![Page 1: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/1.jpg)
Minnesota Power’s Camp Ripley Solar Project
![Page 2: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/2.jpg)
• 2013 Solar Energy Standard (SES) and MP’s solar strategy• Camp Ripley Solar Project
– Development– Execution
Topics
![Page 3: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/3.jpg)
SES and MP’s solar strategy
Solar Analysis ProgramSolarSense Rebates
Made in Minnesota Incentives
Community Solar Garden Pilot Program
Awaiting MPUC Approval
10MW Camp Ripley Solar Project
Approved – under construction
SES compliance => 29 MW utility scale & 4 MW small scale by 2020
![Page 4: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/4.jpg)
![Page 5: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/5.jpg)
• Strengthen Relationships– Meet the site needs of Camp Ripley including microgrid and
Department of Defense Mandates– Provide unique value to all of MP’s customers with education center
and curriculum for schools
• Cost Competitiveness– Demonstrate price is competitive through a Request for Proposal
Process– Build project to Utility standards– Project was able to utilize Union Labor and solar panels made in the
United States– Although solar prices have declined, Wind is still much more cost
effective as a renewable resource– Project was designed to meet end of 2016 date to capture ITC
Camp Ripley Development Principles
![Page 6: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/6.jpg)
Project Development Timeline5/2013
Minnesota Passes Solar
Jobs Act
MP Begins to develop a
solar strategy
8/20149/2013
MP and MN ANG
brainstorm ideas
MP and MN ANG sign MOU
MP issues a site specific
RFP
MP bid selected in
RFP
EPC Contract signed
MPUC Approves
Project
1/2015 4/2015 6/2015 1/20169/2015
MPUCFiling
![Page 7: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/7.jpg)
Project Execution Timeline6/2015
EPC Contract Signed
M+W GroupFirst Solar
Hunt Electric
3/20161/2016
MPUC Approves
Project
Site Preparation and Roads
Piling and Racking
Module Installation
Modules andElectrical
Project Start-up
5/2016 6/2016 7/2016-8/2016 10/20169/2015
Check-out
![Page 8: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/8.jpg)
• 120,000 thin film Solar Panels• 4000 piles• $25,000,000 construction cost including contingency and
interconnection upgrades• $110 per Megawatt Hour (MWh) cost for our customers• 35 year project life• 60 acres of land• 17,500 MWh produced in a typical year• Enough to power 2000 homes for an entire year
Camp Ripley Numbers and Facts
![Page 9: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/9.jpg)
{
Questions?
![Page 10: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/10.jpg)
![Page 11: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/11.jpg)
![Page 12: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/12.jpg)
Piles
• Driven into the ground to support racking
![Page 13: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/13.jpg)
Panels• 122,000 First Solar 112 Watt Panels• Made in Perrysburg Ohio• https://www.youtube.com/embed/87_a7LJhRgY?rel
=0
![Page 14: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/14.jpg)
Inverter Skids
• (4) 2.5 MW Inverter Skids
![Page 15: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/15.jpg)
Microgrid and Control
![Page 16: Camp Ripley Solar Project · 2020. 1. 7. · MP issues a site specific RFP. MP bid selected in RFP. EPC Contract signed. MPUC Approves Project. 1/2015. 4/2015. 6/2015. 9/2015. 1/2016](https://reader036.vdocument.in/reader036/viewer/2022071101/5fda9331162efc029a655eac/html5/thumbnails/16.jpg)
Renewable Cost Comparison
• Camp Ripley Solar~$0.10 per kWh
• Rooftop Solar~$.25 per kWh
• Wind Energy (Utility Scale)~.025 per kWh– Generation (Energy) is only part of your electric bill 30%-50%
• Wires, Capacity, Maintenance, Transmission