Cal/Coronagraph Integration. Lewis Roberts 2/25/2010. Agenda. Schedule Tasks Summary. High Level Schedule. 1 st week – Set up and integrate with Coronagraph 2 nd week – Integrate with AO system. Test system in lab 3 rd week – IFU detector is installed and tested. - PowerPoint PPT PresentationTRANSCRIPT
High Level Schedule
• 1st week – Set up and integrate with Coronagraph
• 2nd week – Integrate with AO system. Test system in lab
• 3rd week – IFU detector is installed and tested.• 4th week – 1 Engineering night and 2 science
nights.
Detailed Week 1 Schedule(This is just the highlights, a more detailed schedule is available on the Twiki)
• March 1– Drive Equipment to Palomar– Start Dewar Pumping/Cooling
• March 2– Sasha Tutors Gautam/Lewis on Coronagraph operations– Install Calibration Bread Board
• March 3– Install & Align Dewar– Alignment
• March 4
• March 5– Install System on AO bench
Detailed Week 2 Schedule(This is just the highlights, a more detailed schedule is available on the Twiki)
• March 8– Drive to Palomar– End-to-End Alignment
• March 9– AO Lab Tests Day 1
• March 10– AO Lab Tests Day 2
• March 11– AO Lab Tests Day 3
• March 12– AO Lab Tests Day 4
–
Detailed Week 3 Schedule(This is just the highlights, a more detailed schedule is available on the Twiki)
• March 15– Install new connectors on Cal System Dewar at JPL
• March 16– Drive to Palomar– Install Cal System Dewar into Cal System before IFU is installed. Need to confer with IFU
team.
Detailed Week 4 Schedule(This is just the highlights, a more detailed schedule is available on the Twiki)
• March 21– In lab testing of Coronagraph, IFU, AO and Cal System
• March 22– Install Instrument on Telescope (Morning)– Engineering Night (Night)
• March 23– Science Observations
• March 24– Science Observations
StaffingWeek 1
Mon3/1
Tues3/2
Wed3/3
Thur3/4
Fri3/5
Lewis ? X X
Gautam ? X X X X
Rob X X X X
Tom ? ?
Iris ? ?
Sasha X
StaffingWeek 2
Mon3/8
Tues3/9
Wed3/10
Thur3/11
Fri3/12
Sat3/13
Sun3/14
Lewis X X
Gautam X X X X
Rob X X X X
Tom X X X X
Mike X X X
Jenny X
Rick X X X
Sasha X X
Ben X X
Ian X X
StaffingWeek 3
Mon3/15
Tues3/16
Wed3/17
Thur3/18
Fri3/19
Sat3/20
Gautam ? ? ? ? ?
Sasha X X X X X X
Ben X X X X X X
Ian X X X X X X
StaffingWeek 4
Sun3/21
Mon3/22
Tues3/23
Wed3/24
Lewis X X X
Gautam X X X X
Iris X X
Tom X X X
Mike X X
Antonin ? X X X
Rick Day Day Day
Sasha X X X X
Ben X X X X
Ian X X X X
Rich ? ? ?
Integration Tasks
• This section summarizes tasks that need to be done at the telescope and involve a modification to the existing instrument.
P1640 Cables emerge from the top of the enclosure here.
Cryotiger Lines
Cal WFS Leach Electronics Box (See next slide)
Enclosure Modifications
~3”
10.715”
Leaving about 1/8” for the panel.
Needed to have a custom part made by Brooks Automation. To bring the end of the gas lines to the edge of the enclosure to allow for access to attach the gas lines to the dewar when the instrument is mounted to the telescope.
Part was ordered 2/19. Will arrive 1st week of march.
Reverse FPM Mount
Need to reverse the FPM Mount to put the long motors in the direction shown.
Also need to reverse the FPM in the mount.
1) Temporarily reroute ADC Cables around Optical Stimulus, while its installed.2) Route New Cables, will tie them in similar places to existing cables.
Optical Stimulus
80/20 Beamsplitter was replaced with a 50/50 beamsplitter.
For additional light during science observations, we can remove the beamsplitter.
Agilis tip/tilt stage will be controlled …
New Location of Quad-Cell for Coronagraph FSM
Integration Tasks• Machine Enclosure to hold Cal Gold Box• Machine Enclosure/install Cal patch panel• Cut hole in enclosure for Cal cold lines• Modify Dewar stand for Cal breadboard• Reverse FPM Mount• Reroute Risley Prism cables• Route New Cables• Move Quad Cell• Relocate Lyot Stop or Swap Mirror for
beamsplitter