c156 preliminary tension test pile t1 t2 rev 0

Upload: tin-aung-tun

Post on 04-Jun-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    1/103

    METHODSTATEMENTFOR

    PRELIMINARYTENSIONTESTPILET1ANDT2BY

    REACTIONPILE

    METHOD

    PreparedBy:

    CONTRACT156:DESIGN,CONSTRUCTIONANDCOMPLETIONOFSTATIONANDASSOCIATEDTUNNELSATMARINASOUTHFORNORTHSOUTH

    LINE

    EXTENSION

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    2/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    TableofContents

    1. Introduction1.1 SummaryOverviewforPreliminaryPileT1andT2

    2. References2.1 References

    3. SiteOrganisationChartforPreliminaryTestPileConstructionandTesting

    4. MethodologyofPreliminaryTestPileConstructionandInstallation

    4.1 ListofPlantandEquipmentforPreliminaryTestPileConstruction

    4.2 BoringandInstallationofPreliminaryTestPile

    4.2.1 SettingOut

    4.2.1.1 PileLocationbySurvey

    4.2.1.2

    Set

    boring

    unit

    4.2.2 InstallationofTemporaryCasing

    4.2.3 DebondingofPreliminaryTestPileT1andT2

    4.2.3.1 PreparationofDebondingCasing

    4.2.3.2 InstallationofDebondingCasing

    4.2.4 BoringofPreliminaryTestPile

    4.2.5 CleaningandDesandingofBoreholes

    4.2.5.1 BaseCleaningbyBucket

    4.2.5.2 DesandingofBentoniteSlurry4.2.6

    Independent

    Verticality

    and

    Depth

    Monitoring

    4.2.7 InstallationMonitoringInstrumentationforPreliminaryTestPile4.2.7.1 VibratingWireStrainGauge(VWSG)

    4.2.7.2 Tell-TaleRodExtensometer

    4.2.8 PreliminaryTestPileSteelReinforcementCage4.2.8.1 FabricationofReinforcementCage

    4.2.8.2 SiteDeliveryofReinforcementCage

    4.2.8.3 InstallationofReinforcementCage

    4.2.9Concrete

    Installation

    4.2.9 H-BeamInstallationbyPlunge-InMethod

    5. TensionLoadTestMethodology

    5.1 ListofPlantandEquipmentforTensionTestSettingUp

    5.2 MethodologyofTensionLoadTestAssemblyandSettingUp

    5 2 1 I ll i f R i Pil

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    3/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    TableofContents,contd

    9. Records

    10. LoadingSequence

    11. ScheduleforPreliminaryTestPileT1andT2Construction

    12. SafeWorkProcedures

    Appendix

    Appendix A Location and Reference Borehole for Preliminary Test Pile T1 and T2

    Appendix B Site Organisation Chart for Preliminary Test Pile Construction and

    TestingAppendix C Debonding Casing Detail and Debonding Material Bituthene 3000 Product

    Detail and Specification

    Appendix D Illustrated Sequence for the Debonding Casing Installation

    Appendix E Type of Bentonite Test and Procedures

    Appendix F Koden Drilling Monitor Brochures and Photo

    Appendix G Preliminary Test Pile T1 and T2 Instrumentation and Reinforcement DetailDrawing

    Appendix H Vibrating Wire Strain Gauges Technical Specification

    Appendix I Sequence of Bored Pile Reinforcement Cage Tandem Lifting

    Appendix J Recording Sheet

    Appendix K HBeam Column Design Calculation

    Appendix L Diagrammatic Sequence for HBeam Column InstallationAppendix M Reaction Pile Design Calculation

    Appendix N Tension Test Settting Up Layout Drawing for Preliminary Test Pile T1 and T2

    Appendix O Loading Sequence for Preliminary Test Pile T1 and T2

    Appendix P Tentative Schedule for Preliminary Test Pile Construction and Testing

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    4/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    1. Introduction

    Contract 156 North East Line Extension comprises of design, construction and completion of a1.6km long, fully underground rail transit system with one non civil defence MRT station andassociated tunnels. The C 156 project site interface with Marina Coastal Expressway project 482and 483 project.

    This method statement presents the methodology of tension test for the Preliminary Test Pile on

    T1 and T2 by using Reaction Pile Method.

    1.1 SummaryOverviewforPreliminaryPileT1andT2

    Preliminary test pile T1 and T2 which have being selected and approved by the Engineer andAuthority for the tension test. The intention test load for the preliminary test pile will be 3xWL,WorkingLoad, and, Table 1 shows the tabulated test load for T1 and T2 piles.

    PileRefPileDia.(mm)

    PileLength

    (m)

    BoreholeRef

    WorkingLoad,WL

    (kN)

    PSF(kN)

    TestLoad,

    3xWL+PSF

    (kN)

    T1 1200 45.21 NS/023 4,035 Debonded 12,105

    T2 1200 50.6 NS/015 4,049 Debonded 12,147

    Table 1. T1 and T2 pile summary table

    The objective of the test are to establish the ultimate skin friction due to uplift force imposed on thepile based on the design load at established socketing depth on Old Alluvium layer. The proposedlocation for the Preliminary Test Pile T1 and T2 installation will be on the reference boreholes, and,the aforesaid location and boreholes details can be referred in AppendixA.3. References2.1 References

    WSH (Construction) Regulations 2007 Project Safety Manual Risk Assessment Singapore Code of Practice, CP4 LTAs Material & Workmanship Specification Clause 5.7 Civil Design Criteria For Road and Rail Transit Systems Clause 6 5 1~6 5 5

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    5/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    i. List of Plant and Equipmentii. Boring and Installation of Preliminary Test Pile

    iii. Tension Test Assembly and Testing Methodology

    4.1 ListofPlantandEquipmentforPreliminaryTestPileConstruction

    The plant and equipment to be deployed for the Preliminary Test Pile T1 and T2 construction arelisted in the Table 2.

    No EquipmentDescription Capacity Units

    1 Boring Rig BG 30 1

    2 Hydraulic Crawler Crane 100 tons 1

    3 Hydraulic Excavator 7m 1

    4 Bentonite Silo 75m 3

    5 Desander 100m/hr 16 Welding Machine 500 Amp 2

    7 Sand Pump 15hp 2

    8 Tremie Pipe 100 meter 1

    9 Vibrohammer 10 tons 1

    Table 2. List of Plant and Machineries for Preliminary Test Pile Construction.

    4.2 BoringandInstallationofPreliminaryTestPile

    The installation procedures for the Preliminary Test Pile cover on the following;

    i. Setting Out of Pile Location by Surveyii. Installation of Temporary Casing

    iii. Installation of Debonding Casingiv. Boring of Preliminary Test Pile

    v. Cleaning and Desanding of Boreholesvi. Installation of Monitoring Instruments for Preliminary Test Pile

    vii. Verticality Checkviii. Steel Reinforcement Cage Installation

    ix. Concrete Installationx. HBeam Installation by PlungeIn Method

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    6/103

    4.2.1.2Prior to

    i. Oa

    c

    i

    ii. Liii. C

    b

    Position

    the settin

    4.2.2 Ii. P

    df

    ii. Ic

    Setborinoring, the fo

    ffset survey

    propriate

    sing. The o

    stallation p

    evel the platheck the ver

    oring.

    he boring ri

    g out bored

    stallation

    rebored to

    epth of 1.5

    om existing

    stall tempo

    sing install

    PR

    unitllowing step

    ed pile posit

    istances fro

    ffset distan

    ocess.

    form for theticality of th

    g at the desi

    pile position

    Figur

    ofTempothe size of o

    to 2m wh

    ground leve

    ary casing i

    tion.

    MET

    LIMINAR

    T2BYCONTRA

    s will be car

    ion in two p

    the pile p

    e will be s

    boring rig be Kelly Bar

    gnated locat

    prior com

    1. Setting

    aryCasinuter diamet

    ichever co

    .

    to ground

    ODSTATTENSIONEACTIONT156:NO

    EXTENS

    ried out:

    erpendicula

    sition, to fa

    ch that the

    placing stef a boring r

    ion to comm

    encement o

    ut pile posit

    r temporar

    es first gov

    y vibroha

    MENTFOTESTPILEILEMETH

    RTHEASTION

    directions

    cilitate the i

    se markers

    el plates.g, by banks

    ence boring

    f boring wor

    ion by surve

    casing at t

    rned by the

    mer, and, Fi

    T1ANDODLINE

    y placing 2

    stallation o

    ill not be

    man prior c

    works, and,

    ks.

    y.

    e set out pi

    existing gro

    gure 2 show

    For App

    REV

    offset mark

    f temporary

    disturbed d

    mmencem

    Figure 1 sho

    le position t

    und water l

    s the tempo

    roval

    0

    rs at

    steel

    ring

    nt of

    w

    o the

    vel

    ary

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    7/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    iii. In control the verticality of Preliminary Test pile during boring works, a temporary casingwill be driven into the ground at minimum to a depth of exceeding the Fill layer or more ifrequires.

    iv. The top of temporary casing will be raised above the ground at required level to attain thetrench stability at Factor of Safety 1.4. The trench stability calculation for every test pile willbe submitted in separate submission.

    4.2.3Debonding

    of

    Preliminary

    Test

    Pile

    T1

    and

    T2

    In the proposed Preliminary Test Pile T1 and T2 design consideration, the piles requires to bedebonded from Fill Layer up to Top of Old Alluvium Layer. The main objective of debonding is toeliminate any shaft resistance contribution from soil parameter layer during the loading of the testpile by tension other than from Old Alluvium layer only. The general sequence for the debondingworks entails are as follows;

    i. Preparation of Debonding Casingii. Installation of Debonding Casing

    4.2.3.1 PreparationofDebondingCasing

    The method proposed for the debonding of Preliminary Test Pile T1 and T2 is by debonding casingmethod. The material and preparation works involved prior installation of the debonding casingare as follows;

    i. Provide 1200mm internal diameter casing with 10mm thick and the debonding length willbe provided up to the top of OA layer.

    ii. The casing will be wrapped all round with proposed Bituthene 3000 debonding membranethat provides smooth surface that creates a debonding effect for the pile.

    iii. In additional measures to prevent the inflow of concrete into the annular space duringconcrete placing, 5 layers of 1200mm x 25mm thick polystyrene plug will be installed at500mm above the bottom of the debonding casing. The polystyrene will be continuously

    wrapped with the debonding membrane to prevent any damage to the polystyrene duringdebonding casing installation.

    The debonding casing detail and the proposed debonding material, Bituthene 3000 product detailand specification can be referred inAppendixC.4 2 3 2 I t ll ti f D b di C i

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    8/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    iii. Installed the 1200mm internal diameter debonding casing up to the final 1500mmdiameter borehole.

    iv. Gradually press down the debonding casing with kelly bar by applying control pressureuntil the toe of the debonding casing reach the top or at minimum 300mm above the top ofOld Alluvium layer.

    v. The 1200mm diameter debonding casing will be securely welded on to the outer temporary

    casing.

    vi. Change the drilling tools from 1500mm diameter to 1200mm diameter and continue boringto the required design toe level.

    vii. The illustrated sequence for the debonding casing installation can be referred in AppendixD.

    4.2.4 BoringofPreliminaryTestPile

    The boring works procedure for the preliminary test pile T1 and T2 will be in accordance to theApproved Method Statement for Bored Pile Construction. Bentonite slurry will be used as thestabiliser fluid for the whole boring process. In addition to the works, various suitable types ofboring tools will be used, and, soil bucket or cleaning bucket will be deployed as the general soilcondition in C156 are primarily consists of clay and sand.

    The general guidelines for the boring works for the Preliminary Test Pile are as follows;

    i. The bentonite slurry level will be maintained at the recommended level tabulated and PEendorsed Trench Stability Calculation during the boring works.

    ii. Soil sampling for the borehole will be collected at 2m interval from existing ground level upto the final founding level. The soil sample collected will be stored in soil sampling bag withclearly labelled by indicating the pile reference no, date and depth of the sample collected,The complete set of soil sample of individual bored pile will be kept in the proper soilsample storage area prepared.

    iii. The bored hole will be measured with graduated measuring reinforced nylon Million tape.

    4.2.5 CleaningandDesandingofBoreholes

    The cleaning of the completed Preliminary Test Pile will be the combination of;

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    9/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    iii. Confirm the depth of the borehole with QPSs site representative.

    4.2.5.2 DesandingofBentoniteSlurry

    The bentonite in the borehole which contains soil particles in suspension is pumped from thebottom of the trench by lowering of tremie pipe with submersible pump for desanding. Thisprocess will carry out after the final founding level has being achieved and counter check by QPSssite representative.

    The submersible pump which securely is attached to the tremie pipes is lowered to the depth atinterval 30m depth. This method is to sequence the bentonite replacement every 30m depth byreplacing the first 30m bentonite with contains heavy suspended sand particles withfresh/treated bentonite. This preference method is to reduce the overload pumping effect to thesubmersible pump. Increased of the pump depth next 30m will be taken effect after the sand or soilparticles coming out from the desander mesh screen is minimal. This process will continue byextending the tremie pipe further until the submersible pumps toe base is 500mm above the finalfounding toe level.

    Upon completion of the desanding works, the bentonite slurry will be extracted out from theboreholes by using bentonite sampler which is shown below in Figure 3.

    Figure 3. Bentonite sampler

    The type bentonite tests that should be carried out on to determine the bentonite slurry extractedfrom boreholes are;

    i. Viscosityii Density

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    10/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    Properties RangeofResults(at Singapore Temperature)

    TestMethod

    Viscosity 30 90 sec Marsh cone methodDensity 1.02 ~ 1.35 g/cm3 Mud density balance

    PH 9.0 12.0 PH indicator paper stripsSand Content Less than 5 % Sand Content Kit

    Table 3. Bentonite Test Criteria.

    4.2.5 IndependentVerticalityandDepthMonitoring

    It is utmost important the verticality of pile to be maintain within the tolerance during the boring fromground level up to the final founding level. At the end of desanding works, the Koden drilling monitorDM 682 or 684 will be utilised to provide an additional and independent quality assurance on pileverticality. The technical brochure and photos of Koden drilling monitor is enclosed in AppendixF.4.2.6 InstallationMonitoringInstrumentationforPreliminaryTestPile

    Monitoring instrumentation will be installed on Preliminary Test Pile T1 and T2. The type ofmonitoring instruments that will be installed on preliminary test pile T1 and T2 are;

    i. Vibrating Wire Strain Gauges, and,ii. Telltale rods.

    TellTale rods and Vibrating Wire Strain Gauges will be installed in T1 and T2 at predeterminedlevels based on the approved design. As requires, the telltale rods will be assembled at;

    i. Top of Old Alluvium.ii. Pile Toe

    In the Preliminary Test Pile T1, The detail layout for the position and level for the two mentionedmonitoring instruments, with inclusive of reinforcement detail for the Preliminary Test Pile T1 andT2, can be clearly referred in AppendixG.4.2.6.1 VibratingWireStrainGauge(VWSG)

    The vibrating wire principle of measuring the strain is based on the fact that the natural frequencyof vibration of the taut wire, restrained at both ends, varies with the square root of the tension inthe wire. Each of the VWSG will be installed by tying to the T13x1000mm reinforcement bar andsecurely spot welded to the main reinforcement bar. The wire sensor is placed on top of the VWSGbefore potting the assembly in epoxy in a rubber hose. The signal cables for all the VWSG will be

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    11/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    4.2.6.2 Tell-TaleRodExtensometer

    Telltale rod extensometer assembly consists of a 6mm diameter stainless steel rod which attachedto a fixed anchor point in the pile, and, placed within a protective 13mm internal diameter GI pipes.As the pile undergoing tension during loading, the inner steel rod remains free in the protectivesteel pipe. Two Linear Vertical Displacement transducers will be used will to monitor themovement of the telltale extensometers. The GI pipes will be securely tied in position to the steelreinforcement cage with galvanised wire or cable tie. The GI pipes will be further sealed from

    cement inclusion at the bottom with end cap and masking tape on the top.

    4.2.7 PreliminaryTestPileSteelReinforcementCage

    4.2.7.1 FabricationofReinforcementCage

    The Contract C 486 Bored Piles reinforcement cage will be prefabricated in the factory and will beclearly marked for identification prior concreting works. The reinforcement cage will be fabricatedin accordance to the Approved Construction Drawing. Internal transfer will be provided if deemed

    necessary.

    4.2.7.2 SiteDeliveryofReinforcementCage

    The delivery of reinforcement cage to site will be 5 days in advance prior the boring of thePreliminary Test Pile. This lag time is for the monitoring instrumentation VWSG and Telltale installation works. The reinforcement cage will be stored at the nearest location to the boredlocation, provided, the reinforcement cage is raised above the ground by placing 4x4 timberbelow. A stopper should be provided by means of chamfered timber to prevent the reinforcementcage from rollover.

    4.2.7.3 InstallationofReinforcementCage

    The installation of the Bored Pile reinforcement cage is explained as follows;

    i. Weld main bars with main links at the top of the reinforcement cage and use Uclips to holdthe main bars and main links together for lifting purposes during installation.

    ii. Hook the wire sling with shackles onto the main links.

    iii. Use the spreader beams (with wire sling) to hoist the reinforcement cage and lower into theborehole.

    iv. The bored pile reinforcement cage will tandem lifted by single crane. AppendixIshows the

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    12/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    viii. Hoist the subsequent reinforcement cage and lap the reinforcement cages using Uclips atalternate main bars.

    ix. Place additional Uclips at the section of the reinforcement cages where the main liftingpoint is located, if necessary.

    x. Repeat the above procedure for other reinforcement cages.

    xi. Forlastreinforcementcage,xii. Support the reinforcement cage on the temporary steel casing with the short rebar (same

    procedure as lapping).

    xiii. Dislodge the wire sling with shackles from the main links.xiv. Hoist the hangers (made up of a hook at the top and different lengths of the reinforcement

    depending on depth of the cutoff level of the bored pile) to the reinforcement cage.

    xv. Use uclips or weld the hangers to the starter bar of the reinforcement cage.xvi. Hoist and lower the hangers together with the reinforcement cages to the designated depth.

    xvii. Suspend the reinforcement cages at the minimum of 100mm above the final founding depthby hooking the hanger onto the temporary steel casing at the top. This is to secure thereinforcement cage in position and maintain the verticality of the reinforcement cageduring concreting works.

    4.2.8 ConcreteInstallation

    The concrete placing for the bored pile will conform to the M&W Specification Clause 5.2.2.6. Theprocedures and sequence of concrete placement are summarised as follows;

    i. Use a tremie pipe of diameter of minimum 250mm and for concreting bored pile.

    ii. Join the sections of the tremie pipe prior to lowering it into the borehole.

    iii. Lower the tremie pipe into the borehole until 300 mm above the level to facilitate flow ofconcrete.

    iv. Place the amount of vermiculite required to have an approximate height of 400mm in thetremie pipe.

    v. Place the vermiculite in the tremie pipe prior to discharging the concrete. This is to

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    13/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    viii. The actual concrete level measured will be plotted in the depth versus concrete volumegraph which attached in AppendixJ, and, the actual concrete volume lines shall compareswith the theoretical concrete volume line.

    ix. Tremie pipe will be withdrawn from the borehole as the concrete level rises. This is tofacilitate the flow of concrete. However, it is important to note that the tremie pipe is to beembedded not less than 3m below the concrete level.

    x. Dismantle the tremie pipe from the top, section by section.xi. Pump the bentonite slurry back to the storage silos by a submersible pump when the

    bentonite slurry is displaced by the volume of concrete. However, it is important to notethat the pumping rate of the bentonite slurry shall not be exceeding extensively from thedischarging rate of the concrete. The level of stabilizing fluid, bentonite slurry shall bemaintained at an appropriate level to prevent collapse of the borehole during concretingworks.

    xii. Terminate the concreting works when the concrete level in the Preliminary Test Pile once

    fresh good quality concrete overflows from casing top. Topping up of concrete shouldfollows after the temporary casing extraction as the concrete level might drop at depthbelow the casing top.

    xiii. The temporary casing will be extracted out by using vibrohammer until the remaining 2meter length casing sink into the ground. It is important that the leftin casing is keptwithin tolerance during the process.

    xiv. Any vibration or boring works is to be avoided at minimum distance of 5 times pile

    diameter from a newly casted pile within 24 hours after casting.

    4.2.9 H-BeamInstallationbyPlunge-InMethod

    In the proposed Preliminary Tension Test Pile, HBeam will be casted into the preliminary test pileto provide an anchoring to the pile during increment of load. The HBeam is design with sufficientbonding length with additional shear studs installed to withstand the ultimate testing load. Thenumbers and coverage length requires for the shear stud will based on the endorsed design

    calculation as attached inAppendixK.

    The sequences for the HBeam installation by plungein method are as follows;

    i. The concrete casting will proceed continuously until good quality fresh concreteoverflows out from the casing top.

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    14/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    v. Once the temporary outer casing had being removed, HBeam will be lifted up by tandemlifting and plunge into the Preliminary Test Pile and embedded into the required depthbased on the submitted Engineers design calculation.

    vi. During the HBeam installation, the verticality and positioning of the HBeam will besolely control by the HBeam casing guide which have preinstalled into the top of thesteel cage. The detail of the HBeam guide casing can be referred in AppendixGandI.

    vii. The Hbeam will securely support and welded to the temporary supporting beam.

    viii. Proper barricades surrounding the test pile shall be provided to prevent any interferenceto the test pile.

    ix. The diagrammatic sequence for the Hbeam installation can be referred in AppendixL.5. TensionLoadTestMethodology

    5.1List

    of

    Plant

    and

    Equipment

    for

    Tension

    Test

    Setting

    Up

    Table 2 shows the list of Plant and Equipment for Tension Test Setting Up Works.

    No EquipmentDescription Capacity Units

    1 Hydraulic Crawler Crane 80 tons 1

    2 Welding Machine 500 Amp 2

    3 Generator Set 50kVA 2

    4 Hydraulic Jack 1000 2

    5 Load Cell 1000 2

    6 Dial Gauge Mitoyo 2

    No EquipmentDescription Capacity Units

    7 Dumpy Level Sokkia 1

    8 Hydraulic Pump Enerpac 1

    9 Linear Vertical Displacement Transducers 2

    10 Main Girder Beam 2 nos

    11 Bearing Plate 4 pcs

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    15/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    loading process, and, the reaction piles installed at each opposite sides will resist the resultantcompression load from the main girder beam during loading.

    The main general preparation works for the Tension Load Test Assembly are as follows;

    i. Installation of Reaction Pilesii. Assembling Works for Tension Load Test

    5.2.1Installation

    of

    Reaction

    Piles

    Two reaction piles of sufficient capacity will be installed either side of the test pile to resist theresultant compression loads. These piles will be concreted up to minimum 1m above the groundlevel and will bear against the reaction beam. The reaction piles will be installed at distance of 3times the preliminary test pile diameter.

    At final preparation, a steel bearing plate will be set centrally on top of the reaction pile and themain girder will be placed on top of the bearing plate.

    The required pile diameter size, reinforcement detail and pile length for the reaction pile can bereferred inAppendixM.5.2.2 AssemblingWorksforTensionLoadTest

    The sequences of assembling tension load test setup are as follows;

    i. A suitable platform will be prepared over the working area of the test. This will aid thestability and accurate assembly of the test setup.

    ii. The main reaction beam(s) are then carefully aligned and levelled to ensure that thebeampile head loading points are in the same vertical axis.

    iii. Placed the two main reaction beams parallel each at opposite position with a space of minimum100mm from edge of the main reaction beams to the edge of the HBeam, and, securely lay onthe Reaction Pile which overlain with 4 steel bearing plate.

    iv. Transfer frame will be welded to the HBeam based on the proposed Professional Engineerdesign.

    v. Place hydraulic jack under the transfer frame with an allowance for load cell installation.

    vi. Tilting plates will be placed on top of the load cells to provide equilibrium balance during the

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    16/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    without leakage. All measuring instruments used in the test shall be calibrated andcertified.

    Figure 4. Dual Jack methods for the Preliminary Tension Test Pile.

    Figure 5. Plan view of dual jack arrangements for Preliminary Tension Test Pile

    i. The pump unit shall be connected to the Hydraulic Jacks.

    ii. As the same pump unit is used, the pressure applied to the two jacks should beequal.

    iii. The load applied to the test pile is therefore the sum of the product of the Jack RamArea and the pressure applied.

    Hydraulic

    Jack

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    17/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    Figure 6. Ruler installed for measuring the pile head movement

    Dial Gauge Method

    Two dial gauges will be supported by rebar that welded to the preliminary test pile casingas in Figure 7.

    Figure 7. Installation of dial gauges on pile head

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    18/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    9. Records

    The settlement data collected during the testing period will be recorded in the SettlementRecording sheet which is attached in AppendixJ.10. LoadingSequence

    Loading Sequence for the Preliminary Test Pile shall be complied with LTAs M&WSpecification clause 5.7.14 5.1.18.3, and, the loading sequence for Preliminary Test pileT1 and T2 can be referred at AppendixO.11. ScheduleforPreliminaryTestPileT1andT2Construction

    The tentative schedule for the Preliminary Test Pile Construction and Testing is attachedinAppendixP.

    12. SafeWorkProcedures

    Ensured that Daily Tool Box Meeting with related topics concerning the works isconducted for all the workers involved on the works.

    Ensured that all the workers are equipped with proper Personal Protective Equipmentor PPE (Safety Boots, Safety Vest, Safety Helmet, Safety Glass, and Ear Plug for

    hacking works, Hand Glove, Dust Mask for hacking works, Safety Harness forworking at height more than 3 meter).

    Ensured that the Site Engineers, Safety Supervisor and Site Foreman are informed onthe risk involved on the works and the necessary safety prevention to be taken asstated in the Risk Assessment which is attached inAppendixQ.

    Ensured that proper working platforms and safety harness are provided securely fixedto the base and attached to lifeline at all the time during the works.

    Ensured that the excavated trench/holes are properly barricaded and securely coverwhen deemed necessary.

    Ensured that the Lifting Gears are check for any defects and colour coded inaccordance to the colours month.

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    19/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    APPENDIX

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    20/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHOD

    CONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    AppendixA

    LocationandReferenceBoreholeforPreliminaryTestPileT1anT2

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    21/103

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    22/103

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    23/103

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    24/103

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    25/103

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    26/103

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    27/103

    METHOD STATEMENT FOR

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    28/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHODCONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    AppendixB

    SiteOrganisationChartforPreliminaryTestPileConstructionandTesting

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    29/103

    CONTRACT156- NORTHEASTLINEEXTENSION

    SITEORGANISATIONCHARTFORPRELIMINARYTESTPILECONSTRUCTION

    MainContractor:

    Construction Analysis

    Design Manager

    YounMan

    Hyun

    Construction Manager

    HP: 92344499

    SongTaeWon

    HP: 92344488

    HsanWynn

    Geotechnical Engineer

    AndyKangSenior Engineer

    Sub- Contractor:

    PhangKianKok

    HP: 91683932Technical Manager

    ConcretingTeam BoringTeam Setting-Up

    GeoEngConsultantsDR Ng Tion Guan

    P: 65466318

    HP: 81688954

    Senior Engineer Safety Supervisor

    HP: 92439604

    TinAungTun

    Team

    HP: 91738975

    SongJuHunProject Manager

    TestPile

    Ramasamy

    HP: 91384320

    ParkInHoConstruction Manager

    HP: 83765209

    METHOD STATEMENT FOR For Appro al

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    30/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHODCONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

    AppendixC

    DebondingCasingDetailandDebondingMaterialBituthene3000ProductDetailandTechnical

    Specification

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    31/103

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    32/103

    BITUTHENE

    3000 ANDBITUTHENE LOW TEMPERATURE

    Self-adhesive, rubberized asphalt/polyethylene water-

    proofing membranes for basements and sub-structures

    Grace Below Grade Waterproofing

    Product Advantages

    Waterproof

    Ripcord

    split release on demandfasterapplication in the straight-aways, ease of

    membrane positioning in detailed areas

    UseBituthene is ideal for waterproofing concrete,

    masonry and wood surfaces where in-service

    temperatures will not exceed 130F (54C). It can

    be applied to foundation walls, tunnels, earth shel-

    tered structures and split slab construction, bothabove and below grade. (For above grade applica-

    tions, seeAbove Grade Waterproofing Bituthene

    3000 and Bituthene Low Temperature.)

    Bituthene is 116in. (1.5 mm) thick, 3 ft (0.9 m)

    wide and 66.7 ft (20 m) long and is supplied in

    rolls. It is unrolled sticky side down onto concrete

    slabs or applied onto vertical concrete faces

    primed with Bituthene Primer WP-3000, Primer

    B2 or Primer B2 LVC. Continuity is achieved byoverlapping a minimum 2 in. (50 mm) and firmly

    rolling the joint.

    DescriptionBituthene 3000 and Bituthene Low Temperature

    are self-adhesive, rubberized asphalt/polyethylene

    waterproofing membranes used in basements and

    sub-structures.

    Advantages Waterproofhigh hydrostatic head resistance

    Cross laminated filmprovides dimensional

    stability, high tear strength, puncture and impact

    resistance

    Cold appliedno flame hazard; self-adhesive

    overlaps ensure continuity

    Chemically resistantprovides effective

    external protection against aggressive soils and

    ground water

    Flexibleaccommodates minor settlement and

    shrinkage movement

    Controlled thicknessfactory made sheet

    ensures constant, non-variable site application

    Wide application window

    Bituthene Low Temperaturesurface and

    ambient temperatures between 25F (-4C)

    and 60F (16C)

    Bituthene 3000 surface and ambient temper-

    atures at 40F (5C) or above

    Hydroduct 220 onHydroduct Tape

    Bituthene WP-3000,Primer B2 or PrimerB2 LVC

    Bituthene 3000

    Hydroduct

    Bituthene is extremely flexible. It is capable of

    b id i h i k k i h d ill

    Apply Bituthene Primer B2 in dry weather

    b ( ) ( d i f

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    33/103

    bridging shrinkage cracks in the concrete and will

    accommodate minor differential movement

    throughout the service life of the structure.

    Application ProceduresSafety, Storage and Handling Information

    Bituthene products must be handled properly.

    Vapors from solvent-based primers and mastic are

    harmful and flammable. For these products, the

    best available information on safe handling,

    storage, personal protection, health and environ-

    mental considerations has been gathered. Material

    Safety Data Sheets (MSDS) are available at

    graceconstruction.com and users should acquaint

    themselves with this information. Carefully read

    detailed precaution statements on product labels

    and the MSDS before use.

    Surface Preparation

    Surfaces should be structurally sound and free of

    voids, spalled areas, loose aggregate and sharp

    protrusions. Remove contaminants such as grease,

    oil and wax from exposed surfaces. Remove dust,

    dirt, loose stone and debris. Concrete must be

    properly dried (minimum 7 days for normalstructural concrete and 14 days for lightweight

    structural concrete).

    If time is critical, Bituthene Primer B2 or

    Bituthene Primer B2 LVC may be used to allow

    priming and installation of membrane on damp

    surfaces or green concrete. Priming may begin

    in this case as soon as the concrete will main-

    tain structural integrity.Use form release agents

    which will not transfer to the concrete. Removeforms as soon as possible from below horizontal

    slabs to prevent entrapment of excess moisture.

    Excess moisture may lead to blistering of the

    membrane. Cure concrete with clear, resin-based

    curing compounds which do not contain oil, wax

    or pigment. Except with Primer B2 or Primer B2

    LVC, allow concrete to thoroughly dry following

    rain. Do not apply any products to frozen concrete.

    Repair defects such as spalled or poorly consoli-

    dated areas. Remove sharp protrusions and form

    match lines. On masonry surfaces, apply a parge

    coat to rough concrete block and brick walls or

    trowel cut mortar joints flush to the face of the

    concrete blocks

    above 25F (-4C). (See separate product infor-

    mation sheet.)

    Priming

    Apply Bituthene Primer WP-3000 by spray or

    roller at a coverage rate of 500600 ft2/gal

    (1215 m2/L). Allow to dry one hour or untilconcrete returns to original color.

    Apply Bituthene Primer B2 by a lambs wool

    roller at a coverage rate of 250350 ft2/gal

    (68 m2/L). Allow primer to dry one hour or

    until tack-free.

    Apply Bituthene Primer B2 LVC by a lambs

    wool roller at a coverage rate of 325425 ft2/gal

    (7.510 m2/L). Allow primer to dry one hour or

    until tack free.

    Dry time may be longer in cold temperatures.

    Reprime areas if contaminated by dust. If the

    work area is dusty, apply membrane as soon as

    the primer is dry.

    Do not apply any primer to Bituthene

    membrane.

    Corner Details

    The treatment of corners varies depending on thelocation of the corner. For detailed information on

    Bituthene Liquid Membrane, see separate product

    information sheet.

    At wall to footing inside corners

    Option 1: Apply membrane to within 1 in.

    (25 mm) of base of wall. Treat the inside corner

    by installing a 34in. (20 mm) fillet of Bituthene

    Liquid Membrane. Extend Bituthene Liquid

    Membrane at least 212in. (65 mm) onto footing,

    and 212in. (65 mm) onto wall membrane.

    Option 2:Treat the inside corner by installing a34in. (20 mm) fillet of Bituthene Liquid

    Membrane. Apply 12 in. (300 mm) wide strip of

    sheet membrane centered over fillet. Apply wall

    membrane over inside corner and extend 6 in.

    (150 mm) onto footing. Apply 1 in. (25 mm)

    wide troweling of Bituthene Liquid Membraneover all terminations and seams within 12 in.

    (300 mm) of corner.

    At footings where the elevation of the floor slab

    is 6 in. (150 mm) or more above the footing,

    treat the inside corner either by the above two

    Protection of Membrane

    P t t Bit th b t id d

    Application on Horizontal Surfaces

    (N t P f li d b

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    34/103

    Protect Bituthene membranes to avoid damage

    from other trades, construction materials or back-

    fill. Place protection immediately in temperatures

    above 77F (25C) to avoid potential for blisters.

    On vertical applications, use Hydroduct 220

    Drainage Composite. Adhere Hydroduct 220Drainage Composite to membrane with Hydrod-

    uct Tape. Alternative methods of protection are

    to use 14in. (6 mm) asphalt impregnated board

    or 1 in. (25 mm) extruded polystyrene. Such

    alternatives do not provide positive drainage to

    the system. Adhere protection board with an

    adhesive or Hydroduct Tape.

    In mud slab waterproofing, or other applications

    where positive drainage is not desired andwhere reinforced concrete slabs are placed over

    the membrane, the use of14in. (6 mm) hard-

    board or 2 layers of18in. (3 mm) hardboard is

    recommended.

    Insulation

    Always apply Bituthene membrane directly to

    primed or conditioned structural substrates.

    Insulation, if used, must be applied over the

    membrane. Do not apply Bituthene membranes

    over lightweight insulating concrete.

    Backfill

    Place backfill as soon as possible. Use care during

    backfill operation to avoid damage to the water-

    proofing system. Follow generally accepted

    practices for backfilling and compaction. Backfill

    should be added and compacted in 6 in. (150 mm)

    to 12 in. (300 mm) lifts.For areas which cannot be fully compacted, a

    termination bar is recommended across the top

    termination of the membrane.

    Placing Steel

    When placing steel over properly protected

    membrane, use concrete bar supports (dobies) or

    chairs with plastic tips or rolled feet to prevent

    damage from sharp edges. Use special care when

    using wire mesh, especially if the mesh is curled.

    Approvals City of Los Angeles Research Report RR 24386

    U.S. Department of Housing and Urban Devel-

    opment (HUD) HUD Materials Release 628E

    (Note: Preprufepre-applied membranes are

    strongly recommended for below slab or for any

    application where the membrane is applied before

    concreting. See Preprufe product information

    sheets.)

    Apply membrane from the low point to the highpoint so that laps shed water. Overlap all seams at

    least 2 in. (50 mm). Stagger all end laps. Roll the

    entire membrane firmly and completely as soon as

    possible. Use a linoleum roller or standard water-

    filled garden roller less than 30 in. (760 mm)

    wide, weighing a minimum of 75 lbs (34 kg) when

    filled. Cover the face of the roller with a resilient

    material such as a 12in. (13 mm) plastic foam or

    two wraps of indoor-outdoor carpet to allow themembrane to fully contact the primed substrate.

    Seal all T-joints and membrane terminations with

    Bituthene Liquid Membrane at the end of the day.

    Protrusions and Drains

    Apply membrane to within 1 in. (25 mm) of the

    base of the protrusion. Apply Bituthene Liquid

    Membrane 0.1 in. (2.5 mm) thick around protru-

    sion. Bituthene Liquid Membrane should extend

    over the membrane a minimum of 212in. (65 mm)and up the penetration to just below the finished

    height of the wearing course.

    Vertical Surfaces

    Apply membrane in lengths up to 8 ft (2.5 m).

    Overlap all seams at least 2 in. (50 mm).

    On higher walls apply membrane in two or more

    sections with the upper overlapping the lower by

    at least 2 in. (50 mm). Roll all membrane with a

    hand roller.

    Terminate the membrane at grade level. Press the

    membrane firmly to the wall with the butt end of a

    hardwood tool such as a hammer handle or secure

    into a reglet. Failure to use heavy pressure at

    terminations can result in a poor seal. A termina-

    tion bar may be used to ensure a tight seal.

    Terminate the membrane at the base of the wall if

    the bottom of the interior floor slab is at least 6 in.(150 mm) above the footing. Otherwise, use

    appropriate inside corner detail where the wall and

    footing meet.

    Membrane Repairs

    Patch tears and inadequately lapped seams with

    Supply

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    35/103

    Physical Properties for Bituthene Membrane

    Property Typical Value Test Method

    Color Dark gray-black

    Thickness 116in. (1.5 mm) nominal ASTM D3767method A

    Flexibility, 180 bend over 1 in. Unaffected ASTM D1970

    (25 mm) mandrel at -25F (-32C)

    Tensile strength, membrane, die C 325 lbs/in.2 (2240 kPa) minimum ASTM D412 modified1

    Tensile strength, film 5,000 lbs/in.2 (34.5 MPa) minimum ASTM D882 modified1

    Elongation, ultimate failure 300% minimum ASTM D412 modified1

    of rubberized asphalt

    Crack cycling at -25F (-32C), Unaffected ASTM C836

    100 cycles

    Lap adhesion at minimum 3000: 4 lbs/in. (700 N/m) ASTM D1876 modified2

    application temperature Low Temp: 5 lbs/in. (880 N/m)

    Peel strength 9 lbs/in. (1576 N/m) ASTM D903 modified3

    Puncture resistance, membrane 50 lbs (222 N) minimum ASTM E154

    Resistance to hydrostatic head 200 ft (60 m) of water ASTM D5385

    Permeance 0.05 perms (2.9 ng/m2

    sPa) maximum ASTM E96, section 12water methodWater absorption 0.1% maximum ASTM D570

    Footnotes:1. The test is run at a rate of 2 in. (50 mm) per minute.2. The test is conducted 15 minutes after the lap is formed and run at a rate of 2 in. (50 mm) per minute at 40F (5C).3. The 180 peel strength is run at a rate of 12 in. (300 mm) per minute.

    Bituthene 3000 or

    Bituthene Low Temperature 3 ft x 66.7 ft roll (200 ft2) [0.9 m x 20 m (18.6 m2)]

    Roll weight 83 lbs (38 kg) gross

    Palletization 25 rolls per pallet

    Storage Store upright in dry conditions below 95F (+35C).

    Ancillary ProductsBituthene WP-3000 5 gal (18.9 L) pail/24 pails per pallet

    Bituthene Primer B2 5 gal (18.9 L) pail/48 pails per pallet

    Bituthene Primer B2 LVC 5 gal (18.9 L) pail/48 pails per pallet

    Bituthene Liquid Membrane 1.5 gal (5.7 L) pail/100 pails per pallet or 4 gal (15.1 L) pail/24 pails per pallet

    Hydroduct Tape 1 in. x 200 ft (2.5 cm x 61.0 m) roll/6 rolls per carton

    Bituthene Mastic Twelve 30 oz (0.9 L) tubes/carton or 5 gal (18.9 L) pail/36 pails per pallet

    Equipment by others: Soft broom, utility knife, brush or roller for priming

    SHEET WATERPROOFING 07 13 00

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    36/103

    1. Product Name Bituthene Waterproofing Systems Hydroduct Drainage Composites

    2. ManufacturerGrace Construction Products62 Whittemore AvenueCambridge, MA 02140

    (866) 333-3SBM (3726)Fax: (617) 498-4311www.graceconstruction.com

    3. Product Description

    BASIC USE

    Bituthene waterproofing systems andHydroduct drainage composites are used inpositive-side waterproofing applications overconcrete, masonry and wood surfaces. Theyare used in new construction and retrofit appli-cations. Typical applications include founda-tion walls, tunnels, earth sheltered structures,and split slab construction such as plaza areas

    and parking decks. Interior uses includemechanical rooms, laboratories and kitchens.

    COMPOSITION & MATERIALS

    The Bituthene waterproofing systems consistof several waterproofing membranes andcompatible accessory products and arecomplemented by the use of the appropriateHydroduct drainage composite.

    The Bituthene membranes are available inrolls, interwound with a disposable silicone

    treated release sheet. The volatile organiccompound (VOC) content of all Bituthenemembranes is 0 g/L.

    Bituthene System 4000 WaterproofingMembrane is a factory made composite witha thickness of 0.060" (1.5 mm) consisting of0 004" (0 1 ) f l i t d l

    4000 Waterproofing Membrane. Its VOC con-tent is 125 g/L.

    Bituthene 3000 and Bituthene LowTemperature Membranes are factory madecomposites with a thickness of 0.060"(1.5 mm). These products consist of 0.056"(1.4 mm) of self-adhesive rubberized asphaltand 0.004" (0.1 mm) of cross-laminated, highdensity polyethylene film.

    Hydroduct drainage composites consist ofdimpled, high impact polystyrene cores and fil-ter fabrics designed to provide positivedrainage and membrane protection. The VOCcontent of all Hydroduct products is 0 g/L.

    Hydroduct 220 Drainage Composite is usedfor vertical applications over Bituthene water-proofing membranes.

    Hydroduct 660 Drainage Composite is usedfor all horizontal applications.

    Hydroduct 200 is intended for areas whichare not waterproofed. Hydroduct 225Drainage Composite incorporates a moldedpolyvinyl chloride core and is intended forareas requiring heat or hydrocarbon resist-ance.

    COMPATIBILITY

    Apply waterproofing membrane directly tostructural surfaces. Bituthene membranes canbe used over EPS wall forming systems if the

    additional guidelines in Technical Letter 18,Insulated Wall Forming Systems, are fol-lowed.

    Bituthene membranes are compatible withaged asphalt and coal tar products.

    Bituthene membranes are incompatiblewith creosote, pentachlorophenol, linseed oiland materials containing polysulfide polymer.

    The rubberized asphalt component ofBituthene membranes is not compatible with

    flexible PVC or rubber sheet membranes.Do not apply Bituthene membranes over

    materials containing petroleum solvents, fuelsor oils. Joint sealants containing solvents mustbe fully cured prior to Bituthene membraneapplication. Refer to Technical Letter 10,Chemical Compatibility with Other

    Regulations limit the VOC content in productsclassified as Architectural Coatings. Refer toTechnical Letters on manufacturers websitefor the most current list of allowable limits.

    Bituthene Primer WP-3000 is a water basedlatex primer used to prime all concrete,masonry and wood surfaces. Its VOC contentis 110 g/L.

    Bituthene Primer B2 is a black, rubber basedprimer in solvent used to prime all concrete,masonry and wood surfaces. In addition, itspatented formulation promotes the adhesionof Bituthene membranes to green concreteand damp surfaces. Its VOC content is 440g/L.

    Bituthene Deck Prep Surface Treatment isa low viscosity, 2-component, asphalt-modi-fied coating used to smooth and level roughdecks prior to installing the Bituthene water-proofing membrane. Its VOC content is 10 g/L.

    Bituthene Liquid Membrane is a 2-compo-nent, cold applied trowel grade waterproof-ing material used to flash corners, form filletsand detail hard-to-reach areas. Its VOC con-tent is 10 g/L.

    Bituthene Mastic is a rubberized asphaltbased mastic used to seal membraneterminations. Its VOC content is 200 g/L.

    Hydroduct Tape is a 2-sided, highly aggres-sive adhesive tape that is specially formulat-ed to adhere Hydroduct drainage compos-ites or expanded or extruded polystyreneprotection board to the membrane. Its VOCcontent is 61 g/L.

    LIMITATIONS

    Do not apply Bituthene membranes in areaswhere they will be permanently exposed tosunlight, weather or traffic.

    Bituthene membranes are not recom-

    mended as pond liners or as tank linersexcept when installed between 2 concreteslabs.

    Bituthene strips over joints in T-beam struc-tures will not provide complete waterproof-ing. For these structures, 9" (225 mm) stripsover properly cured and sealed joints fol

    Grace Construction Products

    SHEET WATERPROOFING 07 13 00

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    37/103

    All Hydroduct drainage composites shouldbe promptly covered. Do not leave drainageexposed to sunlight for more than 2 weeks.Motor vehicles, construction equipment andother trades should not be allowed directly onthe drainage composites.

    Protect Bituthene membranes from UV orsite damage immediately after installation or24 hour flood test. Backfilling or installation ofthe wearing course should be completed assoon as possible.

    4. Technical Data

    APPLICABLE STANDARDS

    ASTM International ASTMC366 Standard Test Methods for

    Measurement of Thickness of Sandwich Cores ASTM C836 Standard Specification for High

    Solids Content, Cold Liquid-Applied

    Elastomeric Waterproofing Membrane forUse with Separate Wearing Course

    ASTM D412 Standard Test Methods forVulcanized Rubber and ThermoplasticRubbers and Thermoplastic Elastomers-Tension

    ASTM D570 Standard Test Method for WaterAbsorption of Plastics

    ASTM D882 Standard Test Method for TensileProperties of Thin Plastic Sheeting

    ASTM D903 Standard Test Method for Peelor Stripping of Adhesive Bonds

    ASTM D1621 Standard Test Method forCompressive Properties of Rigid CellularPlastics

    ASTM D1876 Standard Test Method for PeelResistance of Adhesives (T-Peel Test)

    ASTM D1970 Standard Specification for Self-Adhering Polymer Modified BituminousSheet Materials Used as Steep Roofing

    Underlayment for Ice Dam Protection ASTM D3767 Method A - Standard Practice

    for Rubber-Measurement of Dimensions ASTMD3776 Standard Test Methods for

    Mass Per Unit Area (Weight) of Fabric ASTM D4491 Standard Test Methods for

    Water Permeability of Geotextiles by

    ASTM D4751 Standard Test Method forDetermining Apparent Opening Size of aGeotextile

    ASTM D4833 Standard Test Method forIndex Puncture Resistance of Geotextiles,Geomembranes, and Related Products

    ASTM D5385 Standard Test Method forHydrostatic Pressure Resistance ofWaterproofing Membranes

    ASTM E96 Standard Test Methods for WaterVapor Transmission of Materials

    ASTM E154 Standard Test Methods for WaterVapor Retarders Used in Contact with EarthUnder Concrete Slabs, on Walls, or asGround Cover

    APPROVALS

    City of Los Angeles Research Report RR24386

    U.S. Department of Housing and Urban

    Development (HUD) HUD Materials Release628E

    Miami Dade, NOA 03-0630.04

    SPECIFICATIONS

    American Railway Engineering AssociationChapter 29-2-4

    Federal Construction Guide SpecificationFCGS-07111

    General Service Administration (GSA) GSA-PBS 07115

    National Railroad Passenger Corporation(Amtrak) Section 7.02

    AIA MASTERSPEC Section 07100 U.S. Army Corps of Engineers CEGS-07111 U.S. Department of the Navy NFGS-07111 U.S. Department of Veterans Affairs

    H-08-1 Section 07113

    PHYSICAL PROPERTIES

    Bituthene waterproofing membranes conform

    to the physical property and typical values list-ed in Tables 1 and 3. Hydroduct drainage com-posites conform to the physical property andtypical values in Table 2.

    5. Installation

    Carefully read detailed precaution statementson product labels and MSDS before use, orcontact Grace Construction Products.

    STORAGE & HANDLING

    Protect all materials from rain and physicaldamage. Do not double stack pallets ofmembrane on the jobsite. Provide tarpaulincover on top and all sides, allowing for ade-quate ventilation. Store membrane where

    temperatures will not exceed 90 degrees F(32 degrees C) for extended periods. In lowtemperature conditions, the membraneshould be stored above 40 degrees F(5 degrees C) to promote good adhesion.Store all products in a dry area away fromhigh heat, flames or sparks. Store only asmuch material at point-of-use as required foreach days work.

    PREPARATORY WORK

    Surface ConditionConcrete must be smooth, monolithic andfree of voids, spalled areas, loose substrateand sharp protrusions, dirt and debris, andmust contain no visible coarse aggregate.Repair defects such as spalled or poorly con-solidated areas. Use Bituthene Deck PrepSurface Treatment to smooth and level roughconcrete decks. Remove sharp protrusionsand form match lines.

    CuringConcrete must be cured a minimum of 7 daysfor normal structural concrete and 14 days forlightweight structural concrete. If concrete isplaced over a nonvented metal deck, therequired curing time is doubled. Use formrelease agents that will not transfer to the con-crete. Remove forms as soon as possible frombelow horizontal slabs to prevent entrapment

    of excess moisture. Excess moisture can lead toblistering of the membrane. Cure concretewith clear, resin based curing compounds con-taining no oil, wax or pigment. Allow concreteto thoroughly dry following rain.

    On masonry surfaces, apply a parge coatto rough concrete block and brick walls or

    Grace Construction Products

    SHEET WATERPROOFING 07 13 00

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    38/103

    (-4 degrees C) Apply Bituthene 3000 Membrane only in dry

    weather when air and surface temperaturesare above 40 degrees F (5 degrees C)

    Bituthene Low Temperature Membranecan be used at temperatures above25 degrees F (-4 degrees C) and up to60 degrees F (16 degrees C)

    Cover the membrane immediately in tem-peratures above 77 degrees F (25 degreesC) to reduce potential for blistering

    Apply Bituthene System 4000 SurfaceConditioner and other accessory productsnot listed below in dry weather above25 degrees F (-4 degrees C)

    Apply Bituthene Primer WP-3000 in dryweather above 40 degrees F (5 degrees C)

    Do not apply products to frozen concrete

    APPLICATION

    Surface ConditionerBituthene System 4000 Surface Conditioner issupplied ready to use. Do not dilute with wateror solvents. Spray surface conditioner uniformlyto substrate at a rate of 300 ft 2/gal (7.5 m2/L).Use appropriate sprayer and nozzle.

    Allow surface conditioner to dry completelyand thoroughly prior to membrane application.The surface conditioner is considered dry whenthe substrate returns to its original color. To test

    for dryness, rub small conditioned area by

    hand. Wet conditioner will ball up under the fin-gertips. Let dry until conditioner cannot berubbed off. If conditioned areas are notcovered that day, recondition the area if thereis significant dust or dirt contamination.

    PrimerApply Bituthene Primer WP-3000 by spray orroller at a coverage rate of 500 - 600 ft 2/gal(12 - 15 m2/L). Allow to dry 1 hour or until con-

    crete returns to original color.Apply Bituthene Primer B2 by lambs woolroller at a coverage rate of 250 - 350 ft 2/gal (6- 8 m2/L). Allow primer to dry 1 hour or until tack-free. Dry time may be longer in cold tempera-tures.

    Reprime areas if contaminated by dust. Ifthe work area is dusty, apply membrane assoon as the primer is dry.

    Surfaces treated with Deck Prep Surface

    Treatment do not require conditioning or prim-ing. Metal does not require priming but mustbe clean, dry and free of loose paint, rust orother contaminants. Use Bituthene Primer B2 fordamp or green substrates. Do not applyprimer or surface conditioner to membrane.

    CornersThe treatment of corners varies depending onthe location of the corner.

    At wall-to-footing inside corners: Option 1 - Apply membrane to within 1"

    (25 mm) of base of wall. Treat the insidecorner by installing a 3/4" (19 mm) fillet ofBituthene Liquid Membrane. Extend liquidmembrane at least 3" (75 mm) onto wallmembrane

    Option 2 - Treat the inside corner byinstalling a 3/4" (19 mm) fillet of BitutheneLiquid Membrane. Apply 12" (300 mm) widestrip of membrane centered over fillet.Apply wall membrane over inside cornerand extend 6" (150 mm) onto footing. Apply1" (25 mm) wide troweling of BitutheneMastic or Bituthene Liquid Membrane overall terminations and seams within 12"(300 mm) of corner

    At footings where the elevation of the floorslab is 6" (150 mm) or more above the footing,treat the inside corner either by one of theabove methods or terminate the membrane

    at the base of the wall. Seal the terminationwith Bituthene Mastic or Bituthene LiquidMembrane.

    At plaza deck-to-wall inside corners: Option 1 - Apply membrane on wall and

    deck to within 1" (25 mm) of corner. Treatthe inside corner by installing a 3/4"(19 mm) fillet of Bituthene Liquid Membrane.Extend Bituthene Liquid Membrane at least3" (75 mm) onto deck membrane and 3"

    (75 mm) onto wall membrane. Terminate

    Grace Construction Products

    TABLE 1 PHYSICAL PROPERTIES OF BITUTHENE MEMBRANES

    Property & Test Method Bituthene System 4000 Membrane Bituthene 3000 Membrane Bituthene LowTemperature Membrane

    Color Gray-black Dark gray-black Gray-black

    Thickness, ASTM D3767, Method A 0.060" (1.5 mm) nominal 0.060" (1.5 mm) nominal 0.060" (1.5 mm) nominal

    Low temperature flexibility, ASTM D1970 Unaffected at -45F (-43C) Unaffected at -25F (-32C) Unaffected at -45F (-43C)

    Resistance to hydrostatic head, ASTM D5385 231' (70 m) min 200' (60 m) min 200' (61 m) min

    Lap adhesion at minimum application temperature, 5.0 lb/in (880 N/m) 4.0 lb/in (700 N/m) 5.0 lb/in (880 N/m)width, ASTM D1876, Modified

    Tensile strength, membrane, ASTM D412 (Die C), 325 psi (2240 kPa) min 325 psi (2240 kPa) min 325 psi (2240 kPa) minModified

    SHEET WATERPROOFING 07 13 00

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    39/103

    top of membrane wall flashing withBituthene Mastic, Bituthene LiquidMembrane or termination bar

    Option 2 - Apply membrane on deck towithin 1" (25 mm) of corner. Treat the insidecorner by installing a 3/4" (19 mm)fillet of Bituthene Liquid Membrane. ExtendBituthene Liquid Membrane at least 3" (75mm) onto wall and membrane

    Option 3 - Apply membrane on deck towithin 1" (25 mm) of corner. Treat the insidecorner by installing a 3/4" (19 mm) fillet ofBituthene Liquid Membrane. Apply mem-brane flashing sheet on wall, over fillet and6" (150 mm) onto deck membrane. Apply 1"(25 mm) wide troweling of Bituthene Masticor Bituthene Liquid Membrane over all ter-minations and seams within 12" (300 mm) ofcorner. Terminate top of membrane wallflashing with Bituthene Mastic, BitutheneLiquid Membrane or termination bar

    In planters, reflecting pools and fountains,apply membrane on wall and deck to within1" (25 mm) of corner. Treat the inside corner byinstalling a 3/4" (19 mm) fillet of BitutheneLiquid Membrane. Extend Bituthene LiquidMembrane at least 3" (75 mm) onto deckmembrane and 3" (75 mm) onto wall mem-brane. Terminate top of wall membrane withBituthene Liquid Membrane or terminationbar.

    For wall to wall inside corner, apply 12"(300 mm) membrane strip centered on corner.

    Press membrane tightly into corner to ensure ful lcontact. Cover the treated corner with a fullsheet of membrane to ensure 2-ply coverage.

    For outside corners, apply 12" (300 mm)membrane strip centered on corner. Coverthe treated corner with a full sheet of mem-brane to ensure 2-ply coverage.

    JointsProperly seal all joints with waterstop, joint filler

    and sealant as required. Bituthene mem-branes are not intended to function as theprimary joint seal. Allow sealant to fully cure.Prestrip all slabs and wall cracks over 1/16"(1.6 mm) wide and all construction and controljoints with 9" (225 mm) wide membrane.

    DrainsAt drains, apply a collar of membrane whichextends 6" (150 mm) beyond the drain open-ing. Apply full coverage of membrane over

    the collar. Cut out the drain opening so themembrane extends under the clamping ring.Place a bead of Bituthene Mastic or BitutheneLiquid Membrane between the membraneand clamping ring. An alternate method is toapply Bituthene Liquid Membrane 0.090" (2.3mm) thick so that it extends under the clamp-ing ring and overlaps the deck membrane atleast 3" (75 mm). Install clamping ring afterBituthene Liquid Membrane has cured.

    Application to Horizontal SurfacesApply membrane from the low point to thehigh point so that laps shed water. Overlap all

    seams at least 2 1/2" (64 mm). Stagger all endlaps.

    Roll the entire membrane firmly and com-pletely as soon as possible. Use a linoleumroller or standard water-filled garden rollerless than 30" (762 mm) wide, weighing a mini-mum of 75 lb (34 kg) when filled. Cover theface of the roller with a resilient material suchas a 1/2" (13 mm) plastic foam or 2 wraps ofindoor/outdoor carpet to allow the mem-brane to fully contact the primed substrate.

    Seal all T-joints and membrane terminationswith Bituthene Mastic or Bituthene LiquidMembrane at the end of the day.

    For required testing of horizontal applica-tions, see Flood Testing.

    Application to Vertical SurfacesApply membrane in lengths up to 8' (2 m).Overlap all seams 2 1/2" (64 mm) minimum.

    On higher walls, apply membrane in 2 or moresections with the upper overlapping the lowerby at least 2 1/2" (64 mm). Roll membrane witha hand roller.

    Terminate the membrane at grade level.Press the membrane firmly to the wall with thebutt end of a hardwood tool such as ahammer handle, or secure into a reglet. A ter-mination bar may be used to secure the toptermination. Failure to use heavy pressure at

    terminations can result in a poor seal.Terminate the membrane at the base of

    the wall if the bottom of the interior floor slabis at least 6" (150 mm) above the

    Grace Construction Products

    TABLE 2 PHYSICAL PROPERTIES OF HYDRODUCT DRAINAGE COMPOSITES

    Property & Test Method Hydroduct 220 Hydroduct 660 Hydroduct 200 Hydroduct 225

    Drain core

    Thickness, ASTM C366-B 0.433" (11 mm) 0.433" (11 mm) 0.433" (11 mm) 0.433" (11 mm)

    Compres sive st rength, ASTM D16 21 (mod if ied) 15 ,000 ps f (732 kN/m2) 21,000 psf (1025 kN/m2) 15,000 psf (732 kN/m2) 21,000 psf (1025 kN/m2)

    Flow, 1.0 gradient, 37.9 kPa load, ASTM D4716 16 gal/min/ft 16 gal/min/ft 16 gal/min/ft 16 gal/min/ft

    (0.003 L/min/m) (0.003 L/min/m) (0.003 L/min/m) (0.003 L/min/m)

    Filter fabric

    SHEET WATERPROOFING 07 13 00

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    40/103

    footing. Otherwise, use appropriate insidecorner detail where the wall and footingmeet. Seal all laps within 12" (300 mm) of allcorners with a troweling of mastic. Apply atroweled bead of Bituthene Mastic orBituthene Liquid Membrane to all vertical andhorizontal terminations at the end of eachworkday.

    Protrusions and Penetrations

    Apply membrane to within 1" (25 mm) of thebase of the protrusion. Apply Liquid Membrane0.090" (2.3 mm) thick around the protrusion.Extend Bituthene Liquid Membrane over thesheet membrane at least 3" (75 mm) and upthe protrusion to just below the finished heightof the wearing course (for horizontal applica-tions) or for a minimum of 6" (150 mm) for ver-tical applications.

    FLOOD TESTING

    Flood test all horizontal applications with aminimum 2" (50 mm) head of water for 24hours. Mark any leaks and repair when themembrane is dry. Before flood testing, be surethe structure will withstand the dead load ofthe water. For well-sloped decks, segment theflood test to avoid deep water near drains.

    Conduct the flood test 1 day after com-pleting the application of Bituthene water-proofing system. Immediately after flood test

    is completed, and all necessary repairs made,install Hydroduct 660 Drainage Composite toprotect the Bituthene membrane from trafficand other trades.

    MEMBRANE REPAIR

    Patch tears and inadequately lapped seamswith membrane. Slit fishmouths and repair witha patch extending 6" (150 mm) in all directionsfrom the slit and seal edges of the patch with

    Bituthene Mastic. Inspect the membrane thor-oughly before covering and make any repairs.

    PROTECTION

    Protection of MembraneProtect Bituthene membranes to avoid dam-age from other trades construction materials

    membrane, use Hydroduct 660 DrainageComposite or 1/4" (6 mm) hardboard or 2 lay-ers of 1/8" (3 mm) hardboard.

    On vertical applications, use Hydroduct 220Drainage Composite. Adhere Hydroduct 220 tomembrane with Hydroduct Tape. Alternativeprotection methods are to use 1" (25 mm)expanded polystyrene or 1/4" (6 mm)extruded polystyrene that has a minimumcompressive strength of 10 lb/in 2 (69 kN/m2).

    If 1/4" (6 mm) extruded polystyrene protec-tion board is used, backfill should not containsharp rock or aggregate over 2" (50 mm) indiameter. Adhere polystyrene protectionboard with Hydroduct Tape or compatibleadhesive.

    Cover any exposed Bituthene membranewith weather resistant flashing such as cop-per, aluminum or neoprene. Install Hydroduct660 Drainage Composite or alternate protec-tion the same day the membrane is appliedor immediately after a 24 hour flood test. Nowaiting before backfill or application of wear-ing course is necessary.

    Placement of BackfillUse care during backfill operation to avoiddamage to waterproofing and drainage sys-tem. Follow generally accepted practice forbackfill and compaction. Backfill should be

    added in 6" - 12" (150 - 300 mm) lifts. Forbermed areas that cannot be fully com-pacted, a termination bar is recommendedacross the top termination of the membrane.

    In general, backfill or the final wearingcourse should be placed as soon as possibleafter installation of the membrane.

    Placement of Reinforcing SteelWhen placing reinforcing steel over properlyprotected membrane, use concrete bar sup-

    ports (dobies) or chairs with plastic tips orrolled feet to prevent damage from sharpedges. Use special care when using wiremesh, especially if the mesh is curled.

    6. Availability & Cost

    Products representative.

    7. WarrantyFive year material warranties coveringBituthene and Hydroduct products are avail-able upon request. Contact the manufactur-er for further information.

    8. MaintenanceNone required, if installed in accordance withmanufacturers recommendations.

    9. Technical ServicesSupport is provided by full-time, technicallytrained Grace representatives and technicalservice personnel, backed by a centralresearch and development staff.

    10. Filing Systems Reed First Source Additional product information is available

    from the manufacturer.

    Grace Construction Products

    SHEET WATERPROOFING 07 13 00

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    41/103

    Grace Construction Products

    W. R. Grace & Co.-Conn. hopes the information here will be helpful. Itis based upon data and knowledge considered to be true andaccurate and is offered for the users consideration, investigation

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND For Approval

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    42/103

    T2BYREACTIONPILEMETHODCONTRACT156:NORTHEASTLINE

    EXTENSIONREV 0

    AppendixD

    SequenceofDebondingCasingInstallation

    Prepared by: Page:

    Project: Contract 156 - North East Line Extension SEQUENCE OF DEBONDING CASING INSTALLATION 1 of 2

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    43/103

    Stage 1 Stage 3:

    1, Pre-boring works

    Fill Layer

    Kallang Formation

    500mm

    OA Layer

    1. Continue boring out the soil based on the outer temporary casing

    diameter from ground level up to 500mm above the top of OA layer.

    Fill Layer

    Kallang Formation

    OA Layer

    Bentonite

    Stage 2: Stage 4:

    1. Installtemporary outer casing by vibro hammer. 1. Install the Preliminary Test Pile debonding casing 500mm above the OA layer.

    Fill Layer Temporary Outer

    Fill Layer

    Kallang

    Formation

    500mm

    OA Layer

    Install 1200mmdebonding casing

    until the depth based on trench stability calculation

    Casing

    Kallang Formation

    OA Layer

    Prepared by: Page:

    Project: Marina Coastal Expressway Contract 486 SEQUENCE OF DE-BONDING CASING INSTALLATION 2 of 2

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    44/103

    Stage 5 Stage 7 Stage 9:

    1. Press down the 1200mm debonding casing into Kallang Formation layer 1. Desanding of Preliminary Test Pile

    H-Beam

    To desander

    Fill Layer Fill Layer Fill Layer Casing

    Debonding casing Debonding Casing Debonding Casing

    Casing

    Kallang Kallang Kallang

    Formation Formation Formation

    500mm

    OA Layer

    500mm by using kelly bar.

    Temporary Outer

    1. Install H-Beam into Preliminary Test Pile by plunge-in method

    Polystrene

    Plug

    Polystrene

    Plug

    Stage 6 Stage 8 Stage 10:

    1. Continue boring works with 1200mmboring tools up to design toe level 1. Lowering of reinforcement cage and casting of Preliminary Test

    Downward Force Downward Force

    Fill Layer Fill Layer Fill Layer Reaction Pile

    Casing

    Debonding casing Debonding CasingCasing

    Kallang Kallang Kallang

    Formation Formation Formation

    Concrete

    OA Layer OA Layer OA Layer

    Design Toe Level

    Temporary Outer

    Polystrene

    Plug

    Polystrene

    Plug

    1. Install Reaction Piles.

    pile. 2. Assembling the tension test set up.

    3. Conduct Tension loading test.

    Upward Jackin

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2 BY REACTION PILE METHOD

    For Approval

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    45/103

    T2BYREACTIONPILEMETHODCONTRACT156:NORTHEASTLINE

    EXTENSIONREV 0

    AppendixE

    TypeofBentoniteTestandProcedures

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2 BY REACTION PILE METHOD

    For Approval

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    46/103

    T2BYREACTIONPILEMETHODCONTRACT156:NORTHEASTLINE

    EXTENSIONREV 0

    TESTINGFORSPECIFICGRAVITY

    MudBalanceThe measurement of specific gravity (or density) on untreated mud, gives a simple indication

    on amount of suspended particles in mud

    The Mud Balance consists of three components:

    1)The balancing rule, which comprises the mud cup, the rider sliding along the graduated scale, the knifeedge that rests on the fulcrum and level bubble.

    2)The lid for the mud cup.3)The base with Vnotch functions as the fulcrum

    Test Procedure

    1)Check that instrument is clean and dry.2)Remove the lid and fill the cup with the sample to be tested.3)Replace the lid. Check that it sits snugly. Observe the surplus outflow through the hole in t

    he lid. Lacking of outflow may indicate insufficient mud in cup.

    4)Holding the lid in place with a finger over the hole, clean the exterior of mud balance.5)Place the balance with the knifeedge sitting on the fulcrum.

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2 BY REACTION PILE METHOD

    For Approval

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    47/103

    T2BYREACTIONPILEMETHODCONTRACT156:NORTHEASTLINE

    EXTENSIONREV 0

    THEMARSHFUNNELTEST

    MarshFunnelThe Marsh Funnel Test Kit consists of the following components:

    1)The Marsh Funnel.2)A measuring cup marked to read 946ml (1.U.S. Quart).3)A stop watch.

    The standard funnel used to test clear fresh water will give a reading of 26 seconds.

    Test Procedure

    1)Check that the funnel outlet tube is clear and that the equipment is clean and dry.2)Hold or mount the funnel in an upright position and place a rod or finger to plug the outlet

    while filling.

    3)Fill the test sample into the funnel through the screen till the amount of slurry reached theunderside of the screen.

    4)Subsequently place the empty measuring cup on level platform under the outlet nozzle.

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2 BY REACTION PILE METHOD

    For Approval

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    48/103

    T2BYREACTIONPILEMETHODCONTRACT156:NORTHEASTLINE

    EXTENSIONREV 0

    TESTFORSANDCONTENT

    SandContentKitIn the drilling industry, excessive sand content elevates the risk of drilling tools becoming

    "sandedin" if circulation stopped while the bit is within the bottom of bore hole, aside from

    adding to drag and wear on moving parts and transporting pipelines.

    In the foundation industry, excessive sand content elevates the risk of slurry entrapment

    during the process of tremie concrete when upward displacement of slurry is hindered by the

    heavier sand particles, aside from adding to drag and wear on moving parts and transporting

    pipelines.

    The Sand Content Test Kit measures the volumetric quantity of particles retained on mesh 200

    sieves.

    The test kit consists of the following components:1)A tapered glass measuring tube with volumetric percent graduations.2)A mesh 200 sieve set in an openended tube.3)A funnel to fit the sieve screen and aid the transfer of washed sand back into the measurin

    g tube.

    Test Procedure1)Check that the test kit is clean and free from defects.

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHODFor Approval

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    49/103

    CONTRACT156:NORTHEASTLINEEXTENSION

    REV 0

    6)Cap the funnel over the sandretaining screen and place the glass tube at tip of funnel.7)Invert the assembly and tip some clean water via the opposite side of sand screen to wash

    the sand into the tube.

    8)Read the sand level and record the volumetric percent of sand content in test sample.9)Wash and dry the instrument taking care to clean but not damage the mesh 200 screen.

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHODFor Approval

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    50/103

    CONTRACT156:NORTHEASTLINEEXTENSION

    REV 0

    TESTINGTHEpHVALUES

    PHPaperThe pH value, or Hydrogen Ion determination, is verified in the field using pH indicator papers

    or pH meter. A pH value of 7 is neutral. pH values below or above 7, shall respectively indicate

    the acidic and alkaline nature of test sample.

    High pH value in slurry is indicative of cementious inclusion, while low pH value may indicate

    the presence of salt in slurry, normally brought about towards seaward, organic or at salt

    deposited environment.

    Obtaining pH values by means of visual verification on indicator paper may give rise to

    subjective judgement amongst individuals, besides the tinting of colours introduced through

    dipping in slurry, which may not at all time be lightly coloured.

    The pH value by means of pH meter eliminates subjective judgment. The sensitive nature of

    this electronic device shall require cleansing immediately after use, as well as periodical checks

    through dips in neutralizing solution. Preventive measure is necessary to avoid short circuiting

    the device by over submerging in slurry. For the purpose of clarity, the pH meter is nominated.

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHODFor Approval

    REV 0

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    51/103

    CONTRACT156:NORTHEASTLINEEXTENSION

    REV 0

    AppendixF

    KodenDrillingMonitorBrochuresandPhoto

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    52/103

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    53/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHODCONTRACT 156: NORTH EAST LINE

    For Approval

    REV 0

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    54/103

    CONTRACT156:NORTHEASTLINEEXTENSION

    REV 0

    KODENPhotos

    SettingofKodenRecorderbeforewithdrawingthesensorfromthetrenchbottom

    RealtimeprintingontrenchverticalitybyKodenRecorder

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHODCONTRACT 156: NORTH EAST LINE

    For Approval

    REV 0

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    55/103

    CONTRACT156:NORTHEASTLINEEXTENSION

    AppendixG

    PreliminaryTestPileT1andT2InstrumentationandReinforcementDetailDrawing

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    56/103

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    57/103

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    58/103

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHODCONTRACT156:NORTHEASTLINE

    For Approval

    REV 0

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    59/103

    EXTENSION

    AppendixH

    VibratingWireStrainGaugesTechnicalSpecification

    VW embedment strain gages

    51 5(G L th)

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    60/103

    153(Gage Length)

    158

    250(Gage Length)

    255

    1

    9.8

    19

    .8

    77(Gage Length)158

    19

    .8

    51.5(Gage Length)

    [ Model : 1230 ]

    [ Model : 1235 ]

    [ Model : 1240,1243 ]

    [ Model : 1245 ]

    [Dimension] Descr ip t ionV W E m b e d me n t s t r a in g a g e s are composed of a stainlesssteel tube with flanges at either end. Inside the tube is a

    steel strip near by the plucking coil that is held in tension

    between the ends of the tube.

    Strain in the concrete applied on the flanges is transmitted

    to the tube and a steel strip, changing in the tension of the

    strip. When the strip is plucked near by the plucking coil,

    it vibrates at its resonant frequency changed. This signal

    is transmitte d to the VW re adout unit. The re adout unit

    processes the signal and displays a reading.

    T he gag e is equipped with a lightning protection to protect

    the sensor fr om electrical shock and a temperature device

    to compensate for temperature v ariations.

    F e a t u r e s High stability and reliability

    Not affected by cable length and resistance

    Potted high graded epoxy to prevent against impact on

    the connecting cable.

    Extremely measured strain

    300m H2O waterproof

    Built- in temperature deviceBuilt- in lightning protection device

    Employed permanent anti- corrosive materials

    Automated measurement is possible

    Ap p l icat ionsT he model 1 2 4 0 V W E m b e d m e n t s tr a i n g a g e is designed tomeasure strain in reinforced concrete and mass concrete.

    T he rosette block is used to mount 2~ 4 V W Embedment

    strain gage on steel members in four directions to

    measure the magnitude, distributed direction and trend ofstrain. The enclosure for no stress strain gages is used to

    verify difference of strain between no stress and loading

    conditions, and to find the trend of stress after embedded

    in dams and embankments.

    The model 1 2 3 0 VW Embedmen t s t ra i n g ag e is useful formeasuring strain toward tangential and radial directions in

    tunnel shotcrete.

    The model 1 2 3 5 of the super small sized is applicableusefully when mock- tested with the gag e of 51.5mm or

    there is the limit on the condition of establishment.

    T he model 1 2 4 3 is useful if being applicable in testing theconcrete file improving steel as manufactured with the

    structure for high temperature able to were endurable at

    200.

    The model 1 2 4 5 as the gage with 250mm shows theex cellent performance more than normal type model sincethe seal or compression is great big at the prestressed

    concrete.

    Recom m endat ion

    12351230

    12401243

    1245

    VW embedment strain gages

    1230 1235 1240 1245 1243

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    61/103

    Model Shotcreat) Miniature) Standard) Long gage) High temperature)Sensor element VW Type

    Range 3,000 microstrain

    Resolution 0.5 microstrain

    Accuracy 0.1 FSR

    Nonlinearity 0.5 FSR

    Coefficient of linear

    expansion1110

    -6/

    Operating temperature -40~105 -29220

    Built-in temperature

    deviceStandard : Thermistor (3k) Optional : RTD( 2k)

    Temperature device range Thermistor : -30~80 RTD : -45~100

    Temperature device

    accuracyThermistor : 1 RTD : 0.7

    Gage length 77 mm 51.5 mm 153 mm 250 mm 153 mm

    Gage factor 0.7756 0.3911 3.304

    Materials Special stainless steel 300 series, High grade epoxy potting

    Built-in lightning

    protection deviceGas tube arrester (Frequency output lines)

    Weight 0.2 kg 0.3 kg 0.2 kg

    Signal cable4.5 mm, 0.24 mm

    24C shielded PVC cable 5 m

    5 mm, 0.25 mm24C shielded silicon or Teflon shielded PVC cable 5m for Model 1243

    Anci l lary Equip m entsUniversal terminal box (Model 7012/7024)

    Rosette block for four directions

    Enclosure case kit for no stress strain gages

    Mounting bracket for shotcrete

    [4-Direction Rosette Block]

    Rosette Block

    [ Bracket for tunnel ]

    VW Shotcrete Gage (Model 1240)

    Mount Bracket for

    [Installation kit of No-stress strain gage]

    T h e R e a d o utThe VW Embedment strain gages output the equivalent

    frequency signal to inclination, with equivalent voltage

    to temperature of a Thermistor or RTD. It is connected

    to the syste m such as the V W readout units, data loggers

    to be data logging and data acquisition system to monitor

    readings.

    A ce s R eadou t u ni tA C E - 8 0 0 (VW Palm size readout)A C E - 1 0 0 0 (VW Data recorder)Ace's Auto data acquisition systemA C E - 1 1 0 0 (VW Mini logger)A R F - 1 0 0 (RF Data acquisition system)We prov ide othe r c ompanys data acquisition system

    (CR- 10, DR51 5 etc.) after consulting the kind, amount

    of sensor, installing sites, operating manual or sys tem.Order ing Inform at ion

    Keeping VW readout unit

    Cable length (Standard 5 meters)

    METHODSTATEMENTFORPRELIMINARYTENSIONTESTPILET1AND

    T2BYREACTIONPILEMETHODCONTRACT156:NORTHEASTLINE

    EXTENSION

    For Approval

    REV 0

  • 8/13/2019 C156 Preliminary Tension Test Pile T1 T2 Rev 0

    62/103

    EXTENSION

    AppendixI

    SequenceofBoredPileReinforcementCageTandemLifting

  • 8/13/2019 C156