![Page 1: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/1.jpg)
Sunnyvale Community Meeting
October 10, 2019
CALTRAIN ELECTRIFICATION
UPDATE
![Page 2: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/2.jpg)
2
AGENDA
• Caltrain System Overview
• Project Overview
• Sunnyvale Construction Activities
• Questions
![Page 3: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/3.jpg)
3
CALTRAIN SYSTEM• 32 Stations Gilroy to
San Francisco
• 92 Weekday Trains
• At-Grade Crossings,
Viaducts, and
Bridges
• Intermodal
Connections
• Bike Commuters
![Page 4: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/4.jpg)
4
PROJECT DESCRIPTION
• 51 miles
• San Francisco to San Jose
(Tamien Station)
Electric Trains*
• 19 7-car train sets
• 133 electric cars
*Includes 2018 State TIRCP
Funding
Project Area Project Elements
Electrification
• Overhead Contact
System (OCS)
• Traction Power
Facilities
![Page 5: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/5.jpg)
5
PROJECT DESCRIPTION
Speed
• Up to 79 mph
Service Increase
• 6 trains / hour / direction
• More station stops /
reduced travel time
• Restore Atherton &
Broadway service
Service Elements
Mixed-fleet Service
(interim period)
Continue Tenant Service
• ACE, Capitol Corridor,
Amtrak, Freight
![Page 6: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/6.jpg)
6
PROJECT BENEFITS
Improved Train
Performance,
Increased Service
and Greater Capacity
Improved Regional Air
Quality and Reduced
Greenhouse Gas
Emissions
Positive Economic
Benefits for the
Region
Increased Revenue
and Reduced
Fuel Cost
Reduced Engine
Noise Emanating
from Trains
![Page 7: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/7.jpg)
7
SCHEDULE
* Note: Schedule subject to change
![Page 8: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/8.jpg)
8
CONSTRUCTION PHASING
• 51 Miles Corridor
• 4 Work Segments
• 3,000 Poles
• 10 Traction Power
Facilities
![Page 9: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/9.jpg)
9
SUNNYVALE
![Page 10: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/10.jpg)
10
FIELD WORK PROGRESSION
Work Completed • Utility Survey
• Geotechnical Investigations
• Disposal of Soil from Geotechnical Investigations
• Soil Resistivity Testing
• Site Surveys
• Signal Cable Inspections
Work In Progress • Tree Pruning/Removal
• Potholing
• Paralleling Station
Future Work • Foundation Installation
• Pole Installation
• Wire Installation
• Bridge Barrier Construction
![Page 11: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/11.jpg)
11
FUTURE CONSTRUCTION
Sunnyvale
*Expected completion period indicate first and last day of activity.
Number of actual workdays will be fewer.
Date Work ActivityExpected
Completion*
In Progress Tree Pruning/Removal Early 2020
In Progress Potholing Late 2019
In Progress Paralleling Station Construction Early 2020
In Progress Foundation Installation Late 2019
Late 2019 Pole Installation Summer 2020
Early 2020 Wire Installation Summer 2020
Early 202 Bridge Barrier Installation Summer 2020
![Page 12: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/12.jpg)
12
FOUNDATION CONSTRUCTION
• Excavation
• Rebar and Anchor Installation
• Electrical Grounding
• Concrete Fill
![Page 13: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/13.jpg)
13
FOUNDATION INSTALLATION
On Track Equipment
![Page 14: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/14.jpg)
14
POLE INFORMATION
• 3,000 Installed throughout Corridor
• Approx. 250 poles in Sunnyvale
• Pole Height: 30-50’
• Pole Spacing: ~180’ apart
![Page 15: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/15.jpg)
15
Example of Poles Planned for Use in Sunnyvale
Two Track CantileverSingle Track Cantilever
POLE TYPES SUNNYVALE
![Page 16: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/16.jpg)
16
Example of Poles Planned for Use in Sunnyvale
PortalsCenter
POLE TYPES SUNNYVALE
![Page 17: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/17.jpg)
17
POLE INSTALLATION
Current Pole Installation
![Page 18: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/18.jpg)
18
On-track Equipment
STRINGING WIRE
![Page 19: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/19.jpg)
19
• 10 Traction Power Facilities Installed throughout Corridor
– 1 Paralleling Station installed in Sunnyvale
– Gantry structures up to 50’
• Provides electrical power to trains through the Overhead
Contact System
• Unmanned station
• Day and weekend construction work
• Limited night work during construction
TRACTION POWER FACILITIES
![Page 20: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/20.jpg)
20
PARALLELING STATION LOCATION
![Page 21: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/21.jpg)
21
EXAMPLE PARALLELING STATIONS
Examples from Amtrak Northeast Corridor
![Page 22: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/22.jpg)
22
PARALLELING STATION
CONSTRUCTION
Sunnyvale Paralleling Station Construction site
![Page 23: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/23.jpg)
23
BRIDGE BARRIERS
• Ensure the safety of pedestrians
and electrical infrastructure
• Will be installed at:
– Mathilda Avenue
– Fair Oaks Avenue
– Wolfe Road
![Page 24: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/24.jpg)
24
BRIDGE BARRIERS
9’6” fence height required for pedestrian bridges
Polycarbonate Panel
Screen Mesh
![Page 25: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/25.jpg)
25
CONSTRUCTION INFORMATION
• Work will occur during day and night
• Some 24 hour weekend work
• Crews will utilize acoustical barrier blankets and
position lights away from homes
• Dedicated hotline for construction complaints
![Page 26: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/26.jpg)
26
PUBLIC OUTREACH
Factsheet
Postcard
Doorhanger Public Meeting
![Page 27: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/27.jpg)
27
PUBLIC OUTREACH
• Subscribe to Weekly Updates
– Visit www.calmod.org/get-involved
• Social Media
• Construction Outreach Office
![Page 28: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/28.jpg)
28
WHAT’S NEXT
• Caltrain Business Plan
– Caltrain2040.org
• High-Speed Rail Blended System
– hsr.ca.gov
• Caltrain Downtown Extension
– sftca.org/transbay-transit-center
• Diridon Concept Plan
– DiridonSJ.org
![Page 29: Caltrain Electrification Update - CalMod · 10/10/2019 · FUTURE CONSTRUCTION Sunnyvale *Expected completion period indicate first and last day of activity. Number of actual workdays](https://reader033.vdocument.in/reader033/viewer/2022050111/5f48df4b271ee61e8936a6b3/html5/thumbnails/29.jpg)
29