m
Berth No.3L=65m+11.5m T4L=12m+8.0m Berth No.4L=56m+11.5m
Berth No.7L=50m+9.0m
T8L=14m+8.5m
Berth No.8L=40m+9.5m
500m400m300m200m100m0m
B3L=50m+11.5m
Berth No.5L=56m+11.5m
Berth No.6L=56m+11.5m
Road ElevationImprovementto +12.0mL=1.8km+0.8km
New Passenger Berth
L=100m +12.0m
2 Pontoon
War
eh
ou
se E
Bank ProtectionL=0.9km
19