Callum Black Project Portfolio Profile Overview: Over the past 4 years I have been able to work on some exciting, complex temporary works structures. Varying in complexity, each project in this portfolio represents typical components used in innovative ways to overcome issues on site. Whether it is site access, or propping, I have unique experience in designs and management of superstructure temporary works. Within each of the shown engineered solutions, there has been the consideration of build ability and cost, leading to the final design that was consequently installed. Contact: Callum Black Mobile: 07980133670 Email: [email protected] Callum Black Temporary Works Portfolio [email protected] Doc Issued: 18/07/16

Upload: callum-black

Post on 14-Feb-2017

75 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Callum Black Portfolio_V3_180716

Callum Black Project Portfolio

Profile Overview:

Over the past 4 years I have been able to work on some exciting, complex temporary works

structures. Varying in complexity, each project in this portfolio represents typical components used

in innovative ways to overcome issues on site. Whether it is site access, or propping, I have unique

experience in designs and management of superstructure temporary works.

Within each of the shown engineered solutions, there has been the consideration of build ability

and cost, leading to the final design that was consequently installed.

Contact: Callum Black Mobile: 07980133670 Email: [email protected]

Callum Black Temporary Works Portfolio [email protected] Doc Issued: 18/07/16

Page 2: Callum Black Portfolio_V3_180716

Project Portfolio - Callum Black

Scaffolding

Project Name: Bridge Parapet Encapsulation

Location: Torquay Rail Station

Description: Encapsulation of parapet to facilitate grit blast repairs over low speed rail line. It was required to keep the existing, narrow and weak, bridge open during the works, therefore it was decided that using Haki 750 beams would be the best approach to this project.

Client: Bam Nuttall Ltd

Involvement: Design, Bill of Quantities

Callum Black Temporary Works Portfolio [email protected] Doc Issued: 18/07/16

Page 3: Callum Black Portfolio_V3_180716

Project Name: Bridge Parapet Encapsulation

Location: Bitton Road Rail Bridge, Keynsham

Description: Encapsulation of parapet over high speed train line to facilitate bridge repair works. The structure was built as an up and over scaffold, reducing possession work and allowing the existing road to stay open at the same time.

Client: BAM Nuttall

Involvement: Design, Bill of Quantities

!

Callum Black Temporary Works Portfolio [email protected] Doc Issued: 18/07/16

Page 4: Callum Black Portfolio_V3_180716

Project Name: Handrail Adjustment

Location: Avonmouth M5 Bridge

Description: Support existing handrail to allow platform to be raised to the underside of the Avonmouth M5 bridge. The structure was required to be initially built off a cherry picker therefore there was a high importance of the build ability of the structure.

Client: Four Tees

Involvement: Design, Bill of Quantities

Callum Black Temporary Works Portfolio [email protected] Doc Issued: 18/07/16

Page 5: Callum Black Portfolio_V3_180716

Project Name: Public Access Staircase

Location: Oxford Museum of History or Science

Description: Allow public access staircase within confined space. The staircase was limited to foundation locations, therefore the structure was built top down, hanging from Haki 450 beams and Layher Public Access staircase and All-round Scaffold.

Client: Oxford University

Involvement: Design, Bill of Quantities, Project Management, Valuations

Callum Black Temporary Works Portfolio [email protected] Doc Issued: 18/07/16

Page 6: Callum Black Portfolio_V3_180716

Project Name: Access for Ceiling works repairs.

Location: Private Estate

Description: Scaffold to facilitate repair works to ceiling and dome, while ensuring a minimal foot print and existing staircase stays open. This used various components including but not limited to Layher, RMD Sgperslim and Haki Beams.

Client: Private

Involvement: Design, Bill of Quantities, Project Management

Callum Black Temporary Works Portfolio [email protected] Doc Issued: 18/07/16

Page 7: Callum Black Portfolio_V3_180716

Heavy duty propping

Project Name: Pro Cathedral, Basement opening

Location: Pro Cathedral, Bristol

Description: RMD Megashor was used for propping a 500kN/m unfactored load to facilitate a new structural opening at ground floor.

Client: Vinci

Involvement: Design, Bill of Quantities, Project Management

Callum Black Temporary Works Portfolio [email protected] Doc Issued: 18/07/16

Page 8: Callum Black Portfolio_V3_180716

Project Name: Bristol North Baths

Location: Bristol

Description: Horizontal support to a party wall to allow installation of new foundations near footing of existing wall. RMD Superslim was used to resist the horizontal loads and transmitted the load back into new temporary concrete foundations.

Client: Chatsworth House

Involvement: Design, Bill of Quantities, Project Management

Callum Black Temporary Works Portfolio [email protected] Doc Issued: 18/07/16

Page 9: Callum Black Portfolio_V3_180716

Project Name: Pro Cathedral, Level One Opening

Location: Pro Cathedral, Bristol

Description: RMD Superslim was use in a Seesaw propping method due to it being impractical to go to ground. Unfactored loads of 270kN/m meant that RMD Superslim suited these loads but were close to the limit. The new structural opening was for access for the new extension.

Client: Vinci

Involvement: Design, Bill of Quantities, Project Management

Callum Black Temporary Works Portfolio [email protected] Doc Issued: 18/07/16

Page 10: Callum Black Portfolio_V3_180716

Project Name: Tesco Yeovil

Location: Yeovil

Description: RMD Superslim Soldiers to support rear gable wall to facilitate installation of new steel frame. Due to new foundations for the steel frame, it was required to have a larger clear gap than usual, therefore RMD Superslim needles were used with stabilising RMD Superslim rakers.

Client: ISG Retail

Involvement: Design, Bill of Quantities, Project Management

!

Callum Black Temporary Works Portfolio [email protected] Doc Issued: 18/07/16

Page 11: Callum Black Portfolio_V3_180716

Project Name: 1-3 James St. West

Location: 1-3 James St. West, Bath

Description: Facade Retention to existing building to facilitate demolition of first floor slab and allow installation of new steel frame. Large 1 tonne concrete blocks were used on the RMD Superslim elevation as the only space for the facade retention was the existing pavement. A scaffold tube and fitting solution was more suitable on the other elevations due to more space being made available.

Client: Ikon Construction

Involvement: Estimating, Design, Bill of Quantities, Project Management, Valuations