capability statement rev 4

8
QBCC LICENCE 1304470 CAPABILITY STATEMENT

Upload: keith-callanan

Post on 11-Jan-2017

230 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Capability Statement REV 4

QBCC LICENCE 1304470

Capability Statement

Page 2: Capability Statement REV 4

“We combine flexibility, people, creativity and professionalism to achieve outstanding results.”

“Our vision was to create a company where clients could depend on uncompromised high quality product.”

about uS our hiStory

We are a private company with two shareholders actively involved in the day to day corporate, project and administrative management of the business.

From humble beginnings in 2014, we have grown to become a company operating on independent sites across regional and remote Australia.

During this time, we have evolved into a company that has excelled in residential, commercial and civil construction delivering industry best practice solutions.

Our specific areas of specialty include:• Civil infrastructure• Residential• Commercial works

We have an excellent track record across a full range of disciplines including direct management, construction management, project management, and site management.

Most importantly we work closely with our clients at all times never wavering from our commitment to deliver projects on time and within budget. We work side by side with our clients to ensure they receivemaximum benefit from our involvement. It is this partnership approach with our clients and stakeholders that has contributed to the company’s growth and success.

allconstruct was established in 2014 in Brisbane, built around integrity and quality.

The initial scope of work was based on providing general civil construction projects in regional and remote areas of Queensland. Relatively quickly the company also began to specialise on residential renovations and commercial fit-out work.

From the start the company established two major commitments: to not compromise on providing a quality product, and prioritising good communications and relations.

www.allconstruct.com.au www.allconstruct.com.au

Page 3: Capability Statement REV 4

“Our staff is led by example from the Managing Director to the Leading Hands.”

“Safety, Quality and the Environment is our Core Focus when delivering your project.”

our people our management SyStemS

Flexibility creativity and innovation are derived from talented people working well together in a productive environment. We work across a multitude of disciplines from our highly skilled project managers, cutting edge systems engineers, specialist project teams through to our creative and productive support staff.

Our range of disciplines requires a team- based approach with a flat management structure. This flat structure offers immense benefits. It promotes effective communication between our team and our clients and maximises the quality and efficiency of our projects. Teamwork, accountability and respect are the hallmarks of our company culture, both in our internal and external dealings.

This approach provides our clients with a level of assurance that we will continually meet and exceed their expectations.

We provide our team members withformal and on-the-job training. A system of continuous monitoring and performance appraisal ensures ongoing professional development. The team culture developed throughout the company is most important, and great care is taken in the recruitment of aspiring members. In addition to the investment we make in our people we ensure they have access to the latest equipment and technology. With these core elements we are driven to deliver successful outcomes for our clients and stakeholders.

We are committed to partnering with our clients, local communities, subcontractors and all other relevant stakeholders to ensure appropriate consideration is given to all safety, quality and environmental factors relating to our projects. We offer our clients a comprehensive Third Party Certified Safety, Quality and Environmental Management System.

We have a highly skilled management team that is dedicated to facilitating this system and developing comprehensive project specific management plans. This allows allconstruct to literally hit the ground running upon the award of a project. When awarded a project, our team of professionals ensure the ongoing monitoring and review of each project to ensure all expectations are met to the best of our ability and to facilitate continual improvement throughout our business. allconstructin-depth understanding of the management systems review process that sets us apart from our competitors and has contributed to the company’s growth and success.

www.allconstruct.com.au www.allconstruct.com.au

“Safety, Quality and the Environment is our Core Focus when delivering your project.”

Page 4: Capability Statement REV 4

Design & Build Project Design & Build Project

our projeCtS our projeCtS

Description This project was located at Highgate Hill, Brisbane. The site consisted of an old run down dwelling, which we had to demolish and take off site before the site earthworks could start. Then we commenced the earthworks and construction of the new dwelling.

WorksThe work undertaken included:

• Design and Planning Approval Application

• Demolishing of the existing house.• Earthworks and drainage works.• Concrete slab reinforcement and

pour• Timber frame fabrication and

erection of the dwelling• Electrical, plumbing and AC fitting• 1st and 2nd fix carpentry • Kitchen and wardrobe fit-outs• Painting and decorating• Interior design work

Challenges• Pedestrian management for

construction in an urban area• Underground services

management with a frequent

presence of telecommunication conduits, Electrical cables, water mains and sewer pipes

• Inclement weather conditions

our managementallconstruct were the principal contractor of this project and in charge of the project management, subcontractor management andengagement. allconstruct built a great relationship with the client and were able to complete the project ahead of time and on budget. There were highly qualified and specialised staff managing the project, who ensured that the project was completed to the highest standard.

Value addThe Project reached practical completion early May, which was well ahead of contractual practical completion date. The project team took on a vigorous approach to tackle issues to go the extra mile to cater for our client’s special requirements.

Description This project was located at Redhill, Brisbane. The site consisted of an old run down dwelling, which we had to demolish and take off site before the site earthworks could start. Then we commenced the earthworks and construction of the new dwelling.

WorksThe work undertaken included:

• Design and Planning Approval Application

• Demolishing of the existing house.• Earthworks and drainage works.• Concrete slab reinforcement and

pour• Timber frame fabrication and

erection of the dwelling• Electrical, plumbing and AC fitting• 1st and 2nd fix carpentry • Kitchen and wardrobe fit-outs• Painting and decorating• Interior design work

Challenges• Pedestrian management for

construction in an urban area• Underground services

management with a frequent presence of telecommunication conduits, Electrical cables, water mains and sewer pipes

• Inclement weather conditions

our managementallconstruct were the principal contractor of this project and in charge of the project management, subcontractor management andengagement.

allconstruct built a great relationship with the client and were able to complete the project ahead of time and on budget.

There were highly qualified and specialised staff managing the project, who ensured that the project was completed to the highest standard.

www.allconstruct.com.au www.allconstruct.com.au

Project: Residential Project.Location: Highgate Hill, BrisbaneClient: Private InvestorContract Value: $1.3 millionConstruction Period: September 2014 – May 2015

Project: Residential Project.Location: Redhill, BrisbaneClient: Private InvestorContract Value: $1.2 millionConstruction Period: April 2015 to December 2015

Page 5: Capability Statement REV 4

North Pine Switch Room, QLD Design & Build Decking Project

our projeCtS our projeCtS

Description The project was part of the North Pine Waste Treatment Plant upgrade. allconstruct were contracted to construct the Switch Room Building.

WorksThe work undertaken included:

• • Clearing and grub of the site• • Piling the building slab area• • Detail excavation works of the

slab area• • Formwork, steel fixing and

concrete works• • Block laying of the building.• • Roofing of the building.• • Internal carpentry fit-out• • Supply and fitting of external

fire doors

our managementThe site team was divided into two crews to manage program time frames within the program were achieved. Ongoing consultation with the client addressed design issues on a few of the changes that were overcome with a good finish result.

Value add “The works have been completed to a high standard. Indeed, this is one of the best completed sites I have seen on the North Pine Treatment Plant.” Robert Bearne. North Pine GM.

Description allconstruct offer a complete design and build package to all our clients requiring quality carpentry workmanship around their private dwellings.

WorksKey elements included:

• Earthworks• Foundation pier design and

construction• Carpentry work • Sanding and finish timberwork

our managementThe Project and Management Systems Team implemented a range of safety, quality, and environmental procedures on this site to improve efficiency across each project.

The client acknowledged our commitment and understanding of controlling all documents, traceability and overall project quality.

Value addallconstruct carpentry workmanship and knowledge of local council requirements give our clients true value for money

www.allconstruct.com.au www.allconstruct.com.au

Project: North Pine Waste Treatment Plant Location: North Pine, Queensland Client: Comadin InfrastructureContract Value: $350kConstruction Period: November 2015 – March 2016

Projects: Ongoing Projects in Brisbane QldLocation: BrisbaneClient: Private Owners and DevelopersConstruction Period: October 2014 – Current

Page 6: Capability Statement REV 4

Parklands Commonwealth Games Village Rathdowney Reservoir Project

our projeCtS our projeCtS

Description This high profile project based in the Gold Coast is been constructed to accommodate the sports athletes competing in the 2018 Commonwealth Games. 1400 apartments in total.

WorksKey elements included:

• Sourcing and managing 60 to 80 personal for the duration of our scope of works

• Supply skilled labour to fabricate and erect all the internal stud works for 7 building. Each building with 85 apartments

• Supply skilled labour to erect all ceiling framing

• Supply skilled labour to fit all the external cladding framing and sheeting

• Supply crews to patch, sand and prep all the cladding sheets for painting.

our managementOur experienced management team recruited, managed and coordinated all our tradesmen to deliver this project in time and budget for our customers Kenny Projects.

Value addallconstruct client acknowledged our commitment and understanding of controlling all skilled labour, QA and safety measures required on this high profile commercial fit-out project.

Description This project site was located at Rathdowney Qld. The works program included the widening of 2.4km of existing entrance road to the reservoir, stormwater upgrade, pavement strengthening and landscaping.

WorksKey elements included:

• Earthworks• Construct of all the concrete structures i.e. reservoir foundation footings, air and scour valve pits, culvert precast fitting and in-situ headwalls• Drainage Works• Traffic Management

Challenges• Extreme Weather• Traffic Management

our managementThe Project and Management Systems Team implemented a range of safety, quality, and environmental procedures on this site to improve efficiency across the project engagement. The client acknowledged our commitment and understanding of controlling all documents, traceability and overall project quality.

Value addallconstruct engaged local subcontractors to assist in the delivery of the project which provided economic benefit to the project and flow on effect to the local community

www.allconstruct.com.au www.allconstruct.com.au

Project: Parkland Commonwealth Games Village Accommodation Location: Southport, Gold Coast QldClient: Kenny ProjectsContract Value: $2.8mConstruction Period: May 2016 – Current

Project: Rathdowney Reservoir Upgrade Project Location: Rathdowney QldClient: Comdain InfrastructureContract Value: $480kConstruction Period: October 2015 – March 2016

Page 7: Capability Statement REV 4

Sunnybank Hills – Design and Build

our projeCtS Company DetailS

Description This project site was located at Sunnybank Hills. allconstruct were contracted to complete the full complete design and build landscape package.

WorksKey elements included:

• Driveway & footpaths design and build

• Construction of a quality hardwood deck

• Landscape design and construct • Front boundary wall construction.

our managementThe Project and Management Systems Team implemented a range of safety, quality, and environmental procedures on this site to improve efficiency across the project.The client acknowledged our quality workmanship and dealing with the local council representatives.

Value addallconstruct workmanship and management of all the works onsite has very well arranged and coordinated from start to finish.

www.allconstruct.com.au

Project: Landscape, Driveway, Decking Project Location: Sunnybank HillsClient: Private OwnerContract Value: $70kConstruction Period: June 2016 – Aug 2016

Company Name Allconstruct Pty Ltd

Year established 2014

ABN 50 601 503 986

ACN 601 503 986

Registered Address 5 The Yardarm Runaway Bay Q 4216

Website www.allconstruct.com.au

Phone 07 3814 6369

Postal Address 5 The Yardarm Runaway Bay Q 4216

Contact Eamus Coote - Construction Manger m. 0416 490 597 e. [email protected]

Keith Callanan - Project Manager m. 0406 917 991 e. [email protected]

Ruwanthi Lekamge - Project Engineer m. 0433 773 812 e. [email protected]

Gemma Callanan – Contracts Manager m. 0408 662 810 e. [email protected]