CANHEIT 2012. Building the Digital University. Disaster Recovery Through Cooperation. Disaster Recovery Through Cooperation. We had a Dream - also a Nightmare Where we have been Where we are today Challenges Where we are going. Who We Are. St. Thomas University in Fredericton - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CANHEIT 2012

CANHEIT 2012

Building the Digital University

Page 2: CANHEIT 2012

Disaster RecoveryThrough Cooperation

Page 3: CANHEIT 2012
Page 4: CANHEIT 2012

We had a Dream - also a Nightmare

•Where we have been

•Where we are today

•Challenges

•Where we are going

Disaster RecoveryThrough Cooperation

Page 5: CANHEIT 2012

Who We Are

•St. Thomas University in Fredericton

•Mount Allison University in Sackville

•Université de Moncton in Moncton

Page 6: CANHEIT 2012

We had a Dream... Or Nightmare

•How would we cope?

•How would we get there?

•Who would pay for it?

•Who would join us

Page 7: CANHEIT 2012

Where We Have Been

•ECN

•Datatel cooperation

•Virtualized servers at one datacentre

Page 8: CANHEIT 2012

The ECN•The NB/PEI Educational Computer Network

•Forty Years (!) of cooperation - Yes... There were data networks 40 years ago... Maybe smoke signals???

•Great Organizational model

•Great Financial Model

•Network, Spam filtering, software licensing etc.

Page 9: CANHEIT 2012

ECN Network

St. Thomas at Fredericton

Mount Allisonat Sackville

Université de Moncton at

Moncton

Fredericton to Sackville:250km or < 10ms

Fredericton to Sackville:250km or < 10ms

Page 10: CANHEIT 2012
Page 11: CANHEIT 2012
Page 12: CANHEIT 2012

Datatel Cooperation

• MUSIC Consortium from 15 years ago

• Workorder system run from MTA

• MTA makes customizations etc.

• STU has provided analyst expertise

• Single team - lots of savings

Page 13: CANHEIT 2012

VMs at one site

• MTA early adopter of VM technology

• STU brought capital to the table

• MTA built datacentre, has staff

• Two Universities (120 VMs) in a rack

• Great efficiencies

Page 14: CANHEIT 2012

Where We Were 2010

• Virtualized Servers working very well

• Current agreement works and is model for small university cooperation

• Very productive, staff train and work together

• Huge positive environmental impact

• Management shares common vision

Page 15: CANHEIT 2012

Timeline to 2010

1970

2010

1980

1990

2000

ECN Network

Datatel

Shared Datacentre

Page 16: CANHEIT 2012

Challenges

• NO credible disaster recovery capability

• Rapidly growing storage requirements (memory and disk)

• Server Hosting/Maintenance Agreement ending 2012

• Current Infrastructure EOL in 2012

Page 17: CANHEIT 2012

Where are we going?

• Original agreement set to expire in 2012

• Refresh of current infrastructure (with NO DR capability) would cost about $250,000.00

• Background of rapid growth in storage and to a lesser extent RAM requirements

Page 18: CANHEIT 2012

KIP Funds

•STU Applied for KIP funds for several IT projects

•Received 485K

•Gave us funds to BOTH refresh datacentre AND establish DR facility

Page 19: CANHEIT 2012

DR Site•Looked at several options

•STU - didn’t want to build a machine room

•MTA - didn’t want to expand a machine room

•UNB - in the process of gutting a machine room

•Private rackspace vendors - problem was getting data to them (cost of bandwidth)

•Best solution - a University on the ECN network

•Ended up at Université de Moncton.

Page 20: CANHEIT 2012

D/R Process• Technical Staff did considerable research

framing the problem and looking for a solution

• We issued an RFI - received 5 responses

• Pursued discussions with one respondent to further define plans

• Issued an RFQ to finalize numbers

• Bulletproof was chosen as the partner

Page 21: CANHEIT 2012

Adopted Solution

MTA - Refresh UdeM - New

Servers

Storage

Automatic Replicationover ECN Network

(magic)

Page 22: CANHEIT 2012

Engaging UdeM

• We are excited about engaging another partner, in this case to house equipment

• Offer on the table for UdeM to put a rack at MTA

• Leverages ECN investments

• $500/month + Power

Page 23: CANHEIT 2012

Dell Equallogic• Sticker Shock - but it’s “ALL IN” and easy

to manage...

• Atomic Unit is the SAN

• Simple and powerful

• Replication is part of the package

• Peace of Mind (priceless)

Page 24: CANHEIT 2012

Key Points• New data centre infrastructure PLUS

DR site

• Five years maintenance up front

• Retain leadership position in IT

• New partner U de M, more welcome

• We sleep better now - much better!

Page 25: CANHEIT 2012

... But there’s more

• We’ve been approached by two other institutions, both wish to eliminate data centres, both have received quotes from commercial providers.

• Our costs are about 1/2 the commercial providers

• We must be doing something right!

Page 26: CANHEIT 2012

New Timeline

1970201

0198

0199

0200

0

ECN Network

Datatel

Shared Datacentre

2015

Datacentre + D/R

New Partners

Page 27: CANHEIT 2012

The Future• (1 year) We hope to be hosting servers for at

least four institutions - Huge win financially, environmentally and politically.

• (1 year) ECN plans to conduct a review to explore further cooperation/consolidation

• (3-4 years) be positioned to take advantage of what options exist - ECN Datacentre? Commercial providers? Rebuild of current sites? "the cloud"... Who knows.

Page 28: CANHEIT 2012

Further out...Forecast is cloudy....

But we will be ready for it.

Page 29: CANHEIT 2012

Dilbert• ...of course there's a relevant

Dilbert...

• We are too cheap to pay $45 to show you the cartoon, so see cartoon for 25/May/2012 at http://www.dilbert.com

Page 30: CANHEIT 2012

CANHEIT 2010

Page 31: CANHEIT 2012

2010... Nearby...

Page 32: CANHEIT 2012

Questions ?

? ? ?? ? ?