Asphalt Case StudyRehabilitation of Runway 13R‐31L
Boeing Field
John I. Duval, P.E.
Canadian Airfield Pavement Technical Group SeminarMarriott Hotel| Minneapolis, Minnesota | Sep 19, 2016
Rehabilitation of Runway 13R‐31LBoeing Field
• Introduction to Boeing Field• Fact: Runway Closure is Expensive!• Planning and Coordination• Partnering Through Training
• Production/Placement/Compaction• Innovations• Success!
PAVEMENT SERVICES, INC.
Acknowledgments• Funding—FAA Airport Improvement Program• Sponsor—King County International Airport
– Mr. Rick Renaud, P.E.• Engineer—URS Corporation
– Mr. Shammi Ratti, P.E.,– Ms. Cindy Hirsch, P.E.– Mr. Brian Rapalee, P.E.
• Contractor—ICON Materials (Oldcastle)– Mr. Dave Gent, P.E., Project Manager
• And many others who contributed to this project
PAVEMENT SERVICES, INC.
Introduction to Boeing Field
Sea‐Tac
Boeing Field
4 Miles
5 Miles
PAVEMENT SERVICES, INC.
Introduction to Boeing Field
• Runway 13L‐31R– 3,710 ft x 100 ft
• Runway 13R‐31L– 10,000 ft x 200 ft
PAVEMENT SERVICES, INC.
Introduction to Boeing FieldScheduled and Charter Passenger Operations
PAVEMENT SERVICES, INC.
Introduction to Boeing FieldAir Cargo Operations
PAVEMENT SERVICES, INC.
Introduction to Boeing FieldBoeing B737 Commercial Delivery Center
PAVEMENT SERVICES, INC.
Introduction to Boeing FieldBoeing K46 Testing
PAVEMENT SERVICES, INC.
Introduction to Boeing FieldEconomic Impact Study
• $3.5B Annual Sales– 90% “New Money”
• 16,336 Jobs– 5,209 Jobs at Airport
• 150 Tenant Businesses• National Air Transport Assn “Top 100 Most‐Needed Airports”
PAVEMENT SERVICES, INC.
Introduction to Boeing FieldEconomic Impact Study
QuestionWhat is the impact of closing Runway 13R‐31L?
Answer$30,000 per hour
PAVEMENT SERVICES, INC.
Mountains of Material Required
• 106,000 tons of Hot Mix Asphalt needed– 6‐inch mill/inlay of entire runway– Deep repairs to taxiway connectors
• Nine alternatives were considered– Nighttime closures– Weekend closures– Combinations of nights and weekends– Full closure– Phased partial/full runway closure
PAVEMENT SERVICES, INC.
Runway 13R‐31L RehabilitationPhased Partial/Full Runway Closure
Construction Phasing
123
110 hrs 240 hrs 110 hrs2,500 ft 5,000 ft 2,500 ft
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
PAVEMENT SERVICES, INC.
Success!
• Full runway closure for only 10 days• Major construction operations completed within 20 day closure
• No accidents• 106,000 tons HMA meeting P‐401 specification
• Project came in within $24.5M budget